3‐ Modify the calendar by adjusting the following

‐ working days per week.


‐ working hours per day.
‐ The day off and holidays.

Calendars types: ‐
1-The global calendar pool contains calendars that apply to all projects.
2- The project calendar pool is a separate pool of calendars for each project.
3-The resource calendar pool can be a separate pool of calendars for each resource.
 You can assign either resource or global calendars to resources, and you can
assign either global or project calendars to activities.
 You can link resource and project calendars to global calendars. Then, if you
make changes to a global calendar, your changes apply to all resource and project
calendars that are linked to the modified global calendar.