SCHEDULE FOR INSTALLATION OF TWO PASSENGER ELEVATOR FOR SHOWA HOMES REAL
ESTATE, BULBULLA PROJECT
ACT. No ACTIVITIES START DATE RESPONSIBLE REQUIREMEN PRECEEDING
FOR THE T FOR ACTIVITY ACTIVITY COMPLETING THE ACTIVITY 1 Setting 17/10/2023 CONTRACTOR template and plumbing works 2 Chiseling CLIENT works on the wall if there is any as per the plumb 3 Guiderail CONTARACTOR bracket installation for CAR and CWT 4 Installation of CONTRACTOR guiderails (CAR and CWT) 5 Adjustment CONTRACTOR for Guiderail Alignment Civil work for CLIENT building machine room 6 Machine CONTRACTOR devices installation (Motor, Motor drive, Controller and ETC) 7 Landing door CONTRACTOR installation (Door sill, Door frame, Door mechanism, Door panel and Toe guard) 8 Disassemble CLIENT last two floor scaffolding 9 Travelling CONTRACTOR cable installation 10 Installation of CONTRACTOR rope with all the accessories 11 Compensation CONTRACTOR chain installation 12 Install CWT with fillers 13 Installing speed governor rope 14 15 Installation of shaft wiring (machine room, hoistway, pit and top of car) 16 Landing door and car door adjustment 17 Installation of position sensor 18 Installation of hall call button and decorative car features) 19 Start up for inspection drive 20 Start up for normal drive 21 22 23 24 25 26 27 28 29 30