Professional Documents
Culture Documents
Quantity
DRILLING
Labor Component - 1st well
(1) General Mobilization - Cebu to Surigao 1
(2) Rig Preparation & Set up 1
(3) Drilling of PQ size pilot hole from 0-200 meters depth, including core recovery 200
(4) Georesistivity logging of the hole for aquifer identification/ well design 1
(5) Reaming of hole to 200mm dia by tricone 250
(6) Reaming of hole to 310 mm dia by tricone 250
(7) Reaming of hole to 400 .. Dia by tricone 250
(8) Installation of 300 mm dia BI casings & stainless steel screens 1
(9) Deflocculation of drilling mud by injection of sodium hexametaphosphate 1
(10) Installation of gravel pack,no.10 1
(11) Well development by surging 24
(12) Well development by jetting 36
(13) Pump testing the well (using GRC pump) 72
(14) Pedestal construction & site clean up 1
13,204,101 6,602,051
518,483 259,241
381,545 190,772
300,000 150,000
14,404,129
40,000 40,000
1,150,000 1,150,000
160,000 160,000
1,350,000
58,744,708
58,744,708 4,841,600 29,541,043 5,620,000
2,937,235 242,080 1,477,052 281,000
7,049,365 580,992 3,544,925 674,400
68,731,308 5,664,672 34,563,021 6,575,400
1,227,345 101,155 617,197 117,418
May-24 Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24
60,000
1,924,000
80,000
875,000
875,000
875,000
250,000
125,000
100,000
72,000
108,000
216,000
60,000
60,000
1,924,000
80,000
875,000
875,000
875,000
250,000
125,000
100,000
72,000
108,000
216,000
60,000
300,000
6,602,050.60
259,241.30
190,772.39
150,000.00
5,620,000 13,122,064 - - - - - -
281,000 656,103 - - - - - -
674,400 1,574,648 - - - - - -
6,575,400 15,352,815 - - - - - -
117,418 274,157 - - - - - -
Project : DEWATERING WELLS
Client : Greenstone Resources Corporation
Location : Siana, Tubod, Surigao del Norte
Specifications : (a) depth - 200 meters each hole
(b) 4 holes
Item No. Description of Works
(A) Labor Component - 1st well
1 General Mobilization - Cebu to Surigao
2 Rig Preparation & Set up
3 Drilling of PQ size pilot hole from 0-200
meters depth, including core recovery
4 Georesistivity logging of the hole for
aquifer identification/ well design
5 Reaming of hole to 200mm dia by tricone
6 Reaming of hole to 310 mm dia by tricone
7 Reaming of hole to 400 .. Dia by tricone
8 Installation of 300 mm dia BI casings &
stainless steel screens
9 Deflocculation of drilling mud by injection
of sodium hexametaphosphate
10 Installation of gravel pack,no.10
11 Well development by surging
12 Well development by jetting
13 Pump testing the well (using GRC pump)
14 Pedestal construction & site clean up
15 Rig demobilization - Surigao to Cebu
Sub Total (A)
(B) Labor component - 2nd , 3rd ,4th wells
Items 2 to 14
1 lump 80,000
1 lump 125,000
1 lump 100,000
24 hours 3,000 72,000
36 hours 3,000 108,000
72 hours 3,000 216,000
1 lump 60,000
1 lump 300,000
6,265,000
3 5,620,000 16,860,000
Total (A) &(B) 23,125,000
VAT 2,775,000
Total 25,900,000
estimated 65% of depth
estimated 35% of depth
1,152,611
500,000 Requires ~6-months
132,000 lead time; needs to
225,000 be on-site by March
75,000 2023
38,000
1,152,611
500,000 Requires ~6-months
132,000 lead time; needs to
225,000 be on-site by March
75,000 2023
38,000
1,152,611
450,000 Requires ~6-months
84,000 lead time; needs to
225,000 be on-site by March
75,000 2023
38,000
2,245,140
20,000
3,004,646
56,283
63,650
16,750
15,000 Requires ~4-months
lead time; needs to
15,000 be on-site by March
50,000 2023
10,000
977,500
517,099
10,000
50,000
Requires ~6-months
lead time; needs to
6,499,920 be on-site by March
2023
9,459,463
790,000 790,000
4,500,000
4,580,391
3,261,623 Requires ~4-months
13,896 lead time; needs to
60,000 be on-site by March
1,500,000 2023
100,000
200,000
307,714
2,122,611
2,122,611
2,024,611
7,051,067
6,499,920
9,459,463
790,000 790,000
14,215,910 307,714