PERFORMA FOR REPORT RAIL/WELD/SEJ/GLUED JOINT/X-ING FAILURE

S.N. Description

1 Date
2 ADEN
3 SSE PWAY
4 Gauge
5 Route
6 Major section
7 Block section

8 Location(Km/TP)

9 Rail section & UTS

10 Brand mark / Rolling mark

11 Year of manufacturing
12 Year laid in track
13 Type of fracture (R / W/ OTHERS)

14 Type of weld
15 Welding done by Agency / Deptt
16 Whether heat affected zone Y /N
17 Fish plate zone Y /N
18 Through fish bolt hole Y/N
19 Date of welding

20 Date of last USFD testing of Rail


21 Date of last flange testing of weld

22 USFD remark ie IMR / OBS / IMRW / OBSW / DFW


23 Whether Joggled fish plate provided and supported on wooden block Y/N

24 Date of visual inspection


25 Code of fracture
26 LWR / SWR / SR
27 Date of last Destressing/ Gap survey
28 Destressing Temperature (0 C)
29 Type of sleeper
30 Ballast cushion (clean + caked)
31 Date of last deep screening

32 Gap in mm & temperature at arrival at site

33 SR imposed if any

34 Total GMT carried out by the rail / weld


35 GMT of section
36 Put right time/date

37 Detention of train

38 Reported by & time

39 PWI reached at site

40 Mode of proceeding
41 Last Tamping
42 In case of other failures Detail of SEJ / Glued joints etc

a Manufactured by
b Date of laying
c GMT carried
d Rail Brand / rolling mark
e Movement of T / S rail of LWR of pertaining SEJ
f Modified / Non modified
43 In case of CMS crossing or tongue rail failure
a Manufactured by
b Date of reconditioning
c GMT carried

44 Bolt Hole
45 Welder and JE/SSE/P WAY
46 Curve /Straight
47 Min.Temp.
48 Max. Temp