WORK INSTRUCTION
Rev.00 Page : 1
Procedure of Cleaning and Inspection of
Plate Heat Exchanger
Date 12nd May 2023
1. Purposed
This procedure is applied to carry out cleaning and inspection of Plate Heat Exchanger.
Rev.00 Page : 2
Procedure of Cleaning and Inspection of
Plate Heat Exchanger
Date 12nd May 2023
6. Cleaning
Always remove plates one by one and number them properly.
Use nylon or other types of soft scrubbing brushes to clean the plate.
A high pressure cleaner can be used with absolute care and never add abrasives, make
sure they are re-fitted in the same order.
Rev.00 Page : 3
Procedure of Cleaning and Inspection of
Plate Heat Exchanger
Date 12nd May 2023
8. Leak Test
Leakage detection shall be performed once assembly of PHE has been completed.
Check if any leakages appear at top, bottom and both sides of plate pack by carrying
out hydrostatic test. Testing pressure shall not exceed the design pressure.
Maintain pressure for 10 minutes or longer. All works can be completed if no leakage.
In case of any leakage detected, mark on the leaking part and disassemble PHE again
for visual check on the heat transfer plate and gasket surface.
MPSI-Timor/MTC/XXX
MPSI
Maintenance
WORK INSTRUCTION
Rev.00 Page : 4
Procedure of Cleaning and Inspection of
Plate Heat Exchanger
Date 12nd May 2023
10 REFERENCE
IO&M Manual of Plate Heat Exchanger 2 CFSPP Timor-1 Pages 16-20