WORK INSTRUCTION Maintenance
Rev.00 Page : 1
Procedure of Condensate Extraction
Pump Date 12nd May 2023
Checked and verified by Maintenance Manager, Date Approved by Station Manager, Date
Keywords Replaces
BMS, (please fulfilled)
1. Preparation
Inform to operator that work will be start.
Prepare the necessary document, i.e: SOP, Manual book, drawing,
logic. Etc.
Prepare safety equipment (PPE) ,i.e: Helmet, Safety Shoes, Safety glasses, Safety
belt or body hardness, Mask and gloves.
Prepare safety equipment for woks place,i.e : Safety line , Tagging
Ensure overhead crane can be used and operated by certify operator.
Prepare the necessary parts, tools and equipment before commencing actual work,
ie: Lifting Tools (chain blocks, shackles and wire sling, nylon sling etc), Ordinary
hand tools (Pipe wrench, combination wrench set & socket set, Slogging wrench,
Allen key, wire brush, scraper), Special Tools refer to manual if any, Spare parts if
needed, Consumable material, etc.
Technician (Competen Person) open document for Permit To Work (PTW) and
Authorized leader has been issuing the PTW Document.
Coordinate with electrical department to disconnect cable power, vibration
monitor and thermocouples before starting disassemble work
2. Safety Checking
Ensure the permit to works ( PTW) is available and the equipment is isolated
before comencing the work,i.e :
Ensure the breaker was off & tagging has been installed
Ensure the valve inlet & outlet has been close& tagging has been installed.
MPSI-Timor/MTC/XXX
MPSI
WORK INSTRUCTION Maintenance
Rev.00 Page : 2
Procedure of Condensate Extraction
Pump Date 12nd May 2023
Ensure the equipment has been install the safety line around the workplace .
Note! Any persons except the authorized staffs are not permitted to approach the
equipment during inspection.
3. Diassembly works
Prior to disassembly, each part should be marked for alignment for use at
reassembly
The pump should be broken down in accordance with each disassembly drawing
and procedure
Follow the Pocedure for overhaul of Condensate Extraction pump , refer to
IO&M manual pages 96 .
Arrange the dismantled parts with neat on the suitable place.
Clean all parts of any dirt and other foreign matter.
Measure the shaft run out by utilizing V blocks and a dial indicator.
MPSI-Timor/MTC/XXX
MPSI
WORK INSTRUCTION Maintenance
Rev.00 Page : 3
Procedure of Condensate Extraction
Pump Date 12nd May 2023
An allowable value is in accordance with "AN ALLOWABLE VALUE FOR RUN OUT
OF SHAFT”
5. ReAssembly
The pump should be reassembled in accordance with the rules of engineering
practice. The first of the individual components should be coated with graphite or a
similar lubricant before assembly, and the same applies to the threads of screwed
connections. The step by step procedure for complete unit assembly is
done in the reverse order of disassembling (refer to IO&M Manual CEP)
It is necessary to proceed re-assembling work while checking for conformance with
the dimensions recorded at the time of disassembling.
6. Commisioning test
Inform to operator that works for inspection was finished and needed to run test
to see the perfomance of the pump after internal inspection
Inform to authorized leader to suspend the PTW Document and normalized all
isolated equipment,i.e: breaker, valve, etc , in order to carried out run test.
Run test the equipment.
Rev.00 Page : 4
Procedure of Condensate Extraction
Pump Date 12nd May 2023
9. REFERENCE