This document is a transmittal log that lists various health, safety, and environmental plans and procedures submitted by Wjeen for approval. It includes items like a temporary facility evacuation plan, traffic flow chart, heat stress management plan, emergency response plan for temporary facilities, and contractor site safety program. The log notes that Wjeen's HSE department needs to verify and update some documents before official transmittal to SAPMT for approval. One contractor site safety program procedure is already approved by LPD, while others are still listed as open or awaiting official transmittal approval.
This document is a transmittal log that lists various health, safety, and environmental plans and procedures submitted by Wjeen for approval. It includes items like a temporary facility evacuation plan, traffic flow chart, heat stress management plan, emergency response plan for temporary facilities, and contractor site safety program. The log notes that Wjeen's HSE department needs to verify and update some documents before official transmittal to SAPMT for approval. One contractor site safety program procedure is already approved by LPD, while others are still listed as open or awaiting official transmittal approval.
This document is a transmittal log that lists various health, safety, and environmental plans and procedures submitted by Wjeen for approval. It includes items like a temporary facility evacuation plan, traffic flow chart, heat stress management plan, emergency response plan for temporary facilities, and contractor site safety program. The log notes that Wjeen's HSE department needs to verify and update some documents before official transmittal to SAPMT for approval. One contractor site safety program procedure is already approved by LPD, while others are still listed as open or awaiting official transmittal approval.
Upgrade Buildings for Risk Mitigation JNGLF - BI-10-01747, Contract: 6601000245 Sunday, February 4, 2024
Outgoing Documents Transmittal Log
COMPANY RESPONSE S. N. TRANSMITTAL NO. DOCUMENT REFERENCE NO. DOCUMENT DESCRIPTION Action by REVISION DEPARTMENT DOC. TYPE ISSUED DATE REVIEW STATUS ISSUED STATUS ORIGINATOR REF. REVISION DATE COMPANY STATUS 2 Wjeen-TR-SA-CON-002 Wjeen-TR-SA-CON-002 TEMPORARY FACILITY EVACUATION PLAN Wjeen to Re-forward 0 HSE PLAN 6-Jul-23 Issued for Approval Open Dr. Narciso
3 Wjeen-TR-SA-CON-003 Wjeen-TR-SA-CON-003 TRAFFIC FLOW CHART Wjeen to Re-forward 0 HSE PLAN 9-Jul-23 Issued for Approval Open Dr. Narciso
Wjeen HSE to cross verify
10 Wjeen-TR-SA-S001 Wjeen-TR-SA-S001 HEAT STRESS MANAGEMENT PLAN and update to SAPMT for 1 HSE PLAN 26-Jun-23 Issued for Approval Open Dr. Narciso official transmittal.
Wjeen HSE to cross verify
13 Wjeen-TR-SA-S009 Wjeen-TR-SA-S009 ERP TEMPORARY FACILITY and update to SAPMT for 1 HSE PLAN 19-Jul-23 Issued for Approval Open Dr. Narciso official transmittal.
Wjeen HSE to cross verify
14 Wjeen-TR-SA-S011 Wjeen-TR-SA-S011 CONTRACTOR SITE SAFETY PROGRAM (CSSP) and update to SAPMT for 1 HSE PROCEDURE 29-Aug-23 Issued for Approval Open Muhammad Ihtisham ECPEU-000012.2023 1 5-Sep-23 Approved official transmittal.
Wjeen HSE to cross verify
205 JNGLF-T-WJN-SA-0163 WJN- JNGLF-HS-PRO-017 Wjeen Accident Investigation Procedure and update to SAPMT for 0 HSE PROCEDURE 26-Nov-23 Issued for Approval Muhammad Ihtisham official transmittal. Open 292 JNGLF-T-WJN-SA-0250 WJN- JNGLF-QA-JSA-0021 JSA for Electrical Switch OPS Building. Wjeen HSE to cross verify JSA 25-Dec-23 Issued for Approval Open Jehan Badshah and update to SAPMT. 0 HSE 394 JNGLF-T-WJN-SA-0355 WJN- JNGLF-HS-JSA-0020 JSA for Excavation among SS#22, #27 and Expansion 1 HSE JSA 24-Jan-24 Issued for Approval Open Jehan Badshah Building. REMARKS
CSSP is approved by LPD as per Mr. Qureshi email dated 5
September 2023. Awaiting official Transmittal Approval by SAPMT.