You are on page 1of 9

Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446

Contents lists available at ScienceDirect

Journal of Rock Mechanics and


Geotechnical Engineering
journal homepage: www.rockgeotech.org

Full length article

Grouting techniques for the unfavorable geological conditions of


Xiang’an subsea tunnel in China
Dingli Zhang, Qian Fang*, Haicheng Lou
Key Laboratory for Urban Underground Engineering of the Education Ministry, Beijing Jiaotong University, Beijing 100044, China

a r t i c l e i n f o a b s t r a c t

Article history: One of the major challenges during subsea tunnel construction is to seal the potential water inflow. The
Received 4 May 2014 paper presents a case study of Xiang’an subsea tunnel in Xiamen, the first subsea tunnel in China. During
Received in revised form its construction, different grades of weathered geomaterials were encountered, which was the chal-
16 June 2014
lenging issue for this project. To deal with these unfavorable geological conditions, grouting was adopted
Accepted 3 July 2014
Available online 16 September 2014
as an important measure for ground treatment. The grouting mechanism is first illustrated by intro-
ducing a typical grouting process. Then the site-specific grouting techniques employed in the Xiang’an
subsea tunnel are elaborated. By using this ground reinforcement technique, the tunneling safety of the
Keywords:
Subsea tunnel
Xiang’an subsea tunnel was guaranteed.
Weathered rocks Ó 2014 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by
Grouting Elsevier B.V. All rights reserved.
Water inflow

1. Introduction illustrated by introducing a typical grouting process and specific


grouting measures adopted during the subsea tunneling are
The geological conditions of subsea tunnels are rather difficult to elaborated.
accurately explore because of the close proximity of an infinite
amount of seawater. Therefore subsea tunnels are greatly affected 2. Grouting mechanism
by the geological uncertainties and are more risky than most other
tunneling projects (Palmström, 1994; Chen et al., 2013). During Grouting is critically important in tunnel engineering. The
construction of the Seikan tunnel in Japan, the longest and deepest compaction grouting mode or hydro-fracture grouting mode can be
operational rail tunnel in the world, four disastrous water inflow used depending on the local geological conditions of the given
accidents occurred. These accidents caused serious construction project (Soga et al., 2004). To date, the majority of grouting appli-
delays, enormous financial losses and 34 fatalities (Anderson and cations have adopted the soil fracture technique (Essler et al.,
Roskrow, 2003). The excavation of the Vardo subsea tunnel in 2000). However, as grouting is a complex process, both perme-
Norway was performed through some very unstable faults. At one ation grouting and compaction grouting can be observed in a
of these faults, sliding took place and started to develop upwards fracture grouting dominated process. Many factors may affect the
towards the sea bed (Palmström, 1982). During construction of the eventual grouting modes used, such as the grout material, grouting
Oslofjord subsea tunnel in Norway, an unexpected 15e20 m wide pressure, soil type, and stress state of the ground. A typical rela-
cleft filled with gravel material was detected, only 15 m in front of tionship between the grouting pressure and grouting rate during
the tunnel cutting face. Tremendous efforts were made to deal with the grouting process in a loose soil is shown in Fig. 1. A conceptual
this unfavorable condition (Berggren, 2000). In this paper, a case model of grouting, which consists of the following five stages, can
study of the Xiang’an subsea tunnel in Xiamen, China is presented. be built up accordingly.
During its construction, different grades of weathered rocks were
encountered. Grouting techniques were employed to address these
unfavorable geological conditions. The grouting mechanism is first (1) Stage 1: backfill grouting and permeation grouting

A grouting pipe is first filled with pressurized grout, and the


* Corresponding author. Tel.: þ86 10 51688115. grout enters the ground from holes preset along the pipe. The
E-mail address: qfang@bjtu.edu.cn (Q. Fang). injected grout fills the cavities in the loose soil; this is referred to as
Peer review under responsibility of Institute of Rock and Soil Mechanics, Chinese backfill grouting. Meanwhile, the injected grout may also permeate
Academy of Sciences.
1674-7755 Ó 2014 Institute of Rock and Soil Mechanics, Chinese Academy of Sci-
the voids between the soil particles, which is referred to as
ences. Production and hosting by Elsevier B.V. All rights reserved. permeation grouting (Nonveiller, 1989). Due to the effects of
http://dx.doi.org/10.1016/j.jrmge.2014.07.005 backfill grouting and permeation grouting, the ground permeability
D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446 439

Secondary fracture initiation (2) Stage 2: compaction grouting


Primary fracture initiation
Grouting pressure
The continuously injected grout expands the soil outwards and
Grouting rate
forms a grout bulb around the pipe. With the increase in the
Grouting pressure

grouting pressure, the size of the grout bulb increases until the

Grouting rate
grouting pressure accumulates up to the fracturing pressure. The
formation of the grout bulb displaces and compacts the sur-
rounding soil (Wang et al., 2010). At this stage, the grouting pres-
sure increases to a peak value and the grouting rate drops gradually.

(3) Stage 3: primary fracture grouting


O A B C D E Time
Stage 1 Stage 2 Stage 3Stage 4 Stage 5 When the grouting pressure reaches the first peak value, a plane
Fig. 1. Grouting pressure and grouting rate during a typical grouting process in a loose
of fracture is formed in the soil by hydraulic fracturing (Gothäll and
soil. Stille, 2009). Assuming that grouting is performed in an isotropic
elastic medium, the fracture plane is theoretically perpendicular to
is reduced and the ground is thus strengthened and stiffened. At the secondary principal plane along the longitudinal direction of
this stage, the grouting pressure and the grouting rate can be the pipe, considering that the first principal plane is horizontal
reduced gradually. Generally, the duration of this stage is very (Fig. 2). The primary fracture is initiated by the tensile stress. Due to
short, lasting for only tens of seconds. the grouting pressure inside the borehole, tensile stress occurs in

Fig. 2. Mechanism of grouting fracture initiation.

Tunnel shaft K7+850 Tunnel shaft K11+250


8.5 m diameter 8.5 m diameter
Tunnel portal K6+540 45 m buried depth 45 m buried depth Tunnel portal K12+585 Road to Xibin Town

Start K5+909 End K14+647


Xiamen Xiang’an

Wutong overpass Service zone

Fig. 3. Layout of Xiang’an subsea tunnel.


440 D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446

Elevation (m) ZK6+540 Left line Legend


10 ZK12+485
3.16 m (High water level) Backfill
0 -2.4 m (Low water level)
Monzonite
-10
-20 Diabase
-30
Sludge
-40
-50 Granite
-60 Granodiorite
-70
Coarse sand
Weathered slot F1 Weathered slot F4 Weathered slot F2 Weathered slot F3

Elevation (m) YK6+599 Legend


Right line
10 YK12+510 Backfill
3.16 m (High water level)
0 -2.4 m (Low water level)
Monzonite
-10
-20 Diabase

-30 Sludge
-40
Granite
-50
-60 Granodiorite

-70 Coarse sand


Weathered slot F1 Weathered slot F4 Weathered slot F2 Weathered slot F3

Fig. 4. Longitudinal geological profile of Xiang’an subsea tunnel.

Table 1 the fracture develops very fast due to the stress concentration at
Properties of different rock types in the project. the tip of the fracture. The surrounding ground suffers continuous
Rock type Specific weight (kN/m3) UCS (MPa) splitting until the pressure around the fracture tip is not high
Monzonite 26 111.1
enough to split the ground any further. Meanwhile, with the
Diabase 28 77.7 development of the fracture, additional grout is required to fill the
Granite 26.1 79.3 initiated fracture, leading to an incremental increase in the grout-
Granodiorite 26.6 93.5 ing rate.

(4) Stages 4 and 5: secondary compaction grouting and secondary


the tangential direction in the ground around the borehole. The fracture grouting
maximum tensile stresses are located at two points in a cross-
section of the borehole (points a and b in Fig. 2) where the orig- When the grout flow is confined, the grouting pressure starts to
inal tangential stresses are the lowest in compression (or the increase. With the increase in the grouting pressure, the injected
highest in tension) after borehole drilling. The initiation of the grout can enlarge the width of the primary fracture. When the
fracture changes the boundary conditions abruptly owing to the grouting pressure increases to a certain value, a secondary fracture
grouting effect and the injection pressure drops dramatically. may be initiated and then filled. More secondary fractures may be
Although the grouting pressure is reduced after fracture initiation, initiated due to the subsequent grouting. The initiation location and

Fig. 5. Samples collected from a borehole in the weathered slot F1.


D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446 441

Legend

Slightly weathered
granite

Highly weathered
monzonite and diabase

Completely weathered
granite

YK8+324 YK8+460

Fig. 6. Geological profile of weathered slot F1.

propagation path of the secondary grouting fractures vary in unfavorable geological conditions. In this case, the grouting
significantly. serves as a method to strengthen the ground as well as to reduce
It should be noted that not all grouting applications necessarily the ground permeability.
consist of all the above-mentioned five stages. For example, the
permeation grouting effect in clay is very limited due to the low 3. Project overview
permeability of clay. The primary fracture and especially the sec-
ondary fracture do not always appear during a grouting process. In The Xiang’an subsea tunnel is the first subsea tunnel con-
a subsea tunnel project, multiple boreholes are drilled for grouting structed in Mainland China. It connects Xiamen Island with

Table 2
Properties of different rock types in the weathered slot F1.

Weathered zone Allowable bearing Compressive modulus Specific weight Dynamic elastic Static elastic modulus Friction angle ( )
capacity (kPa) (MPa) (kN/m3) modulus (GPa) (GPa)

Completely weathered 220 9 18 0.7 0.1 25


Highly weathered 300 10 19 2.4 1 30
Slightly weathered >4000 e 26.5 63 40 70

Fig. 7. Construction process and support parameters.


442 D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446

Xiang’an District, reducing the travel time by road from about


95 min to 15 min. This triple-tube tunnel project has two vehicular
tunnels with an excavation cross-sectional area of 170 m2 each, and
one smaller-diameter service tunnel. Each of the vehicular tunnels
serves as a three-lane one-way traffic route. The total length of each
tunnel is about 6.05 km, including a 4.2 km part under the seabed.
The lowest point is 70 m below sea level. The drill-and-blast
method was adopted for tunnel construction. The layout of this
project is shown in Fig. 3. The northernmost vehicular tunnel is
referred to as the left line and the southernmost as the right line.
The undersea tunneling of this project encountered four
weathered granite slots, naming F1, F4, F2 and F3 respectively, in
the direction from Xiamen to Xiang’an. These types of unfavorable
geological conditions could lead to sudden water inrush and were
the most challenging parts in this project. The longitudinal
geological profiles of the left and the right lines are shown in Fig. 4.
The specific weight and saturated uniaxial compressive strength
Fig. 8. CRD excavation method. (UCS) of some typical rock samples are shown in Table 1. In this

YK8+419
YK8+324 YK8+324 YK8+349 YK8+379 1000 1000 1000 1000
500

600

500
1000 750 750
A B C
(1) Grouting from the upper part in the first round. (7) Grouting from upper part in the third round.

YK8+324 YK8+349 YK8+379 YK8+419


YK8+324 YK8+349
600
500

500

(2) Excavation from the upper part in the first round. (8) Excavation of the lower part in the second round.

YK8+324 YK8+349 YK8+379 YK8+324 YK8+349 YK8+379 YK8+419


600

600

500

750 750 750 750


A B C D
(3) Grouting from the upper part in the second round. (9) Excavation of the upper part in the third round.
YK8+460
YK8+379 YK8+419 1000 1000 1000 1000
600

YK8+324 YK8+349 YK8+379


600

500

(4) Excavation of the lower part in the first round. (10) Grouting from the upper part in the fourth round.

YK8+324 YK8+349 YK8+379 YK8+379 YK8+419 YK8+460


600
600

500

500

750 750 750 750


A B C D
(5) Grouting from the lower part in the second round. (11) Excavation of the lower part in the third round.

YK8+324 YK8+349 YK8+379 YK8+379 YK8+419 YK8+460


600

600

500

(6) Excavation of the upper part in the second round. (12) Excavation of the upper part in the fourth round.

Fig. 9. Grouting and excavation process of weathered slot F1 (unit: cm).


D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446 443

paper, the grouting measures adopted for the treatment of the


weathered slot F1 along the right line are outlined.
The weathered slot F1 is located from YK8 þ 324 to YK8 þ 460
along the right line with a total length of about 136 m. It is about
1756 m away from the tunnel portal on the Xiamen side. In this
section, the overburden thickness above the tunnel crown to the
sea bed varies from 30 m to 35 m, and the sea depth ranges from
10 m to 18 m. Samples collected at various depths from the same
borehole before construction of the tunnel are shown in Fig. 5. Both
completely weathered and highly weathered granite were identi-
fied. A probe drilling method in conjunction with the tunnel
seismic prediction (TSP) method was adopted when the cutting
face of the tunnel approached the weathered slot F1 identified by
the previous geological site investigation. It was revealed that the
weathered slot F1, a bowl-shaped slot, was mainly composed of
weathered granite, weathered monzonite and weathered diabase.
These weathered rocks are classified as completely weathered,
highly weathered and slightly weathered (Fig. 6). The typical
physico-mechanical properties of different rock samples of the
weathered slot F1 are shown in Table 2.
A center cross diaphragm (CRD) sequential excavation method
was adopted for this project when the tunnel construction was
performed in the unfavorable geological conditions under sea. The
construction process and support parameters are shown in Fig. 7. A
picture of the CRD excavation method taken during construction is
shown in Fig. 8.

4. Ground grouting for subsea tunneling through the


weathered slot F1

4.1. Construction process for weathered slot F1

During tunnel construction through the weathered slot F1, the


CRD excavation method was employed. Full-face grouting was
adopted to reinforce the ground before excavation. The construc- Fig. 11. Marithan injection samples.
tion process for the weathered slot F1 along the right line consisted
of four rounds. The first two and final rounds of tunneling were
mainly performed through completely and highly weathered
granite formations. The third round was excavated through the core
(2) The second round of excavation started on 22 October 2007
of the weathered slot, where the geological conditions were much
with a total length of 30 m of rock full-face reinforced by grout-
worse. The construction process is illustrated as follows (Fig. 9):
ing. Subsequently a 25 m long tunnel was excavated and
supported.
(1) The first round of excavation started on 20 June 2007. During
(3) The third round of excavation began on 21 March 2008. At
this round, a total length of 25 m of rock was full-face reinforced by
this time, 40 m of the rock was full-face reinforced by grouting, and
grouting, and then a 20 m long tunnel was excavated and
a 35 m long tunnel was excavated and supported.
supported.

(a) Second round. (b) Third round.

Fig. 10. Layouts of grouting boreholes.


444 D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446

Table 3 grouting boreholes were drilled in the first two rounds and final
Laboratory test results of some ordinary CS grout mixes. two rounds, respectively.
Water-cement Cement-sodium Initial UCS (MPa)
ratio (in weight) silicate ratio setting 4.2. Grouting techniques used for the weathered slot F1
1 day 3 days 7 days 28 days
(C:S in volume) time (s)

0.6:1 1:0.3 11 5.8 6.7 7.4 10.2 A chemical grouting product called Marithan and a grout
1:0.5 13.3 5.5 6.5 7.3 9.7
mixture composed of ordinary Portland cement (P.O 42.5R) and
1:0.7 16.6 5.3 6.5 7 9.3
1:1 20.5 4.9 6.4 6.9 9 sodium silicate (Na2O$3SiO2, 30e45 Baume degrees) were selected
0.8:1 1:0.3 14.4 5.3 6.2 8.4 9.6 for injection when tunneling through most sections of the weath-
1:0.5 19.1 5 6.1 8.3 9.1 ered slot F1. Marithan is a two component polyurethane product,
1:0.7 23 4.8 5.9 8.1 8.5 which has high adhesive strength and outstanding mechanical
1:1 26.8 5.2 5.7 7.9 8
1:1 1:0.3 15.9 4.5 4.7 5.8 7.8
properties. It can create a bond with the rock and can remain intact
1:0.5 20.4 3.7 3.9 4.4 6.9 through the lifetime of the project. When the product is injected
1:0.7 24.4 3.1 3.6 3.9 6.7 into the ground, the low-viscosity mixture remains liquid for
1:1 31.5 2.8 3.4 3.6 6.1 several seconds and penetrates easily into the fissures, where it
1.5:1 1:0.3 25.5 2.4 3.4 3.9 5.8
expands, sets and seals the threaded zone. Some Marithan injection
1:0.5 32.7 2.3 2.9 3.5 4.5
1:0.7 38 1.8 2.5 3.3 4.4 samples obtained after excavation are shown in Fig. 11. The Portland
1:1 48.4 1.6 2.4 3.1 5.2 cement-sodium silicate grout (CS grout) is a type of dual-
component grout, which has the properties of early strength,
early setting time, low bleeding and low shrinkage. Moreover, it is
cost-effective, and its setting time is controllable. The initial setting
time and UCS of some typical CS grout mix designs are shown in
(4) The fourth round of excavation started on 18 July 2008; 41 m Table 3. Generally, the setting time of this dual-component grout
of rock was full-face reinforced by grouting, and then the weath- increases with increasing water-cement ratio and decreases when
ered slot F1 was excavated through with support. the cement-sodium silicate ratio increases. The grout strength in-
It should be noted that in the first two rounds the full-face creases rapidly at first, and then slows as time elapses. The grout
grouting was performed through the upper bench and lower strength increases with a decrease in the water-cement ratio and an
bench, respectively, where the upper bench of the tunnel was first increase in the cement-sodium silicate ratio. The optimum grout
grouted and excavated, followed by the lower bench. In order to mix design should be adaptively adjusted according to site-specific
improve the construction efficiency, grouting was only performed conditions based on the laboratory test results. During a typical
through the upper bench in the final two rounds, during which the grouting process, the CS grout was first injected into the ground
full-face ahead of the tunnel cutting face was reinforced by grouting using a double packer that is movable within a sleeve pipe known
from the upper bench first and then the ground was excavated as a tube à manchette (TAM) from the base of the borehole to the
sequentially. The layout of the grouting boreholes in the second surface. The Marithan product was injected to the end of the
round and the third round is shown in Fig. 10. A total of 237 and 216 borehole (Fig. 12). The CS grout was injected to reinforce the ground

Fig. 12. Grouting process in a borehole.


D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446 445

Fig. 14. Grouting fractures after excavation.

that the mechanical properties of the surrounding ground are


Fig. 13. Grouting effects in water sealing.
effectively improved due to grouting.
Because grouting was carried out through multiple boreholes,
the ground was fractured and the grout propagated into the
induced cracks (or the existing discontinuities were filled by
and reduce its permeability. The Marithan injection mainly served grouting). Therefore, both the integrity and stability of the sur-
to solve the water inflow problem. rounding ground were significantly improved. The potential cav-
ities during construction could be effectively controlled. Some
photographs of the grouting fractures taken after excavation are
4.3. Evaluation of grouting effects
shown in Fig. 14.

Grouting mainly serves to improve the water-tightness, strength


and stability of the surrounding ground when it is used in a subsea 5. Conclusions
tunneling project. These three effects are extremely important in
guaranteeing the safety of the tunnel construction. The grouting This paper presents a case study to illustrate the grouting
effects of the Xiang’an subsea tunneling through the weathered slot techniques adopted in the Xiang’an subsea tunnel construction in
F1 are elaborated below. China. First, a conceptual model of grouting is proposed to intro-
A total of 22 inspection boreholes were drilled after the third duce the five stages of a typical grouting process, i.e. backfill and
round of grouting was performed in the weathered slot F1. These permeation grouting, compaction grouting, primary fracture
boreholes were mainly used to determine water inflow after grouting, secondary compaction grouting, and secondary fracture
grouting, two of which were also selected to provide core samples. grouting. Then, the grouting techniques that were used during the
Due to the grouting reinforcement, the maximum water inflow construction of the Xiang’an subsea tunnel in highly weathered
from a single borehole was reduced from 50 m3/h before grouting rock under the seabed are introduced. A cement grouting was used
to 0.6 m3/h after grouting (Fig. 13). The subsequent tunneling could to reinforce and seal the rock, and the permeability was further
then be performed under dry or low leakage conditions. reduced by Marithan injection. This reinforcement technique
Some representative mechanical properties of the rock samples significantly reduced the permeability, strengthened the ground
obtained before and after grouting are shown in Table 4. We can see and guaranteed stability of the excavation. It is noted that due to

Table 4
Properties of rock samples before and after grouting.

Sample Moisture content (%) Wet density (g/cm3) Compressibility (MPa1) Compressive modulus (MPa) Friction angle ( ) Cohesion (kPa)

Before grouting 24.3 1.84 0.47 3.7 21.6 43.3


After grouting 10e20 2.13 0.3 4.9 22 51.3
446 D. Zhang et al. / Journal of Rock Mechanics and Geotechnical Engineering 6 (2014) 438e446

the inherent uncertainties of the geotechnical and geological con- Gothäll R, Stille H. Fracture dilation during grouting. Tunnelling and Underground
Space Technology 2009;24(2):126e35.
ditions and the complex interactions between the ground and
Nonveiller E. Grouting theory and practice. Zagreb, Yugoslavia: Elsevier; 1989.
grouting material, the grouting parameters (e.g. grouting pressure, Palmström A. Problems during construction of the Vardö tunnel e a 2.6 km long
grouting material, and the amount of grouting) employed during submarine road tunnel. In: Proceedings of the 4th International Congress of
construction were mainly determined from field tests. Some International Association for Engineering Geology and the Environment, New
Delhi; 1982. p. 231e44.
further studies should be performed to facilitate the determination Palmström A. The challenge of subsea tunnelling. Tunnelling and Underground
of the grouting parameters. Space Technology 1994;9(2):145e50.
Soga K, Au SKA, Jafari MR, Bolton MD. Laboratory investigation of multiple grout
injections into clay. Geotechnique 2004;54(2):81e90.
Conflict of interest Wang SY, Chan D, Lam KC. Effect of lateral earth pressure coefficient on pressure
controlled compaction grouting in triaxial condition. Soils and Foundations
The authors wish to confirm that there are no known conflicts of 2010;50(3):441e5.
interest associated with this publication and there has been no
significant financial support for this work that could have influ-
enced its outcome.

Dingli Zhang obtained the Bachelor degree and M.Sc.


Acknowledgments degree from Shandong University of Science and Tech-
nology in 1985 and 1988, respectively; and his Ph.D. in
The authors gratefully acknowledge the financial support given Mining Engineering at the China University of Mining and
Technology in 1995. After that he got the post doctoral title
by the State Key Program of National Natural Science of China
on Mining Engineering at the same university in 1998. In
(Grant No. 51134001) and the Fundamental Research Funds for the 2004, he got an Associate Professor position in the China
Central Universities of China (Grant No. 2012JBM081). University of Mining and Technology. He is now a Professor
and the Head in School of Civil Engineering in Beijing
Jiaotong University. He has worked with large engineering
References firms dedicated to tunnel services and design. His research
interests cover risk management for urban tunnel projects,
Anderson G, Roskrow B. The channel tunnel story. Boca Raton, FL: CRC Press; 2003. structural analysis of rock-support interaction, and subsea
Berggren L. The Oslofjord subsea tunnel, a case record. In: Proceedings of the In- tunnel related topics. He is the chief scientist of National
ternational Symposium on Ground Freezing and Frost Action in Soils. Louvain- Key Basic Research Development Program (also known as
La-Neuve, Belgium: A.A. Balkema; 2000. p. 267e72. “973 Program”) and the head of High Technology Research
Chen T, Zhang D, Zeng C, Ying G. Application of new concept waterproofing in and Development Program (also known as “863 Program”).
Xiang’an undersea tunnel, China. China Ocean Engineering 2013;27(1):121e30. He has published over 100 academic papers and is the
Essler R, Drooff E, Falk E. Compensation grouting: concept, theory and practice. In: author of four monographs and four textbooks. He has
Advances in grouting and ground modification. Reston, VA: American Society of got eight national invention patents. He has been invited
Civil Engineers; 2000. p. 1e15. for more than twenty keynotes both at home and abroad.

You might also like