Professional Documents
Culture Documents
P a g e 1 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Table of Contents
1. Purpose ..................................................................................................................................................4
2. Responsibility of Parties .......................................................................................................................4
3. General Safety Information .................................................................................................................6
3.1 High pressure possible. .................................................................................................................6
3.2 Possible release of hazardous gasses. ...........................................................................................7
3.3 Electrical tests. ...............................................................................................................................7
3.4 Heavy equipment. Possible injury from lifting heavy objects. ..................................................8
3.5 Proper personal protective equipment (PPE) .............................................................................8
3.6 Pinch/cut points and hand safety .................................................................................................8
3.7 Oil containers must not be distributed to anyone outside the company ..................................8
4. Equipment Required for Install ........................................................................................................10
5. Pre-Installation....................................................................................................................................12
5.1 Offloading Procedure ..................................................................................................................12
5.2 Pre-Inspection ESP Equipment .................................................................................................13
5.2.1 ESP Preparation at onshore/ workshop .............................................................................13
5.2.2 Job preparation at operating location / rig site. ................................................................14
6. ESP Installation...................................................................................................................................15
6.1 Pre-Caution during installation .................................................................................................15
6.1.1 Taking Photograph ..............................................................................................................15
6.1.2 Well control during installation ..........................................................................................15
6.1.3 Electrical testing during installation ..................................................................................15
6.1.4 ESP Cable Splicing...............................................................................................................16
6.1.5 Annulus bleeding off ............................................................................................................16
6.2 Installation procedure .................................................................................................................17
6.2.1 ESP Installation ....................................................................................................................17
6.2.2 Cable attachment .................................................................................................................18
6.2.3 Installing Production Tubing ..............................................................................................19
6.2.4 Landing the equipment in the wellhead .............................................................................20
7. Pre-commissioning ..............................................................................................................................21
7.1 Verifying Software Update .........................................................................................................21
P a g e 2 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 3 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
1. Purpose
This document provides an overview of the preparation and installation of ESP Single and Zenith
Downhole gauge. To run the ESP Standard Completion string in a safe manner and record all data, to ensure
the ESP is set and operational as per the client requirements.
These procedures apply to all Baker Hughes Electrical Submersible pump personnel involved in the
shipping and the running of ESP tooling and equipment under customer Contract at both Baker Hughes
Electrical Submersible pump base and customer operating locations.
2. Responsibility of Parties
R: Responsible I: Informed C/S: Consultant/ Support
Assembly, RIH, Start-up and Commissioning of Well
№ PVDBakerHughes Vietsovpetro
equipped with Electrical Submersible Pumps (ESP)
P a g e 4 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 5 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
continuously after
23 Flow rate measurements I R
start up
To aid in providing a safe and productive workplace some of the known dangers associated with
this operation have been highlighted in this summary section. However, these same alerts are found
throughout the document where they apply to the operation. This section is not intended to take the place
of a QRA as the site analysis could point to additional hazards that have not been mentioned here.
hazardous agents could cause serious injury, death and/or damage equipment. Consider all potential
exposure hazards including electrical, mechanical, pressure, thermal, radiation, stored energy, and
hazardous agents.
Electrical tests shall be performed at a safe distance upwind or crosswind from the wellhead.
Possible injury of fire hazard:
i. Static discharge.
ii. Possible fire hazard.
iii. No electronic implants allowed.
Establish safe and consistent procedures to prevent injury or damage. Unexpected equipment
activation, energizing of equipment, direct contact with energy sources, or released hazardous agents could
cause serious injury, death and/or damage equipment.
Consider all potential exposure hazards, including electrical, mechanical, pressure, thermal,
radiation, stored energy, and hazardous agents.
The drive should be installed, adjusted, and serviced by qualified electrical maintenance
personnel. Improper installation or operation of the drive may cause injury to personnel or damage to
equipment. The drive must be installed and grounded in accordance with local and national electrical
codes. Potentially lethal voltages exist within the cabinet. Extreme care must be taken to ensure all power
sources are disconnected before starting installation, maintenance, and repair jobs.
The electrical disconnect has an interlock feature which will not allow it to be turned on unless the
cabinet door is closed. The technician can temporarily override this safety feature by turning the interlock
with a slot screwdriver. This allows the cabinet door to be opened while the drive continues to operate,
and power is still applied.
P a g e 7 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Safety Procedures
Work inside the cabinets should be performed with the power off. Isolate energy source(s) and use
proper Lock Out/Tag Out (LOTO) procedures and Personal Protective Equipment (PPE) to ensure
personnel safety. The drive also contains stored sources of energy in the form of capacitors. Allow
sufficient time after power is removed for those capacitors to discharge to a safe level below 50VDC. The
bleed resistors attached to the capacitors will reduce the voltage to safe levels within five minutes of
power down. Confirm removal of energy source using a proven voltage indicator device. As a Baker
Hughes procedure BH-HSE-023 Electrical safety.
i. Hard hats.
ii. Safety shoes.
iii. Safety glasses with side shields.
iv. Flame retardant clothing (FRC).
v. Safety gloves. Hot glove (For VSD Pre-commissioning)
All personal protective equipment (PPE) should be worn at all times in designated areas. Individual
well sites have special equipment requirements for PPE, and it is the field service technician’s responsibility
to be aware of these requirements prior to arriving on site.
3.7 Oil containers must not be distributed to anyone outside the company
i. It presents a possible environmental hazard.
ii. Return empties to the local service center.
iii. Do not distribute to anyone outside the company.
P a g e 8 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Empty or partially empty containers of motor oil shall not be distributed to any person or company
but shall be returned to a local service center for disposal according to local HSE regulations.
P a g e 9 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
11480004201 DSCHG PRESS SUB 2-7/8 EUE BXP FOR 1/4 4.00 0.05
P a g e 10 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Client Vietsovpetro
Block 09-1
Well 803/MSP-8
ESP Set. Angle (deg) - Prod. Casing 6.625”
ESP Set. DLS (deg/100ft) - Prod. Tubing 3-1/2”, 9.3 lb/ft, EUE
Prepare by. Pongphan J/Ngan Cao Date 19-Feb-24
CSE4594P01 DSCHG B/O PMP 400 HV 3.5X8 EUE 1040 4.50 0.07
P a g e 11 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
5. Pre-Installation
5.1 Offloading Procedure
Equipment could be shipped loose, in wooden crates or in metal shipping boxes. When offloading the
shipping box, it is essential that it be supported properly to avoid excess bending of the box which will
make it difficult and possible dangerous to open. The proper lifting method would be to use a spreader bar
of sufficient length to stabilize and support the box.
Step Description
1 From 1 ft (0.3 m)–20 ft (6 m) a single point lift can be used.
If the angled slings are chosen care must be taken to prevent the cable from slipping along the box. A
double-wrapped choker will help but the cable might still slip. Placing the connection behind one of the
box hinges will help. Protection should also be used to keep the slings from possibly being cut by the sharp
corners of the box.
Equipment Placement
When placing the equipment on location before installation the equipment should be placed as close
as possible to the well and oriented so that the top of the equipment is oriented nearest the well.
Placement of the equipment should be with the same spacing as with the lifting procedure which is 25 % of
the total length of the box from each end of the box.
P a g e 12 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Slings should be chosen that will not mar or gouge the finish of the equipment. Baker Hughes suggests a
synthetic material such as nylon or polyester to control slip and marring
P a g e 13 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
5) Check coupling fit, ensure smooth rotation of shaft. The motor heads should be slightly elevated
to maintain contact between the thrust runner and the thrust bearing.
6) Attach sensor and test the sensor reading.
5. Sensor
1) Inspect sensor housing,
2) Record nameplate details and length.
3) Remove the caps, electrical check to verify insulation resistance,
4) Sensor reading test at various temperature and pressure
6. Main cable, MLE, Taurus equipment
1) All main cable, motor lead extensions (MLE) and taurus equipment should be checked for
continuity, Insulation resistance both phase to phase and phase to ground.
2) Record the serial numbers, test certificate numbers and lengths.
3) All results need to be recorded into the cable integrity sheet.
4) The primary MLE cable will be spliced onshore to a length of main cable long enough to reach
the packer.
7. Accessories
1) banding equipment
2) cable protectors
3) workshop/tools
4) spooler
5) worktable/stovepipe
6) cable sheave
7) cable clamp
8) installation kit
9) air hoses and air gun
All equipment and tooling should be checked for operation and function tested. The spooler should
be positioned, powered up and checked for leaks. Load the cable reel. All consumables required for the
installation should be ready and not expire.
Note: See more detail in document AL-GLB-CEN-ESPS-102431_Electrical Submersible Pumping
Procedure
5.2.2 Job preparation at operating location / rig site.
i. Load all equipment to operating area. Equipment should be placed on location or cantilever deck
in such a way that it does not interfere with wellsite activities.
ii. Walk around and perform visual check of all operating area and note any discrepancies or safety
issues. Address any risk issues immediately with VSP representative. Note all other issues and
address during toolbox meeting.
Note: Carefully load equipment from supply boat up to operating area. make sure crane operator
use low speed to avoid a knock-on equipment. tag line must be attached to every equipment during loading.
iii. Lay out position for spooler in a safe condition. Take into consideration the line of cable to
minimize of all tripping and other potential hazard.
P a g e 14 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
iv. Walk around spooler if any unsafe condition. Connect power line to power supply of rig, set up
ground line and secure spooler by safety chain.
v. Prepare all tools, lifting equipment and consumable for performing installation.
vi. Lift ESP equipment out of shipping box and lay down on support. (wooden, pipe support.)
vii. Visual check equipment to ensure ESP have no damage. Confirm equipment length, OD, PN, SN
of equipment that follow ESP installation program.
viii. Fit lifting clamp to ESP. Do not over tighten the bolt to avoid distortions of head section.
Note: Before start installation, conduct toolbox talk and Job Safety Analysis to make sure everyone
understands the work and risk.
6. ESP Installation
6.1 Pre-Caution during installation
6.1.1 Taking Photograph
During ESP installation/Pulling process request hot work permit to allow taking the photograph.
6.1.2 Well control during installation
During ESP installation/pulling it is most important that well control can be achieved in a quick and
efficient manner in the case of emergency. In some situations, the use of BOP blind and shear rams may be
required, but in the less serious conditions the following procedures could be utilized:
NOTE: Cable cutters to be always readily available on the rig floor during ESP installation or
pulling.
If it becomes necessary to close the well while building up ESP:
(a) Pull units completely out of the hole if sufficient height is available, and then close the well.
Or
(b) Close annular ram around ESP unit below pump intake / gas separator.
Or
If running/pulling tubing and time allows, cut the ESP cable just above a cable clamp then run tubing
in the hole so that the cable end is below the annular. Close the annular ram around the tubing and connect
circulating head to the top of tubing to conduct well killing. After the well has been controlled, the
completion string can be pulled back to allow the cable to be spliced back on and continue as per program.
In severe cases, close the shear ram to shear the tubing and cable, and then close the well.
iii. Keep personnel not involved in the testing away from the equipment under test.
iv. Ensure non-discharged megger cables are not left unattended.
NOTE: Make sure the test leads are connected positive to ground and negative to conductor
(so as not to damage the sensor).
NOTE: To maximize the reliability of the ESP system, both packer and wellhead feed thru
should be subjected to the minimum stress. The magnitude and the rate of change of the annulus
pressure needs to be carefully monitored and controlled.
There are two main sources of pressure imbalance, both created by gas present in the annulus, either
free or in solution.
i. Diffused gas present within the cable and the feed thru materials at the wellhead itself.
ii. Diffused gas present within the cable being able to migrate towards the wellhead feed thru.
Therefore, careful control and monitoring of annular pressure is required to minimize the risk of
ESP system failure due to decompression.
For any pressure that occurs in the annulus (including pressure testing the annulus):
- The pressure should be reduced by half at a maximum rate of 50 psi/minute.
- A dwell period of 10 minutes should then follow.
- The process should then be repeated until the desired annulus pressure is achieved.
For example, an annulus pressure of 500 psi reduced to 0 psi would take 45 minutes.
P a g e 16 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Overall, the longer the duration that can be allocated to the pressure schedule, the less stress is placed
on the penetrators and cable.
P a g e 17 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
14) Place the proper bolts with washers in each bolt hole. Start each bolt to ensure that the threads are
aligned. When all bolts are started, lower the equipment onto the motor and tighten the assembly
bolts to the proper torque, as outlined in the specifications. When all bolts are properly torqued,
raise the equipment assembly and remove the lower Lifting/Assembly clamp. Store the clamp away
from the wellbore in a safe place.
15) Pick up pump receptacle assembly (Pump tandem with intake) to connect to top upper seal. Remove
the bottom shipping cap. Remove and discard the O-rings that are used for shipping. Inspect the O-
ring groves for damage and cleanliness. Install new O-rings into the groves. Ensure that the shaft
turns freely. Then follow (14)
16) Raise up the ESP string until the motor pothead reach on acceptable working. Open pothead
shipping cap and check electrical integrity. Rig up cable sheave, feed MLE with power cable
through and connect to the motor terminal.
17) Perform electrical check at the end of power cable (Electrical Spooler)
18) Service seal. Start pumping oil into the seal from the motor drain/fill valve until oil starts coming
out of the first vent hole.
19) Pump more oil into the seal again until more oil/air comes out of the vent again and pause. Continue
this process until only oil comes out of the vent.
20) Install a vent plug with a new sealing washer. Then torque the plug to the proper torque as outlined
in plug specifications. Continue this process for the additional sections of the seal assembly.
21) Lower assembly in well while continuing to attach the MLE cable to the ESP with properly MLE
clamp (Protectolizer for MLE).
22) Lower assembly until top of pump. Open shipping cap. Clean the top of pump flange. Test shaft
rotation by electrical phase rotation test at the end of power cable at electrical spooler.
23) Pick up tubing pup joint with pump discharge to connect with pump. Remove the bottom shipping
cap of pump discharge. Remove and discard the O-rings that are used for shipping. Inspect the O-
ring groves for damage and cleanliness. Install new O-rings into the groves.
24) Lower the pup joint with pump discharge onto the pump and tighten the assembly bolts to the proper
torque, as outlined in the specifications. When all bolts are properly torqued, raise the equipment
assembly remove lifting clamp.
Note:
i. See more detail in document AL-GLB-CEN-ESPS-102431_Electrical Submersible
Pumping Procedure
ii. Specific Torque value, O-ring Part number, Coupling PN refer ESP Schematic and checklist
in Preparation Report. (Appendix)
Divide the total weight of the cable by 25 lbs. (11.3 kg) and this result will be the number of evenly spaced
bands required. However, close inspection of the installed clams is required to verify they are securing the
cable properly. Placement of the band or clamp is important to allow ease of installation and removal from
the well.
Typically, it is not recommended to place a band or clamp within six feet (2 m) of the bottom of a
tubing collar. This space will allow the service unit operator room to set the tubing slips without any
interference of the cable and allows the crew to pull the cable away from the tubing slips when setting them.
Note:
Do not over-tighten the band or clamp, as it will damage the cable.
Do not under-tighten the band or clamp, as it will be loose. If the band is loose, you will need
to remove it and install a new band.
Note: Regardless of the clamping device chosen, it is very important to keep an accurate count
of the number of cable bands or clamps installed. Please log the information on the paperwork so
that when the unit is pulled, it will be obvious if any bands or clamps remain in the well.
P a g e 19 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
iv. The rig operator is required to watch and monitor closely the weight indicator during tight areas
for potential weight loss. Once the equipment is Running in Hole (RIH), periodically stop and
check the sensor readings (if installed), electrical balance and insulation value of the cable-motor.
Carefully check the banding material or cable clamps when stopping for the cable checks to ensure
that they are installed correctly and not damaging the cable.
Note that cable insulation resistance (IR) will degrade with the increased heat of installing into a
well, which is typically hotter than the surface ambient temperature. This is not a concern as long as it is a
gradual change and not an abrupt change.
A gradual change indicates that the cable is in fluid and is heating, while an abrupt change would
indicate that the cable might have been damaged during the installation.
If at any time the phase-to-phase values become unbalanced or phrase-to-ground value become 0
ohm, there is no point of installing the equipment any further as it will not run when it is set to the desired
depth. If this happens, inform the customer that there is a problem and make arrangements to remove the
equipment from the well.
Note: When ready to land pump at determined depth, stop the cable install/pulling process, clear
the area of personnel, and release the sheave cables from the mast. Carefully lower the sheave and hang the
sheave about 12-15 feet (3.6 to 4.5 m) above the rig floor using the appropriate slings, chains and clamps.
Once the sheave is secure, allow only necessary personnel into the area, cut the cable to finish install if
necessary and lower sheave to ground and remove from work area.
P a g e 20 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
7. Pre-commissioning
At this point is good to focus on safety. Keep in mind that driver will be tested in power and
current. On No Load Test and Shorted Output Test might be necessary to connect and disconnect input
jumper wires, and during arranging for shorted output test, we will have to connect and disconnect short
connection between out-put phases on driver or StepUp transformer. During this process, it is highly
recommended to verify absence on voltage before connecting input power cables to converter sections
and before connect / disconnect joint cables for outputs phases:
Note Verify No voltage condition. Always verify no voltage condition taking readings: phase to
phase voltage and phase to ground at the top of the input breaker of the driver, then at the bottom to verify
no voltage then put the meter back on the top of the breaker to verify the condition of the multimeter.
After that, always check absence of voltage across the DC Bus before testing internal components.
1.2 Software can be accessed and downloaded from BHI page. Software should be arranged in the
USB memory under a subdirectory named SW_Upgrd. Inside must be another three (3) subdirectories:
APC, AGD and ASC with the corresponding software upgrades.
1.3 Turn on the power using the main Breaker. Wait Display initialization.
1.4 Insert USB memory stick in the weatherproof USB slot in the front of the main door. Immediately,
drive will start scanning USB memory inserted, and if a later software version number than the current
operating software is founded, screen will show the Load Software Update option.
1.5 Then, pressing ENTER when Load Software Update is selected will cause to ASC to check the
external USB memory for available software update. Once the process is finished, user will need to cycle
power to the drive to cause it to load and run the new software.
3
P a g e 22 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 23 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
10. It’s important to highlight that if the process of substitution of components included the
replacement of at least one 15500 μf capacitor from one capacitor module, must be required to
carry out a process of formation of capacitors. Clamp to 500, VBoost to 0, startup the drive at 30
Hz. Increases Hz at a rate of 10Hz each 5 minutes up to 60Hz; per step check voltage DC balanced
between capacitor modules. The formation of capacitors can be considered a No Load Test.
11. Turn OFF the drive. Apply Lockout / Tag out.
12. Verify absence of voltage on DC Bus.
5
P a g e 24 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
Ensure all cables used have excellent electrical integrity and carry out full electrical test
once system is being commissioned: phase to phase continuity, 1000V insulation resistance test
and physical check will be required.
Once given all clear by Centre Control Room (CCR), the well may be started. Maintain clear
communication at all time between CCR, VSD Engineer and production team.
1. Line well up to process as normal. Open all in-line valves, i.e. master valve and wing valve. Close
swab valve.
2. Monitor pressure in CCR. Open downhole safety valve (SCSSV) by cycling three times at correct
opening pressure. Check hydraulic returns at wellhead to ensure valve is open.
3. Open the choke at minimum opening – preferably at 5%
4. Start ESP at minimum speed – 35 Hz.
5. Production tech monitors tubing pressure, flow line pressure and flow line temperature.
a. Rotation should be confirmed and verified immediately after start-up. If rotation is incorrect
shut down ESP, reverse rotation and repeat start up. ESP rotation can also be identified by
downhole parameters.
b. It is vital that when a well flows naturally, the ESP must always be started against a closed
valve (preferably the choke valve). This is to prevent the risk of a reverse start. Having
P a g e 25 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
proven forward rotation does not guarantee there is no risk of starting and ESP under flowing
conditions as the shaft could be rotating at a higher frequency than the start frequency.
c. For the wells with no data please ensure that the motor amps are increasing with frequency
and observe wellhead pressure and temperature as an indicator of good flow. If the well does
not surface fluids within the expected time frame, please shut the well down and consider
the pump rotation may be incorrect.
6. CCR monitors the process and downhole sensor reading. Adjust choke and speed to achieve target
rate.
7. Route the well into well test to confirm flow rate.
8. If any abnormal trend change is noticed, stop ESP for further analysis and troubleshooting.
P a g e 26 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
APPENDIX
Qualitative Risk Assessment (QRA)
P a g e 27 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 28 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 29 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 30 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 31 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 32 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 33 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 34 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 35 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 36 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 37 | 38
ESP Installation Procedure
Well: 802/MSP-8; 803-MSP-8
P a g e 38 | 38