Professional Documents
Culture Documents
STATUS STAMP
REMARKS
I
Project Name: Customer Document ID:
Document Title:
ILanguage:
EN
Metso:Outotec
MASTER INSTALLATION IDS
Project ID: Plant Code: Plant Unit Code: Document Type: Running Number: Revision: Sheet of Sheets:
BEC11 0
This information is confidential and proprietary to Metso Outotec Corporation or its subsidiaries (“Metso Outotec”) and is protected by Metso Outotec Document ID:
trade secret, copyright and/or other laws. It may not be accessed, used, copied or disclosed without the written consent of Metso Outotec.
All rights reserved. OU500806697
OU500806697_R0_INSPECTION DATA SHEET (IDS)_ALL TYPES.XLSX
1 of 5
Metso:Outotec Installation - Inspection Data Sheet - Single Planetary and SBD - Welded Tank
Metso
Installer Client Other* * E.g. third-party consultants
Outotec
Ensure civil works are designed and installed in Verification by civil works designer that Metso
1.2 accordance with loads stipulated in footing and load Outotec footing loading data was used for Client / installation contractor R H
plan. design.
2 Support structure
Confirm underflow cone location, orientation and Outlet nozzle orientations and RL's to be
2.1
RL is as per installation and layout drawings checked and actual measurements recorded
Installation Contractor Yes S H-
Ensure support structure (columns) top plates are Top of Column connection plate RL's to be as
2.2 Installation Contractor Yes S H-
installed at correct RL per installation drawing tolerance.
Verticality of columns to be in accordance with
2.3
tolerances stipulated in installation drawing.
Record results Installation Contractor Yes S H
-
NDT of radial beam welds to be in accordance with Quantity of NDT to be in accordance with
2.6
(insert project welding code) project specifications.
Installation Contractor S W
Confirm that all support structure bolts are of grade
2.7
stipulated in drawing
Installation Contractor S W
Ensure all bolts are tightened as per installation
2.8
drawing. Mark each bolt when tightened.
Installation Contractor S H
3 Tank
Metso:Outotec Installation - Inspection Data Sheet - Single Planetary and SBD - Welded Tank
Metso
Installer Client Other* * E.g. third-party consultants
Outotec
Record droop of each floor gore section in 3
3.1
Ensure floor gore droop is in accordance with
places. Inner, middle and outer droop Installation Contractor Yes S W
installation drawing
measurements.
Welding of floor gores to be in accordance with
3.2
installation drawing
Welding to be in accordance with AWS D1.6 Installation Contractor S W
NDT of floor gore site welds to be in accordance Quantity of NDT to be in accordance with
3.3 Installation Contractor S W
with (insert project welding code) project specifications.
Weld tank wall in accordance with installation Welding to be in accordance with applicable
3.4
drawings welding code AWS D1.6
Installation Contractor S W
NDT of tank wall site welds to be in accordance Quantity of NDT to be in accordance with
3.5
with AWS D1.6 project specifications.
Installation Contractor S W
Confirm that overflow box and nozzle
3.6 location/orientation is as per tank assembly Installation Contractor Yes S H
drawing. Record location/dimensions.
Metso
Installer Client Other* * E.g. third-party consultants
Outotec
Confirm that bridge bolts are tightened according to For confirmation of bolts being tensioned, mark
5.5 installation drawing. Mark each bolt when each bolt head when tensioning has been Installation Contractor S H
tensioned. completed.
Ensure all handrails are installed correctly, and
5.6
complete.
Refer to bridge assembly drawing, Installation Contractor S W
8 Turbodil
Ensure turbodil drive frame is installed as per
8.1
drawing
Installation Contractor S H
Metso:Outotec Installation - Inspection Data Sheet - Single Planetary and SBD - Welded Tank
Metso
Installer Client Other* * E.g. third-party consultants
Outotec
H = Hold Point: Attendance at site is mandatory and signature is required on the ITP and check sheets of the inspection at the time of the inspection or check being done to to release the work. Work cannot proceed
to the next stage without attendance/sign off of the activity. Notification period 7 working days.
S = Surveillance: Random attendance at site, no signature required on the ITP or its accompanying documentation.
W = Witness: Attendance at site is expected, the signature is required on the ITP and checklist, but if the signatory is not present to sign at the time, follow on work may proceed and the document(s) to be signed
later, after evidence of confirmation of work being satisfactorily completed. Notification of minimum 7 working days is required.
R = Review: of documents
A = Approval: of documents