You are on page 1of 68

Sewerage Code of Australia

WSA 02—2002-2.3

Melbourne Retail Water Agencies Edition


(Including City West Water, South East Water & Yarra Valley Water)

Version 1.0

Part 3: Construction

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 168

CONTENTS

11 GENERAL 173
11.1 SCOPE 173
11.2 INTERPRETATION 173
12 QUALITY 175
12.1 QUALITY ASSURANCE 175
12.1.1 General 175
12.1.2 Quality system 175
12.1.3 Project management plan 175
12.1.4 Inspection and test plans 175
12.1.5 Quality tests 176
12.1.6 Quality audits 176
12.1.7 Traceability 176
12.1.8 Quality records 176
12.1.9 Inspection 177
12.2 PERSONNEL QUALIFICATIONS 177
13 GENERAL CONSTRUCTION 178
13.1 GENERAL 178
13.2 ORDER OF CONSTRUCTION, TESTING AND COMMISSIONING 178
13.3 CONTRACT INTERFACES 178
13.4 CUSTOMER FOCUS 178
13.4.1 General 178
13.4.2 Resolution of complaints 179
13.5 PROTECTION OF PEOPLE, PROPERTY AND ENVIRONMENT 179
13.5.1 Safety of people 179
13.5.2 Protection of other services 181
13.5.3 Disused / Redundant sewers 181
13.5.4 Road reserves or other thoroughfares 182
13.5.4.1 Treatment of pavements and other surfaces 182
13.5.4.2 Traffic management 182
13.5.4.3 Cleanliness of roads, paths, accesses and drainage paths 182
13.5.4.4 Storage of products, materials and equipment 183
13.5.4.5 Obstruction of street drainage 183
MRWA 13.5.4.6 Road opening permits 183
13.5.5 Private and public properties 183
13.5.6 Protection of the environment and heritage areas 183
13.5.6.1 General 183
13.5.6.2 Collection and disposal of wastes 183
13.5.6.3 Protection of adjacent lands and vegetation 184
13.5.6.4 Control of water pollution 184
13.5.6.5 Acid sulphate and contaminated soils 186
13.5.6.6 Control of noise and atmospheric pollution 186
13.6 AFFECTED PARTY NOTIFICATIONS 186
13.7 ALTERATION OF EXISTING SERVICES 187
13.8 SURVEY MARKS 187
13.9 CONSTRUCTION TOLERANCES 187
13.10 LATENT CONDITIONS 187
14 PRODUCTS AND MATERIALS 188
14.1 AUTHORISED PRODUCTS AND MATERIALS 188
14.2 REJECTED PRODUCTS AND MATERIALS 188
14.3 TRANSPORTATION, HANDLING AND STORAGE OF PRODUCTS AND MATERIALS 188
14.3.1 General 188
14.3.2 Plastics-lined concrete products 188
14.4 DELIVERY INSPECTION OF PRODUCTS AND MATERIALS 189

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


169 WSA 02—2002-2.3

14.5 CONCRETE WORKS 189


14.5.1 Delivery 189
14.5.2 Transportation of concrete 189
14.5.3 Formwork 190
14.5.3.1 General 190
14.5.3.2 Formwork for plastics-lined concrete 190
14.5.4 Reinforcement 190
14.5.5 Placement 190
14.5.5.1 General 190
14.5.5.2 Placement in water 190
14.5.6 Slump 191
14.5.7 Compaction 191
14.5.8 Stripping 191
14.5.9 Curing 191
14.5.10 Repair of blemishes 191
14.6 SUPPLY OF WATER TO THE WORKS 192
14.7 ON-SITE STOCKPILES 192
15 EXCAVATION 193
15.1 SAFETY 193
15.2 LIMITS OF EXCAVATION 193
15.3 EXCAVATION ACROSS IMPROVED SURFACES 193
15.4 EXCAVATION IN ROOT ZONES 193
15.5 BLASTING 194
15.6 SUPPORT OF EXCAVATIONS 194
15.7 DRAINAGE AND DEWATERING 194
15.8 FOUNDATIONS AND FOUNDATION STABILISATION 195
15.9 SURPLUS EXCAVATED MATERIAL 195
16 BEDDING FOR PIPES AND MAINTENANCE STRUCTURES 196
16.1 TRENCH FLOOR PREPARATION 196
16.2 BEDDING MATERIALS 196
16.3 PLACEMENT OF BEDDING 196
16.4 SPECIAL PIPE SUPPORT FOR NON-SUPPORTIVE SOILS 196
16.5 BEDDING FOR MAINTENANCE SHAFTS AND BENDS 196
16.6 BEDDING FOR MAINTENANCE HOLES 196
MRWA 16.7 EXCESSIVE EXCAVATION 197
17 PIPE LAYING AND JOINTING 198
17.1 INSTALLATION OF PIPES 198
17.1.1 General 198
17.1.2 Cleaning, inspection and joint preparation 198
17.1.3 Polyethylene 198
17.1.4 Laying 198
17.2 HORIZONTAL AND VERTICAL DEFLECTION OF SEWERS 198
17.2.1 General 198
17.2.2 Methods of deflection 199
17.2.3 Horizontal curves 200
17.2.4 Vertical curves 200
17.2.5 Compound curves 201
17.3 HORIZONTAL AND VERTICAL SEPARATION OF CROSSING PIPELINES 201
17.4 FLOTATION CONTROL 201
17.5 TRENCH STOPS 201
17.6 BULKHEADS 201
17.7 PROPERTY CONNECTION SEWERS 201
17.8 DEAD ENDS 202
17.9 MARKING OF PROPERTY CONNECTION SEWERS AND DEAD ENDS 202
17.10 CORROSION PROTECTION OF CAST IRON 202
17.11 MARKING TAPES AND POSTS 202

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 170

17.11.1 Non-detectable marking tape 202


17.11.2 Detectable marking tape 202
MRWA 17.11.3 Marker posts 202
17.12 BORED PIPES UNDER ROADS, DRIVEWAYS AND ELSEWHERE 203
17.13 AQUEDUCTS 203
17.14 BRIDGE CROSSINGS 203
17.15 PLASTICS-LINED RC PIPE JOINTING 203
17.15.1 General 203
17.15.2 Plastics lining work protection 203
17.15.3 Field jointing 203
17.15.4 Plastics lining ancillary work 204
17.15.4.1 Alignment of lining keys 204
17.15.4.2 Provision of seepage channels 204
17.15.4.3 Use of jointing accessories and adhesives 204
17.16 WELDING OF STEEL PIPELINES 204
17.16.1 General 204
17.16.2 Field welding of flanges 204
18 MAINTENANCE HOLES (MHS) 205
18.1 GENERAL 205
18.2 MH BASE 205
18.3 TRENCH DRAINAGE AROUND MHS 205
18.4 PRECAST CONCRETE MH SYSTEMS 205
18.5 CAST IN-SITU CONCRETE MH 206
18.6 BENCHING AND CHANNELS 206
18.7 CONCRETING FOR PLASTICS-LINED WORK 206
18.7.1 Concrete work planning 206
18.7.2 Fixing of plastics lining for concrete work 206
18.7.3 Concrete placement and formwork removal 206
18.8 INTERNAL COATING OF CONCRETE MHS 207
18.9 COVERS 207
18.10 CONNECTIONS TO MHS 207
18.11 MH DROPS 207
19 MAINTENANCE SHAFTS (MS AND TMS) AND INSPECTION SHAFTS (IS) 208
19.1 GENERAL 208
19.2 SEALING CAPS 208
19.3 COVERS 208
19.4 CONNECTIONS TO MSS AND TMSS 208
20 PIPE EMBEDMENT AND SUPPORT 209
20.1 GENERAL 209
20.2 EMBEDMENT MATERIALS 209
20.3 COMPACTION OF EMBEDMENT 209
20.3.1 Methods 209
20.3.2 Compaction trials / Pre-qualification of embedment compaction method 210
20.3.2.1 General 210
20.3.2.2 Test method 210
20.3.2.3 Interpretation and applicability 210
20.3.3 Compaction control 210
20.4 SPECIAL BEDDING AND EMBEDMENTS / GEOTEXTILE SURROUND AND PILLOW 210
20.5 REMOVAL OF TRENCH SUPPORTS 210
20.6 CONCRETE EMBEDMENT AND ENCASEMENT 210
21 FILL 212
21.1 TRENCH FILL 212
21.1.1 General 212
21.1.2 Material requirements 212
21.1.3 Compaction of trench fill 212
21.2 EMBANKMENT FILL 213

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


171 WSA 02—2002-2.3

21.3 DRIVES AND TUNNEL FILL 213


22 ACCEPTANCE TESTING 214
22.1 GENERAL 214
22.2 VISUAL INSPECTION—ABOVE-GROUND 215
22.3 COMPACTION TESTING 215
22.3.1 General 215
22.3.2 Minimum compaction 215
22.3.3 Embedment compaction testing 215
22.3.3.1 Applicable pipe sizes 215
22.3.3.2 Frequency and location of embedment tests 215
22.3.3.3 Retesting 215
22.3.4 Trench fill compaction testing 216
22.3.4.1 Trafficable Test Zone 216
22.3.4.2 Non-trafficable test zone 216
22.3.4.3 Test method 216
22.3.4.4 Frequency and location of tests 216
22.3.4.5 Retesting 216
22.3.5 Other fill compaction testing 216
22.3.5.1 General 217
22.3.5.2 Trafficable test zone 217
22.3.5.3 Non-trafficable test zone 217
22.3.5.4 Frequency and location of tests 217
22.3.5.5 Retesting 217
22.4 AIR PRESSURE AND VACUUM TESTING OF SEWERS 217
22.4.1 General 217
22.4.2 Air testing methods for sewers 217
22.4.2.1 Vacuum testing 217
22.4.2.2 Low pressure air testing 218
22.4.3 Testing of sewers >DN 1500 219
22.4.3.1 General 219
22.4.3.2 Method of test 219
22.4.4 Testing of concrete MHs 220
22.4.4.1 General 220
22.4.4.2 Test method 220
22.5 INFILTRATION TESTING 221
22.6 DEFLECTION (OVALITY) TESTING OF FLEXIBLE SEWERS 221
22.6.1 General 221
22.6.2 Ovality proving tools 222
22.6.3 Flexible sewers ≤DN 300 222
22.6.4 Flexible sewers >DN 300 222
22.6.4.1 General 222
22.6.4.2 Flexible sewers >DN 300 and <DN 750 223
22.6.4.3 Flexible sewers ≥DN 750 223
22.7 CCTV INSPECTION 223
22.8 INSPECTION AND TESTING OF PLASTIC LINED CONCRETE SEWERS AND MHS 224
22.8.1 Visual inspection 224
22.8.2 Spark testing 224
22.8.3 Locking key pull-out tests 224
MRWA 22.8.4 Digital coating thickness gauge 225
22.9 PRESSURE TESTING OF INVERTED SYPHONS 225
22.9.1 General 225
22.9.2 System test pressure 225
22.9.3 Maximum allowable loss 225
22.9.4 Test procedure 225
22.9.5 Satisfactory pressure test 226
22.9.6 Failure of test 226
MRWA 22.9.7 Rectification of faults 226

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 172

23 TOLERANCES ON AS-CONSTRUCTED WORK 227


23.1 HORIZONTAL TOLERANCES 227
23.1.1 Sewers and on-line structures (e.g. MHs, MSs, TMSs, ISs or vents) 227
23.1.2 Property connection sewers 227
23.2 VERTICAL TOLERANCES 227
23.2.1 Sewers and structures 227
23.2.2 Property connection risers and inspection openings 227
23.2.3 Grade 227
23.2.4 Verticality (“plumb”) 228
23.3 TOLERANCES ON FINISHED SURFACE STRUCTURES AND FITTINGS 228
23.4 CAST IN-SITU CONCRETE STRUCTURES AND SLABS 228
24 CONNECTION TO EXISTING SEWERS 229
25 RESTORATION 230
25.1 GENERAL 230
25.2 PAVEMENTS 230
25.3 LAWNS 230
25.4 GRASSED AREAS 231
25.5 BUSHLAND 231
25.6 PROVISION FOR SETTLEMENT 231
25.7 MAINTENANCE OF RESTORED SURFACES 231
26 WORK AS CONSTRUCTED DETAILS 232
APPENDIX G OVALITY TESTING OF PVC AND GRP GRAVITY SEWERS DEFAULT
PROVER DIAMETERS 233
G1 GENERAL 233
G2 DEFAULT PROVER DIAMETERS 233

TABLES
TABLE 17.1 METHODS OF ACHIEVING CURVED SEWERS 199
TABLE 20.1 MAXIMUM PARTICLE SIZE 209
TABLE 22.1 EMBEDMENT OF FLEXIBLE PIPES MINIMUM COMPACTION 216
TABLE 22.2 EMBEDMENT OF RIGID PIPES MINIMUM COMPACTION 216
TABLE 22.3 TRENCH / EMBANKMENT FILL OF RIGID AND FLEXIBLE PIPES AND
MAINTENANCE STRUCTURES – MINIMUM COMPACTION (NOT
USED BY MRWA)
TABLE 22.4 PRESSURE AND VACUUM AIR TESTING ACCEPTANCE TIMES FOR 218
7 KPA PRESSURE CHANGE
TABLE 22.5 CONCRETE MH TESTING FREQUENCY 220
TABLE 22.6 MINIMUM TEST TIMES FOR CONCRETE MHs 220
TABLE 22.7 MAXIMUM ALLOWABLE SHORT-TERM PIPE DEFLECTIONS 222
TABLE 23.1 SEWER GRADE TOLERANCES 228
TABLE 23.2 PROPERTY CONNECTION SEWER GRADE TOLERANCES 228
TABLE G1 PROVER OUTSIDE DIAMETER FOR PVC AND GRP PIPES 233

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


173 WSA 02—2002-2.3

11 GENERAL
11.1 SCOPE
This Part of the Code details default requirements for the construction of gravity sewers
including maintenance and inspection structures.
This document should be read in conjunction with development agreements, specific
project contract documents, general conditions of contract e.g. AS 2124 and other
documents nominated by the Water Agency.
11.2 INTERPRETATION
Unless specifically stated otherwise, construction of the sewers includes all functions
described in this Part and the provision of any minor materials and services that are not
described but are reasonably necessary to produce a fully functional sewerage system.
For the purposes of this Part, except where otherwise shown:
"Authorised" means acceptable to, authorised by or approved by the Water Agency
or Owner or Regulator.
“Constructor” means the individual, corporation or legal entity including any
contractors and sub-contractors that is accountable at law for delivery of Works under
a specific contract or development agreement.
“Design Drawings” means plans, elevations and drawings required for the
construction of the sewerage systems and showing the locality including roads and
sewer details, the site plan including lots, boundaries, roads, proposed and existing
sewers, proposed property connection sewers, pumping stations, pressure mains,
water mains, drains, watercourses, site contours, proposed aqueducts, proposed
boreholes, a longitudinal section, construction details and a connection to existing
sewer schedule. Supplementary information may include proposed buildings, existing
services, and groundwater and watercourse levels.
The Designer may nominate Standard Drawings or parts thereof as Design Drawings
for the purposes of the project.
“Improvements” are deemed to include but not be limited to pavements, shrubs,
gardens, retaining walls, fences and all other structures.
"Owner” means the Agency, Authority, Board, Company, Controlling Authority,
Corporation, Council, Department, Individual, Regulator, Utility or other legal entity
who is the owner of the asset and/or who has responsibility for the asset.
“Part” means the Sewerage Code of Australia, Part 3: Construction.
“Purchase Specification” means the WSAA Purchase Specification detailing the
requirements for the supply of a product or material (Refer www.wsaa.asn.au) .
“Regulator” means a Regulator who has the power to enforce Regulations related to
the activities and responsibilities of a Commonwealth, State, Territory or Local
government. It applies to environmental management and protection, occupational
health and safety and the like.
"Specification" means the Specification detailing the work involved in the particular
project in hand.
“Specified” means as specified in the Specification, Design Drawings, Purchase
Specifications and/or by the Superintendent.
“Standard Drawings” means the Sewerage Code of Australia, Part 4: Standard
Drawings and any MRWA variations and additional drawings.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 174

“Superintendent” means the individual appointed by the contract principal as an


independent arbiter of contract directions, issues, claims and variations.
“Tester” means an individual, corporation or legal entity registered by the National
Association of Testing Authorities for the relevant classes of tests and that is
accountable at law for delivery of testing services under a specific contract with the
Constructor.
“Water Agency” means an authority, board, business, corporation, council or local
government body with the responsibility for planning or defining planning
requirements, for defining and authorising design requirements, for defining and
authorising construction requirements and for operating and maintaining or defining
operation and maintenance requirements for a water supply and/or sewerage system
or systems.
“Works” means all those Works being sewers, maintenance structures, pumping
stations, pressure mains and accessories and shall include valve chambers and
storage facilities as shown on the Design Drawings and includes any part or parts of
the Works.
Specific requirements, including those in the Specification and Design Drawings, shall take
precedence over general requirements.
Headings are for the convenience of the reader and shall not be used in the interpretation
of this Part. Italicised text is advisory and has been included to assist the reader to better
understand some requirements. It is strongly recommended that the reader consult the
Standard Drawing Commentaries in Part 4 of this Code.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


175 WSA 02—2002-2.3

12 QUALITY
12.1 QUALITY ASSURANCE
The Water Agency is responsible for specifying quality assurance of construction activities
and personnel qualifications. Unless otherwise specified, the requirements of this section
apply.
The Constructor is required to have and maintain a Management System that is third party
accredited to elements of the following:
• ISO 9000 Series Quality
• ISO 14000 Series Environment
• AS 4801 Safety
An acceptable management system that is deemed to meet the requirements of this clause
is the Civil Contractors’ Federation Integrated Management System (IMS), provided that
the system is third party accredited and maintained by the Constructor.
12.1.1 General
The Constructor shall comply with all requirements of the Civil Contractors Federation
(CCF) Civil Construction Management Code or Water Agency authorised equivalent
system. The quality management system shall address the more pertinent elements of
quality assurance (ISO 9001), health and safety issues (AS/NZS 4801) and environmental
requirements (ISO 14001). These elements are incorporated within the Civil Construction
Management Code and shall be addressed within the management system documentation.
The Constructor shall provide evidence of its certification to the CCF Code (or equivalent)
prior to the commencement of any work.
12.1.2 Quality system
The Constructor shall plan, establish, document and maintain a quality system that
conforms to the requirements of the contract and shall provide the Superintendent with
access to the Constructor's quality systems for monitoring and quality auditing. The quality
system proposed by the Constructor shall be used as an aid to achieve compliance with
the requirements of the contract and to document such compliance.
If the Constructor discovers material or work that is not in accordance with the contract, the
Constructor shall promptly initiate the non-conformance procedure required by the quality
system. If the Constructor proposes a disposition of any non-conforming materials or work
which is at variance with the requirements of the contract, the proposal shall be submitted
in writing to the Superintendent whose decision on the proposal shall be obtained in writing
before the non-conforming material or work is covered up and/or incorporated into the
Works, or is the subject of any other disposition.
12.1.3 Project management plan
The Constructor shall conform to the policies and procedures stated in the project
management plan submitted to the Superintendent prior to the commencement of works.
12.1.4 Inspection and test plans
The Constructor shall submit inspection and test plans (ITPs) to the Superintendent for
verification before commencing work on activities covered by the project quality plan. The
ITPs shall include where applicable, observations, measurements or tests at the
Constructor's facilities.
Model ITPs for construction of reticulation sewers will be available at www.wsaa.asn.au.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 176

12.1.5 Quality tests


The Constructor shall be responsible for the quality of all products, processes and services
under the contract, and unless otherwise specified, shall provide all tests required to
demonstrate conformance of all products, processes and services to the technical
requirements of the contract.
In accordance with the specifications, some of the laboratory tests and field tests
undertaken by the Constructor shall be performed by a Tester currently registered with the
National Association of Testing Authorities (NATA) or equivalent authority for the class of
tests being undertaken e.g. compaction.
12.1.6 Quality audits
The Superintendent may nominate selected times and hold points at which quality
compliance audits may be conducted within the contract period.
Upon request, the Superintendent shall be given access in conjunction with or through the
Constructor, to carry out quality audits, reviews or surveillance or to ascertain the
effectiveness of the quality system put in place by the Constructor.
The Superintendent shall be entitled to carry out the second or third party audits of the
Constructor's quality system by:
(a) reviewing of the Constructor's conformance to the project management plan; and
(b) reviewing and verifying of the Constructor's quality procedures and work instructions
and documentary evidence of compliance with technical requirements of the contract.
12.1.7 Traceability
The Constructor shall maintain records clearly identifying the source of materials and
equipment, the supplier’s declaration of conformity, the design drawings used for the
construction of the works and all test results. These shall be stored and maintained in
accordance with Clause 12.1.8.
12.1.8 Quality records
Quality records shall be stored and maintained such that they are readily retrievable in
facilities that provide a suitable environment to minimise deterioration or damage, and to
prevent loss. Quality records shall be available for evaluation by the Superintendent and
the Water Agency during the period of the Contract and shall include all pertinent
Constructor and third party records.
The Constructor shall retain quality records for seven (7) years from the date of practical
completion of the Works.
The Constructor shall maintain records in two categories:
(a) Test records, which shall comprise all working sheets and summaries associated with
testing in accordance with the Inspection and Test Plans.
(b) Project quality records, which shall include, but not be limited to site meeting
minutes, technical reviews, minutes of meetings between Superintendent and
Constructor and other relevant documentation.
The Constructor shall submit to the Superintendent quality records as evidence that the
work has complied with the specified quality requirements. If unsatisfactory, the records
shall be submitted within twenty-four (24) hours of creation or receipt, and within seven (7)
days of creation or receipt if satisfactory.
Within three (3) months of the date of practical completion the Constructor shall make
available a register of all quality records required to be held under the contract. The
Constructor shall supply copies of all quality records or parts thereof as required by the
Superintendent.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


177 WSA 02—2002-2.3

12.1.9 Inspection
The Superintendent and Water Agency shall be given access in conjunction with or through
the Constructor to all laboratories and other facilities used for quality control tests to verify
that specified requirements are being met.
12.2 PERSONNEL QUALIFICATIONS
The handling, laying, jointing, trench filling and testing of all sewers, construction and
testing of associated structures and installation of appurtenances shall be carried out, and
supervised by, acceptably qualified and/or accredited personnel.
Personnel shall hold minimum qualifications or specialist accreditation appropriate for the
work undertaken. Depending on the personnel, minimum qualifications or specialist
training appropriate for the work undertaken may include current accreditation in such
things as:
• Pipe laying and jointing, e.g. Plastec, Polytec
• Plant and equipment
• Lifting equipment
• No Go Zone
• Traffic management
• Confined space entry
• OH&S
• Customer service
• Site safety induction
• Trench safety
• Handling, transportation and disposal of waste asbestos and other prescribed waste
material
Minimum qualifications shall mean Statements of Attainment for all those Units of
Competence, nominated by the Water Agency, from the Water Industry National Training
Package NWP01 or Local Government Training Package LGA00 or the Civil Construction
Training Package BCC98 or other relevant Training or a combination of one or more of the
aforementioned.
Specialist accreditation shall mean a qualification achieved through specialised training
and assessment for a specific product and/or situation that is not covered by relevant
Training Packages.
Qualifications from Training Packages shall be awarded by a registered training
organisation.
Training and assessment for specialist accreditation shall be provided by registered
training organisations or recognised organisations with appropriately qualified and
experienced trainers and assessors.
Registered training organisations shall be those listed by the National Training Information
Service for the provision of training or assessment services as required.
Training packages, together with relevant short training courses and training/assessment
service providers are provided by the National Training Information Service at
www.ntis.gov.au.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 178

13 GENERAL CONSTRUCTION
13.1 GENERAL
Construct the sewerage works to the lines, levels, grades and in the locations using the
materials and methods as specified.
If insufficient detail or instruction is provided in the Design Drawings or Specification,
obtain instruction from the Superintendent prior to commencement.
Use only the types, materials, sizes, lengths, classes, jointing methods and corrosion
protection systems for the pipes, fittings and maintenance structures as specified. Use only
manufacturers products and product range authorised by the Water Agency.
Keep on site at all times a current copy of the WSAA Sewerage Code – MRWA Edition,
Project Specification, all relevant and current Design Drawings, Standard Drawings and the
Water Agency’s manual or catalogue or listing of authorised products and materials.
13.2 ORDER OF CONSTRUCTION, TESTING AND COMMISSIONING
Undertake and complete all Works in accordance with the following process:
(a) Except where connection to a live sewer is required, start construction from the
furthest downstream point. Otherwise, start construction at a point clear of the live
sewer as specified by the Water Agency.
(b) Install all Works in accordance with the Design Drawings and the Specification,
progressively working upstream.
(c) Clean sewer(s) by flushing. Flushing water is to be disposed of in accordance with
EPA requirements and is not to be discharged to the sewer. The sewer is to be
plugged and flushing water pumped out.
(d) Conduct acceptance testing.
(e) Connect to the live sewer after all other Works have been constructed as specified.
13.3 CONTRACT INTERFACES
The Contract Interfaces shall be as indicated on the Design Drawings and/or Specification.
If in doubt, obtain clarification from the Superintendent. Where the Constructor is required
to connect or fit to existing infrastructure provided by Water Agency and/or any other
Agency, check all relevant measurements on site, notwithstanding the dimensions shown
on the Design Drawings, and adjust work to fit as required. The Constructor shall not be
entitled to any claim for loss or damage directly or indirectly due to its failure to take such
measurements.
13.4 CUSTOMER FOCUS
13.4.1 General
Ensure that the execution of the Works complies with the Water Agency's "Requirements
for customer service”.
Fully brief all affected customers and property owners about the impact of the Works on
buildings, garden features, trees and vegetation, noise levels, out of hours work, traffic
restrictions, etc before commencing work.
Keep documented evidence of contact details with all affected customers.
It is the aim of the Water Agency to achieve a high level of customer understanding and
co-operation in the construction process resulting in high satisfaction levels.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


179 WSA 02—2002-2.3

13.4.2 Resolution of complaints


Establish a single point of contact for all customer queries and complaints relating to the
Works being executed.
Resolve enquiries and complaints promptly, sensitively and in accordance with the Water
Agency’s “Requirements for customer service”.
Keep the Superintendent informed and fully briefed of any contentious issues raised about
the Works.
The Water Agencies require resolution of complaints in a quick and sensitive manner. The
Constructor shall:
• contact the complainant within four (4) hours of receiving the complaint to advise the
timeframe for resolution;
• maintain contact with any complainant to ensure they are fully aware of the proposed
actions and the timeframe for resolution;
• notify the Superintendent in writing, giving the reasons and the expected date of
resolution, where a complaint cannot be resolved within 24 hours;
• set up and maintain an effective method of registering and monitoring customer
complaints, to be known as the Complaints Log, to ensure that complaints are not
forgotten, and resolved within the required timeframe.
13.5 PROTECTION OF PEOPLE, PROPERTY AND ENVIRONMENT
13.5.1 Safety of people
Protect the safety of all employees and people on or adjacent to the Works in accordance
with the relevant legislation, statutory requirements, regulations and codes of practice.
All people on the site shall have completed the relevant site induction program and wear
the certified safety apparel including helmets, vests, boots, ear and eye protection.
Conduct a hazard survey to identify potential hazards during construction.
Comply with the requirements of the Office of the Chief Electrical Inspector and any
relevant power authority when operating near overhead power lines.
Store or leave unattended equipment, tools and materials in a condition that minimises
hazards.
Adhere at all times to the OH&S requirements of the Water Agency.
Ensure all employees are suitably trained in OH&S compliance.
The Constructor shall comply with all explicit and implied requirements of any relevant
Acts, including the Occupational Health and Safety Act and the Health Act, any regulations,
local laws and by-laws and codes of practice or standards issued by Federal or State
Government agencies.
Prior to commencing works, the Constructor shall prepare and submit a Safety Assurance
Plan, a Job Safety Analysis, an Environmental Plan and, where appropriate, a Traffic
Management Plan.
Safety Assurance Plan:
(a) The Constructor shall establish, implement and maintain documented procedures for
hazard identification, hazard/risk assessment, control of hazards/risks of activities,
products and services (including activities, products or services of subcontractors and
suppliers) which the Constructor shall use in executing the Works. These procedures
shall be incorporated in the Constructor’s Project Safety Management Plan (SMP).

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 180

The procedures must ensure that work site safety is maintained in accordance with
the Occupational Health and Safety Act, relevant legislation, regulations and codes of
practice.
(b) The Constructor shall ensure that employees engaged in tasks are trained in the Safe
Working Procedure/s for that task, and that the procedures are complied with at all
times. The Constructor shall provide evidence of training to the Superintendent and
the Water Agency as required.
(c) The SMP shall also include procedures for:
(i) Induction and training of all personnel who will be working on the site (including,
but not limited to employees of the Contractor, any subcontractors, and
suppliers).
(ii) Nomination of OHS committee representatives.
(iii) Method/frequency of conducting OHS meetings.
(iv) Accident and Emergency procedures, complete with emergency telephone
numbers.
(v) Investigation and reporting of all incidents involving death, injury or a near-miss.
Job Safety Analysis (JSA)
(a) The Constructor shall prepare a Job Safety Analysis for the Works. The JSA must be
accepted by the Superintendent before the Works may commence.
(b) The primary objectives of the JSA are to:
(i) Identify hazards associated with Works’ activities and tasks.
(ii) Establish appropriate risk control measures.
(iii) Nominate the person responsible for implementing the control
measures.
(c) The JSA shall be site specific. All workers shall be included in the development of
the JSA.
(d) The JSA shall be prepared in a tabular format and to a level of detail acceptable to
the Superintendent. Typical hazards to be considered may include, but are not
limited to:
(i) Temporary electrical supplies, power leads.
(ii) Lasers.
(iii) Untidy work sites.
(iv) Trench / tunnel support.
(v) Excavation.
(vi) Work in confined spaces.
(vii) Plant/equipment operation and maintenance (includes covers, winches,
pressure vessels, excavations, etc).
(viii) Traffic management.
(ix) Noise.
(x) Hazardous materials.
(xi) Lifting and slinging.
(xii) Public safety.
(xiii) Underground/overhead assets.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


181 WSA 02—2002-2.3

(xiv) Disposal of contaminated waste.


(xv) Environmental hazards.
(xvi) Prevention of falls.
(e) If work techniques change during the course of the Works, the Constructor must
amend the JSA to accommodate the changed conditions/situations, then submit it to
the Superintendent for approval.
13.5.2 Protection of other services
Prior to excavation, contact Dial Before You Dig by telephone 1100 or facsimile
1300 652 077 to determine or reconfirm the location of underground services.
Implement special precautions where excavations are to be undertaken near any other
services including petroleum pipelines, gas pipelines, overhead and buried electricity and
communication cables, drains, sewers and water mains. For these assets and any other
services:
(a) Comply with the notification requirements and construction conditions as specified.
(b) Ensure plans for other services are on site.
(c) As appropriate for critical services, arrange for a representative from the service
Owner to be present, unless the service Owner directs otherwise.
(d) Adopt an appropriate method for exposing and protecting the service from damage if
the service is to be exposed.
Industry practice is generally to hand dig and locate underground services prior to
machine digging. Alternatively, location by vacuum potholing may provide a more
efficient and safer means in congested pipe corridors.
(e) Prove the location of all underground services e.g. by potholing.
(f) Take special care to ensure that other services are protected in accordance with the
conditions specified by the service Owner.
(g) Arrange for isolation and subsequent restoration of any service that needs to be
removed from service while the Works are in progress.
(h) Immediately notify the owner or responsible authority of any damage or interference
to any service, structure or property.
If a service is damaged during construction, arrange or perform repair to the
satisfaction of the Owner. Obtain from the Owner, a certificate stating that the repair
has been carried out to their satisfaction.
If the Owner cannot be located within a reasonable time, report the damage to the
Superintendent, and arrange or perform repair to an approved standard. Do not
backfill, cover up or make the repair inaccessible prior to obtaining authorisation from
the Superintendent.
(i) Notify the Superintendent of any interference to the Works caused by an existing
service and the proposed action.
13.5.3 Disused / Redundant sewers
Unless otherwise agreed to by the Water Agency, surface fittings, e.g. maintenance holes
and inspection shafts shall be broken down a minimum of 1 m below surface and filled with
Class A material or an approved grout. Sewer pipes to be abandoned are to be grouted.
The grout shall be a lime-cement slurry consisting of six parts cement to one part lime.
“Flowable Fill” e.g. Liquidfill or Levelfill, possibly with the addition of a plasticiser to aid flow
is an acceptable alternative to grout.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 182

13.5.4 Road reserves or other thoroughfares


13.5.4.1 Treatment of pavements and other surfaces
Any pavement or surface of any road, driveway, footway, nature strip, median strip,
kerbing, channelling or any other thoroughfare disturbed as a result of the Works, shall be:
(a) Continuously maintained as far as practicable, for the duration of the Works.
(b) Restored to its original surface and material condition and to the satisfaction of the
Owner.
Restore the surface of unpaved streets before they are reopened to traffic.
Restore the surface of any excavation in a sealed road, footway or other pavement or
provide a temporary bituminous seal before being reopening it to the public.
13.5.4.2 Traffic management
The Constructor is required to consult with the relevant road authority, ie VicRoads or
Council, to determine if the road authority requires a formal Traffic Management Plan.
Some instances where a road authority approved Traffic Management Plan will be required
include works in the vicinity of roads controlled by VicRoads, other main roads, tram
tracks, railway lines, bus lines, shopping centres and where detour or road closure is
required.
The plan shall detail the access requirements for all developed properties, and outline
specific proposals for continued access to these properties. Traffic management plans
shall be designed and supervised by persons accredited to an approved national course.
The plan shall include names and accreditation details of the Designer and supervisor.
Construction within any public road will generally not be permitted until the traffic
management plan has been authorised by the relevant road Owner.
Manage traffic in accordance with the requirements and guidelines set out in the VicRoads
Signing Code of Practice, which incorporates and enhances AS 1742.3 Manual of Traffic
Control Devices of Works on Roads.
Ensure all personnel working on or adjacent to roadways wear safety vests and are
suitably trained and certified.
As a guide, the following traffic management practices may be considered:
(a) Provide a flagman, temporary traffic lights and/or protection by hurdles, barricades or
safety cones where traffic is restricted or roads closed.
(b) Place detour and warning signs or devices on the hurdles or barricades, in
accordance with the responsible road authority signage code of practice.
(c) As appropriate, notify the relevant road Owner, traffic authority, police, fire services,
ambulance services, bus companies, and any other service whose operations may be
affected by the change to the regular traffic flow pattern in the vicinity of the Works.
(d) Provide an alternative means of access to all rights of way, buildings and property
where the Works disrupt access.
(e) Ensure that pedestrians are kept clear of the work area and are provided with safe
alternative means of passing the Works.
(f) Complete any work involving the opening of street pavements without delay.
(g) Maintain signage.
13.5.4.3 Cleanliness of roads, paths, accesses and drainage paths
Keep the surface of all roads, footways, drainage paths and any access through public and
private lands clear of any build-up of debris such as clay, sand and the like, resulting from

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


183 WSA 02—2002-2.3

plant used on the site. Ensure the exterior of all machinery and plant working on or
crossing roadways is free of all construction debris in accordance with relevant regulation.
13.5.4.4 Storage of products, materials and equipment
Store all products, materials, equipment, packaging materials and excavated material in
accordance with the requirements of Clause 14.7.
13.5.4.5 Obstruction of street drainage
Protect all drains, channels or gutters from any obstruction using silt traps, sediment
control and other means as appropriate in accordance with EPA requirements (Refer
Clause 13.5.6.4).
MRWA 13.5.4.6 Road opening permits
The Constructor is required to obtain a Road Opening Permit from council prior to
commencement of any works within a road or road reserve.
13.5.5 Private and public properties
Where work is carried out in private property or lands owned by Councils or other
authorities, whether in an easement, reserve or otherwise:
(a) Generally access requirements are negotiated as part of the design process. The
Constructor is responsible for compliance with any agreed access arrangements
necessary to actually construct the works through private or public land.
(b) As far as practicable confine operations to easements or reserves. If there are no
easements or reserves, or the area of the easement or reserve is inadequate, confine
operations to an area agreed upon with the Owner.
(c) Comply with the Water Agency requirements for resolution of any dispute associated
with access or entry rights to the Works.
(d) Minimise damage to existing vegetation and improvements.
(e) Obtain the Owner's written permission for storage of materials, equipment or
excavated material for Works on any of Owner's land.
(f) Replace damaged conduits with the same, or agreed equivalent, material and
authorised connectors. Repair and/or replace all property and environmental damage
caused by the Works to the satisfaction of the Water Agency or Owners.
(g) Remove all facilities for the Works from the site within the time frame specified or
agreed.
(h) Restore all services, drains, fences, structures, surfaces and improvements affected
by the Works to the original surface and condition to the satisfaction of the Owner,
and within the time frame specified or agreed.
13.5.6 Protection of the environment and heritage areas
13.5.6.1 General
Take all necessary measures to protect the environment and heritage areas.
13.5.6.2 Collection and disposal of wastes
Provide, operate and maintain adequate facilities for the collection, transportation and
disposal of liquid wastes including portable toilet wastes, fuels, lubricants, oils and
greases.
On no account allow any untreated liquid waste to discharge to the ground surface of the
site or into any drain or open area. Ensure that no contamination of the soil occurs and that
all sludge and solid material is removed and disposed of safely and lawfully.
On Works completion, completely remove all the storage and treatment facilities.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 184

If soil pollution occurs, remove all contaminated material from the site and dispose of in
accordance with the requirements of the Water Agency and relevant Regulators.
13.5.6.3 Protection of adjacent lands and vegetation
Confine all operations associated with the construction Works to the designated Works
area either within roadway reserves or enclosed by temporary and existing fences.
Fence all stockpile areas.
Make every attempt to minimise impact of the Works on adjacent areas and cooperate with
the owners / occupiers of adjacent land to minimise inconvenience.
Protect trees, shrubs and grasses outside the Works area by appropriate site management
and fencing.
The Constructor must at all times comply with any Council requirements regarding
vegetation; this may include having to obtain town planning permits.
Only remove or trim trees and shrubs if essential for the Works. Where applicable:
(a) treat all cut branches and roots with a suitable fungicide; and/or
(b) collect seeds from existing vegetation for use during restoration (Refer to Clause
25.5); and/or
(c) employ a qualified bush regenerator to weed the Works area prior to commencement
to prevent the spread of weeds during construction.
Stockpile vegetation separately on geotextile filter fabric when the line is initially cleared
for use during restoration (Refer to Clause 25.5). Similarly, if present, stockpile bush rock
separately during the initial clearing of the line.
Do not remove trees and shrubs on or adjacent to the Works without obtaining prior written
permission from the Owner and where appropriate, the Council and replace as
required / agreed.
Lop trees and prune shrubs in a professional manner using appropriate tools to the extent
authorised by the relevant Owner before Works commencement.
Suitably dispose of all debris from the cutting, pruning, lopping of trees and shrubs,
including removing trunks and roots.
13.5.6.4 Control of water pollution
Prior to work commencing, develop and provide to the Superintendent, or other approving
authority, an erosion and sediment control plan (or soil and water control plan) for the site.
The plan shall outline:
(a) Measures to be taken to minimise erosion and to trap sediment in any water leaving
the site.
(b) Defined access locations to the worksite.
(c) Location of stockpiles of excavated materials, fill and other erodable materials.
(d) Procedures for construction and rehabilitation activities to minimise erosion and
sediment transport.
(e) Procedures for monitoring, maintaining and removing erosion and sediment control
measures.
(f) Procedures to trap and dispose of excess water during testing, disinfection and
swabbing of the completed Works.
Implement the requirements of the approved plan and comply with all applicable
Commonwealth, State, Territory and Local Government laws and regulations.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


185 WSA 02—2002-2.3

In order to control water pollution and meet the emission limits for waste discharges to
water specified in State Environmental Protection Policy (Waters of Victoria), the
Constructor shall:
(a) Comply with the requirements of the following EPA documents. (These documents
can be downloaded from www.epa.vic.gov.au.)
(i) Environmental Guidelines for Major Construction Sites.
(ii) Construction Techniques for Sediment Pollution Control.
(b) Ensure that the concentration of suspended solids and turbidity in waters pumped into
the drainage system do not exceed the emission limits for waste discharges to water
as specified in Schedule E of the State Environment Protection Policy (Waters of
Victoria). To achieve this, it may be necessary to:
(i) Adequately plan, install and maintain the sediment control of the construction
site and ensure that construction activities such as excavating and dewatering
do not result in turbid water entering drainage networks.
(ii) Implement daily monitoring of the turbidity of water pumped directly to a natural
waterway or a drainage system discharging to a natural waterway.
(iii) Supervise all pumping and implement precautions to minimise the turbidity of
pumped water.
(c) Adopt practices to ensure that turbid water shall not enter the drainage systems.
Suggested practices could include, but are not limited to:
(i) Construction of detention basis and settling ponds particularly on larger sites.
(ii) Discharge of silt laden waters onto vegetated areas of suitable size and slope to
filter out suspended silts.
(iii) Where land is not available or suitable for settling ponds and/or vegetated filter
strips, then silt laden water may need to be subject to a specifically designed
physical filtration and/or chemical flocculation system to remove suspended silts.
(d) Advise the Superintendent of the proposed method prior to commencing construction.
Suggested options/methods that the Constructor may use to achieve the measures
are as follows:
(i) Temporary culvert/side entry pit entry:
Planks of timber around culverts/side entry pits with geotextile and/or gravel
behind timber to allow water to pass through, but retain the silt.
(ii) Silt fences:
Fabric filter (geotextile) reinforced with mesh and crushed rock.
(iii) Side entry pits:
Plug side entry pits and discharge into pit, then dispose of at sites where other
controls have been installed. This may require transportation of water off site.
(iv) Baffle tanks:
(A) Site baffle tanks designed to manage the site flows.
(B) Hessian bags (sausages) filled with crushed rock laid across gutters in
series as required.
NOTE: These options/methods only present a few of what is available and the
Constructor may use others that exist. The Superintendent will need to approve
any such options/methods that the Constructor decides to use.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 186

(e) Stockpiles of spoil and materials are to be kept to a minimum as well as being located
clear of footpaths and street channels.
Other steps that may be necessary to prevent sediment from these stockpiles
entering the drainage system would be the use of such options as:
(i) Tarpaulins or plastic sheeting over the stockpiles.
(ii) Storage bins.
(iii) Use of timber toe boards around the stockpiles.
(f) Use suitable methods on construction sites when dewatering and road
cleaning/jetting.
(g) Hay bales shall not be used as the only sediment control in residential streets.
If all known on-site treatment methods are unsuitable or impracticable, then turbid and silt
laden water must be removed by tankers for treatment and disposal at an appropriate
wastewater treatment facility.
13.5.6.5 Acid sulphate and contaminated soils
Determine from the Design Drawings and mark out prior to work commencing the sites of
acid sulphate (or potential acid sulphate) soil and other contaminated sites to be
excavated. Where such sites exist, the Constructor shall adhere to requirements of the
relevant planning authority and the EPA and take appropriate measures during excavation,
storage, transport and disposal of soil and filling of the trench, to ensure that excavated
material is treated on-site or at an authorised remote location.
Refer to the Product and Material Information and Guidance for pipeline suitability in acid
sulphate and contaminated soils
13.5.6.6 Control of noise and atmospheric pollution
Comply with relevant Regulator requirements for mitigating noise and atmospheric
pollution.
Operate all plant and construction equipment such that it does not cause undue noise and
atmospheric pollution.
Fit compressors, air tools, generators and other plant as necessary with appropriate
silencers.
Take all necessary measures to prevent dust generation on the site and in particular its
spread to adjacent areas. Preventative measures shall include, but not be limited to,
regular watering of the Works area and the access tracks and roads.
13.6 AFFECTED PARTY NOTIFICATIONS
The Constructor must:
(a) Notify (in writing) each property owner and resident who will be affected by the
Works. The notification shall be completed legibly by the Constructor and delivered
between eight (8) and fifteen (15) working days prior to the Works commencing to:
(i) Owners and residents on both sides of the boundary, where the Works are
located along the boundary of a private property.
(ii) Owners and residents of properties on both sides of the road, where the Works
are located in a road reserve.
(b) Advise each owner/resident in person, where practicable, of the work that will be
undertaken within the property.
(c) Provide a copy of a typical notification, and a plan showing the properties to where it
shall be delivered, to the Superintendent.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


187 WSA 02—2002-2.3

Notify commencement of Works to the Superintendent. The period of notice shall comply
with the relevant notification requirements specified in the contract or by the Water Agency.
Comply with the notification requirements of all affected municipal, services and other
Owners having care, management or control over streets, services and/or property affected
by the Works.
Retain copies of all notices for audit purposes.
13.7 ALTERATION OF EXISTING SERVICES
Carry out alterations to other services in accordance with the policies, practices and
procedures specified by the responsible service Owner.
13.8 SURVEY MARKS
Maintain all State and Territory survey marks in their correct position.
When such survey marks are disturbed, re-establish or reinstate the marks to the
requirements of the relevant Regulator.
13.9 CONSTRUCTION TOLERANCES
Adhere to tolerances specified in Section 23.
13.10 LATENT CONDITIONS
Not used by MRWA.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 188

14 PRODUCTS AND MATERIALS


14.1 AUTHORISED PRODUCTS AND MATERIALS
All product and materials shall be supplied to Purchase Specifications that are referenced
in Section IV of Part 0.
Use only products and materials authorised by the Water Agency.
Instruct suppliers of products to declare that all products and materials supplied comply
with the nominated Purchase Specifications.
Some Water Agencies maintain a list of authorised products and materials and their
suppliers.
Unless otherwise approved by the Water Agency, ensure all products and materials used
in construction conform to relevant product standards and Purchase Specifications
available on the WSAA and/or relevant Water Authorities’ websites.
14.2 REJECTED PRODUCTS AND MATERIALS
Reject any damaged, defective or inappropriate product or material. Any rejected product
or material shall be clearly marked or labelled and the Constructor shall issue a Non-
Conformance Report (NCR) on the supplier. The Constructor shall also advise the Water
Agency.
Do not use any rejected product or material in the Works.
Place rejected product or materials in a quarantined area and remove them from the site at
the earliest opportunity.
14.3 TRANSPORTATION, HANDLING AND STORAGE OF PRODUCTS AND
MATERIALS
14.3.1 General
Transport, handle and store all products and materials in accordance with the
manufacturers’ recommendations and in a manner that prevents damage or deterioration
or excessive distortion.
Pay particular attention to the protection of product and material coatings and linings.
Stack all pipe in a manner that minimises pipe ovalisation.
Do not store plastic pipe and fittings and plastic coated pipe and fittings near generators or
other heat emitting equipment.
Store rubber sealing rings, lip seals and gaskets away from sunlight and in an unstrained
condition.
Do not store PVC, GRP, ABS and non-black PE pipe and fittings uncovered in direct
sunlight for more than twelve (12) months. If storage periods are likely to exceed twelve
(12) months, cover and store pipe in a manner that allows 215litation and prevents heat
entrapment.
Except for checking against the purchase order, keep pipe, fittings, valves, seals and other
components delivered within protective crating or packaging, until immediately prior to use.
Keep the ends of plastic pipe and fittings or plastic couplings on GRP pipe free of loading.
Use PVC, GRP, ABS and non-black PE pipe and fittings within two (2) years of
manufacture.
14.3.2 Plastics-lined concrete products
Transport, handle and store plastics lined precast concrete products in accordance with the
product manufacturer's printed instructions. Notwithstanding this requirement:

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


189 WSA 02—2002-2.3

(a) Use only lifting and transportation equipment that does not contact plastics linings
and plastics accessories, except where appropriate padding or protective systems
are used.
(b) Provide special protection for unsecured plastics linings and PVC sheet flaps and
accessories during handling, storage and construction operations until secured in the
completed installation.
(c) Prevent exposure to sunlight of plastics lining sheets and accessories for the duration
of the project.
(d) Provide a secure, clean and dry storage area for plastics linings work materials and
tools.
(e) Do not incorporate in the Works any plastics-lined concrete product or accessory:
(i) which has not complied with the requirements of this sub-clause; or
(ii) whose bore, in the case of pipe or MH product, is affected by plastic lining
corrugations and/or non-circularities, which reduce:
(A) pipe waterway area by more than 1.5%; and/or
(B) pipe diameter by more than 5 mm for pipe <DN 1800; or
(C) pipe diameter by more than 10 mm for pipe ≥DN 1800 over; or
(iii) which is above the dimensional tolerances permitted by the requirements of the
Purchase Specification for unlined concrete product.
14.4 DELIVERY INSPECTION OF PRODUCTS AND MATERIALS
Inspect all products and materials at the time of delivery for damage and excessive
distortion.
Replace products and materials that are damaged, excessively distorted, outside their use-
by date or storage period and indelibly mark or tag with wording such as “Do not use” or
other identification.
Do not use:
(a) PE pipes and fittings scored deeper than 10% of the wall thickness.
(b) Faded / discoloured PVC, PE, ABS, GRP and plastic coated pipes and fittings.
(c) PVC and ABS pipes and fittings scored deeper than 0.5 mm.
(d) GRP pipes and fittings scored deeper than 1 mm or with impact damage.
Remove rejected products and materials and store separately from useable products to
prevent inadvertent use.
14.5 CONCRETE WORKS
14.5.1 Delivery
Concrete shall be delivered to site for placement within 90 minutes of commencement of
mixing at the plant or within the time limitations for the mix and ambient temperature.
14.5.2 Transportation of concrete
Use pneumatic and pumping or other methods for conveying and placing concrete when
nominated in the Specification or when authorised by the Superintendent. Where concrete
is conveyed by wheeled vehicles or barrows, the equipment used and the distance
travelled shall be authorised by the Superintendent.
If concrete is conveyed by chute, the equipment shall be of such size, slope and type as to
ensure the continuous flow of concrete without segregation of materials. The delivery end
of the chute shall be as near as possible to the final position of the concrete and it shall be

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 190

provided with an effective baffle. If the chuting operation is not continuous, the chute shall
discharge the concrete into a hopper.
14.5.3 Formwork
14.5.3.1 General
Formwork, including all temporary supporting structures and precast members, shall
comply with the requirements of AS 3610 and the additional requirements of this Code,
including Standard Drawings.
Forms shall be sufficiently tight to prevent loss of mortar from the concrete. Form surfaces
shall be smooth and free from holes or irregularities detrimental to the finished concrete
surface.
Before placing the concrete, coat the forms with a suitable, non-staining coating, which will
facilitate their release.
Finish surfaces as specified.
14.5.3.2 Formwork for plastics-lined concrete
Set out and install formwork for in-situ concrete structures to be plastic lined so as to
facilitate fixing of plastic lining materials to internal formwork faces and in a manner that
will:
(a) Ensure intimate continuous contact of lining materials with the formwork.
(b) Position fixing holes within areas of lining that will be subsequently covered by
jointing or welding strips.
(c) Avoid the securing of lining materials by means of bands or straps otherwise than as
provided for in the lining material manufacturer's printed instructions.
14.5.4 Reinforcement
Supply, fix and place reinforcement in accordance with AS 3600. Ensure the specified
minimum cover is achievable between ends of members and / or construction joints.
Continuously monitor placement.
14.5.5 Placement
14.5.5.1 General
Place concrete within the time limitations for the mix and ambient temperature. Place in
discrete layers in one continuous operation between ends of members and/or construction
joints.
Continuously monitor placement.
Surfaces upon or against which concrete is to be placed shall be free of standing water,
mud and debris.
Prior to placing concrete on concrete that has set, prepare the surface of the set concrete
by scabbling to expose aggregate, clean off loose material and dampen and apply a
bonding agent recommended by the concrete supplier.
In the placement of vertical elements, do not allow free fall of concrete to exceed 1.6 m.
14.5.5.2 Placement in water
Deposit concrete in water only where specified or authorised by the Superintendent.
Place concrete in water under the direct supervision of the Superintendent.
Take precautions to prevent significant mortar loss where concrete is to be placed in
running water.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


191 WSA 02—2002-2.3

Place concrete in water continuously in a compact mass, with the top surface kept as level
as practicable, by:
(a) Using a properly designed tremie or drop bottom bucket;
(b) Pre-packing and grouting; or
(c) Placing in suitably tied jute bags, each containing not less than 15 litres of concrete.
Where concrete is provided in bags, place the bags in header and stretcher courses so
that the entire mass in interlocked.
14.5.6 Slump
Slump shall be appropriate to the project specified by the Constructor on advice from the
concrete supplier.
There is no default value for slump in the Purchase Specifications because slump is
dependent on the method of placement.
The slump at the point of acceptance shall be in the range 80–120 mm. Under no
circumstances is additional water to be added onsite unless approved by the concrete
supplier.
Higher slumps can result in an increase in bleed water requiring additional precautions
when finishing concrete. The constructor should liaise with the concrete supplier in
determining the slump.
The addition of excess water onsite can adversely affect the strength and durability of the
concrete.
14.5.7 Compaction
Immediately compact concrete after placing. Use internal and/or external vibration in a
systematic manner to ensure that all concrete is thoroughly compacted. Vibrate to the full
depth of each layer and extend into the top 100 mm of the underlying layer. Do not vibrate
to the point where segregation of the ingredients occurs.
Use rotary out of balance vibrators.
Where internal vibrators are used, insert them vertically at successive locations and at
spacings not exceeding the manufacturer’s stated zone of influence. Do not allow vibrators
to contact partially hardened concrete or reinforcement embedded in it.
In regions of closely spaced horizontal reinforcement, ensure full compaction directly
beneath the closely spaced horizontal reinforcement prior to encasing the reinforcement
with concrete.
14.5.8 Stripping
Ensure that concrete has adequate strength before stripping formwork.
Remove forms in a manner that will not injure the concrete. Provide temporary support to
the concrete structure so as to protect freshly stripped concrete from construction loads.
14.5.9 Curing
Cure concrete as specified.
14.5.10 Repair of blemishes
Fill surface holes and damage exceeding specified limits by filling with cementitious mortar
bonded to the concrete.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 192

14.6 SUPPLY OF WATER TO THE WORKS


Obtain an authorisation from the Superintendent for the supply of water for construction
purposes.
Do not take water from any metered or private trunk service without the Owner's
permission.
Maintain all hydrants to protect the quality of water supplied.
Fit an authorised backflow prevention device in accordance with AS/NZS 3500.1.2 to any
equipment drawing water from the water supply system.
The Constructor must have a current permit from the relevant Water Agency before taking
water from the system. A permit to take water may also require training on backflow
prevention devices and correct hydrant use.
Introduction of water supply restrictions over the designated Works area may prohibit the
supply of water to the site. The Water Agency should be consulted to confirm the
availability of water supply during the construction period. Alternative sources of supply
may need to be sought in the case of restrictions.
14.7 ON-SITE STOCKPILES
Store only sufficient materials on-site as are necessary to allow timely and efficient
progress of the work. Locate stockpiles of excavated or imported material where they
cause no interference to the public, drainage routes or vehicular or pedestrian traffic.
Do not obstruct clear lines of sight for drivers.
Do not stack materials against structures, fences, trees or other property improvements.
Leave a clear path between the edge of any excavation and the inner toe of any stockpile
or spoil banks such that no loading is imposed on the trench wall.
Do not stack or stockpile materials under overhead electrical conductors.
Obtain written permission of the Owner for storage of materials, equipment and/or
excavated material for the Works on the Owner's land.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


193 WSA 02—2002-2.3

15 EXCAVATION
15.1 SAFETY
Comply with recommendations and guidelines set out in the Code of Practice: Safety
Precautions in Trenching Operations (Refer www.ohsrep.org.au/legislation/COPs.html.)
Do not commence any excavation until all equipment and materials necessary to make the
excavation safe are on site and available for use. This includes any necessary fencing and
barriers, as well as trench support systems.
Assess site for prior excavations and consider their impact on the new excavation.
Conduct a site hazard and safety assessment prior to commencement of any excavation to
identify all potential hazards in accordance with Clause 13.5.1.
15.2 LIMITS OF EXCAVATION
Keep the extent of excavation to the minimum possible to allow efficient construction of the
Works while meeting the requirements shown on relevant Design Drawings.
Unless specified otherwise, keep the sides of excavations vertical to at least 150 mm
above the sewer.
Ensure that the minimum cover requirements shown on relevant Design Drawings are
satisfied following any earthworks that may occur in the area of the sewer. This is
particularly relevant in new subdivisions or developments where earthworks are expected
to form roads, driveways, footways and for general shaping of the surfaces. If minimum
cover requirements cannot be achieved, refer to the Superintendent to overcome the
problem.
15.3 EXCAVATION ACROSS IMPROVED SURFACES
Obtain written permission of the Owner prior to commencing any excavation across
improved surfaces.
If excavation is required across improved surfaces such as pavements, driveways, kerbs
and gutters, where the surfaces cannot be satisfactorily reinstated, use boring in
accordance with Clause 17.12.
For open excavations across improved surfaces, keep the trench width to the minimum
allowed. Saw cut neat straight lines at least 150 mm beyond the outer limits of the
excavation through bitumen, asphalt and concrete. Remove pavers, blocks or brick
pavements by hand, clean them and set them aside for later replacement. Ensure trench
fill is compacted to requirements of Clause 21.1.3.
15.4 EXCAVATION IN ROOT ZONES
Take every precaution to ensure that no undue damage is caused to a tree root system as
a result of excavation for the Works. Excavation for sewer construction by hand or by
boring may be required to protect the root zone.
Cleanly cut all roots ≤60 mm diameter encountered during excavation.
Do not cut tree roots larger than 60 mm diameter without authorisation of the
Superintendent.
Damage to root zones can also be minimised by:
(a) Fencing off vegetation to keep machinery away.
(b) Tying back stems and branches to keep them out of the path of machinery.
(c) Avoiding piling materials directly over or against the vegetation for prolonged periods.
Also, the Constructor is required to:

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 194

(i) Avoid storing pipes and materials, including soil, rocks or gravel against trees or
under tree canopies.
(ii) Avoid machine excavation beneath the tree canopy. Boring or hand excavation
might be acceptable alternatives.
(iii) Immediately trimming back damaged roots or branches with a sharp saw to
achieve a clean cut, and applying an approved fungicide to reduce chances of
infection.
(iv) Obtain approval from the owner of the trees prior to excavation.
The Constructor should carefully clean machinery between jobs to minimise the risk of soil-
borne contamination between work sites. (This is mandatory in areas where cinnamon
fungus occurs.)
15.5 BLASTING
Use alternative methods of excavation to blasting wherever achievable.
Obtain prior authorisation from the Water Agency, Superintendent, relevant Regulator and
affected Owners of assets within the vicinity before undertaking blasting.
Where authorisation is granted, prepare a blasting plan that includes management of the
blasting and means to be used to satisfy the requirements of AS 2187 and the authorising
parties.
15.6 SUPPORT OF EXCAVATIONS
All excavations shall be supported in accordance with the Occupational Health and Safety
Act, the Code of Practice for Safety Precautions in Trenching Operations and the Job
Safety Analysis (Refer to Clause 13.5.1).
Support all excavations as the work proceeds to meet OH&S requirements. Ensure that
adjacent structures and services are not subject to disturbance by the trench support
system.
When removing, raising or withdrawing supports, prevent slips or falls and ensure that no
damage, disturbance or displacement occurs to the pipes, fittings, geotextile filter fabric,
pipe embedment and trench fill already installed. Fill the trench simultaneously with the
raising or withdrawal of trench supports. Ensure that compaction of pipe embedment and
trench fill material occurs below such trench support and against native ground.
Where specified, leave the trench support system in place as permanent support. Cut off
the support system at a depth below ground surface that will satisfy the structural and
development requirements of the site.
15.7 DRAINAGE AND DEWATERING
Keep all excavations free of water. Provide, maintain and operate intercepting Works to
prevent surface water from entering the excavations. Provide all equipment necessary for
dewatering the excavations and keeping the Works free from water.
Only lower the water table by well points or other external dewatering methods if no
damage is likely to be caused to adjacent structures and services or the environment.
Ensure that all downstream Works that are under construction, completed or in use are
protected at all times against the effects of any drainage that is discharged or likely to be
discharged from the Works.
Do not discharge dewatering to sewers, storm water drains or watercourses without
appropriate authorisation and without complying with the Owner’s or Regulator’s
requirements.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


195 WSA 02—2002-2.3

15.8 FOUNDATIONS AND FOUNDATION STABILISATION


The bottom of the excavated trench is required to provide a foundation suitable for the
adopted construction method.
Prior to placing embedment, check the proposed foundation using Standard Drawing
SEW–1200 as a guide. Where the bottom of an excavation is unable to provide a firm
foundation with minimum bearing capacity of 50 kPa at the required level (tolerance +0, -
50 mm) without abrupt irregularities or undulations, obtain written instruction from the
Superintendent on the means for providing a satisfactory foundation.
The Superintendent will seek the instruction from the Designer in most instances.
Construct special supports in accordance with the Design Drawings.
15.9 SURPLUS EXCAVATED MATERIAL
Surplus material is the property of the Owner of the excavation site.
Where the spoil from trench excavation is to be used for trench fill, isolate the topsoil for
later use in restoration.
Promptly remove and dispose of excavated material that is not required for reuse. Dispose
of lawfully and in accordance with project requirements.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 196

16 BEDDING FOR PIPES AND MAINTENANCE STRUCTURES


16.1 TRENCH FLOOR PREPARATION
Inspect the trench floor on excavation for rock outcrops and soft and loose areas. Take
appropriate action to ensure that the pipe or fitting or other appurtenance or structure will
not be subject to differential settlement in the future.
Where rock outcrops are present, trim the trench floor and fill with granular material to
restore the design trench floor level limits. Treat soft and loose areas as specified in
Clause 15.8.
Compact all fill and all disturbed areas to not less than the density of the natural ground.
Remove all debris and water before bedding sand is placed.
16.2 BEDDING MATERIALS
Use specified bedding materials for different pipeline materials in accordance with WSAA
Product and Material Information and Guidance and Purchase Specifications.
16.3 PLACEMENT OF BEDDING
Provide bedding of the type shown on relevant Design Drawings. Place and rake-in the
bedding to support the pipe uniformly along the whole length of the barrel with chases
provided for sockets, couplings and other appurtenances. Do not compact the bedding.
Do not walk on the centre of the bedding either during or after placement.
If the Constructor wishes to alter the bedding design to suit the actual ground conditions on
site, the Superintendent’s written approval must be obtained. This is especially important
for flexible pipes.
Reference: Standard Drawing SEW–1202
Reference: Drawing SEW–1201-V.
16.4 SPECIAL PIPE SUPPORT FOR NON-SUPPORTIVE SOILS
Construct piered or other special support as specified.
Reference: Standard Drawings SEW–1203, SEW–1204 and SEW–1205.
16.5 BEDDING FOR MAINTENANCE SHAFTS AND BENDS
Prepare bedding in accordance with Clause 16.3 to provide full support of the sewer,
maintenance shafts and bends.
Reference: Standard Drawings SEW–1316 and SEW–1317
Reference: Drawings SEW–1314-V and SEW–1315-V.
16.6 BEDDING FOR MAINTENANCE HOLES
Lay the base of a maintenance hole in supportive ground.
Prior to casting a base, check the proposed foundation using SEW–1200 as a guide.
Where the allowable bearing pressure appears to be less than 50 kPa, obtain instruction
from the Superintendent on the means for providing satisfactory foundation.
Where a precast base is used, place bedding materials in accordance with Clause 16.3.
Construct special supports as specified.
Reference: Standard Drawing SEW–1205
Reference: Drawing SEW–1201-V.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


197 WSA 02—2002-2.3

MRWA 16.7 EXCESSIVE EXCAVATION


The excavation must be equal to or greater than the minimum width shown on the
Standard Drawings and not greater than that required for the ground support system.
Where the minimum width is exceeded by more than 500 mm, the structural condition of
the pipeline must be assessed by the Superintendent.
With the exception of where a special base is required, the excavation below the invert of
the pipe must not be less than that shown on the Standard Drawings and not more than 50
mm below that depth.
All high spots must be removed and holes outside the tolerance and sudden changes in
depth must be filled in accordance with the Water Agency’s requirements or as directed by
the Superintendent.
If the excavation protrudes outside of the easement, the easement must be widened or the
trench backfilled and compacted in accordance with the Water Agency’s and municipal
council’s requirements.
The Superintendent may order the refilling of any excessive excavation as follows:
(a) Foundation and embedment zones:
(i) In wet sandy conditions, 20 mm single size coarse aggregate, compacted to a
density index of 70;
(ii) 10 mm crushed rock, compacted to a minimum dry density ratio of 95%;
(iii) Cement stabilised 10 mm crushed rock, or
(iv) WI N20 Grade concrete, formed or screeded to an even and uniform finish.
(b) Trench fill (backfill) zone:
(i) Embankment/Concrete sand placed and compacted in accordance with the
Water Agency’s trench fill specification;
(ii) 10 mm crushed rock placed and compacted in accordance with the Water
Agency’s trench fill specification;
(iii) Selected excavated material containing no rock fragments larger than 20 mm or
hard clay fragments larger than 40 mm placed and compacted in accordance
with the Water Agency’s trench fill specification.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 198

17 PIPE LAYING AND JOINTING


17.1 INSTALLATION OF PIPES
17.1.1 General
After preparing pipe bedding, lay and joint pipes in locations and sizes as specified. Use
methods, materials, tools and equipment in accordance with manufacturer's and/or
supplier’s instructions and recommendations, relevant Standards and requirements of this
Part. Adhere to any limitations imposed by the Water Agency’s OH&S and/or
environmental requirements.
17.1.2 Cleaning, inspection and joint preparation
Clean and examine all pipeline system items before installation. Inspect each joint seal for
fit and flaws before making the joint in accordance with the manufacturer’s instructions. Do
not use damaged, dirty or incorrect seals. Ensure that the correct joint lubricant is used for
rubber seals.
Inspect all items just prior to use in accordance with Clause 14.4. Remove damaged items
from the Works site and replace.
Chamfer, if required, and provide witness marks on the unmarked length of any cut pipes.
Do not score pipes when providing the witness mark.
Treat cut pipe ends in accordance with pipe manufacturer’s recommendations.
The jointing methods will vary depending upon the material used and the jointing systems
available. The Product and Material Information and Guidance, supplier’s drawings and
Standard Drawings provide information on jointing systems.
17.1.3 Polyethylene
Welds on welded PE pipe system components shall be carried out by accredited PE
welders in accordance with WSA 01.
The internal weld bead in butt welded gravity sewers shall be removed by the Constructor.
17.1.4 Laying
Commence laying at the downstream end. Lay pipes with their sockets at the upstream end
and their barrels firmly and evenly embedded on the bedding material. Form chases in the
bedding to accommodate the pipe sockets and/or couplings to allow even bearing along
the full length of the pipe barrel.
To prevent movement, restrain pipes already laid before the next joint is made. Prevent
flotation of pipes during laying in accordance with Clause 17.4.
After laying each pipe and at the end of each day’s laying, the exposed end shall be
temporarily sealed by an exclusion cap or approved equivalent to prevent ingress of
excavation debris.
Reference Standard Drawing: SEW–1103
Reference Drawing: SEW–1201-V.
17.2 HORIZONTAL AND VERTICAL DEFLECTION OF SEWERS
17.2.1 General
Achieve horizontal and vertical deflections as specified and in accordance with Clause
17.2.2. Where not specified, do not deflect the sewer unless:
(a) the Superintendent’s authorisation has been obtained, and
(b) the Design Drawings have been revised to show the bend or curve details, including
location, angle and methods of achieving deflection.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


199 WSA 02—2002-2.3

Ensure that actual details of deflections are accurately recorded on the Work as
Constructed drawings.
17.2.2 Methods of deflection
Achieve horizontal and vertical deflections as specified using one of the following methods:
(a) Deflecting consecutive flexible joints in accordance with Table 17.1, provided no
individual joint deflection exceeds 80% of the manufacturer’s recommended
maximum joint deflection. Make the pipeline joint in a straight line before deflecting
the joint. In some pipe systems the maximum allowable joint deflection is marked on
the pipe socket.
(b) Manually (not mechanically) cold bending flexible pipes in circular arcs of uniform
radius to exceed the minium prescribed radii specified in Table 17.1. Limit cold
bending to DN 150 and DN 225 pipe sizes only. Do not cold bend SCJ PVC pipe
where branch sewers or property connection branches are to be installed along the
curve. Curves formed by cold bending the pipes should be designed.
(c) Using a variable bend (Refer to Drawing SEW–1315-V).

TABLE 17.1
METHODS OF ACHIEVING CURVED SEWERS
Pipe size Pipe length Minimum horizontal
Material and Deflection and vertical curve
Curve type
joint at joint radius
DN m m
VC Up to 2.5–
Yes 100 – 1400 Note 4
Socket - Spigot varies with DN
VC
Up to 2.5–
polypropylene Yes 100 – 300 Note 4
varies with DN
coupling
Cumulative
PVC
deflection at
elastomeric seal Yes 100 – 375 3.0 – 6.0 Note 4
joints
jointed (RRJ)
Profiled wall PE
Yes 375 – 2100 2.4 – 6.0 Note 4
Socket - Spigot
Profiled wall PP
Yes 225 – 600 3.0 Note 4
Socket – Spigot
PVC Not dependent 0.3 X DN
solvent cement No 100 – 300
jointed Note 1
Manual cold
0.02 X DN at T ≥20 C
o
bending PE
o
welded joints No 160 – 355 Not dependent 0.05 X DN at 0 C
SDR ≤21
Notes 1 and 2
PVC Yes Not dependent Note 3
100 – 375
RRJ only

Manufactured GRP Yes 300 – 1200 Not dependent Note 3


bends Profiled wall PE Yes Up to 1500 Not dependent Note 3
PVC variable
No 150 – 225 Not dependent 0.9
bend

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 200

NOTES:
1 The minimum radius for solvent cement welded PVC pipes and welded PE pipes is based upon:
(a) the deflection that may be achieved without overstressing the pipe or pipe joint; and
(b) ensuring that the necessary restraint of the pipe and joints around the curve is readily
achievable based on manually cold bending the pipe in the field.
2 Interpolate values for temperatures between 0°C and 20°C.
3 The minimum acceptable radii for manufactured bends is 900 mm.
4 The minimum radii for rubber ring jointed pipes is dependent upon the maximum allowable deflection
through the pipe joint, in accordance with the manufacturer’s recommendations or the Purchase
Specification, and the length of the pipes.

17.2.3 Horizontal curves


Install curves either adjacent to an MH or MS or in a straight run between MHs or MSs or
combinations of both. Curves shall be located parallel to kerbs, building lines, etc to
enable future location of the pipe. Where the Water Agency has given permission to use
curves that are not parallel to kerbs, etc detectable marker tape shall be placed above the
sewer pipe in accordance with Clause 17.11.
Place horizontal variable bends on the upstream side of MHs adjacent to the MH but clear
of the external face of the MH wall. It is important that the bend is clear of benching and
the MH wall to allow easier manipulation of equipment.
Place horizontal variable bends on the upstream side of MSs and immediately adjacent to
the MS.
Install horizontal bends clear of all drop structures.
Aside from a single manufactured bend, only one curve, either vertical or horizontal, is
permitted per length of sewer between maintenance structures.
Ensure that the commencement of any cold bent PVC pipe is clear of the external face of
the MH wall.
After completion of pipelaying and placement of embedment material, remove temporary
pegs or stakes used to restrain curved pipes.
Removal of temporary pegs or stakes is essential to avoid point loading of the pipes. Non-
removal may result in pipe failures.
Water Agency approval is required for the use of curves and sweep bends on sewers ≥DN
300.
17.2.4 Vertical curves
Install curves either adjacent to an MH or MS or in a straight run between MHs or MSs or
combinations of both.
Place vertical variable bends on the upstream side of MHs adjacent to the MH but clear of
the external face of the MH wall. It is important that the bend is clear of benching and the
MH wall to allow easier manipulation of equipment.
When installed adjacent to a MS, place vertical variable bends on the side of the MS that
maximises the vertical alignment of the MS riser. Alternatively, install bends either side of
the MS to achieve the total change in grade.
Install vertical bends clear of all drop structures.
Limit vertical variable bends to two locations adjacent to and between MHs or MSs. Place
on the upstream and/or downstream side of the MH/MS immediately adjacent to the
structure i.e. one at the outlet of MH/MS and one at the inlet of the downstream MH/MS.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


201 WSA 02—2002-2.3

Limit cumulative joint and cold vertical bends to one additional location between adjacent
MHs or MSs or combinations of both.
After completion of pipelaying and placement of embedment material, remove temporary
pegs or stakes used to restrain curved pipes.
Removal of temporary pegs or stakes is essential to avoid point loading of the pipes. Non-
removal may result in pipe failures.
17.2.5 Compound curves
Compound curves/bends shall not be used unless specifically authorised by the Water
Agency.
17.3 HORIZONTAL AND VERTICAL SEPARATION OF CROSSING PIPELINES
Maintain minimum horizontal and vertical separation of crossing pipelines as specified. Fill
the separation with embedment material and compact.
Pipelines shall cross as close to 90 degrees as possible, but not less than 45 degrees.
Ensure sewer pipes always cross below water mains.
17.4 FLOTATION CONTROL
Prevent floatation of pipes, MSs and MHs by:
(a) Using trench stops in accordance with SEW–1206; and/or
(b) Placing and compacting sufficient height of fill material; and/or
(c) Filling the pipeline with water, where authorised; and/or
(d) Other appropriate methods authorised by the Superintendent.
Where trench de-watering is necessary, fully place and compact embedment and fill
material in accordance with Sections 20 and 21 while dewatering systems are operating.
Some materials such as PE have a density less than that of water and sewers can float
even when full of water.
17.5 TRENCH STOPS
Construct trench stops with trench drainage as specified.
Reference: Standard Drawings SEW–1206 and SEW–1207.
17.6 BULKHEADS
Construct concrete bulkheads with trench drainage as specified. Do not position the
bulkhead directly beneath a kerb.
Reference: Standard Drawings SEW–1206 and SEW–1207.
17.7 PROPERTY CONNECTION SEWERS
Install property connection sewers as specified.
Ensure tolerances for position, level and plumb are within the limits specified in Section 23.
Fill and compact as specified for the reticulation sewer.
Only approved, specifically manufactured OB’s and IO’s shall be used to connect property
connection sewers to sewer pipes. Cut-in type connections are not permitted on new
works.
Where concrete surround or encasement of a riser is specified, allow a minimum of
16 hours for the concrete to set before constructing a property connection sewer.
Locate vertical drops or risers to prevent damage to the sewer and provide support to
maintain their position during encasement or backfilling.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 202

Mark locations of property connection points by placing a marking tape from the connection
point to a hardwood surface peg or by using detectable marking tape similarly placed.
Reference: Standard Drawing SEW–1316
Reference: Drawings SEW–1105-V, SEW–1153-M, SEW–1154-M, SEW–1155-M and
SEW–1314-V.
17.8 DEAD ENDS
Terminate sewer lines as specified. The Constructor may consider installing an IO at the
end of the line to allow future testing.
Reference: Standard Drawings SEW–1109 and SEW–1316.
17.9 MARKING OF PROPERTY CONNECTION SEWERS AND DEAD ENDS
Mark the position of each dead end and location of each property connection point using
identification tape and hardwood peg or by using a detectable tape.
Reference: Drawings SEW–1153-M, SEW–1154-M and SEW–1155-M.
17.10 CORROSION PROTECTION OF CAST IRON
Sleeve uncoated buried cast iron items with polyethylene, fixed with PVC tape complying
with AS 3680. Install sleeving to AS 3681. Do not allow sleeved items to be exposed to
sunlight for more than seven (7) days.
Sleeving may be omitted for items that have a thermal-bonded polymeric external coating
complying with specified requirements in Part 2 of the Code.
Cast iron includes grey cast iron and ductile (cast) iron.
South East Water does not permit sleeved DICL <DN 300.
17.11 MARKING TAPES AND POSTS
17.11.1 Non-detectable marking tape
When specified, lay non-detectable marking tape on top of the pipe embedment material
before trench filling.
Reference: Drawing SEW–1201-V.
17.11.2 Detectable marking tape
Lay detectable marking tape on top of the pipe embedment material before trench filling or
1 m below the surface for:
(a) non-metallic pipelines, as specified;
(b) all curved pipelines;
(c) property connection sewers, as specified;
(d) all sewers without an upstream access point; and
(e) at other locations as specified.
Lay the tape over the embedment to form a continuous connection between access cover
frames. Strip the ends of the tape to expose its conducting wires. Connect bare wires to a
nut or bolt of the access cover frame to form an electrical connection.
Reference: Drawing SEW–1201-V.
MRWA 17.11.3 Marker posts
Where sewers are located in remote areas or where maintenance structures may be
difficult to locate, marker posts, approved by the Water Agency, shall be specified on the
drawings and installed adjacent to maintenance structures.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


203 WSA 02—2002-2.3

Reference: Drawing SEW–1450-M


17.12 BORED PIPES UNDER ROADS, DRIVEWAYS AND ELSEWHERE
Construct bored sewers under roads, railways, driveways, footways and elsewhere of the
type, size and locations shown in the Design Drawings.
Construct encasing pipe as detailed in the Design Drawings. Where grouting of the annulus
between the encasing pipe and sewer is specified, commence grouting from the downhill
end of the bore. Both gravity and pressure grouting are approved. Check that the applied
pressure will not cause buckling of the main. Achieve full penetration and complete filling
of the void.
Insert plastic slippers between the sewer and the bored hole in accordance with the
manufacturer’s directions.
In the case of an unsupported bore, i.e. no encasing pipe utilised, all pipework and
grouting is to be completed within 24 hours.
Place buffer rings between VC and reinforced concrete pipes that are pushed into bores.
Reference: Standard Drawing SEW–1400
Reference: Drawings SEW–1401-V, SEW–1402-V and SEW–1403-V.
17.13 AQUEDUCTS
Construct aqueducts of the type, size and locations shown in the Design Drawings.
Install protection grills and apply corrosion protection as specified.
Reference: Standard Drawings SEW–1404 and SEW–1405.
17.14 BRIDGE CROSSINGS
Construct bridge crossings of the type, size and locations shown in the Design Drawings.
Reference: Standard Drawing SEW–1406.
17.15 PLASTICS-LINED RC PIPE JOINTING
17.15.1 General
The Water Agency must approve the use of plastic lined RC pipes. Properly accredited
contractors shall carry out this work. All appropriate OH&S requirements shall be
observed, e.g. ventilation.
Protect the protruding plastic lining flaps of precast pipes from sharp changes in flap
direction due to contact with adjoining pipes or due to poor pipe handling or installation
practice.
Install pipes that have been plastics-lined over less than 360° of internal pipe
circumference so that unlined pipe inverts are aligned continuously along the invert of the
installed sewer.
17.15.2 Plastics lining work protection
Protect from damage all plastics linings, PVC sheets and accessories to be field jointed
and maintain in a clean dry condition free of mortar and other foreign materials for the
duration of the jointing process. Do not allow the discharge of sewage or site water into or
through plastics-lined components to be field jointed prior to completion and acceptance of
the joint work by the Superintendent.
17.15.3 Field jointing
Conduct plastics lining, rigid PVC sheet and accessory field jointing following the
installation of precast plastics-lined concrete products.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 204

Joint the plastics flap at the spigot end to the plastic lining of the previously laid pipe by
welding.
Complete jointing work prior to hydrostatic testing and backfilling of plastics-lined pipeline
components.
17.15.4 Plastics lining ancillary work
17.15.4.1 Alignment of lining keys
In order to facilitate drainage of fluid accumulations between structure and lining, vertically
align plastics-lining keys for embedment of lining into in-situ vertical concrete structural
components.
17.15.4.2 Provision of seepage channels
Provide vertical seepage channels between plastics lining and precast or in-situ concrete
components, which do not have vertically disposed keys, as specified.
17.15.4.3 Use of jointing accessories and adhesives
In accordance with the plastics lining manufacturer’s printed specification, provide for
continuity of plastics lining, including accessories, adhesives and jointing compounds, at
changes of direction, lining returns and jointing of lined components.
17.16 WELDING OF STEEL PIPELINES
17.16.1 General
Weld steel pipe in accordance with Category SP of AS/NZS 1554.1 employing welders
qualified in accordance with AS/NZS 1554.1.
Pre-qualify all weld preparations in accordance with AS/NZS 1554.1.
Inspect all welding in accordance with AS/NZS 1554.1, Section 7.
Apply corrosion protection to welded joints, internal and/or external, where specified.
Reinstate cement mortar linings as specified.
Reference: Standard Drawings WAT–1400 to WAT–1404 inclusive and WAT–1408 of
WSA 03.
17.16.2 Field welding of flanges
Field welding of flanges shall only be carried out with the express approval of the Water
Agency.
Weld flanges either directly to the pipe or fitting after machining or to a coaming piece that
can be subsequently butt welded to the pipe or fitting.
Align flanges at right angles to the axis of the pipe or to the relevant leg of the fitting.
Attach flanges by one of the following procedures depending on steel plate thickness:
(a) Where the pipe or fitting is ≤10 mm thick, weld the flange in accordance with AS 4041
Figure 3.24.4.8(H)(a) Type 6 slip-on weld.
(b) Where the pipe or fitting is >10 mm thick, weld the flange in accordance AS 4041
Figure 3.24.4.8(B) Type 2 “face and back” or Figure 3.24.4.8(D) Type 3A “bore and
back”.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


205 WSA 02—2002-2.3

18 MAINTENANCE HOLES (MHs)


18.1 GENERAL
Construct MHs and install covers, surrounds, step irons and ladders as specified.
Reference: Standard Drawings SEW–1310, SEW–1311 and SEW–1312
Reference: Drawings SEW–1300-V, SEW–1301-V, SEW–1302-V, SEW–1303-V, SEW–
1304-V, SEW–1305-V, SEW–1306-V, SEW–1307-V, SEW–1308-V, SEW–1309-V and
SEW–1313-V.
18.2 MH BASE
Determine the offset centreline for the MH in accordance with Drawings SEW–1304-V,
SEW–1305-V and SEW–1306-V. Set out the MH base pipe connections to suit the
diameter and the offset centreline. Support pipe connections to prevent movement during
placement and vibration of concrete.
Provide suitable formwork to retain concrete if required. Position channel formwork
correctly and secure it to prevent movement. Place concrete directly onto firm foundation
and vibrate to produce a dense and watertight base in accordance with Clause 14.5.7.
MH channels are to be formed using appropriate formwork. Channels are not to be formed
by hand.
Plastic pipes etc shall not be used to support framework.
For precast MHs, form the channels after the first component has been placed,
alternatively, precast bases are acceptable.
Reference: Standard Drawings SEW–1310, SEW–1311 and SEW–1312
Reference: Drawings SEW–1302-V, SEW–1303-V, SEW–1304-V, SEW–1305-V, SEW–
1306-V and SEW–1309-V.
18.3 TRENCH DRAINAGE AROUND MHs
Construct trench stops and drainage as specified. Where aggregate has been used in the
bottom of the trench or where some trench water is present, provide trench drainage as
specified in Standard Drawing SEW–1207.
18.4 PRECAST CONCRETE MH SYSTEMS
Select component MH lengths to minimise the number of joints. Select components to give
the specified clearance between the MH component joint and the drop pipe entry.
Use a shaft section between 300 and 600 mm long for the base section.
Prime the lower 200 mm of the precast component with a wet to dry bonding agent or cement
slurry before placing the component onto the wet concrete base. Embed the component
50 mm into the wet concrete base, then build up and compact a 150 mm concrete fillet on the
outside to seal against infiltration. Form channels in the base in accordance with Clause 18.2.
Do not place other shaft sections until the concrete base has set.
Where the concrete in the base sets before the first component can be placed, allow the
base to cure for at least seven (7) days before bonding the first component to the base
using an authorised epoxy adhesive.
Any holes to be constructed in a precast MH shall be core bored and shall not extend to
within 50 mm of any segment joint.
The limitations associated with use of precast MHs shall apply in all cases.
The repair using epoxy coatings or pressure grouting of precast MHs is not permitted in
any cases.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 206

Reference: Drawings SEW–1300-V, SEW–1301-V, SEW–1302-V, SEW–1303-V, SEW–


1304-V, SEW–1305-V and SEW–1306-V.
18.5 CAST IN-SITU CONCRETE MH
Place concrete in accordance with Clause 14.5.5.
At each construction joint, place dowels, remove laitance (cured cement slurry) by
scabbling and prime with a wet to dry bonding agent or cement slurry before pouring the
next lift.
If a waterstop is to be used at any construction joint, support it in such a manner that it will
retain its position during the pour.
Strip external formwork and backfill around MH before stripping internal formwork.
Outside formwork must be used where the excavation exceeds tolerances specified and
when forming the cone and neck of the MH and the surround of cast in-situ covers.
Reference: Drawing SEW–1301-V.
18.6 BENCHING AND CHANNELS
Where possible, formwork shall be used to construct MH channels and benches. Where
the use of formwork is not possible, e.g. works on an existing MH, thoroughly roughen and
clean each base. Brush on a coating of wet to dry epoxy, or sulphate-resistant cement
slurry or other suitable priming product. Render and shape benches and channels in
accordance with Design Drawings using a 2:1 sand:sulphate-resistant cement mix. Ensure
that the render is no less than 15 mm thick. Maintain in a damp condition for 72 hours after
finishing.
Where foam formwork is used, construct MH channels and benching with off-form finish.
18.7 CONCRETING FOR PLASTICS-LINED WORK
Plastics lining of MHs shall only be carried out where approved or specified by the Water
Agency.
18.7.1 Concrete work planning
Plan the sequence of installing in-situ concrete work for floor or base slabs and/or benches
and channels to be plastics lined such that it:
(a) Complies with the plastics lining material manufacturer's printed instructions for
incorporation of lining into in-situ concrete.
(b) Facilitates embedment of plastics lining keys and of rigid PVC or PE invert channel
ribbing into the plastic concrete.
(c) Facilitates compaction of and entrained air release from plastics lined concrete in the
plastic state by means of suitable concrete compaction equipment.
(d) Ensures removal of all concrete mortar from lining areas to be jointed or welded while
the concrete is in the plastic state.
18.7.2 Fixing of plastics lining for concrete work
Prior to placing concrete reinforcement, align the plastics lining such that it is free from
wrinkles and bulges and is securely held to prevent movement during subsequent
operations.
Seal together all plastics lining joint work prior to concrete placement to prevent concrete
grout migration from behind the lining.
18.7.3 Concrete placement and formwork removal
Place and compact in-situ concrete to produce a dense homogeneous concrete. Securely
anchor plastics lining keys in place. Avoid damaging the lining.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


207 WSA 02—2002-2.3

After concrete curing, remove formwork carefully without damaging the lining. Do not use
sharp tools to pry forms from lined surfaces. Repair all tears, abrasions and cuts in plastics
lining in accordance with the plastics lining manufacturer's printed repair instructions.
18.8 INTERNAL COATING OF CONCRETE MHs
Epoxy coating of MHs for repair purposes shall require Water Agency approval.
Epoxy coat MHs in accordance with the manufacturer’s printed instructions and as
specified.
18.9 COVERS
All frames and covers are to be cleaned and greased with an approved lubricant, in
accordance with the manufacturer’s requirements upon installation and after each entry.
When covers are installed within a concrete pavement, an expansion joint is to be installed
around the surround.
Covers that do not have a concrete or recycled plastic surround shall not be used in
unsealed areas, e.g. gravel, grass, gardens.
Reference: Drawings SEW–1300-V, SEW–1301-V and SEW–1308-V.
18.10 CONNECTIONS TO MHs
Make connections to MHs as specified.
Where polyethylene, polypropylene or similar materials are used in connections,
incorporate a hydrophilic seal around the fitting in at least two positions.
Reference: Drawings SEW–1302-V, SEW–1303-V and SEW–1313-V.
18.11 MH DROPS
Construct MH drops as specified.
Core drill holes in precast or cast in-situ MHs using a diamond hole saw of the appropriate
diameter. Only use other techniques for creating holes in precast or cast in-situ MHs with
the authorisation of the Superintendent.
MH drops shall generally be constructed using PVC or PE pipes and fittings. PVC is also
an approved material for MH drops in industrial and commercial areas, due to the ease of
replacing them if necessary.
Reference: Drawings SEW–1303-V and SEW–1306-V.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 208

19 MAINTENANCE SHAFTS (MS AND TMS) AND INSPECTION SHAFTS (IS)


19.1 GENERAL
Install MSs, TMSs and ISs as specified. Where the manufacturer’s printed installation
instructions vary from the Design Drawings, refer to the Superintendent for written
instruction.
Embed and surround MSs, TMSs and ISs with embedment material as specified for the
reticulation sewer.
Compact embedment as specified for reticulation sewer trench fill.
Provide and install covers and surrounds as specified.
Reference: Standard Drawings SEW–1316 and SEW–1317
Reference: Drawings SEW–1105-V, SEW–1153-M, SEW–1154-M, SEW–1155-M, SEW–
1314-V and SEW–1315-V.
19.2 SEALING CAPS
Cut the MS / TMS / IS shaft to provide the access cover clearance as specified. Seal the
shaft with an approved bayonet cap in accordance with the manufacturer’s instructions.
Reference: Standard Drawings SEW–1106, SEW–1316 and SEW–1317
Reference: Drawing SEW–1314-V
19.3 COVERS
Install approved covers and frames as specified.
The Constructor shall ensure covers are adequately supported by compacted bedding
material and by timber where appropriate.
Reference: Standard Drawing SEW–1317
Reference: Drawings SEW–1153-M, SEW–1154-M, SEW–1155-M, SEW–1314-V
19.4 CONNECTIONS TO MSs AND TMSs
Make connections of sewers to MSs and TMSs as specified in the Product and Material
Information and Guidance and the Water Agencies’ Approved Products List and in
accordance the manufacturer’s printed instructions.
Reference: Standard Drawing SEW–1316
Reference: Drawing SEW–1314-V.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


209 WSA 02—2002-2.3

20 PIPE EMBEDMENT AND SUPPORT


20.1 GENERAL
Provide embedment and support of the type shown in the Design Drawings, Purchase
Specifications and the Products and Materials Information and Guidance.
Place embedment material uniformly along and around the whole length of the pipe barrel,
couplings and other appurtenances in a manner to ensure uniform density of side support
(including haunch support) and overlay with no distortion, dislodgment or damage to the
pipeline and maintenance structures.
Ensure that the depth of bedding material below the pipe collar is not less than 50% of the
minimum bedding specified for the pipe.
Where the sewer is supported on concrete, do not place overlay material until the concrete
has obtained its initial set.
20.2 EMBEDMENT MATERIALS
Use embedment materials that:
(a) Comply with the maximum particle sizes in Table 20.1 or
(b) Are as specified in the Design Drawings, Products and Materials Information and
Guidance and the Purchase Specifications.

TABLE 20.1
MAXIMUM PARTICLE SIZE

Pipe size Maximum particle size


DN mm
≤100 10
>100 to ≤160 14
>160 20

Reference: Standard Drawings SEW–1202, SEW–1203, SEW–1316 and SEW–1317


Reference: Drawings SEW-1201-V, SEW–1314-V and SEW–1315-V.
20.3 COMPACTION OF EMBEDMENT
Following placement, compact embedment material to achieve the specified density and to
uniformly support the pipe. Compact in layers to achieve the specified density uniformly
throughout the depth of each layer and the degree of compaction specified in Table 22.1 or
Table 22.2 as applicable.
20.3.1 Methods
When choosing compaction equipment, the number of passes and the thickness of layer to
be compacted, take account of the material to be compacted and the pipe to be installed.
Do not employ compaction equipment or methods that produce horizontal and/or vertical
earth pressures that may cause damage to or excessive distortion of the sewer or
maintenance structures.
Do not use flooding compaction unless specifically authorised by the Superintendent and
the Water Agency.
If flood compaction is authorised:
(a) only use in situations where embedment material is non-cohesive (i.e. no clays) and
the surrounding native soil and the embedment material are completely free draining;

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 210

(b) only use beneath non-trafficable areas where compaction trials have been
undertaken and proven successful; and
(c) do not use beneath trafficable areas.
20.3.2 Compaction trials / Pre-qualification of embedment compaction method
20.3.2.1 General
With reference to Clause 22.3.3.2, pre-qualification of the pipe embedment material and
process, as detailed below, is an alternative to conducting embedment compaction testing
of pipes of size ≤DN 300.
20.3.2.2 Test method
Install a length of pipe at least 4 m long in a trench having minimum side clearance of
200 mm and in soil having a bearing pressure >50 kPa. Bed the pipe and place and
compact embedment in accordance with Clauses 20.1 to 20.3.1 inclusive.
Record the Purchase Specification or equivalent specification to which the embedment
material conforms. Record the compaction method in a format suitable for use as an on-
site work instruction.
Conduct compaction testing at the spring line along the pipe length at its mid-point and at
locations 1 m either side. Assess results of compaction tests for compliance with
Table 22.1 or Table 22.2 as appropriate. Record compaction test results.
Retain records of the compaction method and trial reports.
20.3.2.3 Interpretation and applicability
Provided that all compaction test results conform to the requirements of Table 22.1 or
Table 22.2, as appropriate, the test shall be deemed to pre-qualify the compaction method
for pipelaying subject to:
(a) the diameter of the pipe being the same as that used in the pre-qualification test;
(b) the actual embedment material used in construction being the same as used in the
pre-qualification test;
(c) the documented pre-qualified compaction method being used; and
(d) the native soil having a bearing capacity >50 kPa.
20.3.3 Compaction control
Compaction of the embedment zone shall comply with Table 22.1 or Table 22.2, as
appropriate.
The extent of embedment compaction testing shall be as specified in Clause 22.3.3.
20.4 SPECIAL BEDDING AND EMBEDMENTS / GEOTEXTILE SURROUND AND
PILLOW
Install special embedment as specified.
Reference: Standard Drawings SEW-1203, SEW–1204 and SEW–1205.
20.5 REMOVAL OF TRENCH SUPPORTS
Except where otherwise specified, lift temporary trench support systems progressively
above each layer of embedment to ensure that each layer is compacted against
undisturbed native soil (trench wall).
20.6 CONCRETE EMBEDMENT AND ENCASEMENT
Concrete embed or encase pipes as specified and in accordance with Clause 14.5.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


211 WSA 02—2002-2.3

Set pipes to line and level on either bags of natural fibre filled with sand and cement mix or
on concrete blocks or saddles cast to the outside diameter of the barrel and located near
the socket. Ensure that pipes do not move, float or deform while pouring concrete.
Provide rubber-ring jointed pipe "shorts" 600–1000 mm long immediately upstream and
downstream of the concrete embedment or encasement to allow for differential movement.
Construction joints in concrete embedment or encasement shall be in accordance with
Standard Drawing SEW–1205 and shall only be permitted where shown on the drawings
and where approved by the Water Agency.
Reference: Standard Drawings SEW–1204, SEW–1205, SEW–1208 and SEW–1400
Reference: Drawings SEW–1401-V and SEW–1402-V.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 212

21 FILL
21.1 TRENCH FILL
21.1.1 General
Place trench fill as specified. Use appropriate methods of compaction to achieve the
compaction requirements of the Design Drawings and the Water Agency’s trench fill
specification.
Avoid impact loading of the sewer and maintenance structures during placement of trench
fill material.
Do not place trench fill material within 24 h of placing embedment or encasement concrete,
or longer period if shown in the Design Drawings or Specification.
Fill voids behind timber ground support in close-timbered tunnels, drives and shafts by
pressure grouting or other authorised means.
Raise the fill evenly around MH and MS risers and compact in shallow layers to avoid
unbalanced lateral loading.
Take special care to prevent displacement of precast MH joints and MS risers, access
cover assemblies or supports.
Correct any deficiencies of trench filling exposed by settlement.
Reference: Standard Drawings SEW–1202, SEW–1203, SEW–1204 and SEW–1205
Reference: Drawing SEW–1201-V.
21.1.2 Material requirements
The trench fill material shall comply with the Water Agency’s trench fill specification and
Design Drawings.
Where the filled trench will be subjected to traffic loading, the fill material shall comply with
the requirements of the road Owner. In the absence of a directive from the road Owner, the
fill material shall comply with the Water Agency’s trench fill specification.
21.1.3 Compaction of trench fill
The degree of trench fill compaction shall conform to the Water Agency’s trench fill
specification.
The extent of trench fill compaction testing shall be as specified in Clause 22.3.4 and in the
Water Agency’s trench fill specification.
Compact trench fill material in layers to achieve the required density uniformly throughout
the depth of each layer. Where settlement of the finished surface is to be controlled, use a
fill material that can be compacted to the required high degree of compaction.
Do not commence mechanical compaction of fill material directly above the pipe until the
total depth of cover above the pipe is adequate to prevent damage to the main.
The depth of fill material required before mechanical compaction can be used depends on
the type of compaction device.
For hand-held or walk-behind compaction equipment, provide at least 200 mm cover and
for larger “ride-on” machines operating within the trench, increase this depth at least
300 mm.
Compact trench uniformly and carefully around maintenance structures, jump-ups, stacks
etc.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


213 WSA 02—2002-2.3

21.2 EMBANKMENT FILL


Where the route of a sewer requires filling or construction of an embankment, provide fill
along the route of the type shown in the Design Drawings.
Proceed as follows:
(a) Prepare the foundation for the fill by cleaning away all debris, vegetation, organic
material and topsoil for the full width of the fill area.
(b) Compact the cleared soil surface to not less than 95% of its standard maximum dry
density (AS 1289.5.1.1).
(c) Place the fill in layers not exceeding 200 mm thickness and compact each layer to
not less than 95% of its standard maximum dry density (AS 1289.5.1.1). Bring the
compacted fill level up to a height of at least 300 mm above the design level of the
top of the pipe.
(d) Place the remainder of the fill in layers not exceeding 300 mm thickness and compact
each layer to not less than 95% of its standard maximum dry density (AS 1289.5.1.1).
21.3 DRIVES AND TUNNEL FILL
Refill drives and tunnels above the embedment zone to the obvert of the drive or tunnel
using an approved method of filling in accordance with the Water Agency’s trench fill
specification.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 214

22 ACCEPTANCE TESTING
22.1 GENERAL
Acceptance testing is required to test the capability of the sewer assembly to satisfy design
requirements as specified. It is not intended to test the material capability. Testing is
intended to:
(a) Reveal the existence of any assembly and structural faults.
(b) Ensure the sewer can operate without infiltration or exfiltration.
(c) Confirm the success of placement and compaction of pipe embedment and trench fill,
design and placement of thrust and anchor blocks and installation of pipeline
components.
Undertake acceptance testing of all sewers and structures in accordance with the
Specification and in the following order:
1 Visual inspection—above-ground.
2 Compaction testing.
3 Pressure testing (low pressure air or vacuum or hydrostatic).
4 Infiltration testing.
5 Deflection testing.
6 CCTV inspection.
Deflection testing and CCTV inspection may be performed concurrently.
Vacuum testing is considered superior to air testing for detecting potential infiltration into
non-pressure pipelines; however, low pressure air testing is currently the predominant
acceptance testing practice. The parameters and requirements low pressure air testing
have been included as an interim measure for those Water Agencies still using the
practice.
Notification of acceptance testing and responsibilities for reporting shall be in accordance
with the Water Agency’s requirements. The Constructor must provide two (2) clear working
days notice to the Superintendent and the Water Agency prior to commencement of all
acceptance testing activities. Each notice of testing must include:
(i) Water Agency’s Project Reference Number
(ii) Estate Name, Address and Location
(iii) Constructor’s name and contact details
(iv) Consultant’s name and contact details
(v) Date and timing of test
(vi) Details of testing intended.
All test results, including unsatisfactory results, shall be documented and reported to the
Superintendent.
As appropriate, clean sewers and structures before any test is performed.
Compaction testing shall be carried out by a NATA accredited organisation that holds
current listing for the relevant acceptance test.
If any of the tests prove to be unsatisfactory, detect and rectify the fault. Continue to rectify
and retest the sewer until a satisfactory test result is obtained. Even if testing produces
satisfactory results, rectify any sewer, structure or appurtenance that has a visible or
detectable leak, blockage, malfunction or other defect.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


215 WSA 02—2002-2.3

22.2 VISUAL INSPECTION—ABOVE-GROUND


Visually inspect all sewers, maintenance structures and vents to ensure their assembly and
the type and locations of maintenance structures, including access covers, and vents are
as specified and all materials used are approved products.
22.3 COMPACTION TESTING
22.3.1 General
Undertake field density tests of the embedment and trench fill zones at the frequency and
locations nominated in Clauses 22.3.3 and 22.3.4.
Conduct testing of embedment compaction before trench filling.
22.3.2 Minimum compaction
Ensure compaction of embedment and fill is not less than the values given in Tables 22.1
and 22.2, as appropriate.
22.3.3 Embedment compaction testing
22.3.3.1 Applicable pipe sizes
Undertake compaction testing of pipeline embedment for sewers >DN 300.
Except where the Superintendent nominates random confirmatory tests, do not undertake
compaction testing of pipeline embedment for mains ≤DN 300 where:
(a) the allowable bearing pressure of the native ground is ≥50 kPa when assessed in
accordance with SEW–1200;
(b) pipe laying and embedment compaction was carried in accordance with this Code;
and
(c) a pre-qualified compaction method was used in accordance with Clause 20.3.2.
22.3.3.2 Frequency and location of embedment tests
Except where the provisions of Clause 20.3.2 apply, test sewers ≤DN 300 at the spring line
(±50 mm) for each 100 lineal metres of pipeline or part thereof.
For sewers >DN 375, test at the spring line (±100 mm) for each 50 lineal metres of pipeline
or part thereof.
22.3.3.3 Retesting
If one or more of the initial test results do not comply with Table 22.1 or Table 22.2,
conduct two additional tests in the zone represented by the initial test. If one or more of the
repeat tests does not comply, re-compact the full zone and continue repeat testing.
Continue this cycle until the embedment compaction test results comply with Table 22.1 or
Table 22.2.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 216

TABLE 22.1
EMBEDMENT OF FLEXIBLE PIPES
MINIMUM COMPACTION

Minimum density index


Embedment type Test method
Trafficable areas Non-trafficable areas
Non-cohesive Density index (ID) 70 70
(Note) AS 1289.5.6.1
Cohesive (Note) Density ratio (RD) 95 95
AS 1289.5.4.1 and
AS 1289.5.1.1

NOTE: Type 3 support of SEW–1202 requires non-cohesive embedment material. Cohesive graded
sands and gravels may be authorised by the Water Agency.

TABLE 22.2
EMBEDMENT OF RIGID PIPES
MINIMUM COMPACTION
Embedment type Test method Minimum value
Trafficable areas Non-trafficable areas
Non-cohesive Density Index (I D )
60 60
AS 1289.5.6.1
Cohesive Density Ratio (R D )
(Notes 1, 2) AS 1289.5.4.1 and 90 90
AS 1289.5.1.1

NOTES:
1 Graded gravels or sands having fines (silts and clays) greater than 5% have their compaction
determined by dry density ratio.
2 Type 1 and 2 supports on SEW–1202 permit cohesive material at the side of the pipe above the
support material.

22.3.4 Trench fill compaction testing


All trench fill compaction testing shall be carried out in accordance with the Water Agency’s
trench fill specification.
22.3.4.1 Trafficable Test Zone
Not used by MRWA.
22.3.4.2 Non-trafficable test zone
Not used by MRWA.
22.3.4.3 Test method
Not used by MRWA.
22.3.4.4 Frequency and location of tests
Not used by MRWA.
22.3.4.5 Retesting
Not used by MRWA.
22.3.5 Other fill compaction testing
All trench fill compaction testing shall be carried out in accordance with the Water Agency’s
trench fill specification.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


217 WSA 02—2002-2.3

22.3.5.1 General
Not used by MRWA.
22.3.5.2 Trafficable test zone
Not used by MRWA.
22.3.5.3 Non-trafficable test zone
Not used by MRWA.
22.3.5.4 Frequency and location of tests
Not used by MRWA.
22.3.5.5 Retesting
Not used by MRWA.
22.4 AIR PRESSURE AND VACUUM TESTING OF SEWERS
22.4.1 General
Pressure (leakage) testing, either low pressure air testing or vacuum testing, is only
qualitative as pressure losses do not directly reflect water leakage rates. It is used to
identify points of leakage and potential pipeline infiltration and exfiltration due to damaged
pipe seals and joints.
For sewers of size >DN 750, the Water Agency shall advise testing requirements and/or
enhanced inspection and control requirements during construction. The Constructor shall
take particular care in respect of additional safety precautions required for testing large
diameter sewers.
Vacuum or air pressure test all sewers ≤DN 1500 in accordance with Clauses 22.4.2.1 or
22.4.2.2. Include external MH drops, property connection sewers, vertical risers, MSs and
inspection shafts and fittings.
Undertake vacuum tests where the Specification does not specify the test method.
Test after placement and compaction of pipe embedment, including overlay and
construction of property connections, MSs and ISs.
Make calibration certificates for all air pressure and vacuum testing equipment available to
the Superintendent on request.
Sewers ≥DN 750 should be inspected and tested during construction and before the
construction of MHs. The test may be conducted after trench filling but repair / rectification
costs would almost certainly be greater.
22.4.2 Air testing methods for sewers
22.4.2.1 Vacuum testing
The following testing requirements shall apply where sewer pipeline vacuum testing is
specified.
Plug all sewer inlets and outlets and cap and seal all MS risers in the test length of sewer.
Apply an initial test vacuum pressure (negative pressure) of approximately 27 kPa. Close
the valve on the vacuum line and shut off the vacuum pump. Allow the air pressure to
stabilise for at least 3 minutes to identify any initial leakage.
When the pressure has stabilised and is at or below the starting test vacuum of 23.6 kPa,
commence the test by allowing the gauge pressure to drop to 23.6 kPa, at which point
initiate time recording. Record the drop in vacuum over the test period.
Accept the length of sewer under test if the test vacuum loss is ≤7 kPa for the relevant time
interval specified in Table 22.4.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 218

If the sewer fails the test, re-apply the vacuum to identify any leaks.
Rectify all defects prior to conducting any further testing.
Rectify any visible or audible faults even if the vacuum testing is satisfactory.
This test method is based on ASTM test method C1214M, which may be downloaded from
www.astm.org/cgi-bin

TABLE 22.4
PRESSURE AND VACUUM AIR TESTING
ACCEPTANCE TIMES FOR 7 KPA PRESSURE CHANGE

Test length
m
Pipe size
50 100 150 200 250 300
DN
Minimum test duration
minutes
100 2 2 2 2 3 3
150 3 3 3 5 6 6
225 4 5 8 10 13 15
300 6 9 14 18 23 29
375 7 14 22 29 36 43
450 10 21 31 41 52 66
525 14 28 42 56 70 86
600 18 37 55 73 92 106
675 23 46 70 93 116 144
750 29 57 86 115 143 168
900 41 83 124 165 207 243
1000 51 102 153 204 255 300
1050 56 112 169 225 281 319
1200 73 147 220 294 367 460
1500 115 230 344 459 574 700
NOTES:
1 Timing of the test duration shall commence after the 3 minutes initial
pressurisation and only where pressure has stabilised.
2 Test duration times for other combinations of pipe size and test length
shall be interpolated.

22.4.2.2 Low pressure air testing


Limit testing to sewers ≤DN 1500 and to runs between MHs and/or MSs of ≤300 m.
Low pressure air testing shall be completed after trench backfilling and compaction, and
where maintenance holes/shafts/inspection shafts and property connections have been
completed.
Plug all sewer inlets and outlets and cap and seal all MS risers in the test length of sewer.
All test plugs shall be appropriately secured in accordance with the manufacturer’s
specifications.
Slowly apply an initial test pressure of approximately 28 kPa, since rapid pressurisation
can cause significant air temperature changes that may affect testing accuracy. Where the
sewer is below the water table, increase the stated pressure to achieve a differential
pressure of 28 kPa, but do not exceed 50 kPa actual test pressure.
Close the valve on the air pressure line and shut off the pump. Allow the air pressure to
stabilise for at least 3 minutes to identify any initial leakage.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


219 WSA 02—2002-2.3

For pipelines ≤DN 600, the following test durations and allowable pressure losses specified
in Tables MRWA 22.4.1 and MRWA 22.4.2 shall apply.
Accept the length of sewer under test if the test pressure loss is ≤7 kPa for vitrified clay,
PVC, PE profiled wall, PP profiled wall and GRP rubber ring jointed pipe materials for the
test durations specified in Table MRWA 22.4.1.
TABLE MRWA 22.4.1
RUBBER RING JOINTED PIPE

Pipeline nominal size (DN) Test duration (minutes)

100 and 150 3

225 and 300 6

375 and 450 9

525 and 600 12

Accept the length of sewer under test if the test pressure loss is ≤2 kPa for solid wall PVC,
sandwich wall PVC solvent cement joint pipe materials and PE solid wall fusion jointed
pipe materials for the test durations specified in Table MRWA 22.4.2.
TABLE MRWA 22.4.2
SOLVENT CEMENT AND FUSION JOINTED PIPE

Pipeline nominal size (DN) Test duration (minutes)

100 and 150 6

225 and 375 9

For pipelines ≥DN 675 (irrespective of material or jointing system) and ≤DN 1500, the test
durations and allowable pressure losses specified in Table 22.4 shall apply.
If the sewer fails the test, re-apply the test pressure to identify any leaks.
Rectify all defects prior to conducting any further testing.
Rectify any visible or audible faults even if the pressure testing is satisfactory.
A calibrated pressure relief valve, set at a maximum pressure of 50 kPa, shall be installed
on all low pressure testing equipment.
22.4.3 Testing of sewers >DN 1500
22.4.3.1 General
Test every joint of all sewers >DN 1500 including specified maintenance structures and
inverted syphons in accordance with Clause 22.4.3.2.
Make calibration certificates for all pressure and vacuum testing equipment available to the
Superintendent on request.
22.4.3.2 Method of test
Design and construct a joint test apparatus to enable air pressure or vacuum testing of
each joint from within the sewer.
Test every joint using the relevant test procedure of Clause 22.4.2.1 or Clause 22.4.2.2.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 220

22.4.4 Testing of concrete MHs


22.4.4.1 General
Cast in-situ and precast concrete MHs to be tested shall be selected independently of the
Constructor. The Superintendent or the Water Agency shall nominate the maintenance
hole(s) or maintenance shaft(s) to be tested.
Vacuum test not fewer than the number of MHs as shown in Table 22.5. Where projects
contain both precast concrete and cast in-situ MHs, view each type as a separate
population and the criteria of Table 22.5 shall apply to each population separately within
the project. If any of the sample MHs fail the initial test, test all remaining MHs in that
population.
Test after placement and compaction of embedment surround.
Maintenance and inspection shafts may be tested as part of the sewer.
22.4.4.2 Test method
Apply an initial test vacuum pressure (negative pressure) of approximately 35 kPa to the
top of the MH. Close the valve on the vacuum line and shut off the vacuum pump. Allow
the air pressure to stabilise for at least 3 minutes to identify any initial leakage.
When the pressure has stabilised and is at or above the starting test vacuum of 28 kPa of
mercury, initiate the test by allowing the gauge pressure to drop, if any, for the duration of
the test period.
Accept the MH under test if the time for the vacuum pressure loss is ≤5 kPa after a
minimum of 3 minutes.
If the test failed, re-apply the vacuum to identify any leaks.
Rectify all defects prior to conducting any further testing.
Rectify any visible or audible faults even if the vacuum testing is satisfactory.

TABLE 22.5
CONCRETE MH TESTING FREQUENCY

Number of each type Minimum percentage tested initially (Note 1)


of MHs in the project Cast in-situ concrete Pre-cast concrete
≤5 100%
6 to 10 20% 100%
11 to 20 100%
>20 100%

NOTES:
1 Where projects contain both precast concrete and cast in-situ concrete, each type
shall be viewed as a separate population and the above criteria shall apply to
each population separately within the project.
2 If any of the MHs fail the initial test, all remaining MHs in that population shall be
tested.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


221 WSA 02—2002-2.3

TABLE 22.6
MINIMUM TEST TIMES FOR CONCRETE MHs
MH Depth MH Diameter
mm
900 1050 1200 1500 1800
Time*
m s
2.4 14 17 20 26 33
3.0 18 21 25 33 41
3.7 21 25 30 39 49
4.3 25 30 35 46 57
4.9 29 34 40 52 65
5.5 32 38 45 59 73
6.1 35 42 50 65 81
6.7 39 46 55 72 89
7.3 42 51 59 78 97
7.9 46 55 64 85 105
8.5 49 59 69 91 113
9.1 53 63 74 98 121

NOTE: Times for intermediate diameters and depths may be


interpolated.

22.5 INFILTRATION TESTING


Where a free standing water table exists at a level of ≥1.5 m above a sewer or ≥150 mm
above any side connections along the sewer, conduct an infiltration test to determine the
extent of any infiltration.
Accept the test length if there is no infiltration.
Where the Superintendent accepts some infiltration due to the size of the catchment and
the number of connections serviced by the test length of sewer, the measured infiltration
over a 24 h period shall not exceed 5 L/mm diameter/km/day.
Rectify points of infiltration prior to conducting any further testing.
Rectify any visible or audible faults even if the infiltration testing is satisfactory.
22.6 DEFLECTION (OVALITY) TESTING OF FLEXIBLE SEWERS
22.6.1 General
Deflection testing is a valuable method of confirming the success of embedment placement
and compaction for non-pressure flexible pipelines.
Deflection testing can be undertaken using:
(a) Physical measurement in large diameter sewers.
(b) CCTV light ring and measurement software.
(c) An ovality proving tool calibrated to NATA’s requirements.
Proving tools if not correctly sized may damage the sewer.
Do not conduct deflection testing until at least 14 days after completion of placement and
compaction of trench and embankment fill material.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 222

Test sewers in sections from maintenance structure (MH, MS or TMS) to maintenance


structure.
22.6.2 Ovality proving tools
Ovality proving tools shall be made from a “soft” material, e.g. wood, to minimise damage
to the pipeline and shall have pulling rings at each end and marked to indicate the nominal
pipe size and outside diameter.
The diameter and shape of the proving tool shall be approved by NATA or the Water
Agency for each combination of pipe material, class (stiffness), type (plain wall, sandwich
construction, ribbed and profile wall) and manufacturer. The external diameter of the
proving tool shall be determined from:
OD = [0.01di (100 – n) – 2.5] ± 0.5 mm
where:
OD = prover outside diameter, mm
n = allowable percentage deflection, %
di = internal pipe diameter, mm.
Some product standards do not accurately specify internal diameters. Appendix G lists
default prover diameters for common sewer pipe materials.
22.6.3 Flexible sewers ≤DN 300
Test all flexible gravity sewers ≤DN 300.
22.6.4 Flexible sewers >DN 300
22.6.4.1 General
Test all flexible gravity sewers >DN300 to determine any excessive pipe deflection.
Measure the actual short-term vertical deflection in accordance with Clause 22.6.4.2 or
Clause 22.6.4.3 as appropriate. Accept sewers with deflection values less than those given
in Table 22.7.
Record locations where the measured or calculated deflection exceeds the maximum
allowable deflection stated in Table 22.7.
Repair all sections of pipe that exhibit excessive deflection. Retest each repaired section in
accordance with Section 22.

TABLE 22.7
MAXIMUM ALLOWABLE SHORT-TERM PIPE DEFLECTIONS

Maximum allowable short term vertical pipe deflection


Pipe material
%
3 d* 7 d* 14 d 30 d 3 months 1 yr
Plastics
ABS, PE, PP, PVC 3.8 4.3 4.8 5.0 5.5 6
GRP 3.0 3.4 3.8 4.0 4.4 4.8
Metallic
Ductile iron 0.8 0.9 1.0 1.0 1.1 1.2
Steel
Welded joint with:
—No cement mortar 2.3 2.6 2.9 3.0 3.3 3.6
lining

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


223 WSA 02—2002-2.3

Maximum allowable short term vertical pipe deflection


Pipe material
%
3 d* 7 d* 14 d 30 d 3 months 1 yr
—Cement mortar lining 1.5 1.7 1.9 2.0 2.2 2.4
Elastometric joint 0.8 0.9 1.0 1.0 1.1 1.2

NOTE: *for information purposes only

22.6.4.2 Flexible sewers >DN 300 and <DN 750


Conduct the test not less than 14 days after placement and compaction of trench fill.
Under special circumstances, the Superintendent may authorise the test to be conducted
earlier, but not before 3 days after placement and compaction of trench fill.
Test either by pulling, with a maximum pulling force of 400 N, a proving tool through each
section of pipe by hand winching to demonstrate that the maximum allowable deflection is
not exceeded, or by using another authorised instrumental method capable of measuring
and recording actual pipe deflections to an accuracy of ±0.50% actual pipe internal
diameter.
Failure to pull the prover through the sewer shall be deemed an unsatisfactory test result.
22.6.4.3 Flexible sewers ≥DN 750
Measure the internal vertical and horizontal diameters of each section of flexible pipe at
the joints and mid-points between joints and calculate the mean internal diameter.
Take measurements:
(a) immediately after the pipe embedment has been placed and compacted; and
(b) not less than 14 days after placement and compaction of the trench fill.
(c) between indelibly marked points on the pipeline internal surface.
The measuring equipment shall have an accuracy of measurement of ±1 mm.
Accept sewers with vertical deflections after 14 days that comply with the deflection limits
specified in Table 22.7.
Make calibration certificates for proving tools available to the Superintendent on request.
22.7 CCTV INSPECTION
Carry out a CCTV inspection of specified sewers and maintenance structures in
accordance with WSA 05. Use data capture software authorised by the Water Agency.
Apply the following requirements to the CCTV inspection:
(a) Use certified CCTV operators.
(b) Only accept CCTV videotapes of such quality that an accurate assessment of the
internal condition of the sewer can be made.
(c) Provide the CCTV records to the Superintendent as specified.
Apply the acceptance / rejection criteria of Appendix E of WSA 05.
Rectify all defects prior to conducting any further inspection.
If CCTV equipment used to conduct the inspection is not calibrated to NATA’s
requirements for quantifying observations, record the estimated value as an addendum to
the test report.
The Water Agency may specify alternative verification of the result prior to determining
whether remedial action is required.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 224

22.8 INSPECTION AND TESTING OF PLASTIC LINED CONCRETE SEWERS AND MHs
22.8.1 Visual inspection
Visually inspect all plastics-lined concrete sewers and MHs for defects such as cuts, tears,
or cracks and open or incompletely fused thermoplastic lining welds.
Reject linings with visible projections or depressions that exceed 25 mm depth measured
perpendicularly to the plastics lined surface.
Probe all fields welds of thermoplastic lining with a feeler gauge to determine all defective
welds requiring re-welding i.e. weak welds and welds where the probe enters more than
3 mm.
Mark all defects with chalk or a spirit pen with colour contrasting with the coating or lining.
Repair all visible and weld defects in accordance with the manufacturer’s printed
instructions using qualified welders and authorised methods.
22.8.2 Spark testing
After repair of visible and weld defects, undertake spark testing to detect discontinuities in
accordance with Clause 7 of AS 3894.1. Use equipment calibrated to 20 000 V within the
last 12 months in accordance with Appendix C of AS 3894.1. Allow 20 minutes inclusive of
warm-up for the spark testing equipment to reach equilibrium conditions.
Ensure the surface of the lining is dry. Adjust the voltage of the spark testing equipment to
12 000 +1 000 –0 V and secure an earth connection to the underlying substrate.
Pass the brush electrode of the spark testing equipment over the lining at a rate of not
greater than 0.3 m/s, maintaining contact between the electrode and the test area and
using an appropriate motion. Where the instrument indicates a discontinuity, determine the
exact location of the discontinuity (do not hold electrode stationary against the surface)
and clearly identify it on the test surface with the marker. Continue testing until the whole
of the coating or lining has been tested.
Undertake repair of discontinuities in accordance with the manufacturer’s printed
procedures.
Repeat spark testing and repair cycle until there are no discontinuities detected.
If overheating during repair causes any charring of thermoplastic welds, replace all charred
sections in accordance with the manufacturer’s printed procedures.
22.8.3 Locking key pull-out tests
For plastics-lined cast in-situ concrete MHs, conduct locking key pull-out test for each 5 m 2
of plastics lined work area nominated in either the Inspection and Test Plan or by the
Superintendent.
Use a pull-out force of at least 17.5 N per lineal mm of key applied perpendicularly to the
lined concrete surface for a period of at least one (1) minute at an ambient temperature of
between 20 and 27 °C.
In the event of any locking key failing to withstand the sustained 17.5 N pull-out force,
progressively extend the pull-out test to locations away from the failed key area so as to
determine the extent of non-conforming key embedment. Rework or repair non-conforming
key embedment areas of ≤0.5 m2 in any single pull-out test location in accordance with the
manufacturer’s printed procedures.
Reject MHs with key defective embedment areas >0.5 m2 in any single pull-out test
location.
Testing to be done by an authorised contractor.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


225 WSA 02—2002-2.3

MRWA 22.8.4 Digital coating thickness gauge


The Constructor may also use a digital coating thickness gauge to confirm the thickness of
the plastic or epoxy coating.
22.9 PRESSURE TESTING OF INVERTED SYPHONS
22.9.1 General
Pressure test all inverted syphons after construction and any concrete material has cured
for not less than 7 days, but prior to grouting, as appropriate.
If any of the tests prove to be unsatisfactory, detect and rectify the fault, and re-test.
Continue to rectify and re-test until a satisfactory test result is achieved. Even if testing
produces satisfactory results, rectify any syphon in which there is a visible or detectable
leak or blockage.
Test polyethylene syphons in accordance with WSA 01.
Base the rate of filling on a maximum velocity of 0.05 m/s.
Allow between 3 and 24 hours for the test water temperature to stabilise and dissolved air
to vent from the system. Fill cement-lined pipes 24 hours prior to testing to allow for
saturation of the lining.
Unless otherwise permitted by the Superintendent, adopt a maximum test length of
1000 m.
Acceptance testing may be conducted progressively with the authorisation of the
Superintendent. Testing may be carried out as soon as the Works are completed and
where thrust restraint curing times have lapsed.
22.9.2 System test pressure
Adopt a system test pressure in m equivalent to 10 times the PN rating of the pipe e.g. for
PN 6 pipe test at 60 m head (600 kPa).
22.9.3 Maximum allowable loss
Calculate the maximum allowable loss by:
(0.14 x d i x LP x H) / 1000 (L/h)
where: di = internal pipe diameter, mm
LP = length of inverted syphon under test (km)
H = average value of test head (m)
22.9.4 Test procedure
Use a test rig that has two calibrated pressure gauges. Each gauge shall have a range of
0–2500 kPa and shall have a current calibration certificate. Both gauges shall read within
±5% of the test head and 5% of each other. Use the gauge recording the lower of the two
readings. Before testing, clean the syphon and then slowly fill it with water, ensuring that
air has been completely expelled.
With the exception of polyethylene, which is to be tested in accordance with WSA 01, test
all syphons as follows:
(a) Install blank flanges or caps at each end of the test section. Do not test against
closed valves unless they are fully restrained and it is possible to check for leakage
past the valve seat. Temporarily strut or anchor mechanical ends that are not end
load resistant to withstand the test pressures without movement.

(b) Clearly inform all personnel of the loading limits on temporary fittings and supports.

(c) Pressurise the line to 75% of the test pressure and leave for a minimum of 12 hours.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 226

The preliminary pressurisation is intended to:


(i) stabilise the syphon by allowing most of the time-dependent movement to
occur;
(ii) achieve saturation in absorbent materials; and
(iii) allow pressure-dependent increase in volume of flexible pipes prior to the main
test.
(d) Provided there is no obvious leak in the syphon, steadily raise the pressure in the
syphon until the specified test pressure is reached.

(e) Maintain the test pressure for four (4) hours. Measure and record, at half hour
intervals, the quantity of water added in order to maintain the pressure during the
period of testing.

(f) Visually inspect the line for leaks if practicable. If a leak is suspected but is not
visible, use aural or electronic assistance.

(g) Do not remove temporary supports until the syphon has been depressurised.

(h) Dispose of test water in accordance with the relevant environmental Regulator and
Water Agency requirements.

22.9.5 Satisfactory pressure test


Accept the pressure test on a syphon if:
(a) There is no failure of any thrust block, anchor block, pipe, fitting, valve, joint or any
other pipeline component;
(b) There is no visible leakage;

(c) The measured loss rate for the relevant test period of the pressure testing does not
exceed the maximum allowable loss rate as determined in accordance with Clause
22.9.3; and

(d) For polyethylene syphons, compliance with the requirements of Clause 2.13.5 of
WSA 01 is achieved, which shall comply with the requirements of Clause 2.13.4 or
Clause 2.13.5 of WSA 01.

22.9.6 Failure of test


For failed syphons, either:
(a) Carry out two (2) further pressure tests; or

(b) Rectify the work and retest.

If both additional tests pass, accept the syphon. If one or both of the additional tests fail,
rectify the work.
Within two weeks of the completion of any rectification work, perform another test on the
syphon. If the test fails, rectify the work and retest. Rework until all test results are
satisfactory.
MRWA 22.9.7 Rectification of faults
The use of concrete bandages to rectify faults will not be permitted on vitrified clay
pipelines of nominal size DN 100, DN 150 and DN 225 or PVC, Polyethylene and GRP
pipelines. Approved repair couplings must be used.
The use of epoxies, sealants, caulking compounds, etc in order to pass air tests is not
permitted.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


227 WSA 02—2002-2.3

23 TOLERANCES ON AS-CONSTRUCTED WORK


Construct all specified sewers, associated structures and appurtenances to the tolerances
specified Clauses 23.1 to 23.4.
23.1 HORIZONTAL TOLERANCES
23.1.1 Sewers and on-line structures (e.g. MHs, MSs, TMSs, ISs or vents)
Do not exceed positional tolerances as follows:
Sewers – ±100 mm lateral displacement from the design sewer alignment.
Structures – ±100 mm lateral displacement from the design sewer alignment; and
– ±200 mm displacement (from the design position) along the sewer axis.
Junctions – ±100 mm displacement (from the design position) along the sewer axis.
23.1.2 Property connection sewers
Do not exceed positional tolerances as follows:
Property connection sewers – ±100 mm displacement (from design position) along sewer
axis.
Property connection risers, inspection openings and surface fittings – same lateral
displacement as for the sewer junctions and ±100 mm displacement along the property
connection sewer axis.
23.2 VERTICAL TOLERANCES
23.2.1 Sewers and structures
Do not deviate the inverts of new sewers, property connection sewers and structures from
the specified design level (or interpolated design level) by more than 10 mm higher or
50 mm lower, provided the specified sewer design grades are within tolerance (Refer to
Table 23.1).
Link up to existing sewers and structures at the design levels and equal to or greater than
the minimum acceptable grades.
Reverse grades are not permitted.
23.2.2 Property connection risers and inspection openings
Do not deviate the inverts of property connection risers and inspection openings from the
specified design level (or interpolated design level) by more than 10 mm higher or 150 mm
lower, provided the property connection sewer design grades are within tolerance (Refer to
Table 23.1).
23.2.3 Grade
Do not permit backfall at any point along the sewer. Maintain the inverts of new sewers and
property connection sewers within the tolerances shown in Table 23.1 and Table 23.2.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 228

TABLE 23.1
SEWER GRADE TOLERANCES

Category Design grade Minimum acceptable grade


Flat grades ≤1.0% 10% flatter, 10% steeper
(less than or equal to 1 in 100)
Flat to >1.0% ≤ 5.0% 15% flatter, 15% steeper
moderate (greater than 1 in 100 and)
grades (less than or equal to 1 in 20)
Moderate to >5.0% 20% flatter, 20% steeper
steep grades (greater than 1 in 20)

TABLE 23.2
PROPERTY CONNECTION SEWER GRADE TOLERANCES

Category Design grade Minimum acceptable grade


DN 100 1.65% 15% flatter, 15% steeper
(1 in 60)
DN 150 1.2% 15% flatter, 15% steeper
(1 in 83)

23.2.4 Verticality (“plumb”)


For MHs, MSs, TMSs, inspection shafts, vertical risers and vents, apply a tolerance at any
point on the pipe or structure as follows:
(a) 10 mm deviation (from vertical) per metre rise in any direction, and
(b) limited to a maximum 50 mm cumulative deviation (from vertical) in any one particular
direction for structures higher than 5 m.
23.3 TOLERANCES ON FINISHED SURFACE STRUCTURES AND FITTINGS
For structures and fittings designed flush with the ground/pavement surface or proud of the
surface, (e.g. MHs, MSs, TMSs, inspection shafts, vertical risers, and the like), apply a
vertical tolerance on the finished design surface levels as follows:
(a) ±5 mm in road reserves, including sealed pavements, road verges, driveways,
footpaths, pedestrian thoroughfares and sealed and trafficable areas within private
properties (pedestrian and/or vehicular traffic); and
(b) +50 mm,−20 mm in private property including garden areas, unsealed areas,
non-trafficable areas or areas of occasional traffic (pedestrian and/or vehicular
traffic).
23.4 CAST IN-SITU CONCRETE STRUCTURES AND SLABS
In addition to the tolerances of Clause 23.3, apply a construction tolerance on the specified
internal dimensions (e.g. diameter, length, width, depth etc.) for cast in situ concrete
structures and the external dimensions of slabs of +5%,−2%.
Apply a construction tolerance on all thicknesses specified of +50,−0 mm.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


229 WSA 02—2002-2.3

24 CONNECTION TO EXISTING SEWERS


Ensure that the connection of new works to existing sewerage systems is undertaken only
by authorised Constructors registered with the Water Agency and using authorised
methods and equipment. Ensure that Works in this environment comply with the relevant
Water Agency requirements for work on live sewers. Do not make connections until all
other Works are completed.
Ensure the method and timing of the connection Works take account of operational needs
of the existing sewerage system and customer service requirements.
Ensure all the necessary materials and equipment are available on site prior to
commencement of the connection Works. In making a connection, minimise interruption to
operation of the existing sewerage system and avoid overflow of sewage. If necessary,
provide bypass pumping of sewage flows around the point of connection.
Notify the Water Agency and environmental Regulator immediately if spillage occurs. Make
every effort to contain any spillage.
Carry out all preparatory and backfilling work which may include but not be limited to:
(a) Exposure of the existing MH inlet or sewer to allow ready access for the connection
to be made or, where specified, inserting a junction or construction of a new
maintenance structure over the existing sewer.
(b) Making connection as specified.
(c) Provision of trench support.
(d) Supply of authorised trench fill material in the case of road works or where additional
compaction is required.
(e) Traffic control to allow safe passage of pedestrians, vehicular traffic and various
plant.
(f) Backfilling, compaction and restoration works after completion of the connection.
(g) The Constructor shall make allowance for testing the new works. Where a
maintenance structure is not constructed at the interface between the existing and
proposed works, the Constructor might consider installing an IO in the line to enable
access for testing.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 230

25 RESTORATION
25.1 GENERAL
The requirement to restore surfaces shall apply to construction by means of trenching,
tunnelling or boring.
Restore to pre-existing condition, all surfaces, services and/or improvements disturbed,
destroyed, removed or damaged during construction of the Works and/or during installation
of temporary Works such as access roads to the requirements of the Water Agency and
the Owner(s).
The Water Agency’s relationship with its customers may be significantly enhanced by
providing excellent service, particularly in the area of site restoration. Consequently, there
is an expectation that restoration should be to the highest standards.
The site shall be:
(a) Kept in a safe, clean and tidy manner during construction; unsightly items such as
spoil stockpiles and barricades shall be kept to a minimum; site debris and excess
materials shall be regularly cleaned up, removed and properly disposed.
(b) Restored progressively and as soon as possible; restoration work shall not be
deferred.
(c) Left in a tidy and presentable condition.
25.2 PAVEMENTS
Immediately the filling of a trench excavation through a pavement has been completed,
restore the pavement to a trafficable condition. Where the initial restoration is of a
temporary nature, use a pre-mixed asphaltic material.
Maintain temporary restoration until final restoration is carried out. Carry out final
restoration of the pavement to restore both pavement and sub-base to no less than their
pre-existing condition. If appropriate, remove temporary restoration when carrying out final
restoration work.
After their initial temporary restoration, maintain pavements of other than bitumen or
concrete with crushed metal, gravel or equivalent material, making due allowance for
consolidation, and then restore to a condition equivalent to that of the original pavement.
Complete the final restoration of bitumen and concrete pavements within one (1) month of
temporary restoration.
Council requirements for reinstatement of road and footpath paving must be observed.
Some councils require approved contractors to carry out final reinstatement.
25.3 LAWNS
Reinstate lawns with turf sods cut and set aside from the original surface or with similar turf
imported for the purpose. To make up any deficiencies between the stripped quantity and
the quantity required for reinstatement, use imported topsoil consisting of a sandy loam of
light to medium texture, containing 5% to 10% by weight of humus, and free of weeds.
For areas to be turfed, ensure topsoil is graded to achieve a smooth surface, is free from
lumps, stones or other debris, conforms to finished levels, blends gradually into the
adjoining undisturbed ground and finishes flush with kerbs, footways and other paved
surfaces.
Incorporate into the topsoil at the rate of 40 g/m² a fertiliser mix with a nominal
Nitrogen:Phosphorus:Potassium ratio of 10:4:6.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


231 WSA 02—2002-2.3

25.4 GRASSED AREAS


For grassed areas that are not lawns, restore by replacing the pre-existing topsoil and
maintaining the disturbed area in a condition that will promote the re-growth of pre-existing
grasses.
Alternatively, replace pre-existing topsoil with clean topsoil and seed the affected area with
grass seeds or re-plant with runners of the varieties prevalent in the immediate area.
Should re-growth of grass fail to occur, repeat the process until re-growth is established.
25.5 BUSHLAND
Carry out all works in accordance with the requirements of the environmental Regulator.
Restore the works area as near as practicable to the pre-existing condition and leave the
site in such condition as will promote the rapid re-growth of native bush plant species
prevalent in the immediate vicinity.
Return the topsoil to its pre-existing location and place it in such a way that erosion will be
minimised, eg by the use of small contour banks.
Use the pre-existing vegetation as a seed source where possible. Upon backfilling of the
line and spreading of topsoil, replace the pre-existing vegetation over the line, placing
branches and logs across slope to intercept runoff.
Do not use imported topsoil in native bushland areas.
Employ a qualified bush regenerator to control weeds for a period of 2 years following
restoration.
Only local native species are to be used in revegetation of disturbed sites. On steep
slopes, use jute mesh and plantings to stabilise the soil.
25.6 PROVISION FOR SETTLEMENT
Through other than pavements, lawns or other improved surfaces, place trench fill
sufficiently high to compensate for expected settlement. Subsequently, carry out further
filling or trim the original trench fill, in order that the surface level of the completed trench
conforms to the adjacent surface.
Remove all surplus material and dispose of without breaching applicable regulations or
laws and do not be dispose of on any property without the property owner’s written
permission.
Within public or private property where the reasonable convenience of persons requires
trenches to be levelled off at the time of filling, make any subsequent settlement good as
necessary by placing and compacting additional fill. With the written consent of the Owner,
their agent or lessee, dispose of surplus material by spreading neatly in the vicinity of the
trench in such a way as to minimise further erosion of the backfill and adjacent ground
surfaces.
25.7 MAINTENANCE OF RESTORED SURFACES
Maintain all restored surfaces and improvements in a satisfactory condition until the end of
the defects liability period.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 232

26 WORK AS CONSTRUCTED DETAILS


Prepare Work As Constructed drawings and documentation to the requirements of the
Water Agency.
During the progress of the works, the Superintendent shall arrange for the recording of all
required as-constructed details. On completion of the work, the Superintendent shall
arrange for the preparation of the as-constructed records and submit them to the Water
Agency, all in accordance with the Water Agency’s Survey Manual. In most instances, this
will require as-constructed information to be presented in digital format.
The Superintendent shall retain a copy of all as-constructed records.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


233 WSA 02—2002-2.3

APPENDIX G OVALITY TESTING OF PVC AND GRP GRAVITY SEWERS


DEFAULT PROVER DIAMETERS

G1 General
Australian Standards for PVC (AS/NZS 1260—plain wall and structured wall) and GRP
(AS 3571—external diameter series) sewer pipes do not specify internal diameters of
pipes. The use of the formula in Clause 22.6.2 is therefore not possible.

G2 Default prover diameters


“Pull-through” provers of outside diameters listed in Table G1 may be used, on a “go/no-
go” basis, to demonstrate conformance to the requirements of Table 22.7 for a test
conducted 14 days or more after placement and compaction of embedment and trench fill.

TABLE G1
PROVER OUTSIDE DIAMETER FOR PVC AND GRP PIPES
Pipe size Outside diameter of prover
mm
DN PVC–solid wall PVC–profile wall PVC–sandwich wall GRP
150 140 152 139 NA
225 220 223 218 NA
300 278 299 276 310
375 354 358 NA 386

NOTES:
1 The tolerance on outside diameter of provers is ±0.5 mm.
2 Applies to solid wall, profile wall and sandwich construction PVC pipes conforming to
AS/NZS 1260 and GRP pipes conforming to AS 3571, external diameter series
(centrifugally cast).
3 Where the inside diameter of fittings (eg junctions, bends) is less than the pipe
internal diameter, the pull-through prover method of testing may not be valid.

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004


WSA 02—2002-2.3 234

NOTES

MRWA EDITION – VERSION 1.0 COPYRIGHT JULY 2004

You might also like