Professional Documents
Culture Documents
TELECOMMUNICATIONS
INFRASTRUCTURE FOR
NEW BUILDINGS
MASTER SPECIFICATIONS DOCUMENT
DOCUMENT CONTROL
Change Control
Date Author Version Change Release
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 3 of 63
Reviewers
Name Position
Distribution
Name
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 4 of 63
Table of Content
1.0 Introduction................................................................................................ 6
1.1 Important Note to Reader:....................................................................................... 6
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 5 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 6 of 63
1.0 Introduction
Architects / Consultants and Designers must liaise with DIC at the design stage and
obtain DIC approval on the final design drawings.
Two sets of structured connectivity design drawings, two sets of MEP drawings, and
two set of architecture drawings for GSM service provider, along with two sets
master plan drawings must be submitted to DIC for study and approval before
tendering.
All comments and/or amendments to the design drawings must be corrected and
resubmitted for approval. Upon completion of the project, one set of approved As-
Built drawings and the Building Structure cabling System Completion Certificate
must also be submitted to DIC.
Throughout this document, Dubai Internet City would like to make it clear to
all readers of this document that the choice of manufacturer for SCS is a client
/ consultant decision. Any Structured Connectivity System meeting the
requirements of ANSI/TIA/EIA-568B.2-1-2002 Addendum 1, for Category 6
performance is permitted under this broad specification document.
The structure Cabling System material submittal and design approval is the
consultant’s responsibility. DIC will not accept any material approval
submittal not submitted through the consultant.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 7 of 63
There are several types of building functions. The infrastructure for each of these
types will vary according to the function of the building, i.e. residential tower,
commercial office, hotel, private residential villas, hospital, etc… The type and nature
of service provisioning sought by the building owner will also influence the cabling
system selection and the design.
There are two scenarios for service provisioning. DIC can supply services and
bandwidth all the way to Customer’s desktop, or DIC can supply services and
bandwidth to Customer’s Main Distribution Frame (MDF) only for their own
distribution throughout the building or campus of buildings (bulk service delivery).
For both scenarios, DIC design guidelines include Structured Connectivity System
specifications illustrated in Section 3 of this document. DIC must check and
approve Structure Cabling System specifications for material and design in both
scenarios.
The following guidelines are applicable to all buildings for both scenarios.
2.1.1 General
UPVC pipes, draw-cords, manhole frames and covers, and all other fixtures and
fittings should be furnished by the contractor. Manhole covers to comply with
drawings attached as Annex 5, Duct 54D is manufactured from UPVC and is
available in 6.0 metre lengths. It has a tapered socket at one end which will accept
the barrel of the duct. Couplings (type 54A) should be used for short lengths of ducts
which have no sockets. Couplings should not be used for duct leading in to
buildings.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 8 of 63
• Main routes consist of MRT 7 Manholes. For details please refer to Annex 1.
• Zoned areas should be JRC 14, JRC 12 or JRC 4 Manholes and JRF10 pull boxes.
For details please refer to Annex 1.
• The street cabinet’s plinth to be provided with earth thread road bar (less than 5
? ).
• The distance between manholes should not exceed 250m and routes should free
from right angle bends on longer runs. No more than the equivalent of two 90°
sweeps is allowed in a run. (NOTE: this includes offsets).
• A polypropylene twisted rot and mildew resistant pull rope should be provided in
all conduits. The minimum size is 3/8" outside diameter with 2400 pounds tensile
strength.
• Manholes should not be adjacent to electrical manholes or share any walls. When
communication ducts run parallel to steam and conduit lines, 1.8m separation
needs to be provided in separate trenches.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 9 of 63
• Manholes should have pulling rings opposite to conduit entrances on each wall.
• At the point of entrance to the specified Manhole serving the building, a minimum
of 600mm ground cover should be maintained and the pipe sloped away from the
building.
• Separation of duct bores inside the manhole to be 130mm distance, center to center.
Refer to Annex 5.
The following Civil works considerations should be fully co-ordinated with all other
services:
• The executed design should ensure the co-ordination of all other services located
along the route.
• Open or broken surfaces within the duct routes will not be accepted.
There are two entry routes required for external cables; one primary and one
secondary (redundant). The location of the nearest DIC main duct routes and
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 10 of 63
Entry boxes should be built to DIC standards and at locations as advised by DIC.
The entry box should conform to DIC/Etisalat/DEWA standard JRC12. Poke out
should be provided in manhole in line with DIC duct route. An earth rod must be
provided at the entry box. The earth impedance should not be more than five Ohms
(5O).
A minimum of two (2) nos. entry conduits of internal diameter 100 mm with
appropriate draw ropes should be provided for primary route and a minimum of two
(2) nos. entry conduits of internal diameter 100mm with appropriate draw ropes
should be provided for secondary route. In larger buildings the following table
should be consulted:
Entry conduits should be laid at a depth of at least 600 mm from the top of grade
(finished ground level) and be protected by concrete under all permanent paved
surfaces.
Primary and secondary entry conduits should be extended to the entry boxes and on
to the nearest existing DIC duct locations as advised by DIC.
The outside end of the entry conduit should be properly sealed to prevent ingress of
water and other sub soil materials.
Entry conduits should be clearly marked for identification and easy location. It is the
responsibility of the Contractor to locate the entry conduits.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 11 of 63
No right angle bends should be incorporated throughout the duct length, except for
one wide angle bend (factory made) at the terminating end of the duct inside the DIC
Telco Equipment Room. Alternatively a cable pull box of minimum size 600 (L) x
600 (W) x 800 (D) mm should be provided.
Entry conduits should be exclusively for DIC services and must incorporate a
polypropylene twisted rot and mildew resistant pull rope. The minimum size is 3/8"
outside diameter with 2400 pounds tensile strength.
When cable entry conduits cannot be routed directly into the DIC Telco
Equipment Room (TER), suitable containment must be provided. 300 x 50
mm GI cable tray with cover mounted at a high level should be provided from
the entry conduit points to the TER. For mounting detail please refer to
drawing DIC / CTFD/ 01 attached as Annex 1.
Containment will be required from the TER room to the building owner’s
Main Distribution Frame. The containment should be adequately sized to
accommodate the large volume of cables that may be required. A minimum of
one 300x50 mm GI cable tray with cover to be provided for the
accommodation of link cables. When fibre cables are required, a separate and
dedicated GI cable tray of 100x50 mm cable tray with cover must be provided
for the routing of optical fibre cables. Supply and placement of these cables is
the responsibility of the building owner, termination of these cables will be
carried out by DIC or their approved agent. Sizing and type of these cables
will require co-ordination with DIC to ensure a reliable and robust service.
Entry boxes should be built to DIC standard and at locations as agreed by DIC with
the client’s infrastructure consultant. The entry box should conform to
DIC/Etisalat/DEWA standard JRC4. Poke out should be provided in the manhole
in line with DIC duct route. An earth rod must be provided at the entry box. The
earth impedance should not be more than five Ohms (5O).
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 12 of 63
• Individual entry conduits must be provided to each of the housing units (if
the plot can accommodate more than one unit)
• Entry conduits are only required to the main building for each housing unit
consisting of more than one building. Inter-connection between the main
building and all other buildings should be provided by means of the same size
and type of conduit specified above.
• Entry conduits should be laid at a depth of 600 mm from the top of grade
(finished ground level) and be protected by concrete under all permanent
paved surfaces.
• The outside end of the entry conduit should be properly sealed to prevent
ingress of water and other sub soil materials.
• Entry conduits should be clearly marked for identification and easy location.
It is the responsibility of the Contractor to locate the entry conduits.
• Entry conduits should be exclusively for DIC services and must incorporate a
polypropylene twisted rot and mildew resistant pull rope. The minimum size
is 3/8" outside diameter with 2400 pounds tensile strength.
A two section wall mounted lockable cabinet 600 mm(W) x 515 mm(D) x 12 rack
units (12U) height should be provided per villa for terminating communication cables
at a convenient and easily accessible location in close proximity to where the entry
conduits are terminated. The cabinet should have IP55 rating as per EN 60
529/10.91. The cabinet should be installed at a height of 1200mm above the
finished floor level and adequate safe working space is to be provided around each
location, for detail drawing, please refer to Annex 4. When this cabinet is located in a
cupboard, adequate ventilation must be provided. It is not necessary that this be
forced ventilation.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 13 of 63
3.1 General
To answer any questions in this section co-ordination with DIC and someone who is
thoroughly familiar with the construction of the building, most likely the architect or
MEP consultant must take place. Scaled Architects and MEP drawings detailing floor
plans and coverage areas must be supplied for full evaluation. In most cases actual
sizes are project specific and dependant on the type of end user, e.g. commercial,
financial, hotel, residential, education, car parks, etc…
The following information, which is internal to the building, is required before full
evaluation can be assessed:
• The design, size and shape of all equipment rooms, show room details in 2.4.
• The location and size of all risers and closet systems should be central to the
building and core areas.
• The location, size and shape of Apartment Consolidation Point in the residential
scenario.
• All service elevators and their maximum load capacities if adjacent to Risers.
• Building Entry facilities Primary and Secondary and duct size details.
• SCS single line diagram, shows cable routes details, number of outlets, number of
CP, ACP details, and other related SCS requirements.
The following information, which is external to the building, is required before full
evaluation can be completed:
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 14 of 63
During the design stages, segregation of power and the Structured Cabling Systems
(SCS) must meet the requirements of Power separation guidelines by the IEEE
Regulations based on a suitable design of a cable containment system by the MEP
consultant or others. Unshielded data cables should not be installed near sources of
electromagnetism. There is a standard that specifies these distances for structured
data cabling systems. EIA/TIA-569, the cabling pathways standard, specifies the
following as a guideline:
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 15 of 63
Horizontal sub-system design is based on cable routes detailed in the MEP drawings
following the main routes using cable trays and feeding off those in suitably sized
conduits to the outlet positions. It is mandatory that the containment system be
designed taking into account the 90 metre maximum horizontal cable length from
patch panel to RJ45 outlet at the work area. This must also take into account the
‘interleaving’ required.
As for the horizontal sub-system, the backbone sub-system must be designed using
the shortest routes possible from the MDF rooms to the respective Intermediate
Distribution Frames (IDFs). Diverse routing will generally use the shortest
secondary route available using adjacent risers if available.
Interlink backbone cables linking adjacent Communication Closets will again take the
shortest routes for both primary and secondary routes. Adjacent closets are defined
as being on the same level or as agreed upon during design meetings. This is covered
by the star wired system and re-routing services via patching facilities.
DIC will review and comment on the electrical contract drawings after inclusion of
technology input to ensure complete and accurate transfer of information. The
Client or client’s consultant should define contract drawings to fully incorporate
technology / data/ telecommunications infrastructure designs.
When the containment system is being designed, supplied and installed by others, the
maximum number of UTP cables installed on a tray should be as shown below;
however this may need to be reduced when considering bends, crossovers.
100mm 100
150mm 150
300mm 300
450mm 550
Table/3 (maximum number of UTP cables at the cable trays)
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 16 of 63
The wiring capacity of trunking should be determined from the standard tables
shown below. This specification must be followed as a guideline when deciding upon
the size of trunking/cable tray to be installed. It is based on the formula that for each
25mm x 25mm cross section, 8 cables can be accommodated. No trunking or cable
tray should be more than 75% full on installation.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 17 of 63
The MDF and IDF shall be wall mounted with plywood. All plywood
backboards shall meet the following minimum requirements.
All plywood shall be smooth on one side with the smooth side exposed.
The plywood shall be painted on all six sides with a light colour fire retardant
paint, the Plywood shall be securely anchored to the wall.
TER cabling and racks layout drawings have to be placed in the wall of TER,
showing number and type of patch panels in addition to cabling route. Moreover,
SCS contractor to provide the SCS schematic diagram clearing all cabling routes and
connections with other TER rooms.
Description Specification
Anti Static floor – pedestals to be earthed throughout
with minimum 300mm height from concrete screed, tile
size 600 x 600mm. Tiles to be fire resistant, calcium
sulphate coating to be used. The conductivity
Raised Floor (when resistance from the slab surface to be in the range
required – depending 1.5x105 to 2.0x1010 Ohms.
on usage) Supplier to provide cutting tiles and tile lifter, total
number will be agreed and mentioned in the Raised
Floor material submittal approval.
The raised floor loading must be 500 Kg/m2 (102 lb/ft2)
minimum.
Separate GSM Room to be adjacent to TER.
GSM Area (when 450x200mm slot to be provided below raised floor level
required) with cable basket (as noted below) fitted to allow
routing of cables between TER and GSM room.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 18 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 19 of 63
The Main Distribution Frame (MDF) and Intermediate Distribution Frame (IDF)
rooms are spaces set aside for the communications equipment serving end users.
MDF/IDF locations should be centrally situated midway in the riser complex
collapsing to an appropriately sited DIC Telco Equipment Room (TER); standard
specification for these locations is as per section 3.4
When the number of work areas to be served is known, the MDF/IDF floor space
should be based on the information in the following table. Note that sizes may
change depending on the type of end user and business requirements. In a Multi-
Tenant building there may be different equipment rooms or sectioned areas or one
room for specific tenant. Room specification should be as per section 3.4
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 20 of 63
RJ45 Outlets
All Cat6 RJ45 outlets should be Category 6 performance outlets mounted in shutters,
typically in dual, triple or quad formation in a single or double gang white faceplate.
All RJ45 outlets should be fitted with spring loaded sliding shutters to prevent the
ingress of dirt and dust.
Accessories
All accessory plates should be Dual or Quad white PVC plates. The use of any
special faceplate, which may be specific to any other manufacturer's product range,
such as trunking manufacturers, brass finish etc should be reviewed.
For outlets distribution, location, and type either it is single, dual, or quad DIC will
advice and note the optimum requirements in each area making sure that number
and outlets locations will provide the flexibility and maximum usage of
telecommunication services.
UTP Cables
All horizontal cables should be based on the Category 6 performance 100 Ohm, 4
pair 24AWG UTP cables.
All conductors in each cable should be connected to a single RJ45 socket at the work
area outlets and patch panel. Each cable should be terminated to maintain the twists
in each pair up to within 5mm of the termination. Proper strain relief should be
provided for the cable at the outlets and patch panel, avoiding strain on the
conductors. Numbering and colouring of the pairs should be as defined in EIA/TIA
568B, ISO 11801 / EN50173 using the T568B option.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 21 of 63
Colour coding for the termination should be as per the following table.
1 White Blue
2 White Orange
3 White Green
4 White Brown
Table/8 (Colour coding for cooper termination)
Equipment Cabinets
We recommend equipment cabinets as follows:
Free Standing Types should be:
• Jacking feet
We recommend that the rooms allocated for the equipment cabinets have sufficient
space around the cabinets to allow access for installation and maintenance. We
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 22 of 63
recommend that the MDF Rooms should be located in central locations and in line
with IDF rooms in the other floors for optimisation of the Fibre Runs.
3.9 Patching
The design of equipment and patch frame layouts is critical to create a high level of
manageability within a compact area, whilst maintaining effective operations when
used by the customer. Further detailed equipment layouts can be provided on
request.
We recommend all horizontal UTP cabling should be terminated on CAT6 IDC 110
Frame in the MDF/IDF Rooms. Data services can be fed from the modular
network equipment direct to the user outlet patch frame using standard CAT6 IDC
110 4 Pair Patch Cords or RJ45 Cords.
Voice services can be fed from the services patch frame directly to the user outlet
patch frame-using standard CAT6 IDC 110 4 pair Patch and IDC 110 1 Pair Patch
Cords.
BMS services can be fed from the services patch frame directly to the user outlet
patch frame using standard CAT6 IDC 110 Patch IDC 1 Pair, 2 Pair or 4 Pair Patch
Cords.
Equipment Tie cables will be required from the Customer MDF/IDF to a dedicated
DIC equipment cabinet mounted within the IDF or MDF as required. The cables
must meet the performance criteria as specified in Section 3.6. It should be noted
that termination of these cables within the DIC equipment cabinet will be the sole
responsibility of DIC. Termination of the cables at the customer MDF/IDF will be
the sole responsibility of the Customer. For more detail please refer to Annex 5.
3.10 Labelling
Label Elements
All floor outlets, patch frames and horizontal cables should be labelled. We would
propose the use of a typewritten labelling system. The labelling scheme would follow
a scheme to be agreed on with the clients’ Telecom Team and should be discussed
and finalised at a later date.
Horizontal Cable Labels
Label all horizontal cables at both ends using a self-laminating, wrap around label.
User Outlet Labels
Each RJ45 user outlet should be labelled with a unique identifier, typically using the
agreed scheme.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 23 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 24 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 25 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 26 of 63
The design of the cabling system should comply with relevant requirements and
recommendations of:
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 27 of 63
4.1 General
The purpose of this section is to highlight some design criteria specific to certain
building types. Certain buildings have specialised requirements and as a result the
internal cabling system design may be more complex. DIC are able to provide design
assistance to ensure that the cabling design is optimised for the building’s intended
purpose.
4.2 Multi Tenant Commercial Buildings with One or More Tenants per Floor
In a building planned for use as commercial building office space the following
additional guideline should be followed:
The work station cabling should be installed using a star topology from the work area
to an appropriately placed and sized Consolidation Point (CP), usually in one office
that could potentially be a sublet office. 65% of the total number of workstation
cables should be installed from the CP to the nearest Intermediate Distribution
Frame (IDF) or Main Distribution Frame (MDF); i.e., 20 nos. quad outlets installed
in floor service boxes = 80 workstation cables to CP, therefore 52 nos. 4 pair cables
(80 x 0.65) to be installed to the nearest IDF/MDF.
Using this architecture the maximum flexibility for the building owner can be
provided whilst minimising the number of cables to be installed. For example, if a
company decides to take an entire floor, the IDF located on that floor becomes the
company’s MDF. If a tenant decides to only take one office the CP becomes the
MDF for that tenant.
Copper and fibre backbones between IDFs and the MDF should be sized according
to sections 3.3
Patch and interconnection cables must be provided and stored on site according to
the following requirements:
• Work Area – 2 nos. 3-metre patch cable must be provided per work area
• Consolidation Point – 1 no. 1 metre patch cables 4 pair CAT6 110 IDC- 110
IDC, 1 no. 2 meter patch cable 4 pair CAT6 110 IDC-110 IDC, and 1 no. 1
metre patch cables 1 pair 110 IDC-110 IDC must be provided per work area
served by the CP, i.e. if a CP serves 10 work areas, 10 nos. 1 metre 4-pair
CAT6 110 IDC-110 IDC cords, 10 nos. 2 metre 4-pair CAT6 110 IDC110
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 28 of 63
IDC cords, and 10 nos. 1 metre 1 pair 110 IDC-110 IDC cords must be
provided and stored on site and 12 no. 1 meter 1 pair cords
• IDF – 2 metre 4-pair cat6 RJ45-110 IDC 25% of total incoming cables to
IDF, 3 metre 4-pair cat6 RJ45-110 IDC 25% of total incoming cables to IDF,
3 metre 1-pair 110 IDC-110 IDC 25% of total incoming cables to IDF.
• MDF –2 metre 4-pair cat6 RJ45-110 IDC 25% of total incoming cables to
MDF, 3 metre 4-pair cat6 RJ45-110 IDC 25% of total incoming cables to
MDF.
All cabling within the apartment should be installed in a star topology back to an
appropriately sized Apartment Consolidation Point (ACP) located within the
apartment. The cabling should meet the criteria as defined in section 3. Separate
telephone, CATV and computer cabling will not be required. For more details about
the ACP refer to Annex 5.
3 nos. Category 6, 4 pair cables, as specified in section 3.6, to be installed between the
ACP and the nearest TER. It is critical that the total installed length from TER to
Apartment Consolidation Point is less than 90 metres overall length including any
necessary interleaving. For more details refer to Annex 5.
Careful consideration should be given to the location of the DIC Equipment Room.
In a multi-storey, multi-tenant building the TER may serve several floors, as long as
careful consideration is given to the maximum distance of 90 metres. TER sizing
and room requirements are as specified in sections 3.4 and 3.5. There may be several
TERs required to serve a multi-storey building, however the number of TERs should
be minimised by careful planning of location. In the case of more than one TER
being required in a building a separate and dedicated GI cable tray of 150x50mm
dimension should be provided from the DIC cable entries (both main and
redundant) to the TERs for placement of DIC optical fibre. DIC will supply the
optical fibre which will be placed by the contractor and terminated by DIC as per the
DIC Responsibility Matrix attached as Annex 7.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 29 of 63
Patch and interconnection cables must be provided and stored on site according to
the following requirements:
In the case of a self contained Villa the following guidelines should be adhered to.
All cabling within the villa should be installed in a star topology back to an
appropriately sized DIC Service Entry Point located within the Villa. The cabling
should meet the criteria as defined in section 3. Separate CATV, telephone and
computer cabling will not be required.
Careful consideration should be given to the location of the DIC Service Entry Point
(SEP). The service entry point will allow the incoming feed from DIC network to
terminate in a cabinet, as specified in section 2.2.2. Careful consideration must be
given to the maximum distance of 90 metres. The location of the SEP should be
easily and readily accessible to DIC personnel and should be ventilated. Forced
ventilation and dedicated AC is not required.
Patch and interconnection cables must be provided and stored on site according to
the following requirements:
• DIC Service Entry Point – 7 nos. 1 metre patch cables must be provided for
use at the SEP. 2 nos. 3 metre patch cables must be supplied for data station
connectivity within the villa
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 30 of 63
In the case of a retail park or area the nature of the services required can vary greatly
and careful consideration must be given to current and future needs. Generally
speaking it is recommended to install a multi pair Category 3 and optical fibre cabling
to each retail unit, however Category 6 cabling can also be installed which will negate
the need for optical fibre distribution in case the distance between the Retail CP
(RCP) and TER is less than 90m. For guidelines please see section 3 of this
document. The minimum required pair counts are as follows:
• Small Stores and Coffee Shops (not Internet cafes) 25 pairs Category 3
terminated on IDC 110 frame with 4 strands MM fibre terminated with LC
connectors as sections 3.10 & 3.11 of this document in case the distance
more than 90m between the RCP and TER. Alternatively 6 nos. of 4 pairs
Category 6 UTP cable meeting the guidelines as specified in section 3.
• The shop fit-out contractor will be responsible for installing station cables
back to the IDC 110 frame as part of the retail unit fit out contract. The
number and type of cables will be determined by the shop unit tenants’
requirements
4.6 Warehouses
In the case of Warehouses and other simple structures requiring basic telephony
services only (legacy services) the need for a dedicated DIC Telecom Equipment
Room (TER) may not apply. However this will only be established after closely
reviewing the clients’ current and future telecommunications needs. In the case
where a warehouse type facility is planned the DIC service entry requirements as
defined in Section 2.2.2 should be met. A dedicated TER may or may not be
necessary; however a secure area of at least 3 x 2 metres will be required for
termination of DIC cable within the planned building. This requirement includes
providing adequate free wall or floor space for the installation of Cabinets or Frames
as detailed in Annex 2
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 31 of 63
5.1 General
SCS contractor must arrange a full set of termination and punching tools for each
MDF, also contractor to provide a technical support by provide DIC with two skilled
SCS technicians for one month period from the date of provisioning started, in
addition to the as built drawings and full testing result reports, and other documents.
The minimum size required for a service provisioning room is 4x4x3 (H) metres.
Access to the room is to be restricted to DIC personnel or their approved agents.
The room should have standard office specifications and be well lit with air
conditioning 24 hours/day 7 days a week. The room must be readily accessible to
DIC personnel and equipment 24 hours/day, 7 days a week. It should contain a
telephone and a minimum of four 13 A, 240 V a/c outlets.
5.3 Storeroom
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 32 of 63
10 mm or 12 mm ∅
GI Threaded Rod
with spring nut
GI Channel
DRAWING NO.
FILENAME
SCALE
TITLE
NTS
ENGR.
AJF
DATE
11/06/2003
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 33 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 34 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 35 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 36 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 37 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 38 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 39 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 40 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 41 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 42 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 43 of 63
Printed: 29/05/05
Saved: 29/05/05
15/05/2005
44 of 63
Printed: 29/05/05
General Notes
2.0
Saved: 29/05/05
1. Cable tray and routing above/below
racks not shown.
2. 3 no 4 pair 1071E Category 6
cables to each residence terminated
on VisiPATCH at CP and MDF
3. Direct runs where indicated in 4 pair
1071E Category 6 cables terminated
on RJ 45 at s tation end and
VisiPATCH at IDF
Version:
TITLE
52C CABINET OVERVIEW
SCALE ENGR. DATE
NTS AJF 28/07/2003
FILENAME
52C CABINET OVERVIEW.VSD
DRAWING NO.
52 C CABINET
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 45 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 46 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 47 of 63
Printed: 29/05/05
Saved: 29/05/05
15/05/2005
48 of 63
Printed: 29/05/05
2.0
Saved: 29/05/05
CABINET MOUNTING DETAILS:
110 IDC PATCHPANEL CABINET MOUNTING 2 NOS 110 IDC PATCHPANEL CABINET MOUNTING 1 NO. 110 IDC PATCHPANEL CABINET MOUNTING
DETAILS 10U CABINET RITTAL PART # 7644.000 DETAILS 10U CABINET RITTAL PART # 7644.000 DETAILS 18U CABINET RITTAL PART # 7718.135
Version:
CPE 2
CPE 1
CPE 2 CPE 2
CPE 1 CPE 1
telecommunications infrastructure
Design guidelines for
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 50 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 51 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 52 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 53 of 63
Date : Time :
Location:
Point Not
Description Accepted Fair Notes
Classification Accepted
Room Dimensions as per Approved Drawings? M
Final paint I
Sleeves and Slots in roof, walls, ground as per
I
Approved Drawings?
Civil work in the room M
Final cleaning & Earthing Bar M
Utility Power Sockets & Breaker Label M
Sensitivity of the Electrical Circuits Breakers M
MEGGAR test report for the Electrical wires I
Telecom Grounding Bar Supplied & Earthed? M
Main Air-condition unit & Redundant Unit M
Fire fighting system installation M
Access Control System Working? I
Raised floor fixing & Tilles Alignment M
Earthing the raised floor pedestals I
Lighting system including Emergency Lighting I
Cable Entry Points of Approved Type? M
Additional step in room entry & under manhole ducts
to prevent water or other liquids from floating to I
inside the room.
Cable Labeling Permanent & Legible? I
Comments:
Site Inspector Name: Site Inspector Signature
Infrastructure Engineer:
PND Engineer:
Electrical Engineer:
Provisioning Engineer:
Operations Engineer:
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 54 of 63
Date : Time :
Location:
Point Not
Description Accepted Fair Notes
Classification Accepted
Is the cable installed as per approved design drawing ? M
Is the cable installed in the right way ? M
Cable ties fixing ? I
Cable labeled (temporary / permanent) ? I
Cable protection & condition ? M
Worksheet provided ? I
Cable termination (gaps / over twisted) ? M
Site conditions in the cable working area ? I
Fiber Termination ? M
Copper Termination ? M
Note: One Major Point (Marked as M) will lead to scheduling new date for Telecom Rooms handing over. Total of Four Minor points
(Marked as I) will lead to same result.
Next Inspection Date:
Comments:
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 55 of 63
Date : Time :
Location:
Please Tick On The Found Point
Point Not
Description Accepted Fair Notes
Classification Accepted
Comments:
Site Inspector Name: Site Inspector Signature
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 56 of 63
Date : Time :
Location:
Point Not
Description Accepted Fair Notes
Classification Accepted
Is cable containment system installed as per
M
approved design drawing ?
Is cable containment system sized as per approved
M
design drawing ?
Sharp edges ? I
Accessibility to the containment ? M
90° degree bends ? M
Joints & Links between containment systems ? I
Cable Entry Point ? I
GI Containment System, is earthing completed ? I
Note: One Major Point (Marked as M) will lead to scheduling new date for Telecom Rooms handing over. Total of Four
Minor points (Marked as I) will lead to same result.
Next Inspection Date:
Comments:
Site Inspector Name: Site Inspector Signature
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 57 of 63
Date : Time :
Location:
Comments:
Site Inspector Name: Site Inspector Signature
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 58 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 59 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 60 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 61 of 63
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 62 of 63
List of Abbreviations
ACP: Apartment Consolidation Point.
ANSI: American National Standards Institute.
BDF: Building Distribution Frame.
BMS: Building Management System.
CPE: Customer Promises Equipment.
CP: Consolidation point.
DIC: Dubai Internet City.
EIA/TIA: North American Standards organization.
EN: Euro Norm (i.e. European Standard).
FTTH: Fibre to the Home.
IDF: Intermediate Distribution Frame.
ISO: International Standard Organisation.
KVA: Kilo Volt Ampere.
LAN: Local Area Network.
MDF: Main Distribution Frame.
SCS: Structured Cabling System.
SEP: Service Entry Point.
SFF: Small Fibre Factor.
TER: Telco Equipment Room.
Printed: 29/05/05
Saved: 29/05/05
Dubai Internet City Design guidelines for Version: 2.0
Telco Project telecommunications infrastructure Date: 15/05/2005
for new buildings Page: 63 of 63
Printed: 29/05/05
Saved: 29/05/05