You are on page 1of 68

Module 4

PE Welding on site
Russel Brown
P.E. Coils

2
Preparation

 Risk Assessment

 Ensure all hazards are controlled with appropriate measures

 All PPE to be worn and available when required

 Goggles must be worn whilst carrying out electro-fusion

 Work to be carried out in accordance with other procedures i.e.


"Safe Control of Operations"

3
Restrictions

• Temperatures below ground exceed 20ºC.

• Above ground positions and other positions reached by daylight unless protective
sleeving or other suitable protection is used.

• Where solvents and harmful chemicals are present.

• On in-filled demolition sites, unless suitable backfill is available.

4
Handling of Material

 Delivery

 Inspection - reject if damaged

 Storage

 Unbanded coils

 Stacking no more than 2 high

 Lowering - operators must be competent when using slings and chains


i.e. Lifting operators procedures.

5
Coil Pipe Sizes
Diameter 25 m 50 m 100 m 150 m
25 mm 855 880 930 955
Dimensions
are max 32 mm 876 908 972 1004
external
diameter in 50 mm 1400 1450 1550 1650
mm
63 mm 1436 1489 1562 1625
90 mm 2900 3000
125 mm 3720
180 mm 4000
Addition Information

Weight in KG

Diameter
Length
SDR
Off loading of Coiled pipe
9
Coils - safe off loading

• Ensure the correct equipment is available and in good working order.

• Ensure compliance with site safety rules

• Agree “responsible” person

• Prepare a storage area


Safety precautions - off loading

• Coiled pipe holds an enormous amount of energy and


should be handled with care.

• Particular care should be taken not to damage the


restraining straps.

• In wet conditions PE pipe can become very slippy and


extra care should be taken in these conditions.
Safety precautions - off loading

• It is unsafe to lift coils over the side of caged vehicles.

• Coils should not be dropped or thrown from vehicles.

• Coils should be off loaded with wide webbing slings or a fork lift truck
fitted with a protected boom.
Safety precautions - off loading

• Palletised coils should only be handled by a fork lift truck.

• Individual small coils (32 mm diameter and below) can be easily man
handled.
Lifting Coils

Correct
Incorrect
Storage of Coiled pipe
Coils stored flat
maximum height 2.5m.
Storage
of Coils

2.5m
Timber battens
should be used to
allow access.

If coils are stored upright a suitable cage should be


used.
Wrong

17
Coils per stack
If the coils are stored flat the max / stack:
• 5 coils for 32 mm
• 4 coils for 50 mm
• 3 coils for 63 mm
• 2 coils for 90 mm
• 1 coil for 110 mm
• 1 coil for 125 mm
• 1 coil for 180 mm
Coil stacks
Picture

63mm coils
50 m in Length

Question?
Correctly or Incorrectly Stacked
Remove steel Remove Bands from
the outside first -
security working inwards
bands at A & E.

Ensure the coil in


Never cut all the
properly held in a trailer
bands at once
before cutting bands
Coil Jointing

6 January 2005 FTS/CPH/1


Coil Jointing
Great care is required when welding coils due to
the stored energy retained by coiled pipe
Specific equipment is available to aid the jointing of
coils. This includes:
❑Double ring clamp
❑Coil jointers
Materials Used

• Medium Density Polyethylene PE 80


• (MDPE) – Yellow
• High Density Polyethylene PE 100
• (HDPE) - Orange

23
Standard Dimension Ratio (SDR)

SDR = Specific Outside Diameter of Pipe


Minimum Specified Wall Thickness

• Pipe should not be used/or replaced if any


damage exceeds 10% of the wall thickness of
the pipe.

24
To Calculate Wall Thickness

 SDR 17.6 Wall Thickness - 125 / 17.6 = 7.1 mm


 SDR 11 Wall Thickness - 125 / 11.0 = 11.4 mm

 SDR 17.6 Wall Thickness - 180 / 17.6 = 10.2 mm


 SDR 11 Wall Thickness - 180 / 11.0 = 16.4 mm

25
Bending Limits

Size of Pipe Minimum Bend


Radius
20mm 0.3m
32mm 0.5m
63mm 1.0m
90mm 1.4m
125mm 1.9m
180mm 2.7m

No joints allowed on bends

26
Surface Damage to PE Pipes

10%

90%
Wall Thickness in mm =

Unacceptable deep scoring


Pipe diameter in mm
(defect extends to 10% or
more of wall thickness) SDR
10%

90%

Acceptable surface scratching


(defect less than 10% of wall
thickness)

27
Preparatory Work

Equipment shall not be taken into gaseous atmospheres

or potentially gaseous atmospheres.

 The fusion plates do not have any gouges or dents,

 The non-stick coating is not damaged,

 The temperature indicator is not damaged,

 Electrical cables are not damaged and have no loose connections


29
Electro-fusion: Heat and pressure
Critical Fusion Factors
▪ End pipe
preparation
Terminal pin
▪ Cut square

▪ Cleaning

▪ Centre
registration

Cold Cold Cold


Alignment
Zone Zone Zone
▪ Ovality

▪ Restraining
Coil

30
Electro-fusion Equipment

Wires connected to fitting


Heater
31
Procedure for Straight Coupler

Step 1 Step 2

32
Procedure for Straight Coupler

Step 3 Step 4

33
Procedure for Straight Coupler

Step 5 Step 6

34
Procedure for Straight Coupler

Step 1 Step 2

35
Procedure for Straight Coupler

Step 3 Step 4

36
Procedure for Straight Coupler

Step 5 Step 6

37
Procedure for Straight Coupler

Step 7 Step 8

38
Procedure for Straight Coupler

Step 9 Step 10

39
Procedure for Straight Coupler

Step 11 Step 12

40
Procedure for Straight Coupler

Step 13 Step 14

41
Procedure for Straight Coupler

Step 15 Step 16

42
Procedure for Straight Coupler

Step 17 Step 18

43
Procedure for Tapping Tee

Step 1 Step 2

44
Procedure for Tapping Tee

Step 3 Step 4

45
Procedure for Tapping Tee

Step 5 Step 6

46
Procedure for Tapping Tee

Step 7 Step 8

47
Procedure for Tapping Tee

Step 9 Step 10

48
Procedure for Tapping Tee

Step 11 Step 12

49
Site Audits for faults

50
51
52
53
54
55
56
57
Hydro Testing
Safety Planning / Site Specific Requirements
• Develop a site-specific test plan including descriptions of safety
procedures and requirements
• Review the test specifications
• Suspend the test if equipment is not in working order
• Potential weather extremes should be considered
• Review the piping set up plan
• All temp piping should be connected with welded/flanged/ threaded
joints
• Anchors should be used upstream and downstream of all fittings
Safety Planning / Site Specific Requirements
• Verify all pressure ratings. Place all mainline valves in the open
position and all others in the closed position
• Calculate the back pressure for the injecting water/ running pigs
• Input supply pressure should be below 150psig
• Fill up pig location
• Inspect test heads to confirm all in good condition
Test Sequence
• Confirm barriers and signage in place
• Personnel to patrol all areas of pipe
• Raise the test pressure slowly and smoothly MAOP and hold for 30
mins
• Raise slowly again to 75% test pressure and hold for 30 mins
• Allow to stabilise then raise at a uniform rate not to exceed
10psi/minute
• Upon completion of test use caution when releasing the water
Commissioning services not greater
than 63 mm diameter.

▪ Services greater than 63mm should be treated as


mains.

▪ Services not greater than 63mm should be direct


purged.

▪ A flexible purge hose with a flame trap should be


connected to mcv and hose outlet positioned safely
outside premises.

-ENM- Commissioning etc.: 62


Commissioning
Commissioning pipelines or mains
by direct purging

▪ Commissioning of mains by the removal of bags, or


by the use of an ejector, is forbidden.

▪ Sections of pipelines and mains, up to and including


2”/63mm diameter, may be commissioned by the
controlled release of a squeeze-off or by the
controlled release of a valve or service tee.

-ENM- Commissioning etc.: 64


Commissioning pipelines or mains
by direct purging

•At the discretion of the A.P., sections of pipelines and


mains above 2”/ 63mm diameter, may be
commissioned, by direct purging only, by the controlled
release of a squeeze-off, if the release of the squeeze-
off can be controlled to a position corresponding to the
required rider size for achieving the min. purge velocity.

-ENM- Commissioning etc.: 65


Commissioning pipelines or mains
by direct purging

•At the discretion of the A.P. sections of pipelines and


mains above 2”/ 63mm diameter up to and including 10”/
250mm may be commissioned by the controlled opening
of a valve, using direct purging only.

-ENM- Commissioning etc.: 66


Commissioning pipelines or mains
by direct purging

• Communication and monitoring of upstream


pressure are essential when carrying out the
above operations.

-ENM- Commissioning etc.: 67


Commissioning pipelines or mains
by direct purging

Rider N2
(note 1)
N2
Vent

Pressure Sample
P1 P2 point

Flow

NOTES Physical
1. Rider may be omitted at the discretion of the engineer Isolation
2. Isolation alternative: an approved stop-off method may be used if nitrogen injection (Note 2)
pressure is limited to 1/3 of the pressure in the live pieline and the minimum velocity
can be achieved

-ENM- Commissioning etc.: 68


Slug purging

▪ More economic than complete displacement

▪ May be used on pipelines and mains greater


than 250m in length.

▪ Limited to pipes of nom. diameter 600mm


and below.

▪ Slug volume of inert gas must be at least 10%


of pipe volume.

-ENM- Commissioning etc.: 69

You might also like