Professional Documents
Culture Documents
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 1 of 28
OWNER : PMC : CONTRACTOR :
DESIGN DOCUMENT
FOR
Table of Contents
1 INTRODUCTION ....................................................................................................... 4
3 MATERIALS ............................................................................................................ 12
1 INTRODUCTION
M/s GOA NATURAL GAS PVT LTD has been intends for Survey, Design, detail engineering of
the temporary Cathodic protection (TCP) system using Mg / Zn galvanic anodes to protect the
external surface of 8”, 6", 4" dia, 3LPE Coated pipeline in the Geographical Area (GA) of Goa
against corrosion for a design life of as specified in specification enclosed with the tender for
temporary cathodic protection system, approved design document, data sheets & drawings
M/s MECON Limited has been for Survey, Design, detail engineering of the temporary
Cathodic protection (TCP) system using Mg / Zn galvanic anodes to protect the external surface
of 8”, 6", 4" dia, 3LPE Coated pipeline in the Geographical Area (GA) of Goa against corrosion
for a design life of as specified in specification enclosed with the tender for temporary cathodic
protection system, approved design document, data sheets & drawings.
M/s SARK EPC Projects Pvt. Ltd., a Cathodic Protection Specialist Company, has been
awarded a sub-contract by M/s M P ENGINEERING CONSTRUCTIONS (INDIA) PVT. LTD
for Survey, Design, detail engineering of the temporary Cathodic protection (TCP) system using
Mg / Zn galvanic anodes to protect the external surface of 8”, 6", 4" dia, 3LPE Coated pipeline
in the Geographical Area (GA) of Goa against corrosion for a design life of as specified in
specification enclosed with the tender for temporary cathodic protection system, approved
design document, data sheets & drawings.
This document covers the Design, Detailed Engineering, Procurement & supply of TCP materials,
Installation, Testing & Commissioning of Temporary Cathodic protection system for the corrosion
protection of external surface of the proposed pipeline for two years. The main purpose of the
Temporary Cathodic Protection (TCP) System is to deliver protection to the external surface of
the pipeline during the construction phase of the pipeline for 2 years or Permanent Cathodic
Protection System is commissioned whichever is later.
The following design parameters have been used for the proposed Cathodic protection
system.
2 DESIGN APPROACH
2.1 INTRODUCTION
The tender specifications indicates the type of Cathodic Protection System and provide the
basic criteria and input parameters to be adopted for the detailed design of the Cathodic
Protection System.
The intent of this section is to propose design data and criteria for the Temporary Cathodic
Protection work for Kundai IDC Junction T-Point To Mercy Circle.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 6 of 28
OWNER : PMC : CONTRACTOR :
The general pipeline details under our scope of work are summarized herein as under:
Sr. No. Pipeline Dia. (Inch) Pipeline Length (km) Type of Coating
In accordance with the project technical specification, the Design life for Temporary
Cathodic Protection System shall be Two years (2) or till commissioning of PCP system
whichever is later.
Terms Definition
A or Amps. Ampere.
AC Alternating Current.
DC Direct Current.
Cathode The electrode through which direct current leaves the electrolyte
or the structure receiving corrosion protection with installed CP.
Terms Definition
Protection Current The current made to flow into a metallic structure from electrolyte
in order to protect the metallic structure.
NACE Standard RP- Standard Practice Mitigation of Alternating Current and Lighting
0177 Effects on Metallic Structures and Corrosion Control Systems.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 8 of 28
OWNER : PMC : CONTRACTOR :
NACE Standard RP- Standard Practice The Electrical isolation of Cathodically Protected
0286 Pipelines.
BS 7361 Part I Code of Practice for Cathodic Protection for land and Marine
applications.
Temporary cathodic protection system to pipeline shall be a Sacrificial Anodes system and
be designed using pre-packaged Sacrificial Magnesium. The pre-Packaged Magnesium shall
be installed in a horizontal configuration to earth and perpendicular to the Pipeline.
As per the Mecon technical specifications, along ROW where soil resistivity predominantly
remains low, ranges from 0-10 ohm – m and pH value is within 9, zinc anodes may be
provided. Anodes of type I as per ASTM-B 418 standard shall be used for seawater, brackish
water or saline electrolyte application and anode of type II as per ASTM-B 418 standard
shall be used for fresh water, back fill and soil applications.
Along ROW where soil resistivity predominantly in the range of 10 ohm – m to 30 ohm – m
low potential (-1.55V) magnesium anodes may be provided.
Along ROW where soil resistivity is predominantly in the range of 30 ohm – m to 50 ohm –
m high potential (-1.75V) magnesium anodes may be provided.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 9 of 28
OWNER : PMC : CONTRACTOR :
At high resistivity area where resistivity is of the order of 50 ohm – m and above magnesium
ribbon anodes may be provided.
Anodes shall be installed along the pipeline at suitable intervals as per pipeline protection
voltage attenuation calculations and ground bed resistance/current output of anode
installations.
Minimum one anode installation shall be provided for every 1 (one) km of the pipeline. At
high resistivity area the magnesium ribbon anodes shall be installed all along the pipeline
by the side of the pipeline in the pipeline trench.
Each Electrically continuous section of pipeline shall preferably be protected by single type
of anode to avoid inter-anode circulation currents as per Mecon technical specifications.
The anodes shall be installed at sufficient depth to reach moist soil and shall be separated
from the pipe as far as 5 meter as possible (as per space avaibility) line by at least 5m
respectively. The magnesium ribbon abode shall be separated from the pipeline by at least
½ meter. The anode connections to pipeline shall be routed through test stations.
For sacrificial anode ground bed which shall be integrated with permanent CP System the
leads of all the anodes shall be brought up to the test station and shall be terminated
individually.
Where Magnesium anode is used for protection of polyethylene coated pipeline, the anodes
shall be preferably of low potential type (-1.55V).
Monthly monitoring of TCP system including AC and DC voltages shall be carried out till
commissioning of PCP system.
Pipeline ends have to be sealed with proper end caps to avoid the entry of water / electrolyte
inside the pipeline.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 10 of 28
OWNER : PMC : CONTRACTOR :
The sacrificial anodes shall confirm to the requirements of ASTM-B 418 standard. The
potential and consumption rate of Magnesium anodes shall be as below:
Criteria for determining the adequacy of protection to buried pipeline are defined in Mecon
technical speciation MEC/TS/05/E9/016ARev. 1 and the Cathodic Protection system shall be
designed to meet one of the following criteria:
“The pipe to electrolyte potential measurements shall be between (-) 0.95 V (ON) or more
negative as measured between pipe surface and saturated Cu-CuS04, reference electrode
contacting electrolyte when cathodic protection is applied but on potential measurement
shall not go more negative than (-)1.50 V (ON).“
“To prevent damage to the coating the limiting Pipe to Soil Potential should not be more
negative than (-) 1200 mV to avoid the detrimental effect of Hydrogen production and/or a
high pH at material surroundings.“
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 11 of 28
OWNER : PMC : CONTRACTOR :
“The pipeline shall be considered protected when a minimum of (-) 300 millivolt potential
shift has been achieved from the initial native potential to the CP `ON’ potential.“
“In rare circumstances a minimum polarisation shift of (-) 100 millivolts shall indicate
adequate levels of cathodic protection for the pipeline. The formation of decay of this
polarisation shall be used in the criteria.“
Discretion to use any of the criteria listed above shall solely rest with the Owner / Owner’s
representative.
“A positive potential swing of 50-100 mV during TCP or more shall be considered as
sufficient to indicate the presence of an interference situation requiring investigation and
incorporation of mitigation measures.”
The entire proposed pipeline are coated with Three Layer Polyethylene (3LPE) coating. The
current densities considered for the temporary cathodic protection system design as per
Mecon techhinical specification document no. MEC/TS/05/E9/016A (Rev. 1) are as follows:
Current density for marshy area/HDD (soil resistivity< 10 ohm.m) shall be considered for
design calculations.
A safety margin of 1.3 i.e. 30% shall be provided for the current requirement calculations
over and above the specified protective current densities.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 12 of 28
OWNER : PMC : CONTRACTOR :
3 MATERIALS
The preceding conceptual system design provides relevant references and criteria and
technical specifications for the major components of the temporary cathodic protection
equipments.
This part of the document is essentially devoted to the design and specifications of selected
materials and equipment based on the system design.
The specifications of the offered equipment and materials conform to the general
requirements outlined in the Enquiry specifications and the system design of this document.
The anodes shall be of low potential type Magnesium alloy packed with special backfill. The
technical particulars of the Magnesium anodes are summarized herein under:
Weight 5 kg (Approx.)
Length : 76 mm (+/- 2.5%)
Dimensions Width : 76 mm (+/- 5%)
Height : 500 mm (+/- 5%)
Pre packaged
200 mm (Dia.) x 1500 mm (Long)
dimensions
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 13 of 28
OWNER : PMC : CONTRACTOR :
All sacrificial anodes shall be packaged in a cotton bag and shall be surrounded by a low
resistivity chemical backfill of the following composition:
Gypsum : 75%
Bentonite : 20%
Sodium Sulphate : 5%
The anodes shall be installed horizontally & perpendicular configuration to the pipeline at a
depth such that the top of anode is below the bottom level of pipleine and facing to the test
station to avoid excavation on or nearby to the buried pipeline. In rocky terrain anode shall
be installed at 1.0 m depth in horizontal configuration.Howerver the depth of anode bed
shall be as per specification.
If two or more anodes are to be installed at one location, the centre to centre spacing
between consecutive anodes shall be 5 m for Magnesium anode.
Buried junction box for sacrificial magnesim anodes shall be used when install more than
one anode at particular location. The lead cables from the each anode shall be terminated
and joined in a buried junction box filled with epoxy. A single cable from buried jucntion box
shall be terminated in the test station.
The anode shall be installed in a manner as above to avoid interference problem on the
existing pipeline in a common ROW. (i.e.) anode shall not be installed on existing pipeline
side (if any) / in rare condition at least 3 m distance shall be considered from the existing
protected pipeline.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 14 of 28
OWNER : PMC : CONTRACTOR :
The test station shall be provided along the pipeline route (ROU) for monitoring the
performance of the cathodic protection at approx. every 500 meter interval in uncongested
& 250 meters in congested area and shall also be provided at the following locaitons :
Test stations used for sacrificial anodes shall have shunt for measurement of anode current,
andprovision for variableresistance insertion to limit the anode current output & anode
disconnecting link.
Test stations with current measuring facility shall be provided at each intermidiate CP station
drainage point (to measure parameters from drainage point), interference prone areas, at
min. one for every 10 km (Max.) along the pipeline route (ROU).
All test stations shall have 20% spare terminals, weather proof enclosure, having degree of
protection IP55 with hinged lockable shutter. Enclosure shall be made of sheet steel of at
least 3 mm thickness and shall be suitable for MS post mounting. The inner and outer
surfaces of test stations shall be epoxy coated. The test stations shall be designed with
termianals required for both temporary and permanent CP system and shall be suitable for
total life of permanent C.P. System.
Minimum two cables shall be provided from each pipeline at any test station.
The test stations shall be installed with the front of the test station facing the pipeline. The
name plate of test stations shall in minimum carry the following information.
Test station installation Chainages & types are furnished in test station schedule at the end
of this document. All the chainages are approximate only.
3.6 CABLES
Cables shall be XLPE insulation type Single Core Copper, PVC sheathed 650/1100V Standard
Copper Conductor PVC sheathed confirming to IS1554 Part
1C x 6 mm2 cable
(Unarmoured)( outer sheath Tail cable for Magnesium anodes
Yellow Colour)
1C x 10 mm2 cable
Current measurement cable, Pipeline to test station for
(Armoured) (outer sheath Red
sacrificial anode connection
Colour)
All cables shall be laid in accordance with approved layout drawings. No straight through
joint shall be permitted in a single run of cable. Cable route shall be carefully measured and
cables cut to required length. Half meter cable slack shall be provided near anodes, pipeline
and test station to account for any settling.
All cable inside plant / station area shall be laid at a depth of 0.75 m. cables outside
station/plant area shall area shall be laid at a depth of minimum 1.5 m and in rocky terrain
cable shall be laid at depth of 0.5 m. For cables laid outside the station/plant area,
polyethylene warning mats shall be placed at 60% of depth or 0.9 m of depth from the
finished ground level.
All cable shall be laid in sand under normal brick cover and back filled with normal soil. RCC
or PVC or GI pipes of proper size shall be provided for all underground unarmoured cables
at road crossings. All underground unarmoured cables for PCP including anode tail cables
shall run through PE/PVC sleeves of proper size.
Hume pipe of proper size shall be provided for all underground cables for road crossings.
Cables shall be neatly arranged in trenches in such a manner that crisscrossing is avoided
and final take-off to equipment is facilitated.
In case of above ground cable, all unarmoured CP cables shall be laid in GI conduits of
sufficiently large size, up to accessible height for protecting against the mechanical damage.
The armour of all the cables from pipeline to test station (potential measurement, reference
cell cables, cathode cables, etc.) and test station to ground bed (anode cable) shall be
earthed only at test station end of the cable to avoid armour carrying CP current. The cable
armour shall be insulated by cutting and taping with insulation tape.
In case of above ground cable installations, all un-armoured CP cables shall be laid in GI
conduits of sufficiently large size.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 17 of 28
OWNER : PMC : CONTRACTOR :
Where cable crossing with underground pipeline, all cables shall be placed above the
underground pipeline.
All cable connections to the pipeline shall be made by exothermic Process (Thermit Weld)
for uncharge pipeline
Cable to pipe connection on foreign / charged charged pipeline shall be made by pin brazing.
The resistance of the cable to pipe at pin brazing/thermit weld connection point shall not
exceed 0.1 Ohm.
After the thermit welding / pin brazing has been done, the exposed area shall be completely
covered with plastic funnel and sealed with mastic/M-seal then the funnel is filled by two
part epoxy of make Dr. Beck & Beck. This method shall provide total encapsulation.
Pipeline Material should not be damaged while removing the coating.The pipeline surface of
the weld/braze area should be prepared to white metal finish without any dust or grease.
The thermit weld mould should be kept up right on the pipeline without any tilting. Care
should be taken on that the cable shall not be connected at the seam of the pipeline.
Distance between two cables to pipe connections at a should be a minimum 300 mm.
Charge to be ignited with proper sparking gun. Personnel to keep his head as away as
possible from mould & should wear proper hand gloves. Upon completion immediately
remove the mould and check the connection after cooling.
4 DESIGN CALCULATIONS
The sample calculation for surface area of pipeline having diameter of 8’’ (with 3 LPE
coating) at approx. 4.4 KM provided as below :
SA = x D x L
SA = x 0.203 x 4500
SA = 2872.67m2.
Where :
SA - Surface area of pipeline (m2)
D - Diameter of pipeline (m)
L - Length of pipeline(m)
The sample calculation for current requirement of pipeline having diameter of 8’’ (with 3
LPE coating) at approx. 4.4 Km provided as below :
It = (Sa x Id x Sm)
The sample calculation for Anode requirement by weight of pipeline having diameter of 8’’
(with 3 LPE coating) at approx. 4.5 Km provided as below :
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 19 of 28
OWNER : PMC : CONTRACTOR :
W = (It x Ct x L) / Uf
W = ((93.362x 7.9 x 2) / 0.6)1000
W = 2.45kg.
Where :
W - Total anode weight requirement (kg.)
It - Total current requiremnt (Amps.)
Ct - Consumption rate of anode (7.9kg/Amp-year)
L - Design Life (2 years)
Uf - Utilization Factor (0.6)
NA = W/ WA
= 2.45/5
= 0.49Nos.
Where :
NA - Number of anodes required (Nos.)
W - Total Anode weight requirement (kg.)
WA - Weight of individual Mg. anode (5.00kg.)
The total circuit resistance of TCP system is included the sum of the following resistance :
0.159ρ 8L
R b Ln a 1
b L D
a a
Where :
Rb - Individual anode to backfill resistance (Ohms)
pb - Backfill Resistivity (0.5 Ohm – m)
La - Length of bare anode (0.500m)
Da - Diameter of bare anode(0.097m)
As per site soil resistivity survey, the average soil resistivity of readings for this line at 4
meter depth (twice) 2200 Ohm meter shall be considered for design calculations.:
RGB
2 2
0.159ρ 4L 4L S L
Ln
2 S
S 2 L2
1
L
DS L L
RGB = (0.159 x 2200) / 1.5) x (Ln ((4 x 1.5 x 1.5 + 4 x 1.5 x (4 x 4 + 1.5 x 1.5)1/2) /
(0.2 x 4)) + (4 / 1.5) – ((4 x 4 + 1.5 x 1.5)1/2 / 1.5) – 1)
RGB = 603.19 Ohms.
Where :
RGB - Prepacked anode to soil resistance (Ohms)
p - Soil Resistivity (2200 Ohm – m)
L - Length of prepacked anode (1.5 m)
S - Twice depth of anode installaiton (4 m)
D - Diameter of prepacked anode(0.2 m)
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 21 of 28
OWNER : PMC : CONTRACTOR :
RT = Rb + RGB + RC + RP
RT = 0.43 + 603.19 + 0.049 + 0.1
RT = 603.77 Ohms.
Where :
RT - Total Circuit Resistance (Ohms)
Rb - Individual anode to backfill resistance (Ohms)
RGB - Prepacked anode to soil resistance (Ohms)
RC - Total Cable Resistance (Ohms)
RP - Pipe resistance (0.1 Ohms)
The sample calculation for individual anode current output for the above calculated total
circuit resistance is provided as below :
Ic = Vd / RT
Where :
IC - Individual anode current output (mAmps.)
Vd - Driving voltage (Volts) (Anode OCP – Protective potential of
steel)
RT - Total circuit resistance (Ohms)
N = It / Ic
N = 93.36 / 2.15
N = 43.36 Nos.
Where :
N - Number of anode required by current output (Nos.)
It - Total current requirement (Amps.)
Ic - Individual anode current output (Amps.)
4.6 CONCLUSION
4.6.1 PIPELINE
From the calculation carried out above, the total anode required for the protection of pipeline
is given in below table.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 23 of 28
OWNER : PMC : CONTRACTOR :
We propose to install four Magnesium anode 5 Kg each (Total :84 nos) at approximately
every km interval along the pipeline route and ensure complete protection to pipeline.
However, if adequate protection is not achieved at any of the location then additional anodes
shall be provided to ensure complete protection in that particular portion as per instructions
of Engineer In - charge at site.
The tentative location of anode to be installed is shown in test station schedule furnished at
the end of this document.
5 BILL OF MATERIALS
Attached in Annexure-B
The test station schedule provided in Annexure : C is tentative only. The test station & Mg
anode locations can be changed as per actual site conditions. (i.e.) actual installation
locations shall be decided on site taking into consideration accessibility.
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 24 of 28
OWNER : PMC : CONTRACTOR :
27/07/2020
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 25 of 28
OWNER : PMC : CONTRACTOR :
27/07/2020
Page 1
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 26 of 28
OWNER : PMC : CONTRACTOR :
1 0.500 AI 1 4 40 20 2
2 1.000 AI 1 4 40 20 2
3 1.500 AI 1 4 40 20 2
4 2.000 AI 1 4 40 20 2
5 2.500 AI 1 4 40 20 2
6 3.000 AI 1 4 40 20 2
7 3.500 AI 1 4 40 20 2
8 4.000 AI 1 4 40 20 2
9 4.500 AI 1 4 40 20 2
10 5.000 AI 1 4 40 20 2
11 5.500 BI 1 4 40 160 4
12 6.000 AI 1 4 40 20 2
13 6.500 AI 1 4 40 20 2
14 7.000 AI 1 4 40 20 2
15 7.500 AI 1 4 40 20 2
16 8.000 AI 1 4 40 20 2
17 8.500 AI 1 4 40 20 2
18 9.000 AI 1 4 40 20 2
19 9.500 AI 1 4 40 20 2
20 10.000 AI 1 4 40 20 2
21 10.500 AI 1 4 40 20 2
PAGE 1
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 27 of 28
OWNER : PMC : CONTRACTOR :
ANNEXURE - D : CP DRAWINGS
1 2 3 4 5 6 7 8 9 10
NOTE :
1. ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED.
1500
A
A
500
B
EPOXY FILLING
76 200
DETAIL 'X'
C
C
1C x 10 Sq.MM XLPE/PVC
UNARMOURED ANODE TAIL CABLE
A
D
TWO PART M-SEAL MS IRON
76
(FLAT 18x5)
CABLE TO ANODE CONNECTION
(NUT BOLT)
E
76
1C x 10 Sq.MM XLPE/PVC
UNARMOURED ANODE TAIL CABLE
F
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
G
LENGTH : ±5%
0.50 - 1.30 % BENTONITE : 20%
MANGANESE : WIDTH : ±5% PIPELINE CONTRACTOR:
: Cu-CuSO4 REFERENCE WEIGHT : 5 KG. FABRICATION OF SACRIFICIAL MAGNESIUM ANODE (5KG) HIGH
POTENTIAL (THEORETICAL) POTENTIAL
H
H
CELL
GNGPL Document No.
---
NTS SARK-MECON-MPE-DWG-001 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
1. ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED.
2. ALL CABLES WILL BE REQUIRED TO BE LAID AT A DEPTH OF
0.75 M INSIDE STATION / PLANT AREA AND 1.5 M DEPTH
OUTSIDE PLANT / STATION AREA IN 100 MM THICK SAND
UNDER BRICK COVER BACKFILLED WITH NORMAL SOIL AND IN
A
A
ROCKY TERRAIN AREA CABLE SHALL BE LAID AT 0.5 M DEPTH.
OUTER OR INSIDE PLANT THE ROUTE SHALL BE MARKED WITH
POLYTHENE CABLE WARNING MATS PLACED AT 60% OF
DEPTH OR 0.9 M OF DEPTH FROM FINISHED GROUND LEVEL.
HOWEVER, ALL ANODE TAILS FROM ANODE JUNCTION BOX TO
ANODE WILL BE 1.5 M DEEP APPROX.
3. CABLE ROUTE SHALL BE CAREFULLY MEASURED AND CABLES
TO BE CUT FOR REQUIRED LENGTH INCLUDING REQUIRED
GL GL LOOPS AT EITHER END. MINIMUM ONE METER SLACK/LOOP
SHALL BE PROVIDED NEAR ANODES, PIPELINE AND TEST
STATIONS TO ACCOUNT FOR ANY ADJUSTMENT.
4. CABLE LAYING FOR CURRENT MEASUREMENT TEST STATION,
B
B
REFERENCE ELECTRODE CABLES AND OTHER LENGTHY
CABLES SHALL BE CARRIED OUT ALONG THE TOP OF THE PIPE
BY SECURELY STRAPPING IT WITH ADHESIVE TAPE / NYLON
ROPE OR EQUIVALENT AS REQUIRED.
NORMAL SOIL
900
C
C
PE/PVC CABLE WARNING MATS
1500
ORDINARY BRICKS LAYER COVER
100
D
D
CABLE O.D SAND FILL
CABLES
100 100
100
600
E
E
CABLE TRENCH DETAILS
F
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
2" Ø GI/PVC CONDUIT CEMENT GROUT PROJECT :
DETAILED ROUTE SURVEY FOR PROPOSED
GNGPL’s STEEL & MDPE PIPELINE ROUTES IN
F.G.L F.G.L NORTH GOA
OWNER :
150
VARIES
PMC :
MECON LIMITED
G
G
PIPELINE CONTRACTOR:
M P ENGINEERING
CONSTRUCTIONS INDIA PVT LTD
150
PER CABLE CP CONTRACTOR :
SARK
SARK EPC PROJECTS PVT. LTD.
H
GNGPL Document No.
---
NTS SARK-MECON-MPE-DWG-002 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
250 NOTE :
300 1) ALL DIMENSIONS ARE IN MM UNLESS STATED.
2) EVERY CABLE COMING TO THE TEST STATION IS TO BE LABELED ON BOTH ENDS WITH
250 NOTIFICATION NUMBER AS PER CONNECTION SCHEME USING PVC PERRULES
9 11 8 3) ANODIZE ALUMINUM NAME PLATE (120 X 120 X 1.5 MM) TO BE FIXED IN INNER SIDE OF
1 25 50
40
THE INNER SIDE OF DOOR
4) THE NUMBER OF ALL TEST STATION SHALL BE WRITTEN WITH BLACK PANT USING
A
A
100MM STENCILS ON THE OUTER SIDE OF THE FRONT SHUTTER IN UNIFORM MANNER.
19 5) THE TERMINAL PLATE TO BE SCREW FASTENED WITH MS ANGLES HAVING INTERNAL
175
THREADS
3 40 6) THE SHUTTER SHALL BE HINGED TYPED WITH CONCEALED LOCK AND IT SHALL HAVE
200
DOOR GASKET TO MAKE TEST STATION WEATHER PROOF (IP55) TYPE
4 7) LIGHT GRAY AND POWER COATED (PAINT SHADE 631 OF IS - 5, THICKNESS - 80 MICRON)
A 22 A
275
SHALL BE APPLIED TO THE INTERNAL AND EXTERNAL OF THE ENCLOSURE & MS ANGLES.
21 21
250
275
FO
4 FIX
8) CABLE ENTRY SHALL BE SEALED WITH SEALING COMPOUND AFTER INSTALLATION TO
IN
7
C NG
PREVENT WATER ENTRY INSIDE PIPE.
H
H PIP
CONNECTION SCHEME OF RELEVANT
I
TEST STATION TO BE PRODUCED HERE
O
6
LE E
TEST STATION NO.
CHAINAGE IN KM
TEST STN CONN. SCHEME TYPE
10) TEST STATION INSTALLATION SHALL BE DONE 1.2 M OR AS PER SITE CONDITION ON
DISTANCE FROM PIPE IN MTR
DIRECTION OF MAINLINE FLOW 2 NARROW SIDE OF ROW
11) LUGS FOR CABLE CONNECTIONS TO THE TEST STATION SHALL BE DOUBLE CRIMPED
ON THE CABLE CONDUCTOR.
25
TO BE WELDED 150 12) TEST STATION SHALL BE SO ERECTED AS TO SERVE AS A PIPELINE MARKER. ALSO
200 THEIR SHUTTERS SHALL BE PARALLEL TO THE PIPELINE.
5
B
B
175 25 18
13) THE NUMBER OF TERMINALS SHALL BE SAME FOR ALL THE TEST STATIONS. THE
12 INTERNAL THREADED BUSH SECTION A-A TERMINALS USED FOR ONE TEST STATION DEPENDS UPON THE REQUI-REMENT OF
SUITABLE FOR ALLEN BOLT THE CONNECTION AT THE PARTICULAR LOCATION.
13 WELDED
DOOR
NON THREADED BUSH
SUITABLE FOR ALLEN BOLT
18
1000
13 DOOR FIXING DETAILS
250
C
C
B B
50
75
15 RCC FOUNDATION 20
16 BILL OF MATERIAL
14
ITEM
DESCRIPTION QTY
NO.
1 TOP PLATE 300 x 250 x 3 mm THK. M.S. 1
250
150
2 SIDE PLATE 175 x 275 x 250 x 3 mm THK. M.S. 2
17 17
200
D
25 CONCEALED LOCK WITH 2 KEY(HINGED TYPE)
20 6 1
FGL FGL GL GL 7 HINGE FOR DOOR 2
8 PHENOLIC LAMINATED SHEET TERMINAL PLATE 200x 160 x 6 mm THK. 1
40 4 HOLES FOR FIXING
9 M.S. ANGLE FOR FIXING TERMINAL PLATE 40x40x5 THK. 20 mm LONG 4
TERMINAL PLATE
BRASS NICKEL PLATED BOLT M 6 DIA X 40 mm LONG WITH 2 Nos. M6
30 10 12 SET
WELD POINT NUT & 2 Nos. WASHER FOR EACH TERMINAL
SS316 CROSS HEAD SCREW FOR FIXING TERMINAL PLATE M 6 DIA 20
11 4
ELBOW mm LONG
FRONT VIEW SECTION
600
40 40 40 40 40
E
E
50 18
NEOPRANE (10% MIN) & BALANCE RUBBER 30 X 6 MM THICK AS
RECTANGULAR CROSS SECTION GASKET. REQUIRED
50
30
20 RUBBER BUSH 1
600 600 21 M.S HANDLE DIMENSION 25 mm X 100 mm X 3 mm 1
22 NAME PLATE DIMENSION 120 mm X 120 mm X 1.5 mm 1
700 700
8
23 4"Ø ELBOW M.S SCH 40 90 Deg. (4.5 mm THK. MIN. ) 1
50
AS
FRONT VIEW 10
24 10 MM DIA ROD 200 CIC BOTH WAYS
REQUIRED
SIDE VIEW 25 PCC FOUNDATION M-20 GRADE(1:5:10 ) 700 mm x 700 mm x 50 mm 1
160
50
00 24.07.2020 ISSUED FOR REVIEW RV KD KG
F
F
11
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
30
DETAIL 'X' PROJECT :
DETAILED ROUTE SURVEY FOR PROPOSED
GNGPL’s STEEL & MDPE PIPELINE ROUTES IN
NORTH GOA
8 TERMINAL PLATE (TYP) OWNER :
6
WASHER GOA NATURAL GAS PVT LTD,
26
NUT 120
14
G
50
50
50
50
400
300
300
300
300
120
10
CHAINAGE IN KM
36
SARK
SARK EPC PROJECTS PVT. LTD.
TEST STN CONN. SCHEME TYPE
50
50
50
50
H
DIRECTION OF MAINLINE FLOW
DETAIL 'X' OF TEST TERMINAL 10
HING DETAILS GNGPL Document No.
7 TOP PLATE BOTTOM PLATE ---
TEST STATION IDENTIFICATION DETAIL
SECTION B-B SCALE SARK Document No. SHEET
NTS SARK-MECON-MPE-DWG-003 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
A
3) POSITION MOLD OVER THE EXPOSED AND CLEANED AREA OF PIPELINE.
STARTING POWDER
MOLD POSITION THE CLEANED CONDUCTOR IN THE MOLD AFTER ENSURING
THE MOLD IS DRY BY PRE-HEATING OR MAKING A TEST JOINT.
4) REMOVE APPROXIMATE 40mm OF INSULATION FROM END OF CABLE .
INSERT COPPER SLEEVE FOR #14 AWG. TO #10 AWG. CABLE SIZES.
5) LOCK THE MOLD WITH THE HANDLE CLAMP; IF THE MOLD DOES NOT
CLOSE PROPERLY ADJUST THE TENSION OF THE MOLD AND INSERT
STEEL DISC AT THE BOTTOM OF THE MOLD CRUCIBLE.
PLASTIC CONTAINER 6) POUR THE WELDING POWDER INTO THE MOLD. THE WELDING POWDER
IS RETAINED IN THE UNDERSIDE OF THE CARTRIDGE. SPREAD THE
STARTING POWDER EVENLY OVER THE WELDING POWDER, PLACING A
SMALL AMOUNT ON THE TOP EDGE OF THE MOLD FOR EASY IGNITION.
WELDING POWDER 7) POSITION WELDER OVER EXPOSED AREA OF PIPELINE AND INSERT
B
B
CABLE UNDER MOLD , PACK CABLE AND MOLD WITH PACKING MATERIAL
(IF NECESSARY) TO SEAL MOLD AND CABLE OPENING .
8) COVER THE MOLD, PLACE IGNITER AT OPENING OF THE MOLD AND
APPLY SPARK WHICH WILL IGNITE STARTING POWDER AND THEN
WITHDRAW IGNITER QUICKLY TO PREVENT FOULING / BURNS . AFTER
CA-15/32 COVER STARTING POWDER HAS IGNITE HOLD MOLD IN PLACE FOR 30 SECONDS
FIRMLY . THEN REMOVE MOLD.
9) LIGHTLY TAP WELDER WITH HAMMER TO REMOVE SLAG.
WELDING POWDER 10) THE RESISTANCE OF THE CABLE TO PIPE AT THERMIT WELD
CONNECTION POINT SHALL NOT EXCEED 0.1 OHM.
11) THE CONNECTION SHALL BE TESTED BY STRIKING 0.5 KG HAMMER
DIRECTLY OVER THE CONNECTION. AND IF CONNECTION FAILS, THE
STARTING ABOVE PROCEDURE SHALL BE REPEATED AFTER WAITING TIME OF
APPROX 10 MIN FOR THE PIPELINE SURFACE TO COOL DOWN.
C
C
12) SEALING THE COMPLETED JOINT SEAL WITH EPOXY RESIN
POWDER FORMULATION ENSURING THAT EVERY METALLIC PART OF THE JOINT
IS COMPLETELY INSULATED. M-SEAL SHALL BE APPLIED AT THE POINT
OF CABLE EXIT & AROUND FUNNEL.
13) FUNNEL SHALL BE MINIMUM 15MM OVERLAPPING ON PIPE COATING ON
WELDING EACH SIDE.
POWDER CABLE 14) DISTANCE BETWEEN TWO CABLES TO PIPE CONNECTIONS (THERMIT
WELD) SHOULD BE A MINIMUM 300 MM.
15) A LOOP OF APPROX 1.0 MTR OF CABLE SHALL BE KEPT AT BOTH
DISC 16)
PIPELINE AND TEST STATION END.
THERMIT WELD PORTION OF THE PIPELINE SHALL BE CHECKED FOR ANY
HOLIDAY
PIPELINE
D
D
THERMIT WELDING CONNECTION
E
2
UPTO 10 mm CA-15
16 TO 352 mm CA-32
THERMIT WELDING
CONNECTION
00 24.07.2020 ISSUED FOR REVIEW RV KD KG
F
F
M-SEAL REV.
PROJECT :
DATE DESCRIPTION PRED. CHKD. APPRD.
M-SEAL
GOA NATURAL GAS PVT LTD,
PMC :
G
PIPELINE CONTRACTOR:
M P ENGINEERING
CONSTRUCTIONS INDIA PVT LTD
SARK
SARK EPC PROJECTS PVT. LTD.
DRAWING TITLE:
80MM CABLE TO PIPE CONNECTION BY THERMIT WELD
H
H
GNGPL Document No.
NTS SARK-MECON-MPE-DWG-004 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
A
BLAZING ALLOY 3. THE COATING SHALL BE REMOVED OVER AN AREA OF OF
APPROXIMATELY 50X50 MM USING A COARSE FILE OR SMALL
(FINE/MEDIUM) HAND GRINDING WHEEL. THE STEEL SHALL THEN
PIN BODY BE CLEANED TO BRIGHT METAL USING A NON-METALIC COARSE
GRINDER.
4. PIN BRAZING SHALL ONLY BE CARRIED OUT BY VENDOR USING
THE APPROVED PROCEDURE AND USING OPERATORS WHICH
BRAZING GUN BRASS THREADED BRAZING PIN HAVE BEEN QUALIFIED.
5. THE CONNECTION SHALL BE TESTED BY STRIKING 0.5 KG
HAMMER DIRECTLY OVER THE CONNECTION. AND IF CONNECTION
M8 X 30 MM LONG FAILS, THE ABOVE PROCEDURE SHALL BE REPEATED AFTER
WAITING TIME OF APPROX 10 MIN FOR THE PIPELINE SURFACE TO
B
B
COOL DOWN.
6. FUNNEL SHALL BE MINIMUM 15MM OVERLAPPING ON PIPE
COATING ON EACH SIDE.
DETAIL 'A' CUT SECTION OF PIN BRAZING STUD 7. SEALING THE COMPLETED JOINT SEAL WITH EPOXY RESIN
FORMULATION ENSURING THAT EVERY METALIC PART OF THE
DETAIL 'A' BRAZING PIN JOINT IS COMPLETELY INSULATED. M-SEAL SHALL BE APPLIED
AT THE POINT OF CABLE EXIT & AROUND FUNNEL.
8. DISTANCE BETWEEN TWO CABLES TO PIPE CONNECTIONS (PIN
COATING REMOVED M8 CERAMIC FERRULE BRAZING) SHOULD BE A MINIMUM 300 MM.
(50x50 APPROX.) PIPE WALL 9. A LOOP OF APPROX 1.0 MTR OF CABLE SHALL BE KEPT AT BOTH
PIPELINE AND TEST STATION END.
10.PIN BRAZED PORTION OF THE PIPELINE SHALL BE CHECKED FOR
C
C
ANY HOLIDAY.
11.PIN BRAZING SHALL BE CARRIED OUT ON CHARGED PIPELINE
ONLY.
PIPE WALL
PIN BRAZING TO THE PIPE SURFACE
D
D
PIN BRAZING SET UP COPPER CRIMP LUG (TABLE -1)
9 x 6 mm UPTO 10 mm²
8 x 12 mm 25 mm²
E
E
EPOXY-HARDENER (10:1) TESTING VERIFICATION FOR
1MM THK.PVC FUNNEL CABLE POST ATTACHMENT.
MAKE -(DR. BECK)
(NOTE-6) 1. HOLIDAY TEST.
2. HAMMER TEST.
BRASS THREADED BRAZING PIN M8 BRASS NUT
M8 X 30 MM LONG
COPPER CRIMP LUG 00 24.07.2020 ISSUED FOR REVIEW RV KD KG
BRASS WASHERS
F
F
(REFER TABLE 1) REV.
PROJECT :
DATE DESCRIPTION PRED. CHKD. APPRD.
M-SEAL
GOA NATURAL GAS PVT LTD,
PMC :
G
PIPELINE CONTRACTOR:
M P ENGINEERING
CONSTRUCTIONS INDIA PVT LTD
SARK
SARK EPC PROJECTS PVT. LTD.
50MM
DRAWING TITLE:
80MM CABLE TO PIPE CONNECTION BY PIN BRAZING
H
H
CABLE TO PIPE CONNECTION BY PIN BRAZING WITH THREADED STUD GNGPL Document No.
---
NTS SARK-MECON-MPE-DWG-005 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
TEST STATION TEST STATION 1. ALL DIMENSIONS ARE IN MM. OR OTHERWISE MENTIONED GENERALLY 1
OR 4 MG ANODE SHALL BE INSTALLED PER TEST STATION AS PER
DESIGN.
[275(H) X250(W)X175(D)] [275(H) X250(W)X175(D)] 2. IF REQUIRED MORE NUMBER OF ANODE SHALL BE CONNECTED AS PER
CALCULATION.
A
A
3. CABLE LOOP OF 1M SPARE IS TO BE PROVIDED AT EACH ANODE AND
TEST STATION END.
4. THE PRE-PACKAGED MAGNESIUM ANODES SHALL BE INSTALLED IN A
HORIZONTAL CONFIGURATION TO EARTH AND PERPENDICULAR TO THE
PIPELINE AT A DEPTH SUCH THAT THE TOP OF ANODE IS BELOW THE
BOTTOM LEVEL OF PIPELINE AND FACING TO THE TEST STATION TO
AVOID EXCAVATION ON OR NEARBY TO THE BURIED PIPELINE.
5. PIPELINE DEPTH ARE AS PER PROVIDED DATA FROM CLIENT.
INSTALLATION OF SACRIFICIAL ANODE SHALL BE DONE AS PER DESIGN
1C X 6 Sq.MM XLPE,PVC OR AS PER SITE CONDITION.
B
ARMOURED ,CU CABLE
1C X 10 Sq.MM XLPE,PVC
ARMOURED ,CU CABLE
GL GL GL GL
PIPELINE
DEPTH
C
C
1.5M PREPACKED
1.5M ANODE
1C X 6 Sq.MM XLPE,PVC
UNARMOURED ,CU CABLE
UG .PIPELINE CLOTH BAG WITH
PREPACKED BACKFILL
ANODE MATERIAL
CLOTH BAG WITH 1C X 6 Sq.MM XLPE,PVC
D
D
BACKFILL MATERIAL UNARMOURED ,CU CABLE
UG PIPELINE
ALL CABLE SIZE TO BE AS PER BID DOCUMENT/SPECIFICATIONS
E
E
1C X 10 Sq.MM XLPE,PVC
ARMOURED ,CU CABLE
2M 1C X 10 Sq.MM XLPE,PVC
ARMOURED ,CU CABLE
TEST
RV KD KG
F
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
PROJECT :
DETAILED ROUTE SURVEY FOR PROPOSED
1C X 6 Sq.MM XLPE,PVC GNGPL’s STEEL & MDPE PIPELINE ROUTES IN
NORTH GOA
UNARMOURED ,CU CABLE
OWNER :
PMC :
MECON LIMITED
G
G
PIPELINE CONTRACTOR:
CLOTH BAG WITH M P ENGINEERING
BACKFILL CONSTRUCTIONS INDIA PVT LTD
27/07/2020
MATERIAL CP CONTRACTOR :
PREPACKED SARK
SARK EPC PROJECTS PVT. LTD.
ANODE DRAWING TITLE:
H
PLAN FOR SACRIFICIAL ANODE INSTALLATION GNGPL Document No.
---
NTS SARK-MECON-MPE-DWG-006 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
1. ALL DIMENSIONS ARE IN MM. OR OTHERWISE MENTIONED
2. TEST STATION SIZE SHALL DEPEND ON THE TYPE OF
CONNECTION SCHEME AND THE NUMBER OF TERMINAL
REQUIRED.
A
A
TEST STATION
[275(H) X250(W)X175(D)]
ALL CABLE SIZE TO BE AS PER BID DOCUMENT/SPECIFICATION
VARIABLE
TERMINALS RESISTOR
B
B
LINK
SHUNT
(0.5A/50mv)
1C X 6 Sq.MM XLPE,PVC
UNARMOURED ,CU CABLE
1C X 10 Sq.MM XLPE,PVC
ARMOURED ,CU CABLE
1C X 10 Sq.MM XLPE,PVC
ARMOURED ,CU CABLE
C
C
MG ANODE
PIN BRAZING/
300mm THERMIT WELD
D
TEST STATION
[275(H) X250(W)X175(D)]
E
E
LINK
27/07/2020
1C X 6 Sq.MM XLPE,PVC
UNARMOURED ,CU CABLE
00 24.07.2020 ISSUED FOR REVIEW RV KD KG
F
F
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
1C X 10 Sq.MM XLPE,PVC
PROJECT :
ARMOURED ,CU CABLE DETAILED ROUTE SURVEY FOR PROPOSED
GNGPL’s STEEL & MDPE PIPELINE ROUTES IN
1C X 10 Sq.MM XLPE,PVC NORTH GOA
ARMOURED ,CU CABLE OWNER :
MG ANODE
PIN BRAZING/ 300mm 60000MM(TYP) 300mm PIN BRAZING/
THERMIT WELD THERMIT WELD GOA NATURAL GAS PVT LTD,
PMC :
MECON LIMITED
G
G
PIPELINE CONTRACTOR:
CURRENT MEASUREMENT WITH GALVANIC ANODE
M P ENGINEERING
CONNECTION SCHEME-BI CONSTRUCTIONS INDIA PVT LTD
CP CONTRACTOR :
SARK
SARK EPC PROJECTS PVT. LTD.
DRAWING TITLE:
H
GNGPL Document No.
---
NTS SARK-MECON-MPE-DWG-007 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
1 2 3 4 5 6 7 8 9 10
NOTE :
1. ALL CHAINAGE IN METER UNLESS OTHERWISE SPECIFIED
A
BI CURRENT MEASUREMENT WITH GALVANIC ANODE
4000
4500
2000
2500
3000
3500
5000
1000
1500
500
B
B
MATCH LINE WITH 'A'
AI AI AI AI AI AI AI AI AI AI
Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg
LEGEND:
START
Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg PIPE LINE
C
AI
AI
AI
AI
AI
AI
AI
AI
AI
AI
Mg MG ANODE (5 Kg)
D
D
10000
6000
6500
8000
8500
5500
7000
7500
9000
9500
MATCH LINE WITH 'A'
E
Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg
Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg Mg
BI
AI
AI
AI
AI
AI
AI
AI
AI
AI
00 24.07.2020 ISSUED FOR REVIEW RV KD KG
F
F
REV. DATE DESCRIPTION PRED. CHKD. APPRD.
PROJECT :
DETAILED ROUTE SURVEY FOR PROPOSED
GNGPL’s STEEL & MDPE PIPELINE ROUTES IN
NORTH GOA
OWNER :
PMC :
MECON LIMITED
G
G
10500
PIPELINE CONTRACTOR:
M P ENGINEERING
CONSTRUCTIONS INDIA PVT LTD
MATCH LINE WITH 'B'
AI
CP CONTRACTOR :
Mg Mg
SARK
SARK EPC PROJECTS PVT. LTD.
FINISH
Mg Mg
DRAWING TITLE:
H
GAIL Document No.
---
NTS SARK-MECON-MPE-DWG-008 01 OF 01
1 2 3 4 5 6 7 8 9 10
420 MM X 297 MM - SIZE A3
DESIGN DOCUMENT Doc No. R.
FOR
SARK/MECON/MPE/TCP/DD/01 00
TEMPORARY CATHODIC
PROTECTION Page : 28 of 28
OWNER : PMC : CONTRACTOR :
ABBREVIATIONS
GNGPL SECON
Pipeline Network in North Goa Corrosion Survey Report
TABLE OF CONTENTS
GNGPL SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL SECON
Pipeline Network in North Goa Corrosion Survey Report
DETAILED ROUTE SURVEY FOR GNGPL’S NATURAL GAS PIPELINE IN NORTH GOA
CORROSION SURVEY REPORT
1.0 PREAMBLE
M/s Goa Natural Gas Private Limited (GNGPL), a joint venture of GAIL Gas and BPCL has been
authorized by PNGRB to set up a CGD network in North Goa and Mecon Limited (MECON) has been
appointed as EPMC Consultants for the said work.
To meet the above objective, M/s Goa Natural Gas Private Limited (GNGPL) proposes to lay a Steel &
MDPE Gas Pipeline network for supply of Natural Gas to various consumers in the cities of Panjim,
Mapusa, Porvorim and other cities in North Goa.
2.0 INTRODUCTION
M/s Goa Natural Gas Private Limited (GNGPL) has awarded the job of carrying out detailed route survey
for Natural Gas pipeline to M/s. SECON Private Limited vide FOA No: GNGPL/2016-17/03 dated
15.03.17.
As per scope of services, detailed engineering survey, soil stratification survey, soil resistivity survey
along the pipeline alignment shall be carried out.
The present report covers the details of Soil Stratification survey comprising of auger boring with visual
observations along the pipeline alignment and pipeline route.
As per scope of services, detailed engineering survey, soil stratification survey, soil resistivity survey
along the pipeline alignment shall be carried out.
The present corrosion survey report covers the details of electrical resistivity tests carried out along the
alignment and its inference on corrosion behavior of soil. In addition, chemical analysis of soil and water
samples also carried out.
GNGPL 1 SECON
Pipeline Network in North Goa Corrosion Survey Report
The detail of alignment of proposed pipeline network in North Goa District is as under;
GNGPL 2 SECON
Pipeline Network in North Goa Corrosion Survey Report
ρf = ρw
Ft x Fw
Where,
ρ w = Resistivity of water contained in the formation
Ft = Factor dependent on the texture of the formation
Fw = Factor dependent on the saturation.
From above equation it can be inferred that the resistivity of the water / moisture content has a major
effect on the resistivity of formation. The resistivity of the water / moisture contained in the formation is, in
turn, dependent on the ion forming salts present, which are responsible for the corrosion activities. The
factor Ft is mostly dependent on the porosity of the formation. The effect of saturation on the resistivity is
asymptotic. About 15 to 20% of saturation, which is water, retaining capacity of most of the soils is
sufficient to change the value substantially and any further saturation may have only negligible effect on
the soil resistivity. Hence the measurement of resistivity (ρf) of the formation will help in estimating the
corrosion properties of the sub-surface formation. Uniform subsoil conditions are not generally found in
long pipelines. Different types of soils with varying permeability, different moisture content, porosity and
chemical composition cause different diffusion velocities of oxidising agents to the iron surface. These
result in locally separated anodic and cathodic areas (i.e.) macro cells. The soil resistivity generally
measures the degree of aeration of the soil and along with it the chances of forming oxygen type
electrochemical cells. The relationship between specific soil resistivity and corrosion behavior has been
well established. As the electrical resistance of soil reduces, the electrochemical process takes place
more efficiently. Based on the resistivity values, their effect on the corrosion behavior has been
evaluated. Extensive investigation has been carried out regarding effect of various ranges of resistivities
on steel sections.
The different ranges of values and classification are summarized below:
Resistivity (ohm-m) Degrees of Corrosivity Category
<10 Very highly aggressive A
10-25 Highly aggressive B
25-50 Medium aggressive C
50-100 Low corrosive D
> 100 Very low corrosive E
It has been observed that correct measurement of resistivity in soils is a fairly reliable method in
evaluating the type of corrosion protection necessary for buried pipelines.
GNGPL 3 SECON
Pipeline Network in North Goa Corrosion Survey Report
For Water
Sl. No. Parameters Allowable Limits
1. pH shall be Not less than 6
More than 400 mV, However between 200 – 400 mV is
2. Redox Potential at pH 7 shall be
Considered as moderate
Less than 0.05%, However between 0.05 – 0.20% is
3. Chloride shall be
Considered as moderate
Less than 0.04%, However between 0.04 – 0.05% is
4. Sulphate shall be
Considered as moderate
GNGPL 4 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 5 SECON
Pipeline Network in North Goa Corrosion Survey Report
Where,
V1 = Volume of silver nitrate used for the sample
V2 = Volume of silver nitrate used for the blank
N = Normality of AgNO3
S = Volume of aliquot taken for titration (ml)
Wd = Weight of dry soil taken for filtration (Gms)
V3 = Total volume made for extraction
6.1.5 Determination of Sulphate in Soil
Weigh 20 Gms air dry specimen in a 250-ml conical flask. Add 100 ml of Morgan’s extraction. Shake the
suspension for one-half hour or keep it for overnight and filter through Whatman’s No. 42 filter paper or
equivalent. Take 25 ml aliquot and transfer to a 50 ml volumetric flask, add 20 ml of 10% Barium
Chloride and shake for 1 minute, then add 1 or 2 ml of 0.25 % gum acatia make up the solution to 50 ml
mark with distilled water and shake for a minute. Precipitate the suspension and take the reading
between 5 to 30 minutes i.e. after 20 minutes by using Nephelometer, before taking reading calibrate the
instrument with standard sulphate solution after warm up for a period of 15 minutes.
Calculation:
Sulphate (%) = Concentration X Volume made for extraction X Volume made for test X DF
Weight of soil in Gms X Aliquot taken for test X 10000
Where,
DF is the dilution factor if applicable
Sulphate as SO4, (PPM) = Sulphate as SO4 (%) X 10000
Sulphate as SO3 = Sulphate as SO4 x 0.8333
6.1.6 Determination of Carbonate & Bicarbonate in Soil
40 Gms of oven dried and 2 mm sieved soil is taken & 200 ml of distilled water is added to it and shake
the suspension with the help of mechanical shaker or allow the soil suspension to stand overnight, filter
the suspension and filtrate is used for estimation of Carbonate & Bicarbonate.
Titrate the known volume of aliquot from the above suspension with the help of standard Hydrochloric
acid by using Phenolphthalein & Bromocresol green indicator.
Add 2 to 3 drops of Phenolphthalein indicator to 20 ml of aliquot
If pink colour appears (pH over 8.3), titrate the solution against standard Hydrochloric acid (0.02N)
End Point: Pink Colourless
Add 2 to 3 drops of Bromocresol green indicator to the above solution continue titrating against HCl (0.02
N)
End Point: Dark green Light pink (pH of 4.5)
Record volume of HCl used for both titrations
Calculation:
Phenolphthalein Alkalinity = A X N (HCl) X 50 X V3 X 100
Wd X S X 1000
GNGPL 6 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 7 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 8 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 9 SECON
Pipeline Network in North Goa Corrosion Survey Report
immediately. Let stand for at least 10 minutes. Measure absorbance at 540 nm. Prepare a standard
curve by adding suitable volumes of standard nitrite solutions and diluting to 50 ml with distilled water.
Develop colour as described in above procedure and measure absorbance at 540 nm.
Calculation:
Nitrite (%) = Concentration X Volume made for extraction X Volume made for test X DF
Weight of soil in Gms X Aliquot taken for test X 10000
Where, DF is the dilution factor if applicable
6.2.3 Determination of Total Soluble Solids (TSS) in Soil
30 Gms of oven dried and 2 mm sieved soil is taken & 300 ml of distilled water is added to it and shake
the suspension with the help of mechanical shaker or allow the soil suspension to stand overnight, filter
the suspension and filtrate is used for estimation of Total Soluble Solids.
Take 50-ml of the clear filtrate in pre-weighed porcelain dish, or glass dish and concentrate by
evaporating in the water bath before finally drying in the oven at 110°C. The dish shall then be cooled to
room temperature in desiccators and weighed to get the weight of the residue. The percentage of total
soluble solids in the soil shall then be calculated on the basic of the soil taken for analysis.
Calculation:
Total Soluble Solids (%) = (W2-W1) X Volume of distilled water added X 100
Weight of soil X Aliquot taken for the test
Where,
W2 = Weight of dish after evaporation in Gms
W1 = Weight of dish before evaporation in Gms
6.2.4 Determination of Organic matter in Soil
Take 0.25 gm to 5.0 gm of oven dried (105°C) sample thoroughly ground and sieved through 2 mm
sieve. Transfer the weighed sample to a 500-ml. conical flask and add 10 ml. 1N Potassium Dichromate
(K2Cr2O7) solutions. Then add 20 ml. Conc. Sulphuric acid (H2 SO4) and mix gently by rotation to
ensure complete contact. Allow the mixture to stand for 30 minutes. Add 200 ml distilled water, 10 ml of
Ortho phosphoric acid (H3 PO4, 85%), 0.2 gm of Sodium fluoride and 1 ml of diphenylamine indicator.
Titrate the solution with 0.5 N Ferrous Sulphate (FeSO4.7H2O) solution. The color is dull green at the
beginning and then shifts to turbid blue as the titration proceeds at the end point the colour sharply turns
to brilliant green. Keep a blank titration without sample and follow the same procedure.
Calculation:
Organic matter (%) = BR (V1 – V2) X N of Ferrous Sulphate X 0.003 X 100 X 1.724 X 1.3
Weight of sample in Gms
Where,
i) V1 = ml of 1.0 N Ferrous sulphate solution used for blank titration.
ii) V2 = ml of 1.0 N Ferrous Sulphate solution used for sample titration.
iii) 0.003 = 1 ml of 1 N Potassium Dichromate = 0.003 g of organic carbon
iv) Factor 1.724 is called Van Bemmeler factor with the assumption of 58% of Carbon in soil organic
matter. Therefore Organic carbon (%) is multiplied by 1.724.
GNGPL 10 SECON
Pipeline Network in North Goa Corrosion Survey Report
v) 1.3 = The use of heat of dilution don’t give complete oxidation of organic compound in soil. Walkely &
Black (1934) observed about 60-80 % of the soil organic carbon was oxidized by the heat of dilution and
the correction factor has to be considered to give an approximate estimate of soil.
6.2.5 Determination of Aerobic & Anaerobic bacteria in Soil
Take about 25 ml of sterilized mixture of 5 g yeast extract, 10 g Triptone and 5 g Sodium chloride in 1000
ml of distilled water in two test tubes. One test tube is airtight and the other having free air supply. Add
about 5 g of soil in each of the test tubes and allow the suspension to stand still for about two days.
Increased turbidity in the airtight test tube indicates the presence of anaerobic bacteria and the same in
the second test tube indicates the presence of aerobic bacteria.
6.3 Laboratory Testing Procedures for Water
Representative samples are filtered to remove any unwanted particles present, if any and used for
chemical testing.
6.3.1 Measurement of pH along with Oxygen activity and Redox Potential
100 ml of water sample is taken and stirred thoroughly before testing, the pH meter is calibrated with
standard NIST solution and pH of the water sample is measured.
To measure oxygen activity (Ep) and Redox potential (Eh).
The same sample, which is prepared for pH measurement, is used for the measurement of oxygen
activity. Platinum electrode and the Calomel reference electrode are introduced into the water sample as
per specifications. The Oxygen activity (Ep) value is recorded directly from the display. The Redox
Potential (Eh), at pH 7, of the soil suspension is calculated as shown below.
Calculation:
Redox potential (mV), Eh = Ep + Er+ 60 (pH-7)
Where,
Eh = Standard Redox Potential of soil suspension, in mV.
Ep = Oxygen activity measured with reference to Calomel reference electrode having a potential of Er,
in mV.
Er = + 250 mV for Calomel reference electrode
pH = pH of the water.
6.3.2 Chloride Test for Water
Titrate the known volume of sample (25 ml), in the pH range 7.0 to 10.0. Adjust sample pH between 7
and 10 with sulphuric acid or sodium hydroxide if it is not in the range. Add 1 ml Potassium Chromate
indicator. Titrate with Standard Silver Nitrate titrant to brick red end point. Standardize silver nitrate
solution and establish reagent blank value.
End point: Yellow Brick Red colour.
Calculation:
Chloride (mg/l) = BR (V1 – V2) X 0.0141 X 35.45 X 1000
ml of sample taken for the test
Where,
V1 = Volume of silver nitrate used for the sample
GNGPL 11 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 12 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 13 SECON
Pipeline Network in North Goa Corrosion Survey Report
2
Where,
DF= Dilution Factor
6.3.7 Determination of Sodium & Potassium in Water
Switch on the Flame Photometer and allow 10 minutes for the instrument to warm up before taking
readings calibrate the instrument, feed distilled water to the atomizer, wait at least for 30 seconds and
adjust meter reading to Zero, and then feed the water samples to the atomizer & calculate the
concentration of Sodium & Potassium directly from the standard graph.
Calculation:
Sodium & Potassium, mg/l = Concentration from the graph x DF
Where,
DF= Dilution factor.
6.3.8 Determination of Sulphide in Water
Take 50 ml of water sample in conical flask. Add 2ml of Zinc acetate solution, shake it thoroughly. Leave
the solution for few minutes for precipitate formation. Filter the sample using glass fiber filter paper.
Transfer the precipitate along with filter paper to iodine flask. Add about 50 ml of distilled water. Add 10
ml 0.025N iodine solution + 2 ml of 6N HCl. Shake it vigorously. If iodine colour disappears add more
iodine until colour persists. Titrate against standard sodium thiosulfate (0.025N) solution using starch as
indicator. End point is blue to colourless. Note down the burette reading. Follow the above steps in the
procedure for blank without sample, using distilled water. Iodine solution volume must be the same for
both blank and sample.
Calculation:
Sulphide, mg/l = (V1-V2) X N X 16 X 1000
S
Where,
V1 = Volume of Sodium thiosulphate used for the blank
V2 = Volume of Sodium thiosulphate used for the sample
N = Normality of Sodium thiosulphate
S = Volume of water sample taken for titration (ml)
6.3.9 Determination of Phosphate in Water
Take 50 ml of water sample in the volumetric flask. Add 2ml of ammonium molybdate reagent and mix
thoroughly. Add 0.2 ml of stannous chloride (approximately 5 drops) reagent. Prepare reagent blank by
taking 50 ml D W along with reagents. Measure the intensity of blue color in absorbance mode at 690nm,
for standards as well as samples, by setting the spectrophotometer to “ZERO” absorbance with a blank.
Take readings within 10 to 12 minutes. Plot the graph of concentration in ppm against OD. Find out
concentration factor from the graph.
Calculation:
Phosphate, mg/l = Concentration X 100 X DF
50
Where,
DF= Dilution factor
GNGPL 14 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 15 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 16 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 17 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 18 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 19 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 20 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 21 SECON
Pipeline Network in North Goa Corrosion Survey Report
GNGPL 22 SECON
Pipeline Network in North Goa Corrosion Survey Report
8.0 CONCLUSION
• Soil resistivity survey has been carried out at proposed pipeline alignment and the detailed
explanation is given in sec 5.1 above
• The degree of corrosivity of soil based on resistivity test results along the pipeline alignment are
presented in the table sec 7.1 above.
• Based on the degree of corrosivity along the pipeline alignment, necessary corrosion protective
measures shall be adopted at the locations wherever the soil encountered is of medium to very
highly aggressive nature.
9.0 REFERENCES
IS 1892 - Code of Practice for Sub Surface Investigations for Foundations, Bureau of Indian Standards,
New Delhi
IS 2720 (Part 2) - 1973 Method of test for soils, Part II - Determination of Water Content, Bureau of
Indian Standards, New Delhi
IS 2720 (Part 26) - 1987 Methods of test of soils, Part XXVI - Determination of pH value, Bureau of Indian
Standards, New Delhi
IS 2720 (Part 27) - 1987 Methods of test of soils, Part XXVII - Determination of Total Soluble Sulphates,
Bureau of Indian Standards, New Delhi
IS 3043 - 1987, Code of Practice for Earthing, Bureau of Indian Standards, New Delhi
A Text Book of Soil Chemical Analysis by P.R.Hesse
SECON
GNGPL 23 SECON