Module 1: Assessment (Graded)

1.Question 1
What term corresponds to the definition, “a duty that a person takes on or plays”?

Milestone

Work Product

Task

Role

ANSWER: (d) Role

2.Question 2
Which of the following is an example of a milestone?

When the project is ready to be released.

One month after the beginning of the project.

The end of a two-week sprint.

The date the product is due to be released.

ANSWER: (a) When the project is ready to be released.

3.Question 3
What does an uncertainty space diagram measure?

When a product is going to get built


Ends uncertainty / Means uncertainty

What you are going to build / How you are going to build it

Ends / Means

ANSWER: (b) Ends uncertainty / Means uncertainty

4.Question 4
When a product is built, what would you expect the ends uncertainty and means uncertainty to
be?

High ends uncertainty, High means uncertainty

Low ends uncertainty, Low means uncertainty

High ends uncertainty, Low means uncertainty

Low ends uncertainty, High means uncertainty

ANSWER: (b) Low ends uncertainty, Low means uncertainty

5.Question 5
What does a Work Breakdown Structure represent?

The demonstration of task dependencies.

Breaking down a product into work products or tasks.

The ends and means uncertainty.

The variability in a project.


ANSWER: (b) Breaking down a product into work products or tasks.

6.Question 6
What can a Work Breakdown Structure be used for? Select three answers that apply.

Identifying work products.

Generating developer tasks.

Creating estimates.

Determining the uncertainty in a project.

ANSWER: (a) Identifying work products.

(b) Generating developer tasks.

(c) Creating estimates.

7.Question 7
_____ is what you are agreeing to deliver. _____ is a guess for the time it will take for your
development team to complete a task. _____ is a point in the schedule to meet.

A commitment / An estimate / A target

A target / A commitment / An estimate

An estimate / A target / A commitment

A commitment / A target / An estimate

ANSWER: (a) A commitment / An estimate / A target


8.Question 8
Which of the following are non-negotiable? Choose all that apply.

Estimate

Commitment

Target

ANSWER: (a) Estimate

(c) Target