Professional Documents
Culture Documents
A pressure test is always required for a new pressure system before use or an
existing pressure system after repair or alteration to ensure the following:
Safety
Reliability of operation
and leak tightness of pressure systems
Also The last physical quality test in the fabrication process
Subsequent to repairs and heat treatment and prior to the initial operation or
commissioning of any plant it has to be ensured that there is no evidence of
leakage by Pressure Testing.
Pressure tests (both hydrostatic and pneumatic) must always be performed under
controlled conditions, following an approved test plan, and documented in a test record. A
single approved test plan could be used for several similar tests, but for each test a
separate test record is required.
1/15
As per the governing code, a pressure test has to be performed on the piping system
after all hot works have been completed on a certain piping system. Here the term hot
work means everything related to welding or post-weld heat treatment (PWHT). PWHT
also has the potential of degrading the mechanical properties of piping, in case not
addressed properly. And this is the reason why the code calls for NDT after the PWHT
operation.
In case after carrying out pressure testing, some modification has to be made requiring
hot work, which calls for a retest as per code. Here code specifies that the minor
repairs/modifications may be waived off provided adequate measures have been taken to
ensure sound construction. Now taking this decision as to which repairs or modifications
may be waived off should be taken very carefully. Normally, the maximum extent of
repairs not requiring retesting shall be the tack welding of any piping support or pad.
Anything else shall be done following a retest.
Pressure testing and conducting 100% radiography or ultrasonic inspection shall not be
interchanged. In case carrying out of hydrostatic or pneumatic test stands impractical
then 100% radiography or ultrasonic testing may be performed but in addition to this, it is
advisable to check that the whole piping and its components have been supplied against
acceptable ASTM standards and required test certificates are available.
Conducting 100% radiography of all the weld joints assure that your weld
joints are defect-free but can never provide you with the assurance of
mechanical integrity of a system.
This is also to be noted that radiography / ultrasonic inspection shall also not be waived
off if the pipeline is to be hydrostatically tested. This may pose an additional safety risk
during the test. Moreover, some defects in the weld zones may prove to be detrimental
way after being taken in service due to severe extended service conditions.
2/15
Hydrostatic Testing Pneumatic Testing
In a hydro test, the test media (Water) used is In a pneumatic test, the test
not compressible by pressure application. media, Air is compressible by
pressure application.
In hydrostatic testing, the energy stored per The energy stored per unit
unit volume of water under test pressure is volume of compressed air under
negligible. test pressure in the case of a
pneumatic test is very high.
Needs thorough cleaning after the hydrostatic Easy to clean after pneumatic
test to eliminate moisture, especially for testing.
services that are reactive to moisture/fluids.
Pressure Relief devices are usually Pressure relief devices are a must
recommended to control a sudden increase in during the pneumatic test to
pressure during hydro testing. ensure no over-pressurization.
The weight of equipment along with the hydro The weight of equipment with the
test medium as water is high hence special pneumatic test medium as air is
attention should be given to the floor and comparatively less.
supporting arrangements.
In hydrostatic testing, the test media can be In pneumatic testing, the test
reused or transferred to other places after media can not be reused or
testing. transferred to other places after
testing.
Skilled and semi-skilled personnel can carry Needs the involvement of senior
out the test. experienced staff to monitor the
test.
3/15
Damages made by failures are less compared Damages made by failures in
to failures in pneumatic testing. testing are very huge and
extensive as compared to
hydrostatic testing.
Pneumatic tests could be performed only when at least one of the following conditions
exists:
When the systems are designed in such a way that they cannot be filled with water.
When the systems are such that it is to be used in services where traces of the
testing medium cannot be tolerated.
ASME Code B 31.3 provides the basis for test pressure. The minimum hydrostatic test
pressure for metallic piping shall be as per the following equation:
4/15
Pt=1.5*Pd*(St/Sd)
Here,
Pt=minimum test gauge pressure
Pd=internal design gauge pressure
St=allowable stress value at the test temperature
Sd=allowable stress value at design temperature.
The maximum allowable value of St/Sd is 6.5
Pt=1.1*Pd
1. If the fluid handled by the piping system is liquid then the pipe must be hydro
tested.
2. If the fluid handled is vapor or gas then the internal design pressure dictates
the testing method. For pipe design pressure 10 bar and above the pipe is
hydro tested. For pipe design pressure below 10 bar pipe is pneumatically
tested.
3. If the fluid handled is steam then hydro testing is suggested.
4. If the fluid handled is a two-phase flow then hydro testing is suggested.
However, for big-size flare headers, pneumatic testing is performed.
5/15
During the hydro test in the case of big-bore, it should be decided first that the line
is to be hydro tested on rack or grade if the hydro test is done on the rack, the hydro
test load should be considered in case of vapor lines while providing structure/rack
loading information.
Preparation: Before testing can begin, the system must be cleaned and dried to
remove any debris or moisture that could interfere with the test. All valves, flanges,
and fittings must be properly secured and tightened to prevent leaks during the test.
Filling: Once the system is prepared, it is filled with water or another suitable test
fluid. The fluid is usually pumped into the system until it is completely filled and all
air is purged from the lines.
Pressurization: After the system is filled, it is pressurized slowly and gradually to
the required test pressure. The pressure is usually increased in increments to allow
for any leaks or weaknesses to be detected before reaching the full test pressure.
Stabilization: Once the system has been pressurized to the required test pressure,
it is held at that pressure for a specified period of time to allow for any leaks to be
detected. The duration of the test may vary depending on the type and size of the
system being tested.
Inspection: While the system is pressurized, it is inspected for leaks or other
defects using a combination of visual, audible, and/or electronic methods. Any leaks
or defects that are detected must be repaired before the system can be considered
safe for use.
Depressurization: After the test is completed, the system is slowly depressurized
to prevent sudden changes in pressure that could damage the system. The test fluid
is then drained from the system and properly disposed of.
Documentation: Finally, a detailed report of the test results is prepared, including
the pressure and duration of the test, any defects or leaks that were detected, and
any repairs that were made. This documentation is important for maintaining
records of the system’s safety and compliance with regulatory requirements.
Hydrotest Fluid
As the name signifies, the test has to be performed using clean potable water free from
suspended solids. However different codes specify different requirements for water
quality. Hence, hydro tests need to be performed following those instructions.
6/15
Piping systems that are normally open to the atmosphere, such as drains, vents,
discharge piping from pressure-relieving devices, sewers, and stack downstream of the
seal drum, need not be subjected to the piping test pressure.
For some countries, The provincial local inspector shall be notified at least 48 hours in
advance of pressure testing of piping under the jurisdiction of the provincial safety code
for witnessing at his/her option.
The following equipment shall be excluded from all piping pressure tests:
Vessels and tanks
Heat exchangers
Rotating machinery, such as pumps, compressors, and turbines
Equipment and Supplier furnished piping specifically recommended by the
manufacturer not to be tested
Underground portions of piping systems may be tested and covered before testing
aboveground portions.
Roughly, The following steps should be followed for preparing the piping system for
leakage testing.
The first step is to compare the piping isometrics with the P&ID drawings to check if any
discrepancy exists. All valve types, flow directions, branch tie-ins, and any material
changes, etc are reviewed thoroughly. In-line components are verified and ensured that
they are able to withstand the test pressure.
All sorts of ultrasonic and radiographic inspections or checks must be carried out before
the actual pressure test is started. Conducting 100% radiography of all the weld joints
assures that your weld joints are defect-free but can never provide you with the
assurance of the mechanical integrity of a system. This is also to be noted that
radiography / ultrasonic inspection shall also not be waived off if the pipeline is to be
hydrostatically tested.
7/15
If required Pipings designed for vapor or gas services shall be provided with additional
temporary supports, to support the weight of the test liquid as the test liquid is heavier
than the service fluid.
Instruments
All in-line Instruments shall be either removed or blocked prior to hydro testing to
prevent damage during hydro testing (e.g. meters).
Instrument take-off piping and sampling system piping, up to the first block valve,
shall be tested with the piping to which it is connected.
Instrument lead lines, between the first block valve and the instruments to which
they are connected, shall be pressure tested to the test pressure of the associated
piping. Testing may be performed separately or at the same time as the piping is
tested, but the instruments shall be disconnected.
If there is an expansion joint in the piping system under the leakage test, the following
criteria shall be applied.
8/15
1. An expansion joint that depends on external main anchors to restrain pressure end
load shall be tested in place in the piping system.
2. A self-restrained expansion joint previously shop-tested by the manufacturer
3. A piping system containing expansion joints shall be leak tested without temporary
joint or anchor restraint at the lesser of
4. 150 % of design pressure for a bellows-type expansion joint, or
5. the system test pressure is determined in accordance with para. 345
When a system leak test at a pressure greater than the minimum test pressure
specified in (c), or greater than 150% of the design pressure within the limitations of
para. 345.2.1(a) is required, bellows-type expansion joints shall be removed from
the piping system, or temporary restraints shall be added to limit main anchor loads
if necessary.
Equipment that is not to be tested must be either disconnected from the piping or isolated
by blinds or other means during the test. A valve may be used provided the valve is
suitable for the test pressure.
Rotating Machinery
For rotary machineries, such as pumps, compressors, or steam turbines, have lube and
seal oil systems that could be impaired by the presence of water. These systems shall not
be subjected to the piping test pressure.
Test Water
Clean water that will not corrode and/or damage the test system shall be used for
hydrostatic tests. If municipal water is not available, supply water may be obtained from a
native water supply. Water containing silt or suspended material shall not be used, and a
suitable filter with 40 mesh should be provided in the filling line. A mixture of glycol-water
shall be used where the ambient temperature may reach less than 0°C (32°F) during
testing or prior to dry-out
Check Valves
9/15
Check Valves shall have the piston or flap removed for testing, where pressure can not
be located on the upstream side of the valve. The locking device of the flap pivot pin shall
be reinstated together with the flap and a new cover gasket shall be installed after the
completion of the test.
Wherever applicable All hot works, related to welding or the post-weld heat treatment
have to be completed before the Hydrostatic test.
Installation of Barriers
It is necessary to install safety barriers around the piping system under test prior to
starting pressurization related to testing. Public Address announcements and access
restriction procedures such as permits to work shall be implemented. Under no
circumstances should anyone other than an authorized person be allowed within the
safety barriers.
Control Valves
Prior to the leakage test, Control Valves and soft-seal block Valves shall be removed from
the piping and replaced with pipe spools. However, All welded Valves need to be tested
along with pipings otherwise Radiographic Testing of golden joints (welded) will be
required.
Physical Inspection
10/15
When conducting tests at freezing temperatures, the test shall not take more than 4
hours, and special precautions, such as using a glycol/water mixture, shall be
observed to avoid freezing damage
Hydrotesting Documentation
The individual system documentation i.e. test pack shall be available prior to any testing
and shall include information such as test limits, test pressure, test medium, duration, test
blinds, blind flanges, vents, and drains.
The use of marked-up P&IDs coupled with isolation registers should be utilized to identify
the locations of blinds, Valves, vents, and drains.
Records shall be made of each piping system test. In general, these records shall include
the following information:
Date of test
Identification of piping system
Test medium
Test pressure
Minimum ambient temperature
Test medium temperature
Certification by examiner
Test duration
Pipe standards or specifications for the test
Pressure and temperature recording charts and logs
Location and cause of leaks/failures
Repair procedures used in the event that the pipe leaked or failed
Test results
Name of the test operator
Minimum metal temperature (if applicable)
Test gauge calibration date
Testing equipment such as pumps, manifolds, pressure, and temperature recorders, and
pressure gauges should be within calibration/certification (as per company procedures)
and connected to the lowest convenient connection within the system to ensure the best
results.
11/15
Even though proper industry-approved methods are followed for pressure testing, still due
to some negligence hazards do happen. Some of the most common reasons for failures
during hydro tests and pneumatic tests are:
Over pressurization
Operator error
Inadequate equipment
Poor component design
Improper isolation of the tested system from equipment or remaining parts of the
system.
Inadequate repairs
So it is always a good idea to follow safe work practices for Hydro testing. The below-
mentioned steps can be followed to avoid hazards of Pressure Testing:
Prepare a standard operating procedure (SOP) for the hydro test or pneumatic test
following the latest applicable code
Developing a checklist using the sop and sticking to it.
Train the involved personnel indicating the potential hazards and safety measures.
Develop a Pre-test safety plan and conduct a pre-test safety briefing just prior to
hydro testing.
Perform a Walk down inspection following the checklist to ensure all hydro test
checkpoints are taken care of.
After the hydrostatic test, gradually release the pressure and drain the system.
Hydrotest Checklist
The following section provides a sample of the hydro test checklist to inform the major
points that must be considered.
12/15
Hydrotesting Checklist
13/15
20 Working professionally with all PPE
equipment
Post-Hydrotest Checklist
In general, the cost of hydrostatic testing can range from a few hundred dollars to several
thousand dollars or more. For small, simple systems, the cost may be relatively low, while
larger, more complex systems can require more time, labor, and equipment, resulting in
higher costs.
To get an accurate estimate of the cost of hydrostatic testing of a specific piping system, it
is best to contact a qualified testing contractor or service provider and request a quote
based on the specific details of the system in question.
14/15
What is the difference between the Hydro test and the Hydrostatic test?
Both hydro test and hydrostatic test refer to the same pressure test method. Hence, both
are the same and there is no difference between Hydrotest and Hydrostatic test.
The hydrostatic test pressure considered for pipeline systems is 1.25 times the design
pressure.
A Hydrostatic test is done by filling the system with water and then pressurizing it to hydro
test pressure (usually 1.5 times of design pressure). The pressurized system is kept for a
pre-decided time and then visually all joints are checked for any leakage.
Yes, a hydrostatic test can cause damage. Some examples of hydro test hazards are
provided here.
Hydrostatic testing is the safest type of pressure testing as it generated considerably less
stored energy which in turn involves less risk to workers.
A golden joint is usually the final joint to weld the new pipe with the existing pipe.
As the Hydrostatic test is usually not feasible, NDE (ultrasonic or radiographic test)
is performed in place of pressure testing.
It depends on various factors like the governing codes, standards, and local procedures;
the length of the system, the number of joints to check, etc. Usually, the system should be
pressurized for a least 10 minutes.
15/15