Professional Documents
Culture Documents
Table of Contents
Types of Pressure Testing
What is Hydro-Test or Hydrostatic Test?
What is the Pneumatic Test?
When to perform a Pressure Test
Comparison of Hydrostatic and Pneumatic Testing
Difficulties with hydrostatic testing
Difficulties with Pneumatic testing
The basis for Pressure Test Method Selection
Pressure Test Duration
Hydrotest Fluid
Hydrotest system preparation
Hydrotesting Documentation
Hydrostatic Testing Problems
Hydrotest Checklist
Video Tutorial on Differences between Hydrostatic test and Pneumatic test
A pressure test is always required for a new pressure system before use or an existing pressure
system after repair or alteration to ensure the following:
Safety
Reliability of operation
and leak tightness of pressure systems
Also The last physical quality test in the fabrication process
Subsequent to repairs and heat treatment and prior to initial operation or commissioning of any plant
it has to be ensured that there is no evidence of leakage by Pressure Testing.
Pressure tests (both hydrostatic and pneumatic) must always be performed under controlled conditions,
following an approved test plan, and documented in a test record. A single approved test plan could be used
for several similar tests, but for each test a separate test record is required.
In case after carrying out pressure testing, some modification has to be made requiring hot work, it calls for a
retest as per code. Here code specifies that the minor repairs/modifications may be waived off provided
adequate measures have been taken to ensure sound construction. Now taking this decision as to which
repairs or modifications may be waived off should be taken very carefully. Normally, the maximum extent of
repairs not requiring retesting shall be the tack welding of any piping support or pad. Anything else shall be
done following a retest.
Pressure testing and conducting 100% radiography or ultrasonic inspection shall not be interchanged. In
case carrying out of hydrostatic or pneumatic test stands impractical then 100% radiography or ultrasonic
testing may be performed but in addition to this it is advisable to check that the whole piping and its
components have been supplied against acceptable ASTM standards and required test certificates are
available.
Conducting 100% radiography of all the weld joints assure that your weld joints are defect-free but
can never provide you with the assurance of mechanical integrity of a system.
This is also to be noted that radiography / ultrasonic inspection shall also not be waived off if the pipeline is to
be hydrostatically tested. This may pose an additional safety risk during the test. Moreover, some defects in
the weld zones may prove to be a detrimental way after taken in service due to severe extended service
conditions.
Comparison of Hydrostatic and Pneumatic Testing
The following table lists down the major differences between hydrostatic and pneumatic testing.
When the systems are designed in such a way that it cannot be filled with water.
When the systems are such that it is to be used in services where traces of the testing medium cannot
be tolerated.
Using a pneumatic test instead of hydrostatic requires approval from proper authority or body.
P t =1.5*P d *(S t /S d )
Here,
Pt=minimum test gauge pressure
Pd=internal design gauge pressure
St=allowable stress value at the test temperature
Sd=allowable stress value at design temperature.
The maximum allowable value of St/Sd is 6.5
P t =1.1*P d
The basis for Pressure Test Method Selection
Normally the following basis is followed in the process piping industry for the selection of hydro or
pneumatic tests.
1. If the fluid handled by the piping system is liquid then the pipe must be hydro tested.
2. If the fluid handled is vapor or gas then the internal design pressure dictates the testing
method. For pipe design pressure 10 bar and above the pipe is hydro tested. For pipe design
pressure below 10 bar pipe is pneumatically tested.
3. If fluid handled is steam then hydro testing is suggested.
4. If the fluid handled is two-phase flow then hydro testing is suggested. However, for big size
flare headers, pneumatic testing is performed.
Pressure Test Duration
Normally every EPC company has its own standard for the duration of tests. However, the recommended
practice is that a QC inspector has to walk through the whole piping system and check for leaks. Every single
length of piping, welds, bolted connections shall be visually examined for any leakage. The duration of this
activity varies with the span of the piping system. For larger piping system time taken for this activity is
enough to clear the pressure test. In the case of a piping system having a smaller span, 1 hour time may be
made as standard practice for hydrostatic testing. For the Pneumatic test, the test time is far lesser.
The tower overhead lines which are normally hydro tested shall be decided by stress engineer group
whether to hydro test after erection or at grade, based on the capacity of standard clip available as per
engineering specification for pipe supports.
During the hydro test in case of big-bore, it should be decided first that line is to be hydro tested on
rack or grade if the hydro test is done on the rack, the hydro test load should be considered in case of
vapor lines while providing structure/rack loading information.
Hydrotest Fluid
As the name signifies, the test has to be performed using clean potable water free from suspended solids.
However different codes specify different requirements for water quality. Hence, hydro tests need to be
performed following those instructions.
The following equipment shall be excluded from all piping pressure tests:
Roughly, The following steps should be followed for preparing the piping system for leakage testing.
All in-line Instruments shall be either removed or blocked prior to hydro testing to prevent damage
during hydro testing (e.g. meters).
Instrument take-off piping and sampling system piping, up to the first block valve, shall be tested with
the piping to which it is connected.
Instrument lead lines, between the first block valve and the instruments to which they are connected,
shall be pressure tested to the test pressure of the associated piping. Testing may be performed
separately or at the same time as the piping is tested, but the instruments shall be disconnected.
1. An expansion joint that depends on external main anchors to restrain pressure end load shall be
tested in place in the piping system.
2. A self-restrained expansion joint previously shop-tested by the manufacturer
3. A piping system containing expansion joints shall be leak tested without temporary joint or anchor
restraint at the lesser of
4. 150 % of design pressure for a bellows-type expansion joint, or
5. the system test pressure determined in accordance with para. 345
When a system leak test at a pressure greater than the minimum test pressure specified in (c), or
greater than 150% of the design pressure within the limitations of para. 345.2.1(a) is required, bellows-
type expansion joints shall be removed from the piping system or temporary restraints shall be added to
limit main anchor loads if necessary.
Rotating Machinery
For rotary machinery, such as pumps, compressors, or steam turbines, have lube and seal oil systems that
could be impaired by the presence of water. These systems shall not be subjected to the piping test
pressure.
Test Water
Clean water that will not corrode and/or damage the test system shall be used for hydrostatic tests. If
municipal water is not available, supply water may be obtained from a native water supply. Water containing
silt or suspended material shall not be used, and a suitable filter with 40 mesh should be provided in the filling
line. A mixture of glycol-water shall be used where the ambient temperature may reach less than 0°C (32°F)
during testing or prior to dry-out
Check Valves
Check Valves shall have the piston or flap removed for testing, where pressure can not be located on the
upstream side of the valve. The locking device of the flap pivot pin shall be reinstated together with the flap
and a new cover gasket shall be installed after completion of the test.
Installation of Barriers
It is necessary to install safety barriers around the piping system under test prior to starting pressurization
related to testing. Public Address announcements and access restriction procedures such as permit to work
shall be implemented. Under no circumstances should anyone other than an authorized person be allowed
within the safety barriers.
Control Valves
Prior to the leakage test, Control Valves and soft-seal block Valves shall be removed from the piping and
replaced with pipe spools. However, All welded Valves need to be tested along with pipings otherwise
Radiographic Testing of golden joints (welded) will be required.
Physical Inspection
Prior to test following should be checked :
Hydrotesting Documentation
The individual system documentation i.e. test pack shall be available prior to any testing and shall include
information such as test limits, test pressure, test medium, duration, test blinds, blind flanges, vents, and
drains.
The use of marked up P&IDs coupled with isolation registers should be utilised to identify the locations of
blinds, Valves, vents and drains.
Records shall be made of each piping system test. In general, these records shall include the following
information:
Date of test
Identification of piping system
Test medium
Test pressure
Minimum ambient temperature
Test medium temperature
Certification by examiner
Test duration
Pipe standards or specifications for the test
Pressure and temperature recording charts and logs
Location and cause of leaks/failures
Repair procedures used in the event that the pipe leaked of failed
Test results
Name of test operator
Minimum metal temperature (if applicable)
Test gauge calibration date
Forms, when completed, shall be retained in the Construction Contractor’s QC file as a permanent record.
Over pressurization
Operator error
Inadequate equipment
Poor component design
Improper isolation of the tested system from equipment or remaining parts of the system.
Inadequate repairs
So it is always a good idea to follow safe work practices for Hydro testing. The below-mentioned steps can be
followed to avoid hazards of Pressure Testing:
Prepare a standard operating procedure (SOP) for the hydro test or pneumatic test following the latest
applicable code
Developing a checklist using the sop and sticking to it.
Train the involved personnel indicating the potential hazards and safety measures.
Develop a Pre-test safety plan and conduct a pre-test safety briefing just prior to hydro testing.
Perform a Walk down inspection following the checklist to ensure all hydro test checkpoints are taken
care of.
After the hydrostatic test, gradually release the pressure and drain the system.
Hydrotest Checklist
The following section provides a sample of hydrotest checklist to inform the major points that must be
considered.
Hydrotesting Checklist
Pre HydroTest Checklist
Sr Description Complie Not Remarks
No d Complied
1 All Affected person like Owner, Managers, Workers, Suppliers, informed
2 Test pressure and duration received or estimated
3 Standard Operating Procedure identified
4 Pre-test safety plan completed
5 Required workers properly trained
6 Test Equipment inspected, calibrated and certified
7 Test Temperature verified
8 Test area barricated and warning signs posted to keep non-essential members outside the hydrotest
zone
9 Walk down inspection performed
10 Hydrotest system preparation proper
11 Vent Valve, Block Valve closed
12 All joints exposed, No insulation
13 System parts properly aligned
14 Torque on bolted connections as per manufacturer guidelines
15 Lockout tagout finished as per guidelines
16 Emergency contact information collected
17 proper isolation from equipment and non-test parts following SOP performed
18 Pressure relief valve installed
Checklist during Hydrotest
19 Hydrotest equipment properly installed
20 Working professional with all PPE equipment
21 Pressure applied gradually following work procedure/standards
22 Pressure maintained for the pre-decided time duration
23 All exposed joints thoroghly checked for leakage potential.
Post Hydrotest Checklist
24 Repairs started aifter the release of Hydrotest Pressure.
25 Pressure is released gradually.
26 Water disposed of as per procedure
27 Repairs performed following procedures