You are on page 1of 22

EARTHFILL DAM CONSTRUCTION AND FOUNDATION TREATMENT 341

ao

o B 7l

z
I

tl cqi
O*
-?.60 Soecrtic orotrtt
0 2.70 Soacifrc arorrtt
: <; ro
tl
t: Co3!\V
>a O
I
l-m IO
-lo
o
Jlo m
clr
zl)
-lr .t
.l;
\Sioaillc6l o6ounl ot I I
/
at< I wlumr chsga o tslu.ottoo. €s€
6lI Jrouxoettor ttt^rrtxr f !roul0 llxlt- ls
Els
1 rEourr Eo.\'-fJ-fT-ft

EIE ."
,,
o
Cosc II
vor05
I
----1
s0L r0 5
I
Dr
.E -O -7 o!.o1,
I
* IET FOPTIXUT t ORY
L oos! Voids rquol to the Dense
Oo- @- OPtl IUU IAIEF @ilE|{ll!a at oeY reEtsll-HIIURAL wAteR COtlEXTti 6t Oel wEElr I
wot?r volum! ot
ihe Iiquid limit
o Consiocring 'o-rotio: the rolio of noturol (inplocel dr, dcnsit, to
P.oclor morimum dry densitr. ord ul-(d, oplimum ,oter cont€nt minus
noturol wotrr conltnt. b. Considerrng nolurol dry den3ity ond liqurd limit

Figure l0-9. Criterion for treatment of relatively dry fine-grained foundations. Courtesy of Bureau of Reclamation.

Morimum Lood that of the foundation of Choke Canyon Dam. At this site
lnatiol ond Solurotrd
there are dry low-density alluvial soils up to 33 ft ( l0 me-
DrI dcnsitr(pcf)
ters) in depth, overlain by 3 to 6 ft (l to 2 meters) of lean
88.0 105.4
l{oisturr conlcnt(1} t3.9 zo.!
ocgree of soturofronGl {0.5 89.9 and fat clay soils. The very impervious clay precluded
prewetting the underlying silty and sandy soils by sprinkler
.! unless the clays were removed first. A scheme of using
.9 injection wells was field-tested and shown to be a viable
P solution (Fig. l0-l l). Construction started with excavation
of the cutoff trench, followed by backfilling to the original
ground surface. Holes 12 in. (30 cm) in diameter were
then drilled at 50-ft (I5-meter) centers, a 4-in. (10 cm)
Lod -r3i
slotted-plastic pipe was inserted, and gravel was packed to
form the injection well. Field tests showed that more effi-
cient wetting was attained by not having full well penetra-
tion. The best results were achieved by augering through
the layers of silty material, to determine their full depth,
G then backfilling with impervious clays to appmximately
one-half the thickness of the layer. Water was applied only
at gravity head. Some wells were spaced closer than 50 ft
( l5 meten) when moisture samples from surrounding au-
ger holes indicated a need for additional wells. The original
splcim.n,irorzt,.lIi-'' ohornifii.T' soil moisture was as much as 8% dry of Proctor optimum.
Closliftsrioo lrmM - rL
Moisture was increased only to approximately optimum.
Figurc l0-I0. One-dimensional consolidation tests at natural moisture Consolidation of just over 3% was measured during con-
(dashed) and at optimum moisture (solid). struction, with about 0.5% during reservoir filling.
342 ADVANCED DAM ENGINEERING FOR DESIGN. CONSTRUCTION. AND REHAEILITATTON

xol ?cxctrr?c0
6touilo Surr/lct txrrl?t^?tor rtLL

/r,'rorlnalf ArE/r or r€xgTt^Tto{


lrrEt 6 oirYs or wfTTtx6
CHOK g CAN YON OAM
PiEWETTIX6 FOUXOATIOX

Figure l0-ll. Foundation prewetting by infiltration wells.

Guidelines 6. The amount of moisture to be added can be esti-


mated from standard soil tests.
l. Flooding may seal the surface and limit penetration. 7. Field tests have been very useful for evaluating the
2. It is advisable to sprinkler-irrigate unstripped sur- efficiency of the final wetting method to be used.
faces. 8. A curing time is necessary to distribute moisture
3. Runoff is increased where the surface has been dis- within the deposits.
turbed by construction or farm equipment. 9. Instrumentation should be provided to verify the
4. Water should be applied continuously at the maxi- consolidation.
mum rate without runoff. 10. Flooding has been very successful in areas ofsevere
5. Saturation is not required to achieve consolidation collapse potential.
during embankment construction.

EARTHFILL CONSTRUCTION
CLRuoe A. Frrzen

Control of earthfill construction is fully described in pub- have to be pumped. Spacing of ditches will be dependent
lications of the U.S. Bureau of Reclamationz and the U.S. upon the permeability of the aquifer.
Corps of Engineers.3 This section will be limited to cov- In arid areas where the borrow materials are more than
erage of critical items. I or 2% below the minimum moisture content required for
the fill, the normal practice is to prewet the borrow sources
Operation of Borrow Sources with sprinkler systems. Prewetting to significant depths re-
quires time, which must be taken into consideration by the
Borrow sources are considered to be all sources of mate- contractor in establishing the schedule ofoperations. In hu-
rial, including required excavations and borrow areas. mid areas where the borrow materials arc 3Vo above the
Surface drainage should be diverted away from the bor- maximum moisture content permitted. disking or deep
row sources, and the excavation should be controlled to plowing should be carried out in the borrow areas; the sur-
assure positive drainage at all times. Where a high water face of the borrow area should be sealed when possible
table is present, subdrainage should be provided to pull the before rains.
water table below the level to be excavated except where Inspection forces should make continuous observations
free-draining sand and gravel can be excavated below to assure that materials being excavated in the borrow
water. This subdrainage usually can be accomplished by sources meet specified requirements for the zone receiving
deep ditches, which, depending on the topography, may the fill. Averages do not count-it only requires one lift of
EARTHFILL OAM CONSTRUCTION AND FOUNOATION TBEATMENT 343

weak material to negate the validity of the stability anal- compacted with pneumatic equipment may be requircd be-
yses, or one impenrious or semi-impervious lift to negate fore the switch to the approved tamping (sheepsfoot) roller.
the design function of a drainage layer or of an assumed
drained zone. Hence, timely action is needed to avoid Compaction against Abutments and Structures
placement of detrimental materials in the embankment. All
filter, drainage, bedding, and stone-protection materials Special compactive effort is required for the earthfill against
should be sampled and tested prior to placement in the em- abutments and structures, as uncompacted material at these
bankment, and no deviation should be permitted from the locations has been the source of numerous seepage and pip-
specified gradation Bnges; these materials should also be ing problems. These problems are usually caused by the
tested after placement, as placement and compaction often inability of self-propelled and towed tamping (sheepsfoot)
can cause degradation. rollers to compact the materials adequately within I to 2 ft
(0.3 to 0.6 meter) of steep abutment and structure faces.
Experience on several projects has indicated the difficulty
Control of Surface Drainage
of adequately compacting this gap with hand-held mechan-
As stated earlier, in Chapter 7, surface drainage from side ical tampers; these tampers can only compact very thin lifu'
draws and from slopes above the dam area must be diverted and their production rate is so slow that the remaining fill
outside the area protected by the cofferdams. Provisions rises much more rapidly than they can compact the ga5
must also be made for collecting and pumping out rain- so the gap is often filled in with an extra lift of uncom-
water that falls within the cofferdam area; otherwise, rain- pacted material without the inspector's knowledge. An open
fall will cause undue delays in cleaning the foundation and pipe along the abutment or structure is created when, upon
firr. saturation, the uncompacted layer settles. and the overly-
ing compacted layer arches over the void.
Good compaction against abutments and structures has
Removal of Dewatering SYstem
been obtained by rolling parallel to steep abutmens and
The foundation dewatering system should not be shut off structures with the front tires of loaded, front-end loaders;
and removed until the embankment has more than adequate the tires can rub against abutment and structure faces with-
weight to resist hydrostatic uplift, and until there is no dan- out damaging the rrrck or concrete. The production rate with
ger of hauling and compaction equipment causing pumping this equipment is sufficient to keep up with the remainder
of groundwater into the embankment. Collector pipes and ofthe embankment. In confined areas such as narrow back-
surrounding drainage layers left in the foundation should fill areas next to an outlet structure, hand-held mechanical
be backfilled with grout; and the system must be well tampers or other special compaction equipment may be re-
vented for the grout to flow throughout the pipes. quired. Regardless of the compaction equipment used, sev-
eral densities should be taken in each lift against the faces
of abutments and structures to ensure that the required den-
lnitial Lifts on Rock Foundations
sity is being achieved.
Initial lifts for the impervious core on rock foundations must Where embankment or backfill is being placed against
be placed and compacted by methods that will assure ad- both sides of a structure, the fill of both sides should be
equate compaction without damaging the rock surface. One kept at the same elevation to equalize the thrust of the fill.
method to accomplish these two goals is (a) to use a small As yielding of the structure during compaction is less than
dozer to push an extra-thick lift (approximately 150% of that required to develop active pressure, the forces exerted
the normal lift thickness) of fill material over the founda- by the fill on the structure may be considerably greater than
tion rock (numerous measurements of the loose-lift thick- at-rest pressures.
ness should be made to assure that it has a uniform thick-
ness), and (b) to compact the initial lift with heavily loaded Compaction around lnstrumentation
trucks or other suitable pneumatic equipment' Rolling is
continued until control tests indicate that the required den- The compacted density around instrumentation riser pipes
sity has been obtained at top of rock, as the top-of-rock should be equal to that of the contiguous fill' The riser pipes
density is critical from both shear strength and seepage must be protected from damage by the construction equip-
control standpoints. Prior to placement of the next lift, the ment. On many projects, barriers are placed around the riser
top of the preceding lift must be scarified to assure bonding pipe while the surrounding fill is raiscd I to 2 ft (0'3 to 0.6
with the next lift, but the scarification must be accom- meter) abovc the compacted zone around the pipe. The
plished with a small farm+ype disk or other equipment that barriers are then removed, the loose fill above the com-
does not break through to the foundation rock. Where the pacted zone is removed, and the excavated area is back-
foundation rock has an undulating surface, several lifts filled with compacted material using mechanical tampers.
344 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHAEITITATION

To prevent damage to the riser pipe from rammer-type Moisture Control


tampers, heavy vibratory plates have been successfully used
even for compacting impervious materials at West Point23 The moisture content of fill material should be as close as
and Warm Springs?3 dams. possible to the specified limits when the material is placed
At Warm Springs Dam,3l a compacted mound 3 to 5 ft on the embankment. On a mass production basis, it is dif-
(0.9 to 1.5 meters) high above the general fill level was ficult to appreciably raise the moisture conrent uniformly
maintained around the riser pipes. A red flag was attached through the lift, as considerable disking is required, which
to the riser pipes, but no protection other than the mound interferes with the production schedule. Likewise, it is dif-
was provided. The top of the mound was approximately 4 ficult to appreciably reduce the moisture content on the fill
ft ( I .2 meters ) in diameter, and the conical side slope was in humid climates, and especially on the night shift. Ac-
approximately I on l. As the general fill was raised adja- cording to Hammer,2s "When disking for drying purposes,
cent to the mound, the loose material along the side slope it is especially important that the disk be pulled at a speed
of the mound was bladed off and mixed with the general- sufficient to throw the soil off the individual discs, thus
fill material; and the fill compactor was used to obtain good enhancing the drying process by aerating the material."
compaction along the plane between the mound and the The moisture content must be within the specified range
general fill. Initially a rammer-type compactor was used prior to compaction; otherwise, constant reworking of
for compacting the mound, but the equipment was changed compacted layers will be required. To provide moisture
to a heavy plate vibrator when it was found that the re- data between the time when a lift is placed and it is com-
quired density could be more easily obtained with the plate pacted, the tests must be made very quickly; but the stan-
vibrator. According to the record-test data,2a the imper- dard laboratory method (ASTM D 22rc)26 reguires several
vious and random fill materials in which the instruments hours to dry the materials, making a more rapid method
were located contained considerable granular material. The necessary. Considerable variation in moisture contents has
impervious material had an average of 37 % sand size and been obtained by the hot-plate and pan method when com-
30% gravel size. The random material had an average of pared to the standard laboratory method. However, the mi-
36Vo sand size and 48Vo gravel size. Percentages are based crowave oven has been successfully used for drying sam-
on weight. The fines for both materials were of low plas- ples quickly. The required cooking time for each type of
ticity and in general ploned just above the A-line on rhe material is obtained by plotting the microwave time versus
Atterberg-limits chart. Outer fringes of the mound were moisture content to determine the time when the reduction
compacted with the rubber tires of a backhoe. Lift thick- in moisture content levels off. The moisture content at that
ness forthe plate vibratorwas approximately 4 in. ( l0 cm). time is plotted on a chart versus the moisture content ob-
To prevent twisting of the piezometer riser pipes and in- tained by ASTM D 2216, and a 45" line is drawn through
clinometer casings, the forward direction of the plate vi- the origin. The deviation from the 45o line determines the
brator was reversed after each pass, that is, from clockwise correction factor that must be used for the microwave re-
to counterclockwise, and so on. sults for each type of material. All gravel particles larger
than the No. 4 sieve must be removed from the materials
prior to microwaving, as the stones may explode because
Placement of Lifts
of an intemal water pressure buildup. Materials should not
Layers compacted or sealed with rubber-tired rollers must be left in the microwave longer than the calibrated time, as
be scarified prior to placement of succeeding lifts to assure the microwave will start removing bound water.
a good bond between lifts. Tamping rollers may leave a
Nuclear moisture-density equipment also is used to de-
well-indented liftsurface that does not need scarification; termine the moisture content (ASTM D 3017) very rapidly.
however, even these lift surfaces will contain smooth areas A minimum of one check test (ASTM D 2216) per ten nu-
requiring scarification because the areas have been crossed, clear tests should be performed for assurance that the nu-
sometimes repeatedly, by pneumatic-tired hauling equip- clear test values are correct.
ment. The thickness of each lift placed should be measured
and recorded; otherwise, the lifts will be placed exces- Compaction Control
sively thick. Disking and blading of each loose lift is usu-
ally required to break up large lumps and to provide a more Specifications. Compaction is specified by either the
uniform surface for compaction. end-result or the procedural method. [n the end-result spec-
The surface of the fill should be sloped to drain roward ification, the minimum percent of maximum density as de-
the shoulders, and the slope should always be away from termined by a specific laboratory compaction test method
inclined drains and filters to prevent fines from being is specified; this type of specification would appear to be
washed into the drainage system. the simplest way of controlling the fill compaction, but it
EARTHFTLL DAM CONSTRUCTION AND FOUNDATION TREATMENT 345

is not considered to be the best. The procedural specifica- of these materials will not hold a density: hence, any re-
tion establishes the number of passes of specific equipment sults obtained will indicate a low relative density. One way
for each tift; these requirements are based on past experi- to check the relative density ol these materials, which
ence with similar materials or on analyses of test-fill re- should be compacted in a saturated state with a vibratory
sults. In the procedural specification the required minimum roller, is to perform standard penetntion tests (SPT) at
percent density is given to the resident engineer, but it is depth. The difficulty of obtaining accurate densities in
not included in the specifications as a contract requirement. granular materials is another reason for using the proce-
However, provisions are usually included in the specifica- dural specification for compaction.
tions for payment for extra roller passes as needed to obtain Large-scale water ring displacement tests using a plastic
the desired density. In both methods, the lift thickness and liner are employed to obtain densities for record purposes
the moisture-content range in relation to the laboratory op- in earth-rock fill mixtures and in rockfill zones. In earth-
timum are usually included in the specifications. A slight rock mixtures the placement and compaction procedures
change in gradation, even from a borrow source with fairly are normally established from analyses of test-fill densities
homogeneous materials, can result in a significant change and/or level data from test fills, and the densities obtained
in the maximum density, and earth-rock mixtures cannot in the prototype are not often used for control purposes.
be readily controlled by densities alone; so the procedural
specification is considered the best method for positively Selection of Correct Moisture-Density Compaction
controlling the compaction of the fill to uniformly achieve Curve. The critical factor in the control of earth fill work
the desired density, with density tests providing spot con- is to determine the appropriate maximum density and op-
firmation and as-built data. Also, the procedural specifi- timum moisture content in order to compare the field den-
cation is fairer to the bidders, as the specifications provide sity and moisture content with these values. This compar-
a definitive work effort with extra pay for any extra work. ison is needed quickly to determine whether a completed
The procedural specification requires continuous inspec- lift is satisfactory or needs to be reworked and recompacted
tion for checking that materials placed in each zone are prior to placement of the next lift. On most projects, a fam-
within specification limits, for measuring the lift thickness, ily of five-point moisture-density compaction (ASTM D
and for counting roller passes; however, continuous in- 698 or D 1557) curves is developed in the early stages of
spection also is required under the end-result specification construction for each embankment zone. As construction
for the same reasons except for counting passes. A labo- proceeds, additional moisture-density compaction cun'es
ratory technician is required under both specifications to are developed when new-type materials are encountered.
perform moisture and density tests, but appreciably more As it normally takes at least 48 hours to prepare the spec-
density tests should be performed with the end-result spec- imens and perform five-point moisrure-density compaction
ification on the open fill than would be required for the tests, it is not possible to perform a five-point compaction
procedural specification. The same number of moisture and test for every density test taken on the fill. Hence, the crit-
density tests should be performed at the abutments and ical step is to quickly relate the dry density and moisture
against structures under either specification, and this num- content obtained on the fill to the correct five-point com-
ber should be greater than that on the open fill. paction curve and to its accompanying maximum density
and optimum moisture content. In the visual-observation
Test Methods. Field density test methods and labora- procedure, the five-point compaction curve is selected by
tory moisture-density and relative density test methods are comparing the soil obtained from the field density with jar
fully described in volume 04.08 of the 1987 Annual Book samples saved from the laboratory compaction tests. Ham-
of ASTM Standards.zo The sand displacement method mer,25 who considers this method to be unreliable, devel-
(ASTM D 1556) is commonly used to take densities in earth oped a quick method (2 houn) for Warm Springs Dam
fills. Nuclear equipment (ASTM D 3017) is often used to whereby one-point compaction tests could be performed for
measure density in place for shallow depths in commercial selection of the appropriate five-point compaction curve
work including dams. Prior to using nuclear equipment, where the curves are parallel, or two-point compactior: tests
the technician should have training at the equipment man- could be made where the five-point compaction curves are
ufacturer's school; also, one check test by ASTM D 1556 not parallel. In the one-point method the material from the
for each ten nuclear tests should be performed to assure field density is pulverized and ntixed and allowed to dry to
that the results are consistent. a water content of approximately 2% dry of optimum. lt is
Field density tests of uniformly graded filter and drain- then compacted in a mold and weighed, and the dry density
age materials having less than 5% by weight passing the is calculated from the wet weight and moisture content.
No. 100 sieve are extremely difficult to obtain, as the upper The compacted dry weight and moisture content are plotted
unconfined surface to depths of 6 to l2 in. (15 to 30 cm) on the family of curves, as shown in Fig. 10-12. If the
346 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILTTATION

",oz aro
e uarw
efr.u
N o,att,f7
..taa cufa.7
hN Cad o, eiM)

/ \.t 'tf,''i,Ezi,*#i;il' ato

t 3tl srto l$ \"1 (Lnc a erwo

I
t
a
6
a
/ I
N E
2
I

I
a
o

Y(O \
<ux 'ltot cu*t ,
t',,\
vur trru& effffi
ft57 0 t&w ru rtPtaL-

20 25 to
utet cocrTti?, t srtt coitf xT, !a

'lfi*:me*,ff ;!$:H,:ffi,?,:iir:r E:tr Is,."? L*


' ffi *i :f i'ri.Titi.tflr:iE$::' #r,ffl i'i;':'
2. tsYrutEo co{Bcrloi culvc aasto ox lo.ils a aNo a
:Sraalr$cs
'H€ o olr txa l-xut, wxlcx l3 rHa f ttluaiEo
d a 2rud,q
P^Crrox cuiE3. - '..,:"*IffJ:f.::,::'*T::H:;- "orN7 aio errw qtlr coNrcflY of t*
Lilfli.",ff""rtr
Figurc l0-12. Illustration of one-point compaction correlation method. Figure lGl3. Illustration of two-point compaction correlation method.
After Hammer.r After Hammer.r

point falls between curves, a curve is projected to obtain which has a volume of 2.65 ft3 (0.075 m3;. To reduce the
the maximum dry density and optimum moisture content. sizeof specimens needed in the field laboratory, consid-
A similar procedure is followed for the two-point method. erable research has been accomplished by Donaghe and
Before compaction, one specimen is dried to slightly below Townsend2T and others on scalping and replacing the plus
optimum moisrure, and the second specimen is dried to a l-in. 1Z-cm; gravel for compaction in a 6-in. (15-cm)
lower moisture content. The results are plotted, as shown mold, in compacting scalped minus ol-in. (2-cm) material
in Fig. l0-13, to determine an estimated compaction curve in a 6-in. ( l5-cm) mold, and in correlating the results with
for comparison with the field density and field moisture full-scale testing of minus 3-in. (7.5-cm) gravelly material
content. Hammel5 recommends: "Full five-point curves in an l8-in. (46-cm){iameter mold. The Donaghe-
should be continually run during construction (preferably Townsend2T report is considered essential reading for em-
I forevery l0 or l2 one-point tests) to check the one-point bankment engineers involved in construction control of
data and to supplement the family of curves. The family of earth-gravel mixtures. Although their report's title is
curves must be plotted to a large scale; otherwise, the plot "Compaction Characteristics of Earth-Rock Mixtures."
will become cluttered and errors will result." It is consid- the rock sizes were actually gravel and not broken rock per
ered that five-point laboratory compaction tests should be se.
run at the same ratio used for the two-point method. At Warm Springs Dam2a the random material was re-
The U.S. Bureau of Reclamation has developed the quired to have 100% passing the 4-in. ( lO*m) sieve and
Rapid Compaction Control method, which is fully de- not more than 50% passing the No. 200 sieve, and the ma-
scribed under Designation E-25 inits Eanh Manual.2 terial was required to be compacted to an average percent
compaction of 95% of maximum dry density as determined
Earth-Gravel Mixtures. Where density control is re- by the modified compaction test, ASTM D 1557. The ma-
quired in random fill or earth-gravel mixtures, construction terial was spread in lifts to produce an 8-in. (20-cm) lift
control becomes even more difficult as larger field densities thickness after compaction with eight passes of double-
and larger laboratory compaction specimens are required drum, self-propelled, vibrator mllers having a total static
than for fine-grained soils. It is commonly accepted that weight of 45,500 lb (20,638 kg) and delivering an im-
the maximum particle size in the compaction mold should parted dynamic force of 57,800 tb (26,218 kg) per drum
not exceed one-sixth the diameter of the mold. Hence, full- at 1700 vibrations per minute. As the material contained a
scale testing on material having a maximum diameter of 3 maximum of l0% by weight in gravel sizes in excess of 2
in. (7.5 cm) requires an l8-in. (46-cm)-diameter mold, in. (5 cm), the particles larger than 2 in. (5 cm) recovered
EARTHFILL OAM CONSTRUCTION AND FOUNDATION TREATMENT 347

in the density test holes werc placed back in the hole prior 2. Compaction tests on duplicate specimens by ASTM
to pouring in the density sand; hence, control was based D 1557 Method D in a 6-in. ( l5-cm)-diameter mold:
on the density of the minus 2-in. (5-cm) material, which that is, the experimenters scalped and replaced the
would require a l2-in. (30-cm)-diameter laboratory mold. plus l-in. (2-cm) material.
To reduce the amount of effort required for the field labo- 3. Compaction tests in a 6-in. ( l5-cm)-diameter mold
ratory, a testing Prcgram was performed to determine if on duplicate specimens by ASTM D 1557 lttethod C
results equivalent to the l2-in. (30-cm) compaction tests on scalped minus l-in. (2-cm) material, with results
could be obtained in a 6-in. ( l5-cm) mold (a) by scalping corrected upward for the effect of the oversize.
and replacing the plus f-in. (Z-cm) material in accordance 4. Use of the rtsults obtained from the l2-in. (30-cm)
with ASTM D 1557, Method D, or (b) by compacting the mold to evaluate each Procedure.
scalped f-in. (Z-cm) material in a 6-in. ( 15-cm) mold and
theoretically correcting the density upward and the mois- Some of the pertinent results are shown in Figs. l0-14
ture content downward by these commonly used equations: through l0-17. The gradation curyes for the 30% plus l-
in. (2-cm) material are shown in Fig. l0-14. The mois-
Densiry correction: ture-density compaction curves for the 30% plus ]-in. (Z-
cm) material are shown in Fig. l0-15. The optimum water
"Yf G^^Yn content versus the percent plus l-in. (2-cm) material is
,YA x 100 shown in Fig. 10-16. The maximum dry density versus the
11P, + G^"Y*PI percent plus l-in. (2-cm) material is shown in Fig. l0-17.
These data indicate that the compaction tests on the scalped
where: minus J-in. (2-cm) material with results theoretically cor-
rected provided better correlation up to 30% plus ]-in. 1Z-
?a = calculated dry unit weight of total sample cm) material than did the scalped and replaced tests. As
'yf : dry unit weight of finer fraction (from compaction most random material had 30% or less of plus l-in. 12-cm 1
test on scalped material) material, the procedure used at Warm Springs Dam to se-
G- : bulk specific gravity of coarser fraction (oversize lect the maximum density and optimum moisture content
material) was a one-point compaction test for each field density in a
7- : unit weight of water 6-in. (15-Cm)-diameter mold on scalped minus l-in. 12-
P" = percent of coarse material by weight of the sample
cm) material with the results theoretically corrected for
P, : percent of fine material by weight of the sample moisture and density for the oversize. A five-point, 6-in.
( l5-cm)-diametercompaction curve was run on each shift,
M oi s tu r e - c ont e nt co rr e cti on : and the bulk specific gravity ( G-) of the plus ]-in. 12-cm;
material was determined. Occasional compaction tests in
(wyPs * w,P,) the l2-in. (30-cm) mold were also run as a further check
WT:
r00 on the system.
The experimental data obtained at Warm Springs Dam
where: were very similar to those obtained by Donaghe and Town-
send.27 As shown in Fig. 16 of their report, the scalped
wr = water content of total sample in percent and theoretically corrected test results from the 6-in. ( l5-
l{,/ = p€rccnt water content of fine material cm)-diameter compaction tests up to 40% plus l-in. 12-
P, : percent of fine material by weight to total sample cm) content were more representative of the test results
r/c : percent water Content Of coarse material obtained from the full-scale tests in an l8-in. (46-cm)-di-
p" : percent of coarse material by weight to total sam- ameter mold than were the test results from the scalp-and-
ple replacement method. On every project where density con-
trol is required for earth-gravel or earth-rock mixtures. it
Note: The dividing line for coarse and fine fractions at is considcred advisable to conduct a laboratory experinten-
Warm Springs Dam was l-in. (2 cm), but it could also be tal program similar to the one at Warm Springs Dam to
No. 4 sieve size as used by Donaghe-Townsend.?7 correlate the results from different-size compaction molds.
The experimental work at warm Springs Dam23 in-
cluded the following: Compaction EquiPment

l. Compaction tests in l2-in. (30-cm)-diameter mold On large mass-production projects, self-propellcd, double-
on sfecimens with varying Percentages of plus ]-in. drum, sheepsfoot rollen are becoming the standard, rather
(2-cm) material. than towed rollers, for compacting the impervious fill. A
348 ADVANCED DAM ENGlNEERING FOR DESIGN. CONSTRUCTION. AND REHAEILITATION

u. s slrr{)mo gtYt (Illffi n railfs U. i St^,.()^tO gw€ iUrBtEt rrqxltt


| ! .r,tt I tto t.l6 20 r lo !(, m tolao

I I
e r:
! E
6 6
G
z
6
z
I z
c
E

Gn^I'I EZE UT TILIITTTRS


Gn^rlt SArao
coSSLts 9[r m cuY
w fx IM

Figure l0-14. Warm Springs Dam. gradation curve for 30% plus ]-in. (2-cm) random material used in laboratory compaction studies. After Hammer.ls

recent development is Caron Compaction Wheels, which


IFCM can be used with many compacting machines. Caron Com-
o< 66Mdd.Mirulrakd
e--9 CGdGir-Mhs,46.CuN paction Wheels have interchangeable tamping caps of var-
\-{ 6hMd-Hs}4rrtUd
uFddRqtd(ASTM)
ious sizes. According to the manufacturer's literature.lE a
H l2-i&Md.Mhu!-irH Caterpiller 825 B Compactor equipped with Caron Wheels

r
I
l.trr
za {2
la

e FUU. sc^Il fl2.tN. Dtr MOt!)


4
ar I
d
a REPTACED{CC{, MOTJ))

d
F
, I

5
o.2.?0 sc^lrEDrrHE(nEnc,t .,)q, -.-
s.tffi cdlEffiilT'iliifiilor/
01020!0s0s0
2q68l012trl PERCEIfT PLUS 3/{.N' MATERIAL
WATER CONTENT (I DRY WT.)
Figure l0-16. Warm Springs Dam. random material compaction studies,
Figure l0-15. Warm Springs Dam, random materiirl compaction srudies. optimum water contcnt vs. pereent plus ]-in. (2-cm) matcrial. Aftcr
dry density vs. water content. After Hammer.:l Hammer.:t
EARTHFITL DAM CONSTRUCTION AND FOUNDATION TREATMENT 349

Warm Springs for compacting thc impe rvious eanh fill. as


shown in Fig. l0-18.
142 **=,,, For random fill, earth-gravel and eanh-rock mixtures. a
g
variety of high-production types of compaction equipment
I has been used. As previously described, double-drum, self-
). l!0
propelled, vibratory rollers were used for the random zones
A at Warm Springs Dam,23 where the combined production
Ius
o rates for impervious and random zones ranged from 60.000
2
f to 120,000 ydr (45,873 to 91,141 mr; for two l0-hour
shifts per day. Rollen were used in series as shown in Fig.
IE t,t
A\A 10-19. As these rollers had smooth wheels, each lift had to
be scarified after compaction to assure good bond with the
ll4 A nexr lift.
SC LM & REPT CED
(6N. Dh MOLD) At East Fork Dam,2e Little Miami River, Ohio, produc-
B2 tion rates of 40.000 ya3 llO,saZ mrl were achieved in
ol020l0q0t0
PERCENT PLUS 3/4.IN. MATERIAL
compacting random fill consisting of soft shale and thinly
bedded limestone in S-in. (20-cm) loose lifts with four
Figure 10-17. Warm Springs Dam, random material compaction studies, passes of a self-propelled tamping roller followed by nvo
maximum dry density vs. percent plus ]-in. (2-cm) material. After
passes of a 50-ton (45,a00-kg) rubber-tired roller: the
Hammer.2l
tamping roller had tapered feet projecting 9.5 in. (24.1 cm)
from the drum, a tip contact area of 12 in.z (77.4 cm:),
with w/S-10 ( l0 in.2, 64 cm2; caps would have a weight and a contact pressure of 661 psi (46.5 kg/cmr1.
of 4747 lb/lin ft (706a kg/lin meter) of drum and a foot
contact pressure of 880 \bfin.z (61.9 kg/cm2) based on Utilization of lnstrumentation
two tamping feet per wheel only in full contact with the
ground surface. Equipped with w/S-14 ( 14 in.2, 90 cmz) Installation of the different types of instrumentation is de-
caps, the weight would be a788 lb/lin ft (7125 kg/lin me- scribed in Chapter 25. The responsibility for reading the
ter) of drum, and the foot contact pressure would be 634 instruments and interpreting the data should be given to a
lbfin.z (44.6 kg/cm2;. Self-propelled rollers in series specific individual. On large or complex projects, staffing
equipped with Caron Compactor Wheels were used at is usually provided for an instrumentation engineer. On

Figure l0-18. Warm Springs Dam, self-propelled sheepsfoot rollers used in series for conrpacting inrpervious zone. Photo courtesy, U.S. Army Engineer
District, Tulsa.
350 ADVANCED OAM ENGINEERING FOR DESIGN, CONSTRUCTION. AND REHABILITATION

,...

Figure l0-19. Warm Springs Dam, self-propelled vibratory rollers used in series for compacting random zone. photo courtesy, U.S. Army Engineer
District. Tulsa.

small projects, the embankment engineer may serve also as water levels in the inclinometer tubes. Movement indicated
the instrumentation engineer. The use of computers for by data from the inclinometers or from measurement points
providing updated printouts of the instrumentation data is may also be indicated by surface cracking in the fill where
most helpful in the timely inrerpretarion of the data. With the surface has not been recently disturbed. Most embank-
modern telecommunications equipment, the instrumenta- ment movements involve high pore pressure in combina-
tion data and printouts can be quickly provided to the de- tion with other factors.
sign staff in the home office. A cautious, pessimistic interpretation should be made of
The on-site instrumentation engineer should always be abnormal readings or trends. The questions should always
on the alert for abnormal readings or abnormal trends that be: "What can this lead to, and what is the worst that can
are beyond the guidelines provided by the design staff. occur?" This line of questioning will often show the need
Careful and timely investigations are needed to determine for prompt correction. Possible corrective actions include:
if abnormal readings are due to errors in instrumentation construction of stability berms; drainage by installation of
readings, malfunctioning instruments or developments horizontal drains in the embankment or abutments or by
within the monitored areas. A full set of tested backup in- installation of vertical drains in the embankment or foun-
strumentation readout equipment should be kept on the dation, aided in extreme cases by electro-osmosis;3o partial
project at all times because critical readings would be removal of the fill to remove a wet layer in the embankment
missed in the time required to obtain replacements. Fur- or foundation; cessation of construction until excess pore
thermore, backup equipment is often needed to determine pressures dissipate; and so on. Prompt action to prevent
if readings are valid. If
the in-place instrumentation is excessive movement is crucial, as the reworked material
faulty, it should be replaced, if possible, as soon as a new along the slide plane has a much lower strcngth than it had
instrument can be obtained. before sliding. Once significant movement starts, it may be
Verification of abnormal readings can also be deter- impossible to stop the movement, and failure may occur.
mined by other observations. High pore pressures, as in- At Carsington Dam3r one day after a crack opened above
dicated by piezometer data in the fill, may also be indicated the clay core of the nearly completed I l5-ft (35-meter)-
by heaving or weaving of the fill under the action of the high dam, the upstream side slid away over about one-third
hauling equipment. The high pore pressures in the fill of the dam's 3800-ft ( I158-meter) length. As a resulr, the
shown by the piezometers may also be indicated by high dam was to be demolished and rebuilt.32
EARTHFILL DAM CONSTRUCTION AND FOUNDATION TREATMENT 351

INSPECTION AND CONSTRUCTION RECORDS


Cleuoe A. Ferzen

lntroduction Commission (formerly Federal Power Commission) rc-


quires the owner to submit a quality control (QC) inspcc-
The importance of adequate inspection in earth dam con- tion program for approval by the regional engineer before
struction cannot be overstated. Not one wheel should turn, construction may start; however, the QC progrdm may not
nor should one spade of dirt be turned over, unless an in- be administered by the contractor, but must be the respon-
spector is present. This rule applies to all shifts and not just sibility of the owner or a firm retained by the owner. Con-
the day shift, as the level and competency of inspection tractors are not precluded from having their own QC pro-
should be the same at all times. Verification of the ade- grams for their own purposes.
quacy of the foundation treatment, the suitability of mate- A quality control program should be developed for each
rials, and the placement and compaction over the entire project, and it should be tailored for the specific project
dam is in the eyes of the inspectors, as test records verify with appropriate personnel selected for the specific needs.
only very limited areas that represent a minute fraction of Clear lines should be developed as to the contractor's re-
the total dam area and dam materials. Tests take time, and sponsibility and the engineer's responsibility. Earth dams
several lifts could be placed before the test results indicated are one ofa kind, and for them to function as designed, the
that corrective action was needed; whereas.an experienced foundation and abutments must be prepared correctly
inspector can quickly tell from the action of the hauling throughout; appropriate materials must be placed in each
and compaction equipment if the moisture content is in the zone; and each lift must be moistened and compacted prop-
appropriate range, and if the proper compaction is being erly. Hence, the owner must provide adequhte inspection
achieved. If not, an inspector can stop the work before ad- to ensure that all work is accomplished properly.
ditional lifts are placed and have tests performed to verify
his judgment. Inspecton are especially needed to watch the
placement and compaction of each lift against abutments Construction History
and structures; and they are needed as well to verify that
appropriate materials are placed in each zone and to watch If a dam is worth building, it is worth the cost of a written
for unusual developments, which the design engineers record of how it was built. The construction history is an
should be made aware of, in the materials or foundation invaluable aid in the evaluation of the dam's performance.
conditions. in analyzing problems, and in developing remedial mea-
sures; it is also a source of valuable information in le-eal
issues. The resident engineer and key staff members should
Ouality Control
be retained at the site until the construction history has been
The responsibility for inspection normally lies with the completed. To ensure accuracy and completeness, all rec-
owner's resident engineer and staff, or with an engineering ords should be kept curent as the job progresses. Daily
firm retained by the owner. In the late 1960s, a concept records are essential to preparation of the construction his-
from the U.S. govemment's military procurement pro- tory and in establishing factual information for claims and
gram, known as contractor quality control (CQC), was disputes.
adopted by the Corps of Engineers and the Bureau of Photographs are used to record progress and significant
Reclamation. CQC was designed to place the burden of events. High-quality color photographs are made on most
proof on the contractor for compliance with the require- projects, and color processing laboratories can make good-
ments of plans and specifications. The owner's (the U.S. quality black and white prints from color prints if multiple
government's) program was called quality assurance (QA), printing in black and white is needed. Video tape recording
and was intended to check the effectiveness ofthe contrac- and time-lapse photography are now used for unique op-
tor's quality-control system. As originally initiated, the erations such as installation of relief wells, cutoff walls.
CQC was intended to reduce the number and cost of gov- and so on. The tapes can be reviewed during preparation
ernment inspection personnel. However, experience with of reports and are very useful training aids for similar op-
the CQC program has indicated that adequate quality as- erations on future projects.
surance requires essentially the same level of inspection Records should be kept of all the project equipment, in-
and tests as were accomplished prior to introduction of the cluding the brand nanre and model. A record should be
CQC program. The current responsibilities of the contruc- made of the downtime for each piece of equipnrent. De-
tor and of the Corps of Engineers for quality control are watering methods and their effectiveness should be re-
described on pages 2-2,24, and 2-5 of reference 3. corded. Fill operations should be described with special
According to Corso,33 the Federal Energy Regulatory emphasis on the methods used to compact fill adjacent to
352 ADVANCED DAM ENGINEERING FOB OESIGN. CONSTRUCTION, AND REHABILITATIOT{

abutments and structures. All specialty work, such as fil- pleted. Reduced sizes of the as-built drawings should be
ters, drains, relief wells, cutoff walls, placement of riprap, included in the construction history.
and so forth, should be recorded. Distribution of the construction-history reports would
The foundation-treatment report, including geological normally include copies to the engineer, owner, pmject
mapping of the foundation, should be prepared by the site records center, and applicable state and federal regulatory
foundation engineer and by the site engineering geologist. commissions.
This report should be prepared as the work progresses while
all the details are known. Numerous photographs should REFERENCES
be included to illustrate fully the foundation conditions and
the methods used to prepare the final surface. Grouting rec- l. Terzaghi. Karl, "Does Foundation Technology Really Lag?" En-
gineering News-Record, Feb. 15. 1962, pp. 58-59.
ords are an essential part of the foundation report. A profile
2. Bureau of Reclamation, Earth lvlanual, 2nd ed.. U.S. Department of
of the grout lines should be included, showing the takes for the Interior. 1974.
the different stages and the mixes and pressures used. Grout 3. Corps of Engineers, "Construction Control for Eanh and Rockfill
breakouts and foundation lifting or movements during Dams," EM I I l0-l-19l I, U.S. Depanment of the Army, Jan. t7,
grouting operations should be fully described. 1977.
4. Acker, Richard C., and Jones, Jack C., "Foundation and Abutment
Treatment for Rockfill Dams." tournal of the GT Division, ASCE,
Disputes and Modifications Vol.98. SM 10. Oct. 1972.
5. Barmn, Reginald A., "Aburmentand Foundation Treatment for High
All oral orders given to the contractor should be followed Embankment Dams on Rock," Jourzal ol the GT Dir.ision, ASCE,
up immediately with a letter. This is particularly necessary Vol.98, SM 10, Oct. 1972.
in case of slow progress, unsatisfactory work or materials, 6. Burke, Harris H., Content. Charles S., and Kulesza. Richard L..
"Current Practice in Abutment and Foundation Treatment," Joumal
or other matters that could lead to disputes. of the GT Division, ASCE. Vol. 98. SM 10, Oct. 1972.
Modifications in contract requirements are almost inev- 7. Pratt, Harold K., McMordic, Roben C.. and Dumas, Roben M.,
itable in earth dam construction. The terms and cost of a "Foundation and Abutments-Bennett and Mica Dams." Joumal of
modification should be agreed upon in writing before the the GT Division, ASCE, Vol.98, SM 10, Oct. 1972.
modified work is started; otherwise, the ultimate cost could 8. Stroppini, Elmer W., Babbitt, Donald H., and Struckmeyer, Henry
E., "Foundation Treatment for Embankment Dams on Rock."./oar-
be excessive. Its impacts, if any, on the unchanged work nal of the GT Diyision, /SCE, Vol. 98. SM 10. Oct. 1972.
should be included in the agreement. Timely investigation 9. Wallace. B. J., and Iltihon. J., "Foundation Pracrices for Talbingo
of changed conditions and early development of the mod- Dam. Australia," Joumal of the GT Division, ASCE. Vot. 98. SM
ified design greatly lessen these impacts on the contractor. 10. Oct. 1972.
Contract modifications for weather-delay time extensions 10. Walker. Fred C., and Bock, R. W.. "Tqeatment of High Embank-
ment Dam Foundations," Jounnl of the GT Division. ,.|SCE, Vol.
should be very carefully examined before being granted be- 98, SM 10, Oct. 1972.
cause major increases in cost can accrue to the owner if I l.
Committee on Embankment Dams and Slopes, ASCE. "Foundation
such time extensions allow the contractor an additional and Abutment Trcatment for High Embankment Dams on Rock,"
construction season to complete the.work. Weather is usu- Joumal of the GT Division, ASCE, Vol. 98, SM 10. Oct. 1972.
ally classified as normal, other than normal, or unusually 12. Skempton, A. W., "Long Term Stability of Clay Slopes," Giotech-
nique, Yol. 14, No. 2, pp. 77-102. 1964.
severe. Many contracts now are being written to provide 13. Bjemrm, Laurits, "Progrcssive Failure in Slopes of Overconsoli-
time extensions only for the classification of "unusually dated Plastic Clay and Clay Shales," ASCE, Soil lvlech. &. Foun-
severe," which is defined as weather that mrely happens dation Division, Vol. 93, No. SM-5. pp. 3-49, 1967.
and/or is of such severity that it could not be anticipated 14. Peck. R. W.. "Srabiliry of Natural Slopes." ASCE, Soil Mech. &
Foundation Division, Vol.93, No. SM 4, pp.403-.117. 1967.
by the contractor. To provide a basis for evaluating a con-
15. Knight, D. K.. "Oahe Dam Geology, Embankment and Cut Slopes."
tractor's claim for time extensions, a detailed record of the ASCE, Soil Mech. & Foundation Division, Vot. 89. No. SM 2. pp.
job site temperature, precipitation, humidity, and wind ve- 99-t25.1963.
locities should be kept for comparison with deviations es- 16. Wright, S. G.. and Duncan, J. M.. "Analyses of Waco Dam Slide."
tablished for the month in which the claim delay occurred. ASCE, Soil Mech. & Foundation Division. Vol.9E. No. SM 9, pp.
Appropriate similar data are also needed for evaluating 869-877. Sept. 1972.
17. Insley, A. 8.. Chauerji. P. K.. and Srnith. L. 8.. "Use of Residual
claims for time delays due to unusual stream flows.
Strength for Stability Analyses of Embankrnent Foundations Con-
taining Pre-existing Failures." Canaelian Geotech. Journal, Vol, 14.
pp.405-428, 1976.
As-Built Drawings
18. Casagrande, Arthur. "Contrsl of Seepage thmugh Foundations and
A current set of marked-up as-built drawings shoulci be kept Abutments of Danrs." First Rankine Lecture. Gioteehniepe. Sept.
t96r.
in the resident office. The official set of as-built drawings 19. Houlsby, A. Clive, "Ccment Grouting: Water Minimieing Prac-
should be drafted from the resident engineer's set when the tices." /s.raes in Dam Grouring, ASCE, pp, 34-75, lvtay 1985.
work is completed, or when each stage of the work is com- 20. Lombardi, Giovanni, "The Role of Cohesion in Cement Gmuting of
EARTHFILL DAM CONSTRUCTION AND FOUNDATION TREATMENT 353

Rock." ICOLD-Fiftr.enth Inrernational Congress on Large Dams, tics of Eanh-Rock Mixrurcs, Report 1: Blcndcd lvlatcnal... Mircl-
Lausanne, Swiuerland. 1985. laneous Papcr 5-73-25. U.S. Army Engincer Warcrways Expcrimcnr
21. Deere, Don U.. and Lombardi, Giovanni. "Gmut Slurries-Thick Station. Vicksburg. MS, 1975.
or Thin,': Issues in Dam Grouting, z{5C8. May 1985. 28. "Caron Compaction Whccls," Bullctin No. CW.6-BI. Carun Com-
22. Corps of Engineers. "Grouting Technology." EM l tl0-2-3506, pactor Co.. Modcsto. CA.
U.S. Department of the Army. Jan. 20. 198.1. 29. Fetzer. Claudc A.. "Use of Compacted Shale as Dam Embank-
23. Hammer. David P.. pesonal communication to Claude A. Fetzer. ments." Proceedings Seventh Ohio River Valtcy Soils Seminar.
24. Corps of Engineers. "Embankment Criteria and Performance Re- Lexington. KY, Ocr.8, 1976.
port, Warm Springs Dam-Lake Sonoma Russian River Basin. Dry 30. Fetzer, Claudc A.. "Electro-osmoric Srabilization of Wesr Bnnch
Creek, Califomia," U.S. Army Corps of Engineem, San Francisco Dam." Proceedings Confcrence on Stability and fr:rformance of
District, Oct. 1983. Slopes and Embankmcnrs, ASCE. Soil l{ech. & Foundations Divi-
25. Hammer. David P.. "Methods for Effective Placcmeni and Cont- sion, Berkeley. CA.pp. 95-12.1. Aug. 22-26. 1966.
paction Control During Eanh Embankment Construction." unpub- 31. "British Dam Slip Foretold." Engineering Ncu,s-Recorc!. June 28.
lished paper presented at 1978 ASCE Convention, Chicago, IL. Oct. 1984. p.22.
l6-20,1978. 32. "British Dam to Be Scrappcd." Engineering Nexs-Rccorr/, Oct. 25.
26. American Society for Testing and Materials, Annual Book of ASTM 1984, p. 18.
Standanls, Vol. O{.08, Soi[ and Rock; Building Stones, ASTM. 33. Corso, Ronald A., "Dam Safety Program of rhe Fedcral Eneqlv
Philadelphia, PA. 1987. Regulatory Commission." Associati<tn of State Dan Safert.O!ficials
27. Donaghe. R. T., and Townsend, F. C., "Compaction Chlracteris- (ASDSO) Newsleuer, Vol. No.2, N{ay 1985, pp.7,8, and 20.
LL
EARTHFILL DAM PERFORMANCE AND
REMEDIAL MEASURES
Cueuoe A. Ferzen Wrr-lrnu F. Swrcen
Consuhing Geotechnical Engineer Consulting Engineer
Cincinnati, Ohio Buhl, tdaho
Vice President and Senior Consuking Engineer (Retired)
Stone & Webster Engineering Corporation

RrcHeRo W. Knaupn Jacr G. Wulpr


Civil Engineer President
U.S. Bureau of Reclamation Wahler Associates
Denver, Colorado Palo Ako, California

ESTABLISHMENT OF ACCEPTABLE NORMS


CLeupeA. Ferzen

Earth embankments are massive structures that inherently changes in the foundation treatment or achieving a higher
have movements and seepage. Consolidation of the em- percent of maximum density than was specified may result
bankment and the foundation occurs most rapidly during in less consolidation, movement, and seepage than were
construction and at a lesser rate for an extended period of computed during the design stage. There are no standard
.time
thereafter. The initial filling and its accompanying sat- guidelines that can be applied to the tolerable amounts of
uration may temporarily accelerate the consolidation of the movements and seepage, as each embankment has its own
upstream section of the embankment, and initial filling will characteristics; however, it is often helpful to compare data
also cause downstream seepage to develop. Consolidation from similar structures with similar foundation and abut-
of the embankment and the foundation is accompanied by ment conditions. The analyses and comparative data should
transverse and longitudinal movements that may result in be used to establish the benchmark norms; however, the
transverse and longitudinal cracks. The predicted amounts inspectors, instmmentation personnel, and evaluators
of consolidation, movement, and seepage should be deter- should always be on the alert, even before the benchmark
mined by analyses during the design stage. These analyses norrns are reached, for adverse trends in data plots, cracks,
should be reviewed at the end of construction, and modi- seepage concentrations, boils, evidence of piping, sink-
fied if the as-constructed engineering characteristics are dif- holes, and other signs of distress.
ferent from those assumed during design. For instance,

354
EARTHFILL OAM PERFORMANCE ANO BEMEOIAL MEASURES 355

INITIAL FILLING
Clauoe A. Ferzen

Preparation vulnerable locations for potential distress should be pointed


out. Individual members of the inspection team should be
The initial filling represents a critical testing of the em- thoroughly oriented on the importance of their observa-
bankment. The preparation for the initial filling should in- tions, which may indicate distress not detected by the in-
clude a review of: the design reports, the construction rec- strumentation.
ords, the operations manual, and the instrumentation data
obtained during construction and during the intermediate
lnstrumentation Data
time since the embankment was completed.
Particular emphasis should be given to data obtained The validity of the instrumentation data should be checked
during temporary impoundments or longer-term lower im- constantly. Instrumentation readers should take a check
poundments. All springs and weeps that existed before the reading anytime there is significant divergence from the
dam was constructed and that developed during any im- previous reading. When significant movements are indi-
poundments should be located on the ground, numbered, cated since the last inclinometer reading, the accuracy of
and plotted on large-scale maps; the discharges should be the readout device should be verified in the check inclino-
measured and plotted against pool elevations and rainfall. meter, and additional inclinometer readings should be ob-
Adequate staffing should be arranged for inspection of tained. Alignment and settlement data from surveys are es-
the dam, for reading the instruments, and for plotting the pecially subject to elrors' particularly on long
data. To conserve manpower on large projects, the instru- embankments. Site observations are helpful in evaluating
mentation data should be transmitted to computers with data. For instance, if the alignment survey data indicate a
plotting printout capability at the job site. Lighting should spread of 0.5 ft (15 cm) between the upstream and down-
be set up for that portion of the dam and downstream area stream crest monuments, there should be a wide crack in
that is to be monitored on a 24-hour basis. A spare set of the crest. Cross checks should also be made between in-
instrumentation readout devices should be purchased and clinometer data and surveY data.
site-tested, as critical data could be lost through failure of The schedule for obtaining instrumentation data and for
a readout device during the monitoring program. A check site observations should be based on site conditions and the
inclinometer should be installed in stable ground on the filling schedule. For most projects, a reasonable schedule
abutment (preferably in bedrock), and the accuracy of the may initially require: daily readings on all piezometers, re-
readout device should be verified by taking readings in the lief-well discharges, and spring discharges; twice-daily
check inclinometer each time readings are scheduled for walk-over inspections of the embankment and downstream
the site inclinometers. area; weekly readings on inclinometers and extensometers;
and monthly surveys of alignment and settlement monu-
ments. As the filling continues' the monitoring schedule
On-Site lnspection
should be revised to meet the needs of the evaluators. On
The inspection force should include lead personnel who rapid-filling projects, such as pumped storage' the instru-
have a thorough understanding of the embankment design mentation readings must be obtained at a much morc fre-
and construction. The lead personnel should hold training quent rate.
sessions for the entire force to explain: the design of the
embankment, the operations manual, the locations and pur- Evaluation
poses of the instruments, the monitoring Program, the per-
formance of the embankment to date, and the duties and Evaluation of the data should be made daily. Abnormal
schedules of each inspector. data should not be discarded until they are proven to be
Personnel should be taken into the field and shown each erroneous. The data evaluation must give due considera-
instrument and each monitoring point. The operation of all tion to the geological site condltions and the embankment
measurement and recording devices should be explained, design; and, in this context, the data should be projected
and each instrumentation reader should make trial runs with to determine the ultimate condition or worst{ase condi-
the measurement and recording devices. The embankment tion. For instance, a rise in the downstrcam valley-bottom
and downstream area shoutd be inspected by the entire piezometers at various intermediate pool levels should be
party, and current defects such as cracks, depressions, and projected to the scheduled operation pool levels to deter-
so on, should be noted and photographed. Possible signs mine whether excessive uplift would exist at those levels.
of distress should be thoroughly explained, and the most Further projections of the piezometric levels should be
356 ADVANCED DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILITATION

made to the maximum flood-pool level for the same pur- the seepage, and it may be advisable temporarily to lower
pose. Projections of the data in this manner will indicate the pool while investigations are made to determine the
whether or not the filling should be stopped at some inter- cause of the increases. The evaluators should have full au-
mediate level until remedial action, such as installation of thority to intemrpt the filling schedule ro make investiga-
relief wells or drains, is accomplished. During the filling tions or to do remedial work, as the basic purpose of the
operation, sudden increases may occur in the piezometric monitoring program is to ensure the safety of the dam, and
levels, in the seepage flows or in the sediment content of not to meet a predetermined filling schedule.

LONG.TERM MONITORTNG
Cleuoe A. Ferzen

Ifno incidents have occurred during the initial filling, there been shut down, and the cloudy seepage was observed dis-
is a tendency to downgrade or de-emphasize. long-term charging into the shallow tailwater from joints in the lime-
monitoring. However, as long as water is impounded in the stone bedrock.
reservoir, the potential exists for incidents to occur from Piezometers cannnot detect the grain-by-grain removal
slope failures due to saturation and/or drawdown, under- that leads to underground piping. In many cases, the first
mining or piping failure from long-terrn seepage, and so knowledge that a hole has eroded beneath or through an
on. Hence, it is necessary to establish a long-term moni- earth dam occurs when a sediment-laden spring erupts
toring program to ensure the safety of the dam. downstream. The sooner the spring is discovered, the
sooner it is that action can be taken to save the dam. It is
Value of Continued On-Site Monitoring impossible to observe a dam for 24 hours each day on a
long-term basis, but the chances ofobserving distress signs
The powerplant, the outlet-works gates, and the spillway in time to take corrective action are greatly increased if
gates at many dams are operated remotely from some other observations are made daily rather than weekly or monthly
central station; and it is possible to collect instrumentation when piezometers are read. All site personnel including
data electronically and transmit the information to a central grounds keepers should be trained to look for distress signs
computer without having anyone at the site. However, therc and to report such signs promptly to appropriate authori-
is no substitute for on-site monitoring to ensure the safety ties. The better trained observers are, the more likely it is
of a dam. Even monitoring with a television camera is not that distress signs will be observed.
considered an adequate substitute for on-site inspections.
In practice, the dams at dry flood-control reservoirs only
Monitoring and Evaluation
require periodic walk-over inspections except during stor-
age periods; however, for storage reservoin, frequent in- The training of personnel, detection of criticat factors, va-
spections of the dam, abutments, and downstream area are Iidity of instrumentation readings, and evaluation of data
advisable. In many cases, on-site personnel have alerted were covered above under "Initial Filling." Continued
authorities to problems that could not have been detected timely evaluation of the instrumentation data is mandatory;
by instrumentation. For example, the detrimental cloudy otherwise, the manpower and cost of collecting the data
seepage at Wolf Creek Dam,r which retains the largest- and maintaining the system are wasted. Collecting data and
capacity reservoir east of the Mississippi River in the filing them in a drawer may give a false sense of security
United States, was first observed by a powerplant operator to the owner, and to the downstream public, and may be
on a Sunday moming; the flow through the turbines had indefensible in a court of law after a failure.
EARTHFTLL OAM PERFORMANCE AND REMEDIAL MEASURES 357

REMEDIAL MEASURES
CLeuoe A. Fe'rzrn

Necessity for Timely Action through pervious'foundation materials with littlc or no sur-
face discharges. Seepage carrying fines from the embank-
The amount of movement and seepage that an embankment ment or foundation may continue for an extended period of
will tolerate without failure depends on a complex inter- time without any visible effects on the dam until sulficient
action of the site geology and the characteristics of the as- material is removed to permit formation of an upstream
constructed embankment. Embankments constructed of sinkhole. This sinkhole permits the reservoir to have free-
flexible materials and founded on soft sediments can sus- flow access under full reservoir head into the eroded pipe,
tain appreciably greater movements without failure than thus causing a dramatic increase in flow through the pipe
brittle embankments founded on rigid foundations. probably accompanied by development of a large down-
The critical factor is to determine whether the move- stream spring. The increased flow accelerates the removal
ments are normal movements or are on a continuing or ac- o[ material from the dam and foundation, and can result in
celerating path that could lead to failure. Once the move- a very rapid failure of the embankment, as happened at
ments pass a critical point, it may not be possible to stop Teton Dam.{
them because of the massiveness of the structure; hence, it The difficulty facing the monitoring staff is to detect det-
is imperative that timely efforts be made to reduce the driv- rimental seepage before it develops into a major irreversi-
ing force or provide additional support before the critical ble failure mode. Without any surface expression of a de-
point is reached. For example, if detrimental movement of veloping piping problem, the monitoring staff may assume
the upstream slope is being caused by drawdown of the that no problem exists. However, once impounded in the
reservoir, the drawdown should be stopped immediately, reservoir, water will forever seek out the easiest flow path
and an underwater free-draining berm should be placed at to the downstream area; and if there are any defects in the
the upstream toe to provide stability for the future draw- embankment or foundation, the water will find those de-
down. If movement of the downstream slope is being fects that afford the easiest seepage path to the lower ele-
caused by a high seepage line, the reservoir should be vation. Hence, the monitoring staff, in cooperation with
drawn down, if possible. and drains should be installed in the designers, should review the geological site conditions,
the fill to reduce uplift, and/or a free-draining stabilization the foundation treatment, the embankment design, and
berm should be provided for the downstream slope. Other construction records to determine whether conditions are
options include removal of a few feet from the embank- favorable for piping and detrimental seepage to occur. If
ment crest to reduce the driving force on the slide. conditions do favor piping, it should be assumed that pip-
With regard to seepage, earth embankments founded on ing is occurring until proved otherwise. To prove that pip-
well-graded pervious materials may experience considera- ing is not occurring, extensive investigations may be re-
ble underseepage without detrimental effects: whereas a quired, including but not limited to the follow'ing:
small amount of seepage carrying fines from a critical sec-
tion of the embankment or foundation can cause failure if l. Sediment and quantity measurements in all down-
quick action is not taken. Wolf Creek Damr was saved by stream springs, seepage flows, and flows in under-
an emergency foundation grouting program. Both Fonte- ground rock fissures.
nelle Dam2 and East Branch Dam3 were saved by emer- 2. Periodic walk-over and aerial surveys of the down-
gency drawdown of the reservoir. However, the erosion of stream area to determine if springs and wet areas are
material out of Teton Dama was so rapid, and the river increasing in size.
inflow was so large, that the reservoir could not have been 3. On-site inspections to determine if depressions or
drawn down to prevent failure. Although not all dams can sinkholes are developing.
be saved after detrimental seepage is detected, many dams 4. Equipotential plots of the piezometric data to deter-
can be saved by quick and appropriate action. rnine if relatively high piezometric hcads extend
downstream in any area, as this condition may indi-
cate an opcn passageway either through or beneath
Seepage Problems
the core trcnch.
Detecting and locating the path of detrimental scepage are 5. Devclopment of temperature-contour plots ftom
very difficult problems. Seepage occurs at all earth dams, tempcrature measurements in the piezomcters to de-
whether visible or not. At most dam sites it is difficult to temrine if the colder water frotn the deepest part of
collect and measure all the seepage, as much of it may be the reservoir is feeding any piezometers.
occurring underground through cavernous formations or 6. Dye and saline tests to check the path and velocity of
358 ADVANCED DAM ENGINEERTNG FOR DESIGN, CONSTRUCTTON, AND REHABILITATION

seepage flows from the reservoir to piezometers and 3. Cutoff wall through the embankment and the seepage
to downstream springs. strata, tied into a thick impervious stratum or into
7. Drilling in suspect areas to determine the presence of bedrock-
cavities or soft spots and to install additional piezo- 4. Cement or chemical grouting, depending on the size
meters. of void and type ,rf foundation material.
8. Partial removal of the embankment to locate a defect,
as was accomplished at one dam in the Conewango In many cases, reverse filters are used to fill in low-lying
Creek Watershed.5 areas where seepage occurs: and relief wells are used to
relieve the pressures at depth. For earth embankments
If it is determined that piping is occurring, the foregoing founded on deep pervious alluvial deposits, impoundment
procedures will help establish the most likely seepage path, of the reservoir often raises the downstream groundwater
which may deviously pass through various materials in the to the ground surface; this often causes concentrated seep-
embankment and foundation. The conditions will dictate age areas, particularly in the outlet-works discharge chan-
whether the reservoir needs to be drawn down to avoid an nel, which can be controlled by lining the bottom and chan-
emergency and/or to complete remedial action. If the nel side slopes with stone prc,tection underlain by properly
seepage path is through the foundation rock (valley bottom graded filters to prevent removal of fines from the foun-
or abutments), the following alternatives may be consid- dation. For bleeding abutments, horizontal drains may be
ered: used to collect the seepage back of the face.
Cutoff walls arc very expensive and are used only as a
l. Grouting-cement, chemical or asphalt. last resort. Steel sheetpile walls have been used as cutoff
2. Cutoff walls-concrete-element wall as installed in some dams; but if the piling is driven to a depth of more
at
Wolf Creek Damr or concrete-panel wall as installed than 20 ft (6.1 meters), or even less deep in highly com-
pacted materials, it is apt to be driven out of interlock and
at Walter F. George Dam.6
3. Removal of embankment and treatment of rock to thus would not be effective. Because of corrosion, sheet-
permanently plug the voids in the rock, as was done pile walls may not be permanent. A slurry-trench cutoff
for one dam in the Conewango Creek Watershed.s consisting of graded soil placed into a bentonitic-slurry-
filled trench is a possible solution, but extreme care is
needed to prevent pockets of slurry from being trapped in
Grouting may be only a temporary solution. The grout the backfill; furthermore, the portion of the slurry trench
fills only the existing voids in the rock fissures, and the that is located above the saturation line in the embankment
grout in many cases may be surrounded by soil or highly
may dry out and crack. Another altemative is to use a ce-
weathered rock, which could be susceptible to removal in
ment-bentonite slurry to support the trench walls and as
time by the seepage. Installation of a concrete cutoff wall
the permanent seepage barrier; however, after initial hard-
provides a nonerodible barrier through the weathered, cav-
ening the portion of the wall above the embankment satu-
emous, or open-jointed rock; this type of wall is consid-
ration line may dry out and crack, and would not provide
ered permanent. AII work through the embankment must
an impervious barrier for higher reservoir levels. A per-
be done with extreme care to prevent damage from exces-
manen[ type of wall would be a concrete wall as described
sive hydrostatic pressure that could cause splitting or lifting
for bedrock foundation-seepage problems.
of the embankment. The watchword is: "First, do no Where the seepage path passes through the embankment
harm."
and is not related to foundation conditions, the following
Removal of a section of the embankment and proper
alternatives may be considered:
treatment of the foundation have been used for seepage
problems at the aforementioned dam on Conewango Creek
Watershed and for the right abutment at Fontenelle Dam.?
l. Reverse filters on the downstream seepage area to
control piping temporarily until permanent repairs can
Where the seepage path passes through overburden be-
be made.
neath the embankment and is not related to bedrock defi-
2. Cutoff walls as described above for foundation-
ciencies, the following alternatives may be considered:
erburden seepage.
3. Cement or chemical grouting, depending on the size
l. Relief wells along the downstream toe to reduce the of the void and the type of embankment materials.
pressure and to collect the seepage in a controlled 4. Removal and replacement of the faulty embankment
manner. section after drawdown.
2. Reverse filters graded to prevenr piping and weighted 5. Reverse filter on downstream slope overlain by but-
to prevent heaving ofthe foundation. tress fill.
EARTHFILL OAM PERFORMANCE ANO REMEDIAL MEASURES 359

Cracking and Slides and determine whether these adverse factors could lead to
a failure of the embankment. As prcviously indicated,
Cracking sometimes occurs along the crest and along the timely action may be needed to Prevent failurc. Investiga-
slopes during initial filling. These cracks are usually caused tions that may be needed to evaluate these conditions in-
by adjustment of the embankment to the water load and to clude: daily measurements of the width and length of the
differential settlement of the embankment zones and/or cracks; measurement of joint movements in conduits pass-
foundation as the embankment becomes saturated. An ex- ing through or beneath the embankment; measurement of
cellent description of the cracks and analyses of their causes movements of bridges or other structures located on the
for a high earth and rockfill dam is presented in a paper by embankment; surveys of stakes on the embankment, abut-
Patrick on Round Butte Dam.8 Most cracks are longitudi- ments, and downstream area: frequent readings of the
nal, but transverse tension cracks often develop near the available inclinometers; and, where inclinometers are not
abutments as the higher valley section of the impervious available, quick installation of thin-walled rigid plastic pipe
core settles more than the abutment sections settle. Trans- in a drilled hole for probing with a straight rod to determine
verse cracks often occur across the crest where there is an the location of the slip plane. Plots of the measurement
abrupt change in the underlying abutment contact, that is' data versus other factors such as reservoir rise or fall and
where the descending slope abruptly changes from a gentle pertinent piezometric data are helpful in projecting the ul-
to a steep slope. Cracks, slides, and crest slumping may timate progression of the cracks. A graph of conduit move-
also be caused by earthquakes. As previously discussed, ments and height of fill versus time for West Branch Dame
cracks and slides may be caused in the upStream slope by is shown in Fig. ll-1.
reservoir drawdown and in the downstream slope by a high If it is determined that.the cracks are not indicative of
seepage line. Other possible causes of instability of the potential slides, action should be taken to obliterate or fill
downstream slope include excavations that remove toe sup- the cracks to prevent them from filling with water. For
port and excessive hydrostatic uplift in a critical foundation cracks that are only l0 to 12 ft (3 to 3.7 meten) deep'
layer. Cracks and slides in either slope can also be caused excavation can be made along the crack with a backhoe,
by excessive stress on a weak layer in the embankment or and the excavated material can be used to refill the trench
in the foundation. in a compacted state. Deep cracks can be filled with a high-
The evaluator must determine the cause of any observed fluid nonshrinkable grout, preferably a chemical grout that
cracks, or of movements detected by the instrumentation, remains somewhat flexible.

s
c '5
9
t
U
o o
c co
.9
o
,u, .\ | Stsolir
15-16
o
o
-+-Johl
E
F

U' /-lora s.paoriLn

Figure ll-1. West Bmnch Dam-conduit movements, Oct.22 to Nov.25' 196'{.


360 ADVANCED DAM ENGINEERING FOR OESIGN, CONSTRUCTION, AND REHABILITATION

If it is determined that the cracks do indicate potential d. Temporarily remove the embankmcnt crcst to a
slides, timely actions as previously described should be ini- point where the movement stops.
tiated immediately to reduce the driving force and/or to
provide additional support. [f th'e movement plane is in the
bedrock, in either the foundation or the abutments the fol-
Settlement
lowing remedial actions should be considered: The evaluator must determine whether large areas of set-
tlement are due to normal consolidation of the embankment
l. Vertical or angled relief drains into the foundation. and foundation, or the settlement is a forerunner of a deep-
2. Horizontal or slightly inclined drains into the dis- seated slide. Essentially the same investigations or checks
tressed abutments. should be made as previously discussed for cracks and
3. Berms to buttress the embankment or the abutment. slides. The rate of normal consolidation should decrease
4. Temporary removal of the embankment crest to a with time, whereas settlement due to shear displacement in
depth where the movement stops. the embankment or foundation may increase with time,
5. Removal of the embankment and the weak rock strata particularly if the causative loading is holding steady or is
and reconstruction of the embankment. increasing. Corrective measures may not be needed for set-
tlement due to normal consolidation unless the crest has to
If the movement plane is in an earth foundation or an be raised to maintain the required freeboard. However,
earth abutment, the following remedial acrions should be corrective measures for shear displacement would be in ac-
considered: cordance with those previously described for slides.
Small areas of settlement may result from many factors,
l. Installation of retief wells in the foundation, with including but not limited to: piping into cavernous rock;
pumping used on a temporary basis to increase their piping into improperly graded drainage layers; piping along
effectiveness. animal burrows; piping along tree roots or along rotted-out
2. Installation of horizontal drains in the abutment. tree roots; piping of dispersive clays into drainage layers;
3. Installation of stone columns in the foundation. piping of embankment materials into conduits; settlement
4. Electro-osmosis to reduce the pore pressures and in- of poorly compacted backfill along structures or abut-
crease strength. ments, possibly accompanied by piping into the voids cre-
5. Placement of berms to buttress the embankment or ated by the settlement; and localized zones of poor com-
the abutment. paction. The investigations needed to determine the cause
6. Temporary removal of the embankment crest to a of the local settlement would be based on an assessmenr of
depth where the movement stops. the site conditions; but they could include measurement of
7. Removal of the embankment and removal of the weak the rate of settlement, drilling of test holes to determine the
shallow strata, as planned for Carsington Dam.l0 relative density of the materials or to locate voids, drilling
Where the weak strata are too thick or too deep to be of large-diameter holes for visual inspection of the em-
removed, other alternatives may be used to strengthen bankment and foundation materials, dye tests in drill holes,
the base of the embankment, as described in the case and so forth.
history for Mohicanville Dike (below). The appropriate remedial measures would depend on the
causative conditions, and could range from excavation and
If the movement plane is in the earth embankment, the recompaction of a local area to removal of a substantial
following remedial actions should be considered: part of the embankment for proper foundation treatment or
replacement of faulty filters.
1. For a submerged upstream slope, a granular upstream
toe berm can be placed through the water. In an
CASE HISTORIES
emergency, a portion of the crest could be removed
temporarily.
2. For movement within the downstream section: Mohicanville Dike No. 2
a. For a high seepage line, install horizontal drains;
Cleuoe A. Frrzen
or for surface sloughing, install drainage trenches
backfi lled with free-draining material. The Huntington District of the U.S. Army Corps of Engi-
b. For a weak layer in the embankment, install sand neers used a layer of steel mesh at the base of N{ohicanville
drains or stone columns through the layer to pro- Dike No. 2 to provide the srrengrh needed to complete rhe
vide drainage and to accelerate consolidation. 24-ft (7.3-meter)-high dike. Construcrion of the original
c. Install a berm, preferably of free-draining mate- dike was halted in 1937 at a height of 8 ft (2.4 meters)
rial. after repeated failures occurred before the design height
EARTHFILL DAM PERFORMANCE AND REMEDIAL MEASURES 361

Er. 984

Steel Mesh
Impervloua FIII El. 960
zold Dtke rllt F
Membrane - -
F-Cutoff--__

\
)sott ctay < 60,
/
Figure I l-2. Ivlohicanville Dike No. 2-reconstructed section. After Frrnks.rl

could be achieved. Recent investigations and analyses in- thick membrane, was provided on the upstream side of the
dicated that the failures were primarily due to a weak foun- slurry trench to maintain the integrity of the cutoff for the
dation consisting of peat and soft clay.rr lSee the typical settlements and displacements expected during reconstruc-
section in Fig. ll-2.) tion of the dike. The 2.5-ft (0.76-meter)-wide by 30-ft
Because of real estate limitations at the site, sufficient (9.1-meter)-deep slurry trench was backfilled with soil ob-
width for adequate-stability berms could not be provided tained from the existing dike that had been mixed with ben-
to develop an end-of-construction factor of safety of 1.3. tonite.
Limit equilibrium stability analyses performed by Law En- The old existing dike was degraded to a point approxi-
gineering and Testing Company indicated rhat an addi- mately 2 ft (0.6 meter) above the surrounding ground, and
tional maximum force at the levee base of 30,000 lb the steel mesh was laid on the degraded surface. The steel
( 13,608 kg) per lineal foot (0.3 meter) of levee was re- mesh was 2 x 6-in. (5 x l5-cm) Dl2/D4.5, fabricated
quired to provide a factor of safety of 1.3. A finite-element in S-ft (2.4-meter)-wide rolls. The rolls were strai_ehtened
analysis was performed by Waterways Experiment Station at the job site and cut into 160-ft (48.8-meter) lengths, the
to determine the most appropriate reinforcing material and length needed to extend from the upstream toe to the down-
to develop instrumentation predictions for monitoring con- stream toe. The 2-in. (5-cm) spacing was laid perpendic-
struction. Steel wire mesh was chosen as the reinforcing ular to the dike axis along the direction of maximum stress,
material in preference to polyester filter cloths, fiberglass, with the wire having an area of 0. l2 in.z (0.77 cmr;. The
and Kevlar Geo-fabrics. Steel mesh was the only material 6-in. ( l5-cm) spacing was laid parallel to the axis and had
that would provide the needed strength in one layer. Ad- an area of 0.045 in.: 10.29 cm21. The foundation and the
ditionally, much smaller movements would occur within first overlying lift were treated with lime to reduce the risk
the embankment and foundation with steel mesh, compared of the wire's corroding. Long-term stability analyses in-
with using the other materials. dicated that the wire mesh would not be required for sta-
An upstream membrane-lined slurry trench was provided bility after ten years, when consolidation of the foundation
through the peat and into the soft clay to cut off foundation soils would have increased their shear strength sufficiently
seepage. A downstream horizontal drainage blanket was for stability.
provided with a collector pipe at the downstream toe to The cutoff trench was constructed in 1983. In 1984 the
intercept any seepage that bypassed the cutoff. The cutoff dike was degraded to El. 960 ft (292.6 meters), the wire
trench was considered necessary because of observed mesh was installed, and the dike was raised to a height of
seepage during the flood of 1969, when the reservoir was I I ft (3.35 meters). The dike was cornpleted between June
impounded against the dike to a depth of approximately 3 and September 1985. The embankment, foundation, and
ft (0.9 meter). Based on permeability data obtained in the wire mesh were extensively instrumented to measure hor-
peat at the centerline, the seepage should have been I izontal and vertical movemcnts, pore pressures. and stresses
gal./min. (0.06liters/sec); whereas rhe observed secpage within the steel wire mesh. The movemcnts were in good
was approximately 500 gal./min. (31.5 liters/sec). Most agreerncnt with thosc predicted from finite-element anal-
of the seepage was believed to have occurrcd through yses. The maxirnum stress recorded for the wire mesh was
cracks, fissures, or pervious zones in the peat and in the 34,200Ib ( 15,513 kg) per lineal floot (0.3 meter). By Feb-
embankment. These seepage paths may have been partly ruary 1986, all instrumentation d.lta had peaked, and their
caused by large displacements during the original dike con- values were decreasing. A construction and pedormance
struction. A high-density polyethylene, 100-mil (0.25-cm)- report will be issued by the Huntington District.
362 ADVANCEO DAM ENGINEERING FOR DESIGN, CONSTRUCTION, AND REHABILITATION

Logan Martin Dam pears to have been dominantly vertical with local widening
at more readily soluble beds. Solution effects extend to
WrLLrnu F. SwrcER depths of more than 400 ft (122 meters).
The dam was completed in 1964. lts plan is shown in
Logan Martin Dam is located on the Coosa River southeast Fig. I l-3. It includes a powerhouse on the right bank with
of Birmingham, Alabama. Before construction of the dam adjoining spillway. The right floodplain was removed to
the river was flowing across exposed bedrock at about El. construct these structures. An embankment section founded
395 ft (120.4 meters). It was bordered on the right by a on residuum adjoins the powerhouse on the west (right)
narrow floodplain that overlapped moderately rising cherty side. Extending east (left) from the spillway is an embank-
residuum developed by deep weathering of the underlying ment section constructed across the rest of the river chan-
dolomite. On the left of the river there was a broad flood- nel. This is approximately 600 ft ( 183 meters) long. This
plain about 900 ft (275 meters) wide, and then again cherty embankment continues across the floodplain and then on
residuum. These floodplain deposits are about 20 to 30 ft cherty residuum. The total length of the east embankment
(6.1 to 9.1 meters) thick and grade downward from silty is about 4650 ft ( 1417 meten). Typical cross sections of
clays at the surface to sand and gravel above the top of the embankments as built are shown in Fig. I l-3.
rock. A number of sinkholes were present in the flood- Shortly after the reservoir was filled, a number of springs
plains upstream of the dam site. The bedrock is nearly flat- and discharges in the river were noted downstream of the
lying dolomite of the Lower Knox Formation. It contains dam. In 1968 a sinkhole developed in the dam. It was lo-
some limestone, less than l0%, and minor impurities in- cated just downstream of the crest and about 400 ft ( 122
cluding chert, silt, and sand. There has been extensive so- meters) east of the end of the spillway. This sinkhole was
lution activity, which has developed along several joint sets treated by filling it with quarry-run stone. Through borings
and along steeply dipping minor faults. The upper portion around the chimney sink, sand was sluiced into voids in
of the rock is pinnacly, with many isolated blocks sur- the embankment. Discharge from a spring at the toe of the
rounded by residuum and alluvial deposits. Solution ap- dam and opposite the sinkhole, over a period of time, had

Oct c r ual CoxsrRucrroto


- --Mo o r Fl cA Tro N 117 8'71
A Comcecreo Lneert CuaY
BFr-ooo Puarn DePosrrs
C QuaqRv Rurt Rocrc
D Peocr,ssep l?ocr<

\-a,

EF
'FF

Be o Rocx -Srcrrox A-A


@
Sca ue Fec r
VrB,r c s g6'
-ri-;-
---_/ -'1

Aecrrox B-R

Figure I l-3. Logan Martin Dam-plan and sections.

You might also like