You are on page 1of 190

SCC800-S1 SmartSite Management System

V100R003C10

Installation Guide

Issue 01
Date 2020-08-20

HUAWEI TECHNOLOGIES CO., LTD.


Copyright © Huawei Technologies Co., Ltd. 2020. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions

and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.

The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China

Website: https://e.huawei.com

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. i


SCC800-S1 SmartSite Management System
Installation Guide About This Document

About This Document

Purpose
This document describes the SmartSite management system in terms of its
components, installation, and commissioning.
Figures provided in this document are for reference only.

Intended Audience
This document is intended for:
● Technical support engineers
● Installation and commissioning engineers

Symbol Conventions
The symbols that may be found in this document are defined as follows.

Symbol Description

Indicates a hazard with a high level of risk which, if not


avoided, will result in death or serious injury.

Indicates a hazard with a medium level of risk which, if not


avoided, could result in death or serious injury.

Indicates a hazard with a low level of risk which, if not


avoided, could result in minor or moderate injury.

Indicates a potentially hazardous situation which, if not


avoided, could result in equipment damage, data loss,
performance deterioration, or unanticipated results.
NOTICE is used to address practices not related to personal
injury.

Supplements the important information in the main text.


NOTE is used to address information not related to personal
injury, equipment damage, and environment deterioration.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. ii


SCC800-S1 SmartSite Management System
Installation Guide About This Document

Change History
Changes between document issues are cumulative. The latest document issue
contains all updates made in previous issues.

Issue 01 (2020-08-20)
This issue is the first official release.
Monitoring unit software version: SCC800_S V100R003C00

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. iii


SCC800-S1 SmartSite Management System
Installation Guide Contents

Contents

About This Document................................................................................................................ ii


1 Safety Precautions...................................................................................................................1
1.1 General Safety.......................................................................................................................................................................... 1
1.2 Personnel Requirements....................................................................................................................................................... 5
1.3 Electrical Safety........................................................................................................................................................................ 6
1.4 Installation Environment Requirements.......................................................................................................................... 7
1.5 Mechanical Safety................................................................................................................................................................... 9
1.6 Battery Safety......................................................................................................................................................................... 11

2 Product Introduction............................................................................................................ 15
3 Preparing for the Installation.............................................................................................20
3.1 Tools.......................................................................................................................................................................................... 20
3.2 Wiring Description................................................................................................................................................................ 21
3.3 Cable Preparation................................................................................................................................................................. 22
3.4 Component Layout............................................................................................................................................................... 24

4 Component Installation....................................................................................................... 26
4.1 Installing an SCC800-S1..................................................................................................................................................... 26
4.1.1 Wall-Mounted Installation............................................................................................................................................. 26
4.1.2 Rack-Mounted Installation............................................................................................................................................. 30
4.1.3 Installing Power Cables................................................................................................................................................... 31
4.1.4 Installing an Antenna Tray............................................................................................................................................. 32
4.1.5 Installing Antennas........................................................................................................................................................... 34
4.1.6 Installing Network Management Cables (IP Networking)................................................................................. 37
4.1.7 Installing Network Management Cables (In-Band Networking)......................................................................37
4.1.8 Installing Network Management Cables (4G Networking)................................................................................37
4.1.9 Installing Communications Cables for Third-Party Smart Devices...................................................................40
4.2 Installing an Outdoor Wireless AC Meter Box ACMB...............................................................................................41
4.2.1 Securing an Outdoor Wireless AC Meter Box.......................................................................................................... 41
4.2.2 Installing AC detection cables....................................................................................................................................... 46
4.2.2.1 Single-Phase Scenario.................................................................................................................................................. 47
4.2.2.2 Dual-Live Wire Scenario.............................................................................................................................................. 48
4.2.2.3 Three-Live Wire Scenario.............................................................................................................................................49
4.2.2.4 Three-Phase Four-Wire Scenario...............................................................................................................................50

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. iv


SCC800-S1 SmartSite Management System
Installation Guide Contents

4.3 Installing an Indoor Wireless AC Meter Box ACMB.................................................................................................. 50


4.3.1 Securing an Indoor Wireless AC Meter Box..............................................................................................................50
4.3.2 Installing AC Detection Cables......................................................................................................................................55
4.3.2.1 Single-Phase Scenario.................................................................................................................................................. 56
4.3.2.2 Dual-Live Wire Scenario.............................................................................................................................................. 57
4.3.2.3 Three-Live Wire Scenario.............................................................................................................................................58
4.3.2.4 Three-Phase Four-Wire Scenario...............................................................................................................................59
4.4 Installing a Wireless AC Power Failure Sensor iACSENSE....................................................................................... 60
4.4.1 Securing a Wireless AC Power Failure Sensor......................................................................................................... 60
4.4.2 Installing a Dual-Mode Antenna..................................................................................................................................63
4.4.3 Installing Power Failure Detection Cables................................................................................................................ 64
4.5 Installing a Wireless DC Meter iDCMETER...................................................................................................................66
4.5.1 Installing the Dual-mode Antenna..............................................................................................................................67
4.5.2 Installing Detection Cables............................................................................................................................................ 68
4.6 Installing a Wireless Data Converter iDATA................................................................................................................ 69
4.6.1 Securing the iDATA........................................................................................................................................................... 69
4.6.2 Installing Antenna............................................................................................................................................................. 70
4.6.3 Installing the Power Cable............................................................................................................................................. 71
4.6.4 Installing a Communications Cable (RS232)........................................................................................................... 73
4.6.5 Installing the Communications Cable (RS485)....................................................................................................... 73
4.7 Installing an Wireless DG Monitoring Box iDG.......................................................................................................... 73
4.7.1 Securing an Wireless DG Monitoring Box................................................................................................................. 73
4.7.2 Installing Antenna............................................................................................................................................................. 76
4.7.3 Installing the Power Cable............................................................................................................................................. 78
4.7.4 Installing a DG Reset Cable........................................................................................................................................... 79
4.7.5 Installing a DG Fault Alarm Cable............................................................................................................................... 79
4.7.6 Installing Cables for Controlling DG Startup and Shutdown............................................................................. 79
4.8 Installing a Wireless Fuel Level Sensor iFUEL............................................................................................................. 80
4.8.1 Installing a Wireless Magnetostrictive Fuel Level Sensor....................................................................................80
4.8.2 Installing a Wireless Submersible Fuel Level Sensor (on the Fuel Tank).......................................................83
4.8.3 Installing a Wireless Submersible Fuel Level Sensor (Through the Air Hole)..............................................89
4.9 Installing an Indoor Camera............................................................................................................................................. 90
4.10 Installing an Outdoor Camera....................................................................................................................................... 95
4.11 Installing an Equipment Room Door Lock iACCESS............................................................................................... 99
4.12 Installing an Outdoor Cabinet Door Lock iACCESS.............................................................................................. 113
4.13 Installing an Outdoor Fence Door Lock iACCESS..................................................................................................114
4.14 Installing a Cabinet Electronic Lock Cylinder iACCESS........................................................................................114
4.15 Installing a Wireless Temperature and Humidity Sensor iTEMP..................................................................... 116
4.16 Installing a Wireless Motion Detector iMOTION.................................................................................................. 119
4.17 Installing a Wireless Smoke Sensor iSMOKE.......................................................................................................... 123
4.18 Installing a Wireless Water Sensor iWATER........................................................................................................... 128
4.19 Installing a Wireless Door Status Sensor iDOOR.................................................................................................. 132

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. v


SCC800-S1 SmartSite Management System
Installation Guide Contents

4.20 Installing an Audible and Visual Alarm.................................................................................................................... 136

5 Commissioning.....................................................................................................................139
5.1 Power-On Commissioning............................................................................................................................................... 139
5.2 Logging In to the WebUI................................................................................................................................................. 139
5.3 Wireless Component Networking................................................................................................................................. 140
5.4 Setting Deployment Wizard Parameters.................................................................................................................... 142
5.5 Setting Camera Passwords.............................................................................................................................................. 149
5.6 Setting Motion Detection Alarm Parameters for Outdoor Cameras................................................................ 151
5.7 Setting Access Control Management Parameters................................................................................................... 156
5.7.1 Creating Users.................................................................................................................................................................. 156
5.7.2 Enabling a Mobile Phone to Log In to the NetEco APP.................................................................................... 160
5.7.3 Modifying the Equipment Room Door Lock Password...................................................................................... 162
5.7.4 Configuring an Outdoor Cabinet or Fence Door Lock....................................................................................... 164
5.7.5 Application (NetEco WebUI)....................................................................................................................................... 167
5.7.6 Application (NetEco APP)............................................................................................................................................ 169
5.7.7 Unlocking (Equipment Room Door Lock).............................................................................................................. 169
5.7.8 Unlocking (Outdoor Cabinet or Fence Door Lock)............................................................................................. 171
5.8 Setting NAT Gateway Parameters................................................................................................................................ 173

A FAQ......................................................................................................................................... 174
A.1 How Do I Prepare RS485 Conversion Cables?..........................................................................................................174
A.2 What Do I Do If WebUI Login on a PC Fails?...........................................................................................................175
A.3 How Do I Upgrade Software for SCC800?.................................................................................................................179
A.4 How Do I Install the Protocol Package for Intelligent Equipment?..................................................................180
A.5 What Do I Do If the DC Power System Cannot Connect to the SCC800?...................................................... 181
A.6 What Do I Do If the iACMETER Reports a Wiring Error Alarm?........................................................................181
A.7 What Do I Do If Electricity Data Reported by the iACMETER Is Erroneous?.................................................182
A.8 What Do I Do If the Wireless Communication Signal of the iFUEL Is Poor?................................................ 182

B Acronyms and Abbreviations........................................................................................... 183

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. vi


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

1 Safety Precautions

1.1 General Safety


Statement
Before installing, operating, and maintaining the equipment, read this document
and observe all the safety instructions on the equipment and in this document.
The "NOTICE", "CAUTION", "WARNING", and "DANGER" statements in this
document do not cover all the safety instructions. They are only supplements to
the safety instructions. Huawei will not be liable for any consequence caused by
the violation of general safety requirements or design, production, and usage
safety standards.
Ensure that the equipment is used in environments that meet its design
specifications. Otherwise, the equipment may become faulty, and the resulting
equipment malfunction, component damage, personal injuries, or property
damage are not covered under the warranty.
Follow local laws and regulations when installing, operating, or maintaining the
equipment. The safety instructions in this document are only supplements to local
laws and regulations.
Huawei will not be liable for any consequences of the following circumstances:
● Operation beyond the conditions specified in this document
● Installation or use in environments which are not specified in relevant
international or national standards
● Unauthorized modifications to the product or software code or removal of the
product
● Failure to follow the operation instructions and safety precautions on the
product and in this document
● Equipment damage due to force majeure, such as earthquakes, fire, and
storms
● Damage caused during transportation by the customer
● Storage conditions that do not meet the requirements specified in this
document

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 1


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

General Requirements
● Before installing, operating, or maintaining the equipment, remove any
conductive objects such as watches or metal jewelry like bracelets, bangles,
and rings to avoid electric shock.
● When installing, operating, or maintaining the equipment, wear dedicated
protective gears such as insulation gloves, goggles, and safety clothing,
helmet, and shoes, as shown in the following figure.

● Use insulated tools or tools with insulated handles, as shown in the following
figure.

● Follow the specified procedures for installation, operation, and maintenance.


● Ensure that bolts are tightened with a torque wrench and marked using red or
blue color. Installation personnel mark tightened bolts in blue. Quality
inspection personnel confirm if the bolts are tightened and then mark them in
red. (The marks should cross the edges of the bolts, as shown in the following
figure.)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 2


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

● Before installing, operating, or maintaining a cabinet, clean up any water, ice,


snow, or other sundries on the top of the cabinet to prevent sundries from
falling into the cabinet when you open the cabinet door.
● Do not install, use, or operate outdoor equipment and cables (including but
not limited to moving equipment, operating equipment and cables, inserting
connectors to or removing connectors from signal ports connected to outdoor
facilities, working at heights, and performing outdoor installation) in harsh
weather conditions such as lightning, rain, snow, and level 6 or stronger wind.
● Before handling a conductor surface or terminal, measure the contact point
voltage and ensure that there is no risk of electric shock.
● Ensure that all slots are installed with boards or filler panels. Avoid hazards
caused by hazardous voltages or energy on boards. Ensure that the air
channel is normal, control electromagnetic interference, and prevent dust and
other sundries on the backplane, baseplate, and boards.
● After installing the equipment, remove idle packing materials such as cartons,
foam, plastics, and cable ties from the equipment area.
● In the case of a fire, immediately leave the building or the equipment area,
and turn on the fire alarm bell or make an emergency call. Do not enter the
building on fire in any case.
● Do not stop using protective devices. Pay attention to the warnings, cautions,
and related precautionary measures in this document and on the equipment.
Promptly replace warning labels that have worn out.
● Keep irrelevant people away from the equipment. Only operators are allowed
to access the equipment.
● All cable holes should be sealed. Seal the used cable holes with firestop putty.
Seal the unused cable holes with the caps delivered with the cabinet. The
following figure shows the criteria for correct sealing with firestop putty.

● Do not use water, alcohol, oil, or other solvents to clean electrical components
inside and outside a cabinet.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 3


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

Personal Safety
● If there is a probability of personal injury or equipment damage during
operations on the equipment, immediately stop the operations, report the
case to the supervisor, and take feasible protective measures.
● To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits
to telecommunication network voltage (TNV) circuits.
● Do not power on the equipment before it is installed or confirmed by
professionals.

Symbol Conventions
To ensure personal and equipment safety, observe all the safety instructions
marked on the equipment when installing, operating, and maintaining the
equipment.

Symbol Description

Indicates a part exposed to high voltage. This symbol


warns operators that both direct and indirect contact with
the power grid is fatal. Such areas include hazardous
voltage points or protective power supply covers that may
be removed during maintenance.

Warns users of overheating. This symbol is attached to a


device surface that may overheat and cause scalding. It
warns users not to touch the surface during operations or
maintenance. Users should wear heat insulation gloves
before operations to prevent scalding.

Indicates protection earthing. This symbol is attached next


or to a protection ground terminal next to grounded
equipment and an external ground system. An equipment
ground cable is connected to an external ground bar
through the protection ground terminal.

Indicates equipotential bonding. This symbol is found with


equipotential terminals inside equipment.

Indicates electrostatic discharge (ESD). This symbol is used


in all electrostatic sensitive areas. Before operating
equipment in these areas, wear ESD gloves or an ESD
wrist strap.

Indicates that the equipment is safe to use at altitudes


below 2000 m (6561.6 ft.).

Indicates that the equipment is not safe to use in tropical


climates.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 4


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

Symbol Description

Indicates a fan assembly or moving part. This symbol is


silkscreened on or attached to the panel of a fan
or assembly, warning operators to keep away. Do not touch
the blades when the fan is rotating.

Indicates that users should refer to the instruction. This


symbol is used when the usage of a device port cannot be
or clearly described. For example, this symbol can be used in
but not limited to the following scenarios:
1. For a multi-power device, use it near the power supply
to replace the multi-power supply identifier. The
symbol indicates that the device has multiple power
inputs. Therefore, when powering off the device, you
must disconnect all power inputs.
or
2. If there are multiple output ports, use the symbol near
the output ports. Connect cables according to the rated
power output and configuration parameter information
in the instruction.
3. If there are multiple slots, use the symbol near the slot
information. For details, see the description of slot
information, restrictions on boards, and usage
conditions in the instruction.

1.2 Personnel Requirements


● Personnel who plan to install or maintain Huawei equipment must receive
thorough training, understand all necessary safety precautions, and be able to
correctly perform all operations.
● Only qualified professionals or trained personnel are allowed to install,
operate, and maintain the equipment.
● Only qualified professionals are allowed to remove safety facilities and inspect
the equipment.
● Personnel who will operate the equipment, including operators, trained
personnel, and professionals, should possess the local national required
qualifications in special operations such as high-voltage operations, working
at heights, and operations of special equipment.
NOTE

● Professionals: personnel who are trained or experienced in equipment operations and


are clear of the sources and degree of various potential hazards in equipment
installation, operation, and maintenance
● Trained personnel: personnel who are technically trained, have required experience, are
aware of possible hazards on themselves in certain operations, and are able to take
protective measures to minimize the hazards on themselves and other people
● Operators: operation personnel who may come in contact with the equipment, except
trained personnel and professionals

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 5


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

1.3 Electrical Safety


Grounding
● The protective ground of the equipment should be reliably connected to the
ground screw on the metal enclosure (grounding resistance ≤ 0.1 ohm).
● For the equipment that needs to be grounded, install the ground cable first
when installing the equipment and remove the ground cable last when
removing the equipment.
● Do not damage the ground conductor.
● Do not operate the equipment in the absence of a properly installed ground
conductor.
● For the equipment that uses a three-pin socket, ensure that the ground
terminal in the socket is connected to the protection ground.

AC and DC Power

DANGER

● The power system is energized by power sources with hazardous voltage. Direct
or indirect contact (through damp objects) with the power sources may result
in electric shock.
● Non-standard and improper operations may result in fire or electric shock.
● Do not connect or disconnect power cables with power on. Transient contact
between the core of the power cable and the conductor will generate electric
arcs or sparks, which may cause fire or personal injury.

● If the power supply to the equipment is permanently connected, install an


easily accessible disconnector at the exterior of the device.
● Before making electrical connections, switch off the disconnector on the
upstream device to cut off the power supply if people may contact energized
components.
● If a "high electricity leakage" tag is attached on the equipment, ground the
protective ground terminal on the equipment enclosure before connecting the
AC power supply; otherwise, electric shock as a result of electricity leakage
may occur.
● Before installing or removing a power cable, turn off the power switch.
● Before connecting a power cable, check that the label on the power cable is
correct.
● Before connecting the power supply, ensure that cable connections are
correct.
● If the equipment has multiple inputs, disconnect all the inputs before
operating the equipment.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 6


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

Cabling
● When routing cables, ensure that a distance of at least 30 mm exists between
the cables and heat-generating components or areas. This prevents damage
to the insulation layer of the cables.
● Do not route cables behind the air intake and exhaust vents of the
equipment.
● Ensure that cables meet the VW-1 flame spread rating requirements.
● Bind cables of the same type together. When routing cables of different types,
ensure that they are at least 30 mm away from each other.
● Ensure that all cables are securely bound. Route and bind cables so that they
appear neat and tidy and their cable sheaths are intact.
● If an AC input power cable is connected to the cabinet from the top, bend the
cable in a U shape outside the cabinet and then route it into the cabinet.
● Ensure that the bending radius of each cable is at least five times the
diameter of the cable.
● When routing power cables, ensure that there is no coiling or twisting. Do not
join or weld power cables. If necessary, use a longer cable.

ESD
● When installing, operating, and maintaining the equipment, comply with the
ESD protection regulations and wear the ESD clothing, gloves, and wrist strap.
● When holding a board, hold its edge without touching any components. Do
not touch the components with your bare hands.
● Package boards with ESD packaging materials before storing or transporting
them.

1.4 Installation Environment Requirements


● To prevent fire due to high temperature, ensure that the ventilation vents or
heat dissipation system are not blocked when the equipment is running.
● Ensure that there are no acid, alkaline, or other corrosive gases in the
installation place.
● Do not place the equipment near heat sources or exposed fire sources, such
as electric heaters, microwave ovens, roasters, water heaters, furnace fire,
candles, or other places where high temperature may occur. Otherwise, the
enclosure will melt or the equipment will heat up, which can cause a fire.
● Install the equipment in an area far away from liquids. Do not install it under
areas prone to condensation, such as under water pipes and air exhaust vents,
or areas prone to water leakage, such as air conditioner vents, ventilation
vents, or feeder windows of the equipment room. Ensure that no liquid enters
the equipment to prevent faults or short circuits.
● Before installing the equipment into a cabinet, ensure that the cabinet is
secured and will not tilt or fall down due to loss of balance, which can cause
personal injury or equipment damage.
● Do not expose the equipment to flammable or explosive gas or smoke. Do
not perform any operation on the equipment in such environments.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 7


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

Installation at Heights
Working at heights refers to operations that are performed at least 2 meters
above the ground.

Do not at heights in any of the following situations:

● Rainwater remains on steel pipes or other risky conditions exist. After the
preceding conditions no longer exist, the safety director and relevant technical
personnel need to check the involved equipment. Operators can begin
working only after obtaining consent.
● When working at heights, comply with local relevant laws and regulations.
● Only trained and qualified personnel are allowed to work at heights.
● Before working at heights, check the climbing tools and safety gears such as
safety helmets, safety belts, ladders, springboards, scaffolding, and lifting
equipment. If they do not meet the requirements, take corrective measures or
disallow working at heights.
● Wear personal protective equipment such as the safety helmet and safety belt
or waist rope and fasten it to a solid structure. Do not mount it on an
insecure moveable object or metal object with sharp edges. Make sure that
the hooks will not slide off.

DANGER

● Set a restricted area and eye-catching signs for working at heights to warn
away irrelevant personnel.
● Carry the operation machinery and tools properly to prevent them from falling
off and causing injuries.
● Personnel involving working at heights are not allowed to throw objects from
the height to the ground, or vice versa. Objects should be transported by tough
slings, hanging baskets, highline trolleys, or cranes.
● Do not perform operations on the upper and lower layers at the same time. If
unavoidable, install a dedicated protective shelter between the upper and lower
layers or take other protective measures. Do not pile up tools or materials on
the upper layer.
● Ensure that guard rails and warning signs are set at the edges and openings of
the area involving working at heights to prevent falls.
● Do not pile up scaffolding, springboards, or other sundries on the ground under
the area involving working at heights. Do not allow people to stay or pass
under the area involving working at heights.
● Inspect the scaffolding, springboards, and workbenches used for working at
heights in advance to ensure that their structures are solid and not overloaded.
● Dismantle the scaffolding from top down after finishing the job. Do not
dismantle the upper and lower layers at the same time. When removing a part,
ensure that other parts will not collapse.
● Do not loiter when working at heights. Do not sleep at heights.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 8


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

● Any violations must be promptly pointed out by the site manager or safety
supervisor and the involved personnel should be prompted for correction.
Personnel who fail to stop violations will be forbidden from working.
● Operators who violate the safety regulations are responsible for accidents
caused. The supervisor has to bear the responsibility accordingly.

1.5 Mechanical Safety


Hoisting Devices

DANGER

Do not walk under hoisted objects.

● Only trained and qualified personnel should perform hoisting operations.


● Check that hoisting tools are available and in good condition.
● Before hoisting objects, ensure that hoisting tools are firmly secured onto a
load-bearing object or wall.
● Ensure that the angle formed by two hoisting cables is no more than 90
degrees, as shown in the following figure.

● Do not drag steel ropes and hoisting tools or bump hoisted objects against
hard objects during hoisting.

Using Ladders
● Use wooden or fiberglass ladders when you need to perform live working at
heights.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 9


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

● When a step ladder is used, ensure that the pull ropes are secured and the
ladder is held firm.
● Before using a ladder, check that it is intact and confirm its load bearing
capacity. Do not overload it.
● Ensure that the wider end of the ladder is at the bottom, or protective
measures have been taken at the bottom to prevent the ladder from sliding.
● Ensure that the ladder is securely positioned. The recommended angle for a
ladder against the floor is 75 degrees, as shown in the following figure. An
angle rule can be used to measure the angle.

When climbing a ladder, take the following precautions to reduce risks and ensure
safety:

● Keep your body steady.


● Do not climb higher than the fourth rung of the ladder from the top.
● To climb onto a roof, ensure that the ladder top is at least one meter higher
than the roof line, as shown in the following figure.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 10


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

● Ensure that your body's center of gravity does not shift outside the legs of the
ladder.

Drilling Holes
When drilling holes into a wall or floor, observe the following safety precautions:

NOTICE

Do not drill holes into the equipment. Doing so may affect the electromagnetic
shielding of the equipment and damage components or cables inside. Metal
shavings from drilling may short-circuit boards inside the equipment.

● Wear goggles and protective gloves when drilling holes.


● When drilling holes, protect the equipment from shavings. After drilling, clean
up any shavings that have accumulated inside or outside the equipment.

Moving Heavy Objects


● Be cautious to avoid injury when moving heavy objects.

● When moving the equipment by hand, wear protective gloves to prevent


injuries.
● Move or lift the equipment by holding its handles or lower edges. Do not hold
the handles of modules (such as power supply units, fans, and boards) that
are installed in the equipment because they cannot support the weight of the
equipment.

1.6 Battery Safety


If no battery is involved, skip this section.

Before installing, operating, or maintaining batteries, read the battery


manufacturer's instructions. The safety precautions specified in this document are
highly important precautions that require special attention. For additional safety
precautions, see the instructions provided by the battery manufacturer.

Basic Requirements
Before operating batteries, carefully read the safety precautions for battery
handling and master the correct battery connection methods.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 11


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

DANGER

● Do not expose batteries at high temperatures or around heat-generating


devices, such as sunlight, fire sources, transformers, and heaters. Excessive heat
exposure may cause the batteries to explode.
● Do not burn batteries. Otherwise, the batteries may explode.
● To avoid leakage, overheating, fire, or explosions, do not disassemble, alter, or
damage batteries, for example, insert sundries into batteries or immerse
batteries in water or other liquids.
● When replacing a battery, use a battery of the same model or type. Improper
replacement may cause the battery to explode.
● Do not connect a metal conductor to the battery poles or touch the battery
terminals. Otherwise, the battery may be short-circuited and heat up, which
can cause injuries such as burning.

To ensure safety during battery installation, operation, and maintenance, pay


attention to the following:

● Do not wear conductive articles such as watches, bracelets, bangles, and rings.
● Wear goggles, rubber gloves, and protective clothing to prevent skin contact
with electrolyte in the case of electrolyte overflow. If a battery leaks, protect
the skin or eyes from the leaking liquid. If the skin or eyes come in contact
with the leaking liquid, wash it immediately with clean water and go to the
hospital for medical treatment.
● Use dedicated insulated tools.
● Move batteries in the required direction. Do not place a battery upside down
or tilt it.
● Keep the battery loop disconnected during installation and maintenance.
● Do not drop, squeeze, or puncture a battery. Protect batteries from external
high pressure to prevent internal short circuits and overheating.
● Dispose of waste batteries in accordance with local laws and regulations. Do
not dispose of batteries as household waste. If a battery is disposed of
improperly, it may explode.
● Do not use a damaged battery.
● To prevent injuries or explosion, do not allow children or pets to swallow or
bite a battery.
● If batteries experience discoloration, deformation, abnormal heating, or other
abnormalities during working, charging, or storage, stop using the batteries
and replace them with new ones.
● Batteries can work properly with the allowed charge and discharge
parameters when the temperature is within the specified range. If the
temperature is outside the specified range, the battery charge and discharge
performance and safety are affected.

Battery Installation
Before installing batteries, observe the following safety precautions:

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 12


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

● Install batteries in a dry and cool environment with good ventilation, which is
away from high temperature and flammable materials, and take precautions
against fire.
● Place and secure batteries horizontally.
● Note the polarities when installing batteries. Do not short-circuit the positive
and negative poles of the same battery or battery string. Otherwise, the
battery may be short-circuited.
● When installing a battery string, retain at least one breakpoint to prevent a
loop being formed. After checking that the installation is correct, close the
breakpoints to finish the installation.
● During the installation, insulate the terminals of cables connecting batteries.
Ensure that the terminals do not come into contact with metal components
such as the cabinet.
● Secure battery cables or copper bars by tightening bolts to the required
torque. Loose connections will result in excessive voltage drop or cause
batteries to burn out in the case of excessive current.
● Check battery connections periodically, ensuring that all bolts are securely
tightened.

Battery Short Circuit

DANGER

Battery short circuits can generate high instantaneous current and release a great
amount of energy, which may cause equipment damage or personal injury.

● If permitted, disconnect the batteries in use before performing any other


operations.
● To avoid battery short-circuit, do not maintain batteries with power on.

Flammable Gas

NOTICE

● Do not use unsealed lead-acid batteries.


● To prevent fire or corrosion, ensure that flammable gas (such as hydrogen) is
properly exhausted for lead-acid batteries.

Lead-acid batteries emit flammable gas when used. Ensure that batteries are kept
in a well-ventilated area and take preventive measures against fire.

Battery Leakage

NOTICE

Battery overheating causes deformation, damage, and electrolyte spillage.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 13


SCC800-S1 SmartSite Management System
Installation Guide 1 Safety Precautions

If the battery temperature exceeds 60°C, check for and promptly handle any
leakage.
Electrolyte overflow may damage the equipment. It will corrode metal parts and
boards, and ultimately damage the boards.

WARNING

When the electrolyte overflows, absorb and neutralize the electrolyte immediately.
When moving or handling a battery whose electrolyte leaks, note that the leaking
electrolyte may hurt human bodies.

If the electrolyte overflows, follow the instructions of the battery manufacturer or


neutralize the electrolyte by using sodium bicarbonate (NaHCO3) or sodium
carbonate (Na2CO3).

Lithium Battery
The safety precautions for lithium batteries are similar to those for lead-acid
batteries except that you also need to note the precautions described in this
section.

WARNING

There is a risk of explosion if a battery is replaced with an incorrect model.

● A battery can be replaced only with a battery of the same or similar model
recommended by the manufacturer.
● When handling a lithium battery, do not place it upside down, tilt it, or bump
it with other objects.
● Keep the lithium battery loop disconnected during installation and
maintenance.
● When the ambient temperature is lower than the lower limit of the operating
temperature (charge is forbidden at 0°C), do not charge the battery.
Otherwise, a short circuit would occur inside the battery.
● Do not throw a lithium battery in fire.
● When maintenance is complete, return the waste lithium battery to the
maintenance office.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 14


SCC800-S1 SmartSite Management System
Installation Guide 2 Product Introduction

2 Product Introduction

Table 2-1 Product introduction


Appearance Name Function

Smart site Connects to power and environment


monitoring monitoring devices such as electricity meters,
unit SCC800- cameras, and sensors, and reports monitoring
S1 (SCC800 for data to the network management center in real
short) time.

4G antenna Transmits and receives wireless transmission


signals.

Dual-mode Transmits and receives wireless transmission


antenna signals.

Rod antenna Transmits and receives wireless transmission


signals.

Wireless AC Detects whether an AC power failure occurs.


Power Failure The sensor connects to the SCC800 in wireless
Sensor mode to report data in real time.
iACSENSE

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 15


SCC800-S1 SmartSite Management System
Installation Guide 2 Product Introduction

Appearance Name Function

iACMETER Detects AC electric energy.

Outdoor Integrates the iACMETER, AC current


Wireless AC transformer, and surge protective device (SPD).
Meter Box It is applied in an outdoor environment.
ACMB

Indoor Integrates the iACMETER, AC current


Wireless AC transformer, and SPD. It is applied in an indoor
Meter Box environment.
ACMB

Wireless DC Detects DC electric energy.


Meter
iDCMETER

Wireless data Detects smart devices and transmits device


converter data to the SCC800 in wireless mode to
iDATA monitor smart devices.

Wireless diesel Starts, stops, or resets a DG, receives DG fault


generator (DG) signals, and reports the DG status and fault
monitoring box information to the SCC800.
iDG Can connect to an audible and visual alarm.

Wireless Detects the fuel level in a fuel tank.


magnetostricti
ve fuel level
sensor iFUEL

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 16


SCC800-S1 SmartSite Management System
Installation Guide 2 Product Introduction

Appearance Name Function

Wireless Detects the fuel level in a fuel tank.


submersible
fuel level
sensor iFUEL

Indoor camera Shoots photos or videos indoors.

Outdoor Shoots photos or videos outdoors.


camera

Equipment Collects the equipment room door status and


room door lock controls the opening and closing of the door.
iACCESS

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 17


SCC800-S1 SmartSite Management System
Installation Guide 2 Product Introduction

Appearance Name Function

Reader Authenticates fingerprints and access cards.


iWRITER

Outdoor Intelligently controls the opening and closing of


cabinet door the door.
look iACCESS

Outdoor fence Intelligently controls the opening and closing of


door lock the door.
iACCESS

Bluetooth Controls an outdoor cabinet door lock or


electronic key outdoor fence door lock.

Wireless Measures the ambient temperature and


temperature humidity in real time.
and humidity
sensor iTEMP

Wireless Generates an alarm when detecting a moving


motion heat source.
detector
iMOTION

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 18


SCC800-S1 SmartSite Management System
Installation Guide 2 Product Introduction

Appearance Name Function

Wireless Detects smoke in real time.


smoke sensor
iSMOKE

Wireless water Monitors the site for water in real time.


sensor iWATER

Wireless door Detects the door open/close status in real time.


status sensor
iDOOR

Audible and Generates sounds and flashes when an infrared


visual alarm or door status sensor alarm is generated onsite.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 19


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

3 Preparing for the Installation

3.1 Tools

NOTICE

Use tools with insulated handles.

Table 3-1 Tools

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 20


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

3.2 Wiring Description


The system wiring description is for reference only. Connect cables only to
appropriate components based on the actual configuration solution.

NOTICE

● Use corrugated pipes or polyvinyl chloride (PVC) pipes for protection when
routing cables outdoors.
● If a cable is routed from outdoors to indoors, the cable hole should be sealed
with sealing putty.

Component Numbering
● If there are two or more components of the same type in the wiring diagram,
number the components before connecting cables. For example, you can
number components as DC power system 1 and DC power system 2.
● If N DC power systems are configured, determine the sequence numbers of
the DC power systems first. Ensure that the sequence numbers of the iDATA
and iDCMETER corresponding to a DC power system are the same as the
sequence number of the DC power system.
● If an outdoor ACMB and an indoor ACMB are installed at the site, set the
sequence number of the iACMETER in the outdoor ACMB to 1 and then
number the iACMETER in the indoor ACMB.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 21


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

Cable and Terminal Description


This section describes the mapping between cables and terminals in the wiring
diagrams. Some terminals may not match the onsite devices. Use cable terminals
based on site requirements.

Table 3-2 Cable and terminal description


No. Cable Type Cable Size (Single Core)

1-core cable 2.5 mm2

2-core cable 0.3 mm2

0.75 mm2

4-core cable 0.5 mm2

Network cable -

Yellow-green cable 6 mm2

2.5 mm2

Cable supplied with -


equipment

NOTE

A thicker cable can be used as a substitute during cable connection. For example, a 0.5
mm2 cable can be used as a substitute for a 0.3 mm2 cable.

3.3 Cable Preparation


Cable Overview

Table 3-3 Cable overview


Appearance Type Function

Two-core (black Used as signal cables and


and brown) cable 12 V power cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 22


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

Appearance Type Function

Two-core (blue and Used as 48 V power cables


brown) cable For example, install the
SCC800 power supply.

Four-core (yellow, Used as signal cables and


white, purple, and 12 V power cables
green) cable

Yellow-green cable Used as the ground cable

Network cable Used as communications


cables and 12 V power
cables

Preparation Details
Cut a cable of proper length and install an OT terminal or a cord end terminal.

It is recommended that a single-core cable (including power cables and signal


cables) be crimped with a single-wire cord end terminal.

Figure 3-1 Preparing a cord end terminal

(1) Cable (2) Cord end terminal (3) Crimping tool

Figure 3-2 Preparing an OT terminal

(1) Cable (2) OT terminal (3) Heat shrink tubing

(4) Hydraulic pliers (5) Heat gun

If a multi-wire cord end terminal is used for crimping, tighten the core wires and
then insert them into the terminal.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 23


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

Figure 3-3 Preparing a multi-wire cord end terminal

(1) Cable (2) Multi-wire cord end terminal (3) Crimping tool

When preparing a network cable, keep the connector fastener downwards and the
metal spring plate upwards. After preparing a straight-through network cable, test
it with a network cable tester. The following figure is for reference only. The actual
wire sequence and colors may be different.

Figure 3-4 Wire sequence of a straight-through network cable

3.4 Component Layout


Determine the installation positions for newly added devices based on the
installation positions of existing devices and the available space. The following
figures are for reference only.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 24


SCC800-S1 SmartSite Management System
Installation Guide 3 Preparing for the Installation

Figure 3-5 Recommended indoor site layout

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 25


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4 Component Installation

4.1 Installing an SCC800-S1

4.1.1 Wall-Mounted Installation

Installation space requirements

Figure 4-1 Installation space requirements for wall-mounting

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 26


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the Plastic Base


The plastic base can be installed in three modes: magnet, adhesive, and screw.

Figure 4-2 Plastic base

Table 4-1 Installing the plastic base


Installation Mode Installation Procedure

Magnet Secure the base in an appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a
1.0 mm or thicker steel plate if
attaching by magnet is
adopted.
● Ensure that the installation
position is level, coarse, clean,
and meets the condition (iron,
cobalt, or nickel) for attaching
with magnet.
● Keep the component secured
with magnet away from
sources of vibration because
vibration can cause the
component to fall off.
● Exercise caution to prevent the
component from falling off
during installation; otherwise,
the magnet may be damaged.
If the component slides during
operations, also use adhesive
or screws to secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 27


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Installation Procedure

Adhesive Secure the base in an appropriate area on the wall.


NOTE
● Ensure that the installation
position is dry, level, smooth,
and free from dust or oil
stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 28


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Installation Procedure

Screw 1. Mark mounting holes in an appropriate area on the wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 29


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing an SCC800

Figure 4-3 Installing an SCC800

4.1.2 Rack-Mounted Installation


Procedure
Step 1 Install mounting ears for the SCC800.

Figure 4-4 Installing mounting ears

Step 2 Installing the SCC800 in a 19-inch rack.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 30


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-5 Installing an SCC800

----End

4.1.3 Installing Power Cables


Figure 4-6 Installing power cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 31


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.1.4 Installing an Antenna Tray

NOTICE

● An antenna tray must be installed in an outdoor area with few shelters and
there should be no metal objects or other antenna radiators (except the
antenna tray) within 200 mm from the antenna tray.
● It is recommended that the antenna tray be installed at least 2 m above the
ground.
● The antenna tray must be installed horizontally.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 32


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Table 4-2 Installing an antenna tray


Concrete Wall Scenario Wall Panel Scenario

1. Mark mounting holes for the antenna 1. Mark mounting holes for the antenna
support in an appropriate outdoor area. support in an appropriate outdoor area.

2. Drill holes and install expansion sleeves. 2. Drill holes at the marked positions.
NOTE
1. Drill a hole into the wall using a hammer drill.
2. Slightly tighten the expansion bolt and
vertically insert it into the hole. Drive the
expansion bolt using a rubber mallet until the
expansion sleeve is fully inserted into the hole.
3. Partially tighten the nut clockwise until the
expansion anchor bolt and expansion sleeve
stick to the wall.
4. Loosen the nut counterclockwise and remove
the spring washer and flat washer.

3. Secure the antenna support to the wall.

(1) Expansion anchor bolt (2) M6 nut (3)


Spring washer (4) Flat washer 4. Install the antenna tray on the support.
(5) Expansion sleeve (6) Wall (7) Rubber
mallet (8) Socket wrench
3. Install the antenna tray on the support.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 33


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Concrete Wall Scenario Wall Panel Scenario

4. Secure the antenna support to the wall.

4.1.5 Installing Antennas

NOTICE

● If all wireless components are installed indoors and are close to each other,
install a rod antenna only.
● It is recommended that a dual-mode antenna be installed on the outdoor
antenna tray. In the cabinet scenario, attach the dual-mode antenna to the top
of the cabinet.
● The antennas must be installed vertically and must not be too close to cables
nearby. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm
● The bending radius of a cable must be greater than 200 mm. Bind the cable
after connecting it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 34


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-7 Installation position

Installing a Rod Antenna

Figure 4-8 Installing a rod antenna

Installing a Dual-Mode Antenna


Step 1 Install a dual-mode antenna.

Figure 4-9 Installing a dual-mode antenna (tray installation)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 35


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-10 Installing a dual-mode antenna (cabinet installation)

Step 2 Connect the antenna cable.

Figure 4-11 Connecting the antenna cable

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 36


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.1.6 Installing Network Management Cables (IP Networking)

Figure 4-12 IP networking

4.1.7 Installing Network Management Cables (In-Band


Networking)

Figure 4-13 In-band networking

4.1.8 Installing Network Management Cables (4G


Networking)

Installing SIM Cards


Step 1 Remove the cover from the side panel of the SCC800.

Step 2 Install SIM cards.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 37


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-14 Installing SIM cards

(1) SIM card

Step 3 Reinstall the cover on the side panel of the SCC800.

----End

Installing a 4G antenna

NOTICE

● You are advised to install a 4G antenna in the specified area on the outdoor
antenna tray. In the cabinet scenario, attach the 4G antenna to the top of the
cabinet.
● The antenna must be installed vertically and must not be too close to cables
nearby. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm; distance between the antenna and the
wall: ≥ 100 mm
● The bending radius of a cable must be greater than 200 mm. Bind the cable
after connecting it.

Step 1 Install a 4G antenna.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 38


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-15 Installing an antenna (tray installation)

Figure 4-16 Installing an antenna (cabinet installation)

Step 2 Connect the cable.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 39


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-17 Connecting the cable

----End

4.1.9 Installing Communications Cables for Third-Party Smart


Devices
Figure 4-18 Connecting a communications cable (RS485/CAN protocol)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 40


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-19 Connecting a communications cable (SNMP protocol)

4.2 Installing an Outdoor Wireless AC Meter Box ACMB

4.2.1 Securing an Outdoor Wireless AC Meter Box


You are advised to install the ACMB near the ACDB. Do not use it in environments
with heavy chemical pollution and corrosive gases.

Installing the Metal Base


The metal base can be secured by screws, rivets, or clamps.

Figure 4-20 Metal base

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 41


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Table 4-3 Installing the metal base


Installation Installation Procedure
Mode

Screw 1. Mark mounting holes in an appropriate area on the wall.

2. Drill holes and install expansion anchor bolts.


NOTE
1. Drill a hole into the wall using a hammer drill.
2. Slightly tighten the expansion anchor bolt and vertically insert it into the hole. Drive
the expansion anchor bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
3. Partially tighten the nut clockwise until the expansion anchor bolt and expansion
sleeve stick to the wall.
4. Loosen the nut counterclockwise and remove the spring washer and flat washer.

(1) Expansion anchor bolt (2) M6 nut (3) Spring washer (4) Flat washer
(5) Expansion sleeve (6) Wall (7) Rubber mallet (8) Socket wrench
3. Install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 42


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Procedure


Mode

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 43


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Procedure


Mode

Rivet 1. Mark mounting holes in an appropriate area on the wall.

2. Drill holes at the marked positions.

3. Secure the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 44


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Procedure


Mode

Clamp Secure the base in an appropriate area on the pole.


NOTE
Clamps
support a pole
with the
diameter of
48–114mm.

Installing the Box

Figure 4-21 Installing the box (wall-mounted)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 45


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-22 Installing the box (pole-mounted)

4.2.2 Installing AC detection cables


The mains and DG are used as examples of AC equipment in the wiring diagram
provided in this section.

NOTICE

● After installing cables in the outdoor meter box, use sealing putty to seal the
cable holes from the inside of the box.
● An upstream protection device (such as a circuit breaker, switch, or
interconnection terminal) must be installed for the AC meter box voltage
detection.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 46


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.2.2.1 Single-Phase Scenario

Figure 4-23 Installing AC detection cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 47


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.2.2.2 Dual-Live Wire Scenario

Figure 4-24 Installing AC detection cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 48


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.2.2.3 Three-Live Wire Scenario

Figure 4-25 Installing AC detection cables

NOTE

The current detection wires Ia, Ib, and Ic of the AC meter must map to the L1, L2, and L3
wires of the measured device. Ia maps to L1, Ib maps to L2, and Ic maps to L3. The live
wires shown in the figure are for reference only.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 49


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.2.2.4 Three-Phase Four-Wire Scenario

Figure 4-26 Installing AC detection cables

NOTE

The current detection wires Ia, Ib, and Ic of the AC meter must map to the L1, L2, and L3
wires of the measured device. Ia maps to L1, Ib maps to L2, and Ic maps to L3. The live
wires shown in the figure are for reference only.

4.3 Installing an Indoor Wireless AC Meter Box ACMB


4.3.1 Securing an Indoor Wireless AC Meter Box
You are advised to install the ACMB near the ACDB. Do not use it in environments
with heavy chemical pollution and corrosive gases.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 50


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the Metal Base


The metal base can be secured by screws or rivets.

Figure 4-27 Metal base

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 51


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Table 4-4 Installing the metal base


Installation Installation Procedure
Mode

Screw 1. Mark mounting holes in an appropriate area on the wall.

2. Drill holes and install expansion anchor bolts.


NOTE
1. Drill a hole into the wall using a hammer drill.
2. Slightly tighten the expansion bolt and vertically insert it into the hole. Drive the
expansion bolt using a rubber mallet until the expansion sleeve is fully inserted into
the hole.
3. Partially tighten the nut clockwise until the expansion anchor bolt and expansion
sleeve stick to the wall.
4. Loosen the nut counterclockwise and remove the spring washer and flat washer.

(1) Expansion anchor bolt (2) M6 nut (3) Spring washer (4) Flat washer
(5) Expansion sleeve (6) Wall (7) Rubber mallet (8) Socket wrench
3. Install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 52


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Procedure


Mode

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 53


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Procedure


Mode

Rivet 1. Mark mounting holes in an appropriate area on the wall.

2. Drill holes at the marked positions.

3. Secure the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 54


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the Box

Figure 4-28 Installing the box

4.3.2 Installing AC Detection Cables


The wiring diagrams provided in this section use two DC power systems and two
air conditioners as an example to illustrate how to install cables.

NOTICE

Install upstream protection devices (such as circuit breakers and interconnection


terminals) for ACMB voltage detection.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 55


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.3.2.1 Single-Phase Scenario

Figure 4-29 Installing AC detection cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 56


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.3.2.2 Dual-Live Wire Scenario

Figure 4-30 Installing AC detection cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 57


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.3.2.3 Three-Live Wire Scenario

Figure 4-31 Installing AC detection cables

NOTE

The current detection wires Ia, Ib, and Ic of the AC meter must map to the L1, L2, and L3
wires of the measured device. Ia maps to L1, Ib maps to L2, and Ic maps to L3. The live
wires shown in the figure are for reference only.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 58


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.3.2.4 Three-Phase Four-Wire Scenario

Figure 4-32 Installing AC detection cables

NOTE

The current detection wires Ia, Ib, and Ic of the AC meter must map to the L1, L2, and L3
wires of the measured device. Ia maps to L1, Ib maps to L2, and Ic maps to L3. The live
wires shown in the figure are for reference only.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 59


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.4 Installing a Wireless AC Power Failure Sensor


iACSENSE

4.4.1 Securing a Wireless AC Power Failure Sensor


The recommended installation height is about 1.5 m. Do not use the sensor in
environments with heavy chemical pollution and corrosive gases.

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Installing a Base
The base can be secured by magnet, adhesive, or screw.

Table 4-5 Installing a base


Installation Mode Procedure

Magnet Secure the base in the appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a 1.0 mm
or thicker steel plate if attaching by
magnet is adopted.
● Ensure that the installation position is
level, coarse, clean, and meets the
condition (iron, cobalt, or nickel) for
attaching with magnet.
● Keep the component secured with
magnet away from sources of
vibration because vibration can cause
the component to fall off.
● Exercise caution to prevent the
component from falling off during
installation; otherwise, the magnet
may be damaged. If the component
slides during operations, also use
adhesive or screws to secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 60


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Adhesive Secure the base in the appropriate area on the wall.


NOTE
● Ensure that the installation position is
dry, level, smooth, and free from dust
or oil stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 61


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the


wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 62


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iACSENSE

Figure 4-33 Installing the iACSENSE

4.4.2 Installing a Dual-Mode Antenna

NOTICE

● The dual-mode antenna should be installed on the top of the cabinet or on the
metal cable tray. When the antenna is installed on the cable tray, the antenna
top should face downward.
● The antenna must be installed vertically and must not be too close to cables
nearby. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm; distance between the antenna and the
wall: ≥ 100 mm
● The bending radius of a cable must be greater than 200 mm. Bind the cable
after connecting it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 63


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-34 Installation position

Figure 4-35 Installing the antenna

4.4.3 Installing Power Failure Detection Cables

NOTICE

● Ensure that the top side (with the Huawei logo) of a probe face upward, and
the bottom side is closely bound to an AC power cable.
● Use two cable ties to bind a probe to the AC power cable securely.
● Keep a probe at least 10 mm away from the nearby cables.
● Do not bind signal cables and AC power cables together.

Figure 4-36 Binding the probe

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 64


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-37 Installing power failure detection cables (single-phase)

Figure 4-38 Installing power failure detection cables (dual–live wire)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 65


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-39 Installing power failure detection cables (three–live wire)

Figure 4-40 Installing power failure detection cables (three-phase, four-wire)

4.5 Installing a Wireless DC Meter iDCMETER

CAUTION

Do not install the iDCMETER in environments with strong magnetic sources. The
distance between the iDCMETER and magnets or metal plane should be greater
than or equal to 100 mm.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 66


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.5.1 Installing the Dual-mode Antenna

NOTICE

● The dual-mode antenna should be installed on the top of the cabinet or on the
metal cable tray. When the antenna is installed on the cable tray, the antenna
top should face downward.
● The antenna must be installed vertically and must not be too close to cables
nearby. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm; distance between the antenna and the
wall: ≥ 100 mm
● The bending radius of a cable must be greater than 200 mm. Bind the cable
after connecting it.

Figure 4-41 Installation position

Figure 4-42 Installing an antenna

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 67


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.5.2 Installing Detection Cables


Figure 4-43 Installing DC power detection cables

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 68


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-44 Installing battery detection cables

4.6 Installing a Wireless Data Converter iDATA

4.6.1 Securing the iDATA


The iDATA can be secured by magnet or adhesive. When the iDATA needs to be
installed on an iron wall, secure it using both magnet and adhesive.

NOTE

● Ensure that the installation position is dry, level, smooth, and free from dust or oil
stains. Otherwise, the adhesion performance will decrease.
● If the iDATA is used to manage a DG, install it in the DG control box.
● If the iDATA is used to manage other devices such as the power supply, the
recommended installation height is about 1.5 m.
● Second-time adhesion is not supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 69


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-45 Installing the iDATA

4.6.2 Installing Antenna

NOTICE

● Install a rod antenna or a dual-mode antenna based on site requirements.


● The dual-mode antenna should be installed on the top of the cabinet or on the
metal cable tray. When the antenna is installed on the cable tray, the antenna
top should face downward.
● If the iDATA is used to manage a DG, install it on the top of the DG.
● The antenna must be installed vertically and must not be too close to cables
nearby. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm; distance between the antenna and the
wall: ≥ 100 mm
● The bending radius of a cable must be greater than 200 mm. Bind the cable
after connecting it.

Installing a Rod Antenna

Figure 4-46 Installing a rod antenna

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 70


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing a Dual-Mode Antenna

Figure 4-47 Installation position

Figure 4-48 Installing the antenna

4.6.3 Installing the Power Cable


The following figure shows the connections of power cables when the iDATA is
used to detect intelligent diesel generators.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 71


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-49 Installing the power cable

The following figure shows the connections of power cables when the iDATA is
used to detect other smart devices such as the DC power supply.

Figure 4-50 Installing the power cable

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 72


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.6.4 Installing a Communications Cable (RS232)


Figure 4-51 Installing a communications cable

4.6.5 Installing the Communications Cable (RS485)


Figure 4-52 Installing the communications cable

4.7 Installing an Wireless DG Monitoring Box iDG

4.7.1 Securing an Wireless DG Monitoring Box


You are advised to install the iDG in the ATS control box. Do not use the iDG in
environments with heavy chemical pollution and corrosive gases.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 73


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Installing a Base
The base can be secured by magnet, adhesive, or screw.

Table 4-6 Installing a base


Installation Mode Procedure

Magnet Secure the base in the appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a 1.0 mm
or thicker steel plate if attaching by
magnet is adopted.
● Ensure that the installation position is
level, coarse, clean, and meets the
condition (iron, cobalt, or nickel) for
attaching with magnet.
● Keep the component secured with
magnet away from sources of
vibration because vibration can cause
the component to fall off.
● Exercise caution to prevent the
component from falling off during
installation; otherwise, the magnet
may be damaged. If the component
slides during operations, also use
adhesive or screws to secure it.

Adhesive Secure the base in the appropriate area on the wall.


NOTE
● Ensure that the installation position is
dry, level, smooth, and free from dust
or oil stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 74


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the


wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 75


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iDG

Figure 4-53 Installing the iDG

4.7.2 Installing Antenna

NOTICE

● When the iDG is used only to connect to the audible and visual alarm and the
installation position is close to the SCC800, use a rod antenna. In other cases,
the dual-mode antenna is used.
● You are advised to install the dual-mode antenna on the top of the DG or ATS
control box.
● Ensure that the antenna is installed vertically and keep a proper distance
between the antenna and the cables. Do not install antennas horizontally.
● Distance between antennas: ≥ 200 mm; distance between the antenna and the
wall: ≥ 100 mm
● The bending radius of a cable must be greater than 200 mm. After cables are
installed, bind them.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 76


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing a Rod Antenna

Figure 4-54 Installing a rod antenna

Installing a Dual-Mode Antenna

Figure 4-55 Installation position

Figure 4-56 Installing the antenna

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 77


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.7.3 Installing the Power Cable


When the iDG is used to detect only the DG, the power cable connections are
shown in the following figure.

Figure 4-57 Installing the power cable

When the iDG is used to detect the DG and connect to an audible and visual
alarm or connect to an audible and visual alarm only, the power cable connections
are shown in the following figure.

Figure 4-58 Installing the power cable

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 78


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.7.4 Installing a DG Reset Cable


Figure 4-59 Installing a DG reset cable

4.7.5 Installing a DG Fault Alarm Cable


Figure 4-60 Installing a DG fault alarm cable

4.7.6 Installing Cables for Controlling DG Startup and


Shutdown
Figure 4-61 Site DG control diagram

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 79


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-62 Installing cables for controlling DG startup and shutdown

4.8 Installing a Wireless Fuel Level Sensor iFUEL

4.8.1 Installing a Wireless Magnetostrictive Fuel Level Sensor


Drill holes in an appropriate area on the cover or flat surface of the fuel tank.

DANGER

● To avoid accidents, keep far away from flames and sparks during operations.
● Before drilling holes on the fuel tank cover, remove the fuel tank cover and
perform the operations far away from the fuel tank.
● Before drilling holes on the fuel tank, drain all fuel from the fuel tank into a
clean container.

NOTICE

● Before installing a fuel level sensor, ensure that its measurement range is
greater than the height of the fuel tank.
● When installing a fuel level sensor, ensure that the sensor touches the bottom
of the fuel tank. If the sensor cannot touch the bottom, set a blind zone or
replace with a fuel level sensor of the required measurement range.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 80


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-63 Drilling holes

NOTICE

● Ensure that the measuring rod of the sensor is free from scraping or bending
and that the float is free from damage.
● When installing the float, ensure that the side with a larger diameter faces
down.
● After installation is complete, protect all connection points with sealant.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 81


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-64 Assembling a sensor

(1) Compression nut (2) Taper sleeve (3) Threaded connector

(4) Flange (5) Float (6) Jump ring

Figure 4-65 Securing the sensor

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 82


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-66 Securing the flange

4.8.2 Installing a Wireless Submersible Fuel Level Sensor (on


the Fuel Tank)
Drill holes in an appropriate area on the cover or flat surface of the fuel tank.

DANGER

● To avoid accidents, keep far away from flames and sparks during operations.
● Before drilling holes on the fuel tank cover, remove the fuel tank cover and
perform the operations far away from the fuel tank.
● Before drilling holes on the fuel tank, drain all fuel from the fuel tank into a
clean container.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 83


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-67 Drilling holes

The sensor control box can be installed on a fuel tank, wall, or pole.

NOTE

● In the following table, the sensor is installed on the fuel tank cover. You can install the
sensor onto the fuel tank in the same way.
● Ensure that the sensor probe touches the bottom of the fuel tank and is naturally
vertical.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 84


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Table 4-7 Installing a wireless submersible fuel level sensor


Installation Installation Step
Mode

Installing the 1. Install the base.


control box on a
fuel tank
NOTE
● It is
recommended
that the
component be
installed on a 2. Install the sensor.
1.0 mm or
thicker steel
plate if
attaching by
magnet is
adopted.
● Ensure that
the installation
position is
level, coarse,
clean, and
meets the
condition
(iron, cobalt,
or nickel) for 3. Secure the flange.
attaching with
magnet.
● Keep the
component
secured with
magnet away
from sources
of vibration
because
vibration can
cause the
component to
fall off.
● Exercise
caution to 4. After securing the flange, apply sealant to the screws on the flange.
prevent the
component
from falling
off during
installation;
otherwise, the
magnet may
be damaged. If
the component
slides during
operations,
also use
adhesive or
screws to
secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 85


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Step


Mode

Installing the 1. Mark mounting holes for the control box base in an appropriate area on
control box on a the wall.
wall

2. Drill holes and install expansion sleeves.

3. Install the sensor.

4. Install the sensor probe.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 86


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Step


Mode

5. Secure the flange.

6. After securing the flange, apply sealant to the screws on the flange.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 87


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Installation Step


Mode

Installing the 1. Install the sensor in an appropriate area on the pole.


control box on a
pole

2. Install the sensor probe.

3. Secure the flange.

4. After securing the flange, apply sealant to the screws on the flange.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 88


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.8.3 Installing a Wireless Submersible Fuel Level Sensor


(Through the Air Hole)

NOTICE

● Ensure that the sensor probe touches the bottom of the fuel tank and is
naturally vertical.
● When installing the fuel level sensor control box, ensure that the cable outlet
on the control box faces downwards or the lowest point of the cable is lower
than the cable outlet.

Figure 4-68 Installation through the air hole 1

Figure 4-69 Installation through the air hole 2

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 89


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Step 1 Open the cover of the control box, record the information about the cable
connected from the sensor to the control box, and disconnect the cable.
Step 2 Wrap the cable airway tube opening and cable terminal using insulation tape to
prevent the airway tube from being blocked by oil stains during cable routing.
Step 3 Insert a soft iron wire that is long enough into the fuel tank through the air hole
until the wire reaches the position touchable by hand.
Step 4 Gently place the sensor probe onto the bottom of the fuel tank and bind the cable
wrapped by insulation tape and iron wire by using cable ties.
NOTE

You can select the hole that is closest to the air hole and through which the sensor can be
placed.

Step 5 Gently pull the iron wire from the outside of the air hole until the cable comes out
of the air hole.
Step 6 Install a hose clamp and cable holder at the air hole, and secure the cable with
the cable holder.
Step 7 Reconnect the cable to the control box based on the recorded information, and
reinstall the control box cover.
Step 8 Install the base and attach the control box to an appropriate position on the fuel
tank.

Figure 4-70 Securing the sensor

----End

4.9 Installing an Indoor Camera


The indoor camera can be installed on a wall or ceiling in the same way. The
following procedure describes how to install it on the ceiling.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 90


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

NOTE

● The camera should face the door, cabinet, or fuel tank. There should be no obstacles
between the camera and the door, cabinet, or fuel tank.
● After the camera is installed, adjust its position to prevent the camera from directly
facing the position with light source.

Indoor Camera A

Figure 4-71 Pasting a sticker

Figure 4-72 Drilling a hole and installing an expansion sleeve

Figure 4-73 Removing the camera fastener

NOTE

There is a cable hole on the camera base. Use pliers to remove the extra part from the
cable hole as required.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 91


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-74 Installing the camera

Figure 4-75 Adjusting the angle

Indoor Camera B

Figure 4-76 Pasting a sticker

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 92


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-77 Drilling a hole and installing an expansion sleeve

Figure 4-78 Removing the camera cover

Figure 4-79 Installing the camera

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 93


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-80 Adjusting the angle

Figure 4-81 Reinstalling the camera cover

NOTE

Reinstall the camera cover after commissioning the camera and ensuring that it has the
proper angle.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 94


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Cable Connections

Figure 4-82 Installing camera cables

4.10 Installing an Outdoor Camera

NOTICE

● The intelligent alarm reporting function is used only to facilitate monitoring. Its
accuracy and false reporting rate may be unsatisfactory. In scenarios that have
high requirements for intelligent alarm reporting, it is recommended that
dedicated intelligent alarm reporting devices be used.
● Installing cameras in appropriate positions effectively reduces the false
reporting rate and improves the accuracy of intelligent alarm reporting.
● For more stable and accurate photos, it is recommended that the object size be
less than 50% of the camera detection scope and the object height be greater
than 10% of the camera detection height.
● Do not install cameras in a place with reflection, such as on a glass, floor tile,
or lake.
● In the daytime and nighttime environments with sufficient light, a camera
provides clear images with good contrast. When the light is insufficient at
night, light needs to be supplemented to ensure that the area where targets
may enter has sufficient light.
● It is recommended that the camera be installed about 4 m above the ground.
The camera should face the door, cabinet, or fuel tank. There should be no
obstacles between the camera and the door, cabinet, or fuel tank.
● After the camera is installed, adjust its position to prevent the camera from
directly facing the position with light source.
● If it is installed outdoors, drill a hole, route cables into the indoor space
through the hole, and then apply sealant at the cable hole.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 95


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Outdoor Camera A

Table 4-8 Installing outdoor camera A


Wall-Mounted Installation Pole-Mounted Installation

1. Mark mounting holes. 1. Install the camera base.

2. Assemble the camera.

2. Drill holes and install expansion sleeves.

3. Install the camera.

3. Assemble the camera.

4. Install the camera.

4. Adjust the angle.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 96


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Wall-Mounted Installation Pole-Mounted Installation

5. Adjust the position of the rainproof cover of


the camera.

5. Adjust the angle.

6. Adjust the position of the rainproof cover of


the camera.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 97


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Outdoor Camera B

Table 4-9 Installing outdoor camera B


Wall-Mounted Installation Pole-Mounted Installation

1. Mark mounting holes. 1. Install the camera base.

2. Install the camera.

2. Drill holes and install expansion sleeves.

3. Adjust the angle and tighten the screws.


3. Install the camera.

4. Adjust the position of the rainproof cover of


the camera.

4. Adjust the angle and tighten the screws.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 98


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Wall-Mounted Installation Pole-Mounted Installation

5. Adjust the position of the rainproof cover of


the camera.

Cable Connections

Figure 4-83 Installing camera cables

4.11 Installing an Equipment Room Door Lock iACCESS

NOTICE

● The equipment room door lock should be installed 1.1-1.3 m above the floor.
● The door for installing the equipment room door lock needs to be 40–120 mm
thick.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 99


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the Lock Body


Step 1 Attach the indoor positioning sticker to an appropriate area on the door.

Figure 4-84 Attaching a positioning sticker

Step 2 Drill a hole into the door using a hole-drilling tool.


Step 3 Cut the key spindle and square spindle according to the thickness of the door. You
can use a hacksaw or hydraulic pliers for cutting.

NOTICE

● Formula for calculating the key spindle length to be retained: Key spindle
length = Door thickness + 25 mm. For example, if the door is 45 mm thick, the
key spindle length to be retained is 70 mm (45 mm + 25 mm).
● Formula for calculating the square spindle length to be retained: Square spindle
length = Door thickness + 50 mm. For example, if the door is 45 mm thick, the
square spindle length to be retained is 95 mm (45 mm + 50 mm).

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 100


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-85 Retained key spindle and square spindle lengths

Step 4 Cut the screws according to the thickness of the door. You can use a hacksaw or
hydraulic pliers for cutting.

NOTICE

● For the two screws used for securing the lock head: Screw length to be retained
= Door thickness - 10 mm. For example, if the door is 45 mm thick, the square
spindle length to be retained is 35 mm (45 mm - 10 mm).
● For the four screws used for securing the lock body to the panel = Door
thickness + 15 mm. For example, if the door is 45 mm thick, the square spindle
length to be retained is 60 mm (45 mm + 15 mm).
● If a screw is cut at the screw thread, polish the cross section burrs or polish the
edge of the cross section to a slope angle to ensure that the screw thread is
tidy around the cross section.

Figure 4-86 Retained screw lengths

Step 5 Remove the battery cover and take out batteries.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 101


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-87 Removing the battery cover and taking out batteries

Step 6 Unscrew the lock body and take out the lock core structure box.
NOTE

Remove the two screws on the outer left side and the two screws on the outer right side of
the lock body.

Figure 4-88 Unscrewing the lock body

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 102


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-89 Taking out the lock core structure box

Step 7 Check whether the lock tongue matches the door opening mode. If not, adjust the
lock tongue based on the door opening direction.

Figure 4-90 Removing the lock cover

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 103


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-91 Direction of the small lock tongue

(1) Right hand inswing (2) Right hand outswing (3) Left hand outswing (4) Left hand inswing

NOTE

When determining the door opening direction, you need to stand outdoors.

Figure 4-92 adjust the lock tongue

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 104


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-93 Installing the lock cover

Step 8 Install the lock head and the bottom cover of the lock body.

Figure 4-94 Installing the lock head and the bottom cover of the lock body

Step 9 Install the outdoor part of the lock body and tighten the screws.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 105


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-95 Installing the outdoor part of the lock body

Step 10 Connect the communications cable to the outdoor part of the lock body.
NOTE

If the communications cable is long, insert the cable into the door hole.

Figure 4-96 Connecting the communications cable

Step 11 Install the lock core structure box and tighten the screws.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 106


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-97 Installing the lock core structure box

Figure 4-98 Tightening screws

Step 12 Connect the communications cable to the lock core structure box.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 107


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-99 Connecting the communications cable

Step 13 Install batteries and connect battery cables.

Figure 4-100 Installing batteries and connecting battery cables

Step 14 Install the battery cover.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 108


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-101 Installing the battery cover

----End

Installing the Door Locking Plate


NOTE

Check whether the direction of the door locking plate matches the door opening mode. If
not, adjust the direction of the door locking plate.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 109


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-102 Direction of the door locking plate

(1) Left hand outswing and right hand inswing (2) Left hand inswing and right hand outswing

Figure 4-103 Assemble the door locking plate and partially tighten the screws

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 110


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-104 Adjusting the direction of the door locking plate

Step 1 Mark mounting holes, and drill holes in the corresponding positions.
NOTE

● Hole diameter: 3.5 mm


● The iron door is secured using rivets, and the wooden door is secured by tapping screws.
Tapping screws can be used with expansion screws.

Figure 4-105 Marking mounting holes

Step 2 Install the door locking plate and secure it using screws.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 111


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-106 Securing the door locking plate

----End

Installing the Rainproof Cover


Step 1 Mark holes in appropriate positions above the lock body, and install the rainproof
cover.
NOTE

Install the rainproof cover in a proper position. Ensure that the rainproof cover does not
interfere with the door frame.

Figure 4-107 Securing the rainproof cover

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 112


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.12 Installing an Outdoor Cabinet Door Lock iACCESS


Figure 4-108 Installing an outdoor cabinet door lock

NOTE

After locking the door, close the rubber cover at the bottom of the lock body.

Figure 4-109 Bluetooth electronic key

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 113


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.13 Installing an Outdoor Fence Door Lock iACCESS


Figure 4-110 Installing an outdoor fence door lock

NOTE

After locking the door, close the rubber cover at the bottom of the lock body.

Figure 4-111 Bluetooth electronic key

4.14 Installing a Cabinet Electronic Lock Cylinder


iACCESS
Prerequisites
● The cabinet door key and required tools are available.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 114


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

● The lock cylinder to be installed is of the correct model.

Procedure
Step 1 Open the cabinet door.
Step 2 Take out and initialize the cabinet electronic lock cylinder. For details about how
to initialize the lock cylinder, see Configuring an Outdoor Cabinet or Fence Door
Lock.
Step 3 Loosen the screw (M5) that secures the mechanical lock cylinder to the cabinet
door and remove the mechanical lock cylinder. Install the cabinet electronic lock
cylinder and tighten the screw (M5).
NOTE

Remove the hex key from the cabinet door key chain and attach the hex key to the
Bluetooth electronic key chain to facilitate future unlocking.

Figure 4-112 Replacing a lock cylinder

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 115


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.15 Installing a Wireless Temperature and Humidity


Sensor iTEMP

NOTICE

● You are advised to install the sensor on a cable tray. If no cable tray is available
onsite, attach it to the side of a cabinet (the installation height is about 1.5 m).
● Do not install the sensor on an external wall. (The external wall may encounter
a great temperature difference, which results in inaccurate measurement
results.)
● The sensor should not be directly exposed to sunlight, should not be placed
near an air vent or air conditioner vent, and should not come into direct
contact with a heat source or cold source.

Figure 4-113 Incorrect installation

● Do not use it in environments with heavy chemical pollution and corrosive


gases.

Installing the iTEMP Base


The base can be secured by magnet, adhesive, screw, or cable tie.

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 116


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Table 4-10 Installing the base


Installation Mode Procedure

Magnet Secure the base in an appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a 1.0 mm
or thicker steel plate if attaching by
magnet is adopted.
● Ensure that the installation position is
level, coarse, clean, and meets the
condition (iron, cobalt, or nickel) for
attaching with magnet.
● Keep the component secured with
magnet away from sources of
vibration because vibration can cause
the component to fall off.
● Exercise caution to prevent the
component from falling off during
installation; otherwise, the magnet
may be damaged. If the component
slides during operations, also use
adhesive or screws to secure it.

Adhesive Secure the base in an appropriate area on the wall.


NOTE
● Ensure that the installation position is
dry, level, smooth, and free from dust
or oil stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 117


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the


wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

Cable tie Bind the base to an appropriate position using cable ties.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 118


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iTEMP

Figure 4-114 Installing the iTEMP

4.16 Installing a Wireless Motion Detector iMOTION


It is recommended that the installation height be about 2.2 m. Install the detector
in an area (for example, sideward to the door; ensure that the cross-section profile
of people entering the door can be sensed) where unauthorized access is most
likely to happen (referring to figure ①②③). The detector should not be directly
exposed to sunlight and should be away from a cold or hot air outlet. Avoid
strong airflow or blind spots in the coverage area (referring to figure ④).

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 119


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-115 Incorrect installation

Installing the iMOTION Base


The base can be secured by magnet, adhesive, screw, or cable tie.

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Table 4-11 Installing the base

Installation Mode Procedure

Magnet Secure the base in an appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a 1.0 mm
or thicker steel plate if attaching by
magnet is adopted.
● Ensure that the installation position is
level, coarse, clean, and meets the
condition (iron, cobalt, or nickel) for
attaching with magnet.
● Keep the component secured with
magnet away from sources of
vibration because vibration can cause
the component to fall off.
● Exercise caution to prevent the
component from falling off during
installation; otherwise, the magnet
may be damaged. If the component
slides during operations, also use
adhesive or screws to secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 120


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Adhesive Secure the base in an appropriate area on the wall.


NOTE
● Ensure that the installation position is
dry, level, smooth, and free from dust
or oil stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 121


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the


wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

4. Install the screw hole cover.

Cable tie Bind the base to an appropriate position using cable ties.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 122


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iMOTION

Figure 4-116 Installing the iMOTION

Adjust the sensor to cover the target area.

Figure 4-117 Adjusting the iMOTION angle

4.17 Installing a Wireless Smoke Sensor iSMOKE

NOTICE

When installing a iSMOKE, do not press its dust filter. Otherwise, the dust filter
may be damaged, and the iSMOKE cannot work properly.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 123


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

It is recommended that the sensor be installed in an open position in the upper


part of the equipment room or cabinet. When the iSmoke is installed within the
cabinet, there shall be certain clearance between the iSmoke and the inner wall of
the cabinet, and there shall be no materials within 0.2m around the sensor.

Figure 4-118 Installation diagram

Do not install it in a corner, above a heat source, in an air channel, or at a dusty or


high-humidity place (referring to figure ①). When the iSmoke is mounted in the
room with air supply and air return ducts, such sensor shall be mounted on the
path through which the airflow goes towards the air return duct (referring to
figure ②). When the iSmoke must be mounted near an air inlet, a certain distance
must be kept (referring to figure ②). Correct installation position may enable the
sensor to fast and accurately detect a fire. Incorrect installation position may
cause the iSmoke to be even issue a false alarm due to airflow interference.

Figure 4-119 Installation diagram

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 124


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iSMOKE Base


The base can be secured by magnet, adhesive, screw, or cable tie.

NOTE

● If the base needs to be installed on a concrete top surface, secure the base using screws.
● If the base needs to be installed on an iron top surface, secure the base using both
magnet and adhesive.

Table 4-12 Installing the base


Installation Mode Procedure

Magnet Secure the base in an appropriate area on the ceiling of the


NOTE equipment room.
● It is recommended that the
component be installed on a 1.0
mm or thicker steel plate if
attaching by magnet is adopted.
● Ensure that the installation
position is level, coarse, clean,
and meets the condition (iron,
cobalt, or nickel) for attaching
with magnet.
● Keep the component secured
with magnet away from sources
of vibration because vibration
can cause the component to fall
off.
● Exercise caution to prevent the
component from falling off
during installation; otherwise,
the magnet may be damaged. If
the component slides during
operations, also use adhesive or
screws to secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 125


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Adhesive Secure the base in an appropriate area on the ceiling of the


NOTE equipment room.
● Ensure that the installation
position is dry, level, smooth,
and free from dust or oil stains.
Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 126


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the ceiling


of the equipment room.

2. Drill holes and install expansion sleeves.

3. Install the base.

Cable tie Bind the base to an appropriate position using cable ties.

Installing the iSMOKE

Figure 4-120 Installing the iSMOKE

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 127


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

4.18 Installing a Wireless Water Sensor iWATER

NOTICE

● It is recommended that the installation height be about 0.45 m. Install the


sensor in the area where water is most likely to occur, for example, near the
equipment room door or under the air conditioner.
● To prevent false alarms, ensure that the iWATER electrode probe does not
come in contact with a conductor.

Installing the iWATER Base


The base can be secured by magnet, adhesive, screw, or cable tie.

NOTE

● If the base needs to be installed on a concrete wall, secure the base using screws.
● If the base needs to be installed on an iron wall, secure the base using both magnet and
adhesive.

Table 4-13 Installing the base


Installation Mode Procedure

Magnet Secure the base in an appropriate area on the wall.


NOTE
● It is recommended that the
component be installed on a 1.0 mm
or thicker steel plate if attaching by
magnet is adopted.
● Ensure that the installation position is
level, coarse, clean, and meets the
condition (iron, cobalt, or nickel) for
attaching with magnet.
● Keep the component secured with
magnet away from sources of
vibration because vibration can cause
the component to fall off.
● Exercise caution to prevent the
component from falling off during
installation; otherwise, the magnet
may be damaged. If the component
slides during operations, also use
adhesive or screws to secure it.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 128


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Adhesive Secure the base in an appropriate area on the wall.


NOTE
● Ensure that the installation position is
dry, level, smooth, and free from dust
or oil stains. Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is not
supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 129


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the


wall.

2. Drill holes and install expansion sleeves.

3. Install the base.

Cable tie Bind the base to an appropriate position using cable ties.

Installing the iWATER


Step 1 Install the iWATER.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 130


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-121 Installing the iWATER

Step 2 Install the iWATER electrode cable.

Figure 4-122 Installing the electrode cable

Step 3 Secure the iWATER electrode.


1. Drill a hole in an appropriate position on the floor based on the length of the
electrode cable.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 131


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-123 Drilling a hole

2. Secure the electrode.

NOTICE

– Ensure that the electrode notch faces downward to prevent conductive


objects from falling on the probe, which can cause an false alarm.
– Take adhesive cable ties out of the auxiliary material package to secure the
sensor cables. If the adhesive cable ties are not available, secure them
using a cable trough or other methods.

Figure 4-124 Securing the electrode

----End

4.19 Installing a Wireless Door Status Sensor iDOOR


Install the iDOOR at the inner upper side of the door and near the door opening
side. The iDOOR switch must be installed on the door frame, and the iDOOR
magnet must be installed on the door. The two parts must be aligned and the
clearance between them should be less than 10 mm.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 132


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

NOTICE

● The small triangle marks on the iDOOR switch and magnet must be as close as
possible to avoid affecting the use effect.
● Do not install components such as magnetic locks within 20 cm away from the
iDOOR. Otherwise, the iDOOR may not work properly.

Figure 4-125 Layout (the door is aligned with the door frame)

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 133


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-126 Layout (the door is not aligned with the door frame)

Installing the iDOOR Base


The base can be secured by adhesive or screw.

Table 4-14 Installing the base


Installation Mode Procedure

Adhesive Secure the base in an appropriate area on the door.


NOTE
● Ensure that the
installation position is dry,
level, smooth, and free
from dust or oil stains.
Otherwise, the adhesion
performance will decrease.
● Second-time adhesion is
not supported.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 134


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installation Mode Procedure

Screw 1. Mark mounting holes in an appropriate area on the door.

2. Use tapping screws to install the base.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 135


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Installing the iDOOR

Figure 4-127 Installing the iDOOR

4.20 Installing an Audible and Visual Alarm

NOTICE

● It is recommended that the audible and visual alarm be installed about 2.5 m
above the floor.
● If it is installed outdoors, drill a hole, route cables into the indoor space
through the hole, and then apply sealant at the cable hole.

Wall-Mounting
Step 1 Take out the bracket and mark mounting holes for the bracket in the appropriate
position.
Step 2 Drill holes and install expansion anchor bolts.
1. Drill a hole into the wall using a hammer drill.
2. Slightly tighten the expansion bolt and vertically insert it into the hole. Drive
the expansion bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
3. Partially tighten the nut clockwise until the expansion anchor bolt and
expansion sleeve stick to the wall.
4. Loosen the nut counterclockwise and remove the spring washer and flat
washer.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 136


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Figure 4-128 Drilling a hole and installing an expansion bolt

(1) Expansion anchor bolt (2) M6 nut (3) Spring washer

(4) Flat washer (5) Expansion sleeve (6) Wall

(7) Rubber mallet (8) Socket wrench

Step 3 Secure the bracket on the wall.

Step 4 Install the audible and visual alarm on the bracket.

Figure 4-129 Installing an audible and visual alarm

----End

Pole-Mounting

NOTICE

In the case of pole-mounting, choose the appropriate clamps that fit the pole size.

Step 1 Install the audible and visual alarm on the bracket.

Step 2 Loosen the clamps and route them through the bracket mounting holes.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 137


SCC800-S1 SmartSite Management System
Installation Guide 4 Component Installation

Step 3 Place the clamps around the pole and tighten the clamps.

Figure 4-130 Installing an audible and visual alarm

----End

Cable Connections
Connect the audible and visual alarm cable to the SIREN port on the iDG.

Figure 4-131 Installing the audible and visual alarm cable

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 138


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

5 Commissioning

NOTE

Internet Explorer is used as an example to illustrate all WebUI operations mentioned in this
document.

Operating Environment
Supported operating system: Windows XP or later

Browser: Internet Explorer 11 or later

5.1 Power-On Commissioning


Step 1 Switch on the upstream input circuit breaker for the SCC800.

Step 2 Switch on the SCC800 input circuit breaker.

Step 3 Check that the green Run indicator on the SCC800 is blinking fast at 4 Hz.
NOTE

After the SCC800 communicates properly with the upstream NMS, its indicator is blinking
slowly at 0.5 Hz.

----End

5.2 Logging In to the WebUI


Step 1 Remove the cable connected to the GE_1 port on the SCC800. Use a network cable
to connect the network port on the PC to the GE_1 port on the SCC800.

Step 2 Set the PC IP address in the same network segment as the SCC800 IP address.

For example, if the SCC800 has an IP address of 192.168.0.10, a subnet mask of


255.255.255.0, and a default gateway of 192.168.0.1, set the IP address to
192.168.0.11, subnet mask to 255.255.255.0, and default gateway to 192.168.0.1
on the PC.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 139


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

NOTE

● The default IP address of the SCC800 is 192.168.0.10, the subnet mask is 255.255.255.0,
and the gateway is 192.168.0.1.
● If the default IP address has been changed, you can view it on the NetEco.

Step 3 Enter https://SCC800 IP (for example, https://192.168.0.10) in the browser


address box on the PC, and then press Enter. The login page is displayed.

Figure 5-1 WebUI login page

Step 4 On the login page, enter the preset user name admin and preset password
Changeme, set the language, and click Log In.
NOTE

After login, change the password. Choose Maintenance> User Management, select a user
name, and click Modify.

Step 5 Reinsert the cable removed in Step 1 into the GE_1 port on the SCC800.

NOTICE

After all commissioning is complete, insert the cables removed from the GE_1 port
on the SCC800.

----End

5.3 Wireless Component Networking


Context
● Hold down the networking button on a wireless southbound component for
3s to begin networking. Hold down the networking buttons on the SCC800 for
8s to delete the networking information.
● Blinking slowly: If an indicator is blinking at 0.5 Hz (at intervals of 2s, on for
1s and then off for 1s), communication with the host is successful. Blinking

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 140


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

fast: If an indicator is blinking at 4 Hz (at intervals of 0.25s, on for 0.125s and


then off for 0.125s), networking is in progress.

Procedure

Step 1 Hold down the networking switch on the SCC800 for 3s until the indicator
above blinks fast.

Step 2 Consider the component type and hold down the networking switch on each
wireless component for 3s to implement networking until the indicator of the
component blinks slowly.
NOTE

● After the iDATA, iDG, or iDCMETER is powered on for the first time, it automatically
searches for the network for networking. If the networking fails, hold down the
networking switch for 3s for networking.
● Network the outdoor wireless ACMB before the indoor wireless ACMB. There is no
requirement on the networking sequence of other wireless components.
● If networking fails in 180s, the component will exit the networking mode and you need
to perform the networking operation again.

Step 3 After all wireless components are networked, log in to the WebUI and check
whether the networking is successful.
Step 4 Choose Home > Site Topology check whether the communication between
components at the site is normal.

Figure 5-2 Verifying component communication 1

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 141


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-3 Verifying component communication 2

NOTE

● If a component fails to communicate, hold down its networking switch for 3s to begin
networking again.
● If the networking of a component fails, adjust the antenna position to ensure that the
networking is successful (ensure that there is no blockage between the component
antenna and the SCC800 antenna).

Figure 5-4 Antenna position

Step 5 Check whether the indicators on the SCC800 is blinking slowly. If not, hold
down their networking switches for 3s until the indicators blink slowly, which
indicates that networking is complete.

----End

5.4 Setting Deployment Wizard Parameters


This section describes how to set parameters necessary for site deployment. Set
the parameters based on site requirements.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 142


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Procedure
Step 1 Set the site ID. Choose System Setting > Deployment Wizard on the WebUI, set
Site ID and click Submit.
NOTE

Obtain the Site ID from the customer.

Figure 5-5 Setting the site ID

Step 2 Click Next in the lower right corner.


Step 3 Set mobile data and click Submit.
● Network operator: Automatic/Others
● Access Point Name, Access Point Number, User Name and User Password:
Obtain the data from the customer.
NOTE

● When the public network is used and a 4G network is used for transmission, select
Automatic. Otherwise, select Others.
● Access Point Name, Access Point Number, User Name and User Password are displayed
when Network Operator is set to Others.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 143


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-6 Setting mobile data

Step 4 Click Next in the lower right corner.

Step 5 (Optional) Set the site IP address and click Submit.


NOTE

● Set IP address when IP networking is used.


● Obtain the IP address from the customer.

Figure 5-7 Setting IP information

Step 6 Click Next in the lower right corner.

Step 7 (Optional) Set NetEco communications parameters, and click Submit.


NOTE

● Set NetEco communications parameters when IP networking or wireless networking is


used.
● Obtain the NetEco IP address and port number from the customer.

Figure 5-8 Setting NetEco IP information

Step 8 Click Next in the lower right corner.

Step 9 (Optional) Set the scenario configuration file.


NOTE

The scenario configuration file is required for the customization project.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 144


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

1. Click Browse select a scenario configuration file, and click Upload.


2. Select Scene Config File and click Submit.

Figure 5-9 Setting the scenario configuration file

Step 10 Click Next in the lower right corner.


Step 11 Set device port parameters. Set port parameters for smart devices and click
Submit.
NOTE

Set this parameter based on the onsite device. The configuration file can be imported by
importing the port configuration file.

Figure 5-10 Setting port parameters

Step 12 Click Next in the lower right corner.


Step 13 Set the parameters for the mains, DG, fuel tank, DC power system, air conditioner
and battery, and click Submit.
NOTE

● Set the number of devices based on the site requirements.


● If lead-acid batteries are connected, you need to set battery parameters. If lithium
batteries are connected, the system automatically identifies the batteries.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 145


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-11 Setting parameters

Step 14 Click Next in the lower right corner.


Step 15 Set the detection channels such as iACSENSE and iDCMETER based on the actual
cable connections.

1. Press the button on the iACSENSE for 1s. The iACSENSE is displayed in
yellow on the WebUI.

Figure 5-12 Setting the iACSENSE detection channel

2. Allocate the iACSENSE to the corresponding detection channel according to


the site configuration.
3. Press the button on the iDCMETER for 1s. The iDCMETER is displayed in
yellow on the WebUI.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 146


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-13 Setting the iDCMETER detection channel

4. Allocate the iDCMETER to the corresponding detection channel according to


the site configuration.
5. Check whether the iACMETER detection channel matches the actual cable
connections. If no, configure the iACMETER detection channel based on the
actual cable connections.

Figure 5-14 Setting the iACMETER detection channel

Step 16 Click Next in the lower right corner.


Step 17 Set the parameters for the DC Power, Battery, DG, mains and air conditioner, and
click Submit.
NOTE

● Set the device parameters based on the site device specifications, quantity, and wiring
situation.
● The AC mains parameter is available only when the ACMB is configured at the site.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 147


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-15 Setting device parameters 1

Figure 5-16 Setting device parameters 2

NOTICE

● The lower limit of the fuel level measurement for the wireless magnetostrictive
fuel level sensor is 26 mm, and the upper limit is the maximum measurement
range minus 50 mm.
● The lower limit of the fuel level of the wireless submersible fuel level sensor is
20 mm. The upper limit is the maximum range.

Step 18 Click Next in the lower right corner.

Step 19 Set camera parameters.

Figure 5-17 Set camera parameters

Step 20 Click Next in the lower right corner, click Finish, and then click Confirm.

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 148


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

5.5 Setting Camera Passwords


You need to set passwords when you log in to cameras for the first time.

Camera Settings
Step 1 Remove the cable connected to the GE_1 port on the SCC800. Use a network cable
to connect the network port on the PC to the GE_1 port on the SMU.
Step 2 Enter https://SCC800 IP address: local port number of the camera (for example,
https://192.168.0.10:444) in the browser address box on the PC, and then press
Enter. The login page is displayed.
NOTE

● To query the local port number of a camera, log in to the WebUI, choose System
Settings > Network Config > NAT Mapping Configuration, and query the camera port
number based on the camera IP address. The port number starts with 4, for example,
444 or 445.
● To query the camera IP address, see Setting Deployment Wizard Parameters.

Step 3 Set the camera password.


NOTE

Set the camera password based on the customer's plan.

Figure 5-18 Setting a password for camera A

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 149


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-19 Setting a password for camera B

Step 4 Set passwords for other cameras.

----End

WebUI Settings
Step 1 Log in to the WebUI, choose System Settings > IP Camera, set the password in
ONVIF User Parameters to the password set in Camera Settings, and click
Submit.

Figure 5-20 Setting a camera password

Step 2 Reconnect the cable you removed to the GE_1 port on the SCC800.

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 150


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

5.6 Setting Motion Detection Alarm Parameters for


Outdoor Cameras
Setting Motion Detection Alarm Parameters for Outdoor Camera A

Figure 5-21 Outdoor camera A

Step 1 Log in to the IP camera.


NOTE

Preset user name: admin; password: password in 5.5 Setting Camera Passwords

Figure 5-22 IP camera login page

Step 2 Choose Configuration > Smart Event > Intrusion > Detection > Area Settings,
select Enable, draw a motion detection area, set Threshold, and click Save.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 151


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-23 Drawing a motion detection area

NOTE

● Draw a motion detection area as required and then right-click to save it.
● The time threshold is the intrusion duration that will trigger an alarm. The value range
is 0-10s. It is recommended that the threshold be set to 2s to avoid false alarms caused
by accidental factors.

Step 3 Choose Configuration > Smart Event > Intrusion Detection > Arming Schedule,
set time, and click Save.

Figure 5-24 Setting the arming time

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 152


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Step 4 Choose Configuration > Smart Event > Intrusion Detection > Linkage Method
and select Upload to FTP/Memory Card/....

Figure 5-25 Setting the linkage method

----End

Setting Motion Detection Alarm Parameters for Outdoor Camera B

Figure 5-26 Outdoor camera B

Step 1 Log in to the IP camera.


NOTE

Preset user name: admin; preset password: password in 5.5 Setting Camera Passwords

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 153


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-27 IP camera login page

Step 2 Choose Setting > Event > Smart Plan, select IVS, and click Save.

Figure 5-28 Setting a motion detection solution

Step 3 Choose Setting > Event > IVS, click , and set Rule Type to Intrusion.

Figure 5-29 Setting the type

Step 4 Click Draw Rule, draw a motion detection area, click the area that is not the
motion detection area, and save the drawing.

Figure 5-30 Drawing a motion detection area

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 154


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Step 5 In the Parameter Setup area, set the following parameters, and click Save.
● Period: Set as required.
● Appears: Select
● Cross: Select
● Direction: Set as required.
● Snapshot: Select

Figure 5-31 Period 1

Figure 5-32 Period 2

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 155


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-33 Parameter settings

NOTE

It is recommended that Appears be selected. If there are many site personnel, it is


recommended that you do not select this option to avoid generating a large number
of invalid snapshots.
Cross and Direction need to be used together. The direction can be set to Enters,
Exits, or Enter.
– Cross + Enters: When the camera detects that an object enters the detection area
in the direction indicated by the arrow in the drawn area, an alarm snapshot is
triggered, and multiple alarm snapshots are captured if there are multiple entries.
– Cross + Enter: When the camera detects that an object enters the detection area in
the direction indicated by the arrow in the drawn area and exits the area on the
other side of the direction, an alarm snapshot is triggered. If there are multiple
actions within the area (not touch the area boundary), no alarm snapshot is
triggered.
– Cross + Exits: When the camera detects that an object exits the detection area in
the direction opposite to the arrow in the drawn area, an alarm snapshot is
triggered, and multiple alarm snapshots are captured if there are multiple exits.
– Only Appears is selected: When the camera detects that an object crosses the area,
an alarm snapshot is triggered, and multiple alarm snapshots are captured if there
are multiple crossings.

----End

5.7 Setting Access Control Management Parameters

5.7.1 Creating Users


Step 1 Connect the reader cable to USB ports on a PC.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 156


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

NOTE

● The reader provides two USB ports. One is used to connect to a PC for communication
and power supply, and the other is used for auxiliary power supply.
● The reader is used to record the IC card and user fingerprint.

Figure 5-34 Connecting a reader

Step 2 Log in to the NetEco.


NOTE

Obtain the user name and password from the NetEco administrator.

Figure 5-35 Logging in to the NetEco

Step 3 Optional: Choose Security > Site Security > Access Control Management >
Global Settings. Touch to enter the secret key of the Bluetooth electronic key.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 157


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

NOTE

When using the Bluetooth electronic key for the first time, you need to enter the key.

Figure 5-36 Secret key

Step 4 Choose Security > Site Security > Access Control Management > User
Management.

Figure 5-37 User management

Step 5 Click Create, specify the user information, set card dispenser parameters, record a
fingerprint, and set other information.
NOTE

● For details about the rules, see the iManager NetEco product documentation of the
corresponding version.
● The access user created here can receive an unlock password only by email or SMS, and
has no permission to log in to the NetEco app. If unlocking using the NetEco app is
required, you can grant the access permission to a NetEco user.
An access user can unlock with a password.
A NetEco user (granted with access permission) can unlock using the NetEco app or a
password.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 158


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-38 Creating an access user

Figure 5-39 Setting card dispenser parameters

Figure 5-40 Recording a fingerprint

NOTE

● The password of the reader iWRITER is 8888888888.


● The port number is the number of the USB port connected to the iWRITER.

Step 6 Click the Access User Group tab and create an access user group as required.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 159


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

NOTE

● For details about the rules, see the iManager NetEco product documentation of the
corresponding version.
● The access user group list displays the Default Group, Untreated Group, and NetEco
groups by default. NetEco group users are system users.

Figure 5-41 Creating an access user group

Step 7 Choose Security > Site Security > Access Control Management > Settings >
Global Settings > Assign Approver and create an access user group as required.
NOTE

● Only NetEco users with the access control system approver or administrator role can be
added as approvers.
● Choose Security > System Security > User Management > Users, Click the user name.
On the Roles page, click Edit, add Access Control System Approver permission.

Figure 5-42 Creating an approver

----End

5.7.2 Enabling a Mobile Phone to Log In to the NetEco APP


Step 1 Log in to the NetEco, Choose Security > System Security > User Management >
Users. Click the user name.

Step 2 On the Basic Information page, click Edit, click Advanced Settings, select Allow
login on mobile terminals, click OK.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 160


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-43 Allow login on mobile terminals 1

Figure 5-44 Allow login on mobile terminals 2

Step 3 Log in to the NetEco APP.


NOTE

● Obtain the user name and password from the NetEco administrator.
● The IP address of the NetEco APP is the IP address of the NetEco.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 161


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-45 Log in to the NetEco APP

----End

5.7.3 Modifying the Equipment Room Door Lock Password

NOTICE

If the equipment room door lock iACCESS is in sleep state, you can open the cover
or press # (The lock cover has been lifted and the screen is off.) to wake up the
lock. After the lock is woken up, the main screen is displayed.

Step 1 On the main screen of the equipment room door lock, hold down # to access the
administrator login screen. Then, enter the password to access the administrator
background screen.
NOTE

● The preset password for administrator login is 123456.


● The administrator background screen allows you to set the background login password
and the door lock password.

Figure 5-46 Administrator login screen

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 162


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-47 Administrator background screen

Step 2 Press 1 to access the screen for changing the background login password. You can
change the background login password.
NOTE

The preset background login password is 123456.

Figure 5-48 Setting the background login password

Step 3 Press 2 to access the screen for changing the door lock password. You can change
the door lock password.
NOTE

The door lock password is used to open the door. The initial password of a new lock is
12345678. If a door lock is successfully bound to a site on the NetEco and the initial door
lock password has been cleared on the NetEco, log in to the NetEco and issue a password
to open the door.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 163


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-49 Change the door lock password

----End

5.7.4 Configuring an Outdoor Cabinet or Fence Door Lock


Initializing a Key
NOTE

● You can scan the QR code of the key to manually connect or initialize the key. This
section uses initialization by scanning the QR code as an example. If you need to

manually connect the key, tap in the lower right corner of the initialization screen.

● Before initializing the key, tap on the ikey screen to ensure that the screen is
on.

Figure 5-50 Initializing a key

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 164


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Initializing a Door Lock

Figure 5-51 Initializing a door lock

Binding a Door Lock to a Site


NOTE

You can perform binding (or unbinding) by scanning the QR code of the key or by manual

connection. You can tap in the lower right corner of the Bind Lock (or Unbind Lock)
screen to perform manual connection.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 165


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-52 Binding a door lock to a site

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 166


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Unbinding a Door Lock from a Site

Figure 5-53 Unbinding a door lock from a site

5.7.5 Application (NetEco WebUI)


Step 1 Choose Security > Site Security > Access Control Management > Site Visit
Application, and click Create to create an application.
NOTE

For details about the rules, see the iManager NetEco product documentation of the
corresponding version.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 167


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-54 Create application

Step 2 Choose Security > Site Security > Access Control Management > Site Visit
Application, click Waiting for my Approval, and approve the application.

Figure 5-55 Approving the application

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 168


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

5.7.6 Application (NetEco APP)

Creating a Site Visit Application

Figure 5-56 Creating a site visit application

Approving a Site Visit Application

Figure 5-57 Approving a site visit application

5.7.7 Unlocking (Equipment Room Door Lock)


The equipment room door lock supports the access control IC card, fingerprint
unlock, password unlock, key unlock, NetEco WebUI, and NetEco App remote
unlock.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 169


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

If you use the NetEco WebUI or mobile app to remotely unlock a door, after the
unlock command is issued, manually open the lock cover or press # (press # only
when the lock cover is opened and the screen is off) to open the door.

Obtain a password
Log in to the NetEco, Choose Security > Site Security >Access Control
Management > Lock Management, and click in the Operation column, fill in
related information for sending a dynamic password. Click Send.

Figure 5-58 obtain a password

Remote unlocking
● NetEco WebUI Remote unlocking

Log in to the NetEco, Choose Security > Site Security >Access Control
Management > Lock Management, and click in the Operation column, in
the displayed dialog box, enter the permission information required for door
opening. Click Send.

Figure 5-59 Remote unlocking

● NetEco APP Remote unlocking


Log in to the NetEco, Choose Access Control Management > Smart Lock.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 170


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Figure 5-60 Remote unlocking

5.7.8 Unlocking (Outdoor Cabinet or Fence Door Lock)


Unlocking by Phone

Figure 5-61 Unlocking by phone

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 171


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

Unlocking Using a Password

Figure 5-62 Bluetooth key

Table 5-1 Button description


Button Name Description

Left button Moves to the left to select a digit.

Right button Moves to the right to select a digit.

Confirm button ● Turns on the backlight of the Bluetooth


key.
● Saves a digit.

Procedure
Step 1 Obtain a password.
Log in to the NetEco, Choose Security > Site Security > Access Control
Management > Lock Management and obtain a password.

Figure 5-63 Obtaining a password

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 172


SCC800-S1 SmartSite Management System
Installation Guide 5 Commissioning

NOTE

NetEco APP Operation Path: Overview > Access Control Management > Unlocking by
Phone > Send Dynamic Code

Step 2 Press OK to turn on the backlight of the Bluetooth key.


Step 3 Enter the password (enter each digit in the password and press OK to save each
digit).
Step 4 After entering the correct password, insert the Bluetooth key into the keyhole.
When you hear a beep, turn the Bluetooth key for unlocking.
NOTE

Unlock within 10 minutes after entering the correct password. Otherwise, you need to enter
the password again.

----End

5.8 Setting NAT Gateway Parameters


This parameter needs to be set when a third-party intelligent device uses the
SNMP protocol to connect to the SCC800.

Procedure
Step 1 Choose System Settings > Network Config > Enable NAT Gateway on the
WebUI, setting Enable NAT Gateway to Yes and click Submit.

Figure 5-64 Setting Enable NAT Gateway parameters

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 173


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

A FAQ

A.1 How Do I Prepare RS485 Conversion Cables?


Figure A-1 Preparing a four-wire RS485 conversion cable

Figure A-2 Preparing a two-wire RS485 conversion cable

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 174


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

A.2 What Do I Do If WebUI Login on a PC Fails?


Procedure
Step 1 Check whether the PC runs Windows XP or later and whether the browser is
Internet Explorer 11 or later.
● If yes, go to the next step.
● If no, update the configuration.
Step 2 Check that the cable connection is correct.
NOTE

The GE_1 port on the SCC800 should be connected to the network port on the PC using a
cable.
● If yes, go to the next step.
● If no, reconnect the cable.
Step 3 Optional: Check whether the IP address setting for local connection on the PC is
correct.
NOTE

Address: 192.168.0.2; subnet mask: 255.255.255.0; gateway: 192.168.0.1


● If yes, go to the next step.
● If no, correct the settings.
Step 4 Open the browser and choose Tools > Internet Options.
Step 5 On the Connections tab, click LAN settings.
Step 6 Cancel proxy server settings.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 175


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

Figure A-3 Canceling proxy server settings

Step 7 Choose Tools > Internet Options > Safety.


Step 8 Click Internet and then Custom level.
NOTE

After you specify Internet security settings, click Local intranet and then Custom level to
specify security settings for the local Intranet.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 176


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

Figure A-4 Internet Explorer security

Step 9 Specify the security settings.


Enable the following functions:
● Initialize and script ActiveX controls not marked as safe for scripts
● Allow previously unused ActiveX controls to run without prompt
● Include local directory path when uploading files to a server
● Automatic prompting for file downloads

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 177


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

Figure A-5 Internet Explorer security setting 1

Figure A-6 Internet Explorer security setting 2

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 178


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

Figure A-7 Internet Explorer security setting 3

Step 10 Enter https://192.168.0.10 in the address box of the browser to log in to the
WebUI again. If the login still fails, contact Huawei Customer Service Center.
NOTE

Default IP address: 192.168.0.10

----End

A.3 How Do I Upgrade Software for SCC800?


Prerequisites
You have obtained the software upgrade package from Huawei technical support.

Procedure
Step 1 Choose Maintenance > Software Upgrade on the WebUI to install the SCC800
and BSP upgrade packages.
1. Click Select a file and select the BSP upgrade package (for example,
V200R002C00SPC025.tar.gz)
2. Click Upload. The Software Upgrade list displays the information about the
package and sub-packages. Select the package.
3. Click Select a file and select the SCC800 upgrade package (for example,
SCC800_S V100R003C00SPC001.tar.gz)
4. Click Upload. The Software Upgrade list displays the information about the
package and sub-packages. Select the package.
5. Click Local Upgrade.

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 179


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

Figure A-8 Software upgrade

NOTE

The SCC800 restarts after the upgrade is complete.

----End

A.4 How Do I Install the Protocol Package for


Intelligent Equipment?
Prerequisites
You have obtained the software upgrade package from Huawei technical support.

Procedure
Step 1 Optional: Choose Maintenance > Software Upgrade to install the protocol
package for intelligent equipment.
1. Click Select a file and select the protocol package for intelligent equipment
(for example, Lib_dev_fuel_huawei_ifuel_rs485_0.2.3_a7.tar.gz).
2. Click Upload. The Software Upgrade list displays the information about the
package and sub-packages. Select the package.
3. Click Local Upgrade.
NOTE

The SCC800 restarts after the upgrade is complete.

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 180


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

A.5 What Do I Do If the DC Power System Cannot


Connect to the SCC800?
Procedure
Step 1 Check whether the cable connection is correct.
NOTE

The RS485 cable is connected to the COM2/CAN port. Pins 1 and 4 of the network cable on
the SCC800 side are connected to RS485 A, and pins 2 and 5 are connected to RS485 B.
● If yes, go to the next step.
● If no, connect the cable correctly.

Step 2 Use a clamp meter to check whether the cable is normal.


● If yes, go to the next step.
● If no, reconnect the cable.

Step 3 Check whether the correct protocol is loaded.


● If yes, go to the next step.
● If no, load the correct protocol.

Step 4 Try to connect again. If the fault persists, contact Huawei Customer Service Center.

----End

A.6 What Do I Do If the iACMETER Reports a Wiring


Error Alarm?
Procedure
Step 1 Check whether the phase cables of the meter are correctly connected.
● If yes, go to the next step.
● If no, connect the phase cables correctly.

Step 2 Log in to the WebUI and check whether the cable connection settings are correct.
● If yes, go to the next step.
● If no, correct the settings.

Step 3 Check whether the iACMETER alarm is cleared. If the alarm persists, contact
Huawei Customer Service Center.

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 181


SCC800-S1 SmartSite Management System
Installation Guide A FAQ

A.7 What Do I Do If Electricity Data Reported by the


iACMETER Is Erroneous?
Procedure
Step 1 Check whether the phase cables of the meter are correctly connected.
● If yes, go to the next step.
● If no, connect the phase cables correctly.

Step 2 Log in to the WebUI and check whether the cable connection settings are correct.
● If yes, go to the next step.
● If no, correct the settings.

Step 3 Check whether the Hall effect sensor is in a reverse direction.


● If yes, connect it correctly.
● If no, go to the next step.

Step 4 Check the reported electricity data again. If the fault persists, contact Huawei
Customer Service Center.

----End

A.8 What Do I Do If the Wireless Communication


Signal of the iFUEL Is Poor?
Context
The wireless communication signal of the iFUEL is poor, and the communication is
interrupted.

Procedure
Step 1 Check whether obstacles exist between the iFUEL and the antenna of SCC800.
● If yes, relocate and re-network the iFUEL.
● If no, go to the next step.

Step 2 Check whether the communication distance is too long.


NOTE

The designed communication distance is 50 m.


● If the distance is more than 50 m, relocate the iFUEL in a position within 50 m
and re-network it.
● If the distance is within 50 m, contact Huawei Customer Service Center.

----End

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 182


SCC800-S1 SmartSite Management System
Installation Guide B Acronyms and Abbreviations

B Acronyms and Abbreviations

A
AC alternating current
ATS automatic transfer switch

D
DC direct current
DG diesel generator
DIN dry contact input

G
GE gigabit Ethernet

H
HTTPS Hypertext Transfer Protocol Secure

I
IP Internet Protocol

P
PDB power distribution box
PoE power over Ethernet

S
SCC site control center

U
UI user interface

Issue 01 (2020-08-20) Copyright © Huawei Technologies Co., Ltd. 183

You might also like