0 A User Group should review Is product fit for purpose and fit for use? User Insight Group
project and deliverables
4 System / Administration Design, build and systems management docs Support manager(s)
documentation distributed to 1st, 2nd and 3rd line support, and
filed
Page 1 of 7
IT Services
10 Infrastructure / server readiness New hardware tested and approved Systems & Operations Manager
16 Database / server management Ready and performance / volume tested. Web, Database and Middleware
Backup schedule confirmed and documented, Manager
and stored appropriately
17 Application readiness Application software ready to move to IT Services technical lead
production and support environments
Page 2 of 7
IT Services
18 Data readiness Data migration (including data cleansing) IT Services technical lead
ready
19 Service Desk readiness IT Services Service Desk aware of new service Service Desk Manager
and how it will be supported
20 Zone Team readiness Zone Teams aware of new service and their Zone Team Leaders (6)
role in how it will be supported
21 Service catalogue change Any changes to the Service Catalogue are Services Manager
readiness scheduled and ready.
24 Change Advisory Board Go Live Report including this checklist Change Advisory Board
presented to CAB
Page 3 of 7
IT Services
Operational readiness
25 IT readiness for operation IT Services ready for planned Go Live Date, Senior supplier
and capable of taking over their project
outputs into business as usual management
26 User readiness for operation Users are ready for planned Go live Date, and Senior User
capable of taking over their project outputs
into business as usual management
27 Known risks addressed No outstanding risks that are without Project Manager
mitigating action
30 Disaster Recovery The system has successfully been tested for Relevant Managers
recovery in case of disaster.
A written disaster recovery plan has been SMT
written for this service and added to the
disaster recovery main plan.
Page 4 of 7
IT Services
31 User readiness for cut-over Senior managers confirm that the Assistant Director or Account
(Business view) organisation is fully prepared and geared up Manager responsible
for cut-over activities:
- procedure/system training complete
- users confident with applying new
procedures
- super-users confident with new
system’s functionality and stability
- super-users prepared and cut-over
activity business resources in place (incl.
dual running if applicable)
- user-based systems administration staff
trained and prepared
- data management & archiving
controlled
- cut-over data reconciliation procedures
ready
Communications actioned/ready to go
32 Known business risks addressed Risk analysis updated. AD has confirmed no Assistant Director or Account
outstanding cut-over risks and that mitigation Manager
requirements are in place for all identified
risks.
Fall-back plans prepared and distributed
33 Post implementation process Monitoring and Business Support Assistant Director or Account
monitoring and support arrangements in place for post go-live period. Manager
Page 5 of 7
IT Services
Senior User
Project Manager
Project Executive
There may be additional checks specific to your project. If there are, include them below.
For example, is there a need for cross-checking with other Processes - Web& New Media, Estates, etc
Additional requirements
35
Page 6 of 7
IT Services
Guidelines
The purpose of the New Service Go Live Checklist is to ensure as far as is possible that the service is ready to go live before it does so. There are a
number of criteria which need to be satisfied before a PRINCE2 project should hand over a production service to the team which will operate it.
These are just a sample of the questions which should be asked and answered. For some projects the preference is to hold a meeting of all
interested parties, where these questions can be answered. For other projects, the project manager will seek individual meetings with each
authoriser. Documentation should be circulated before meetings so that it can be read thoroughly.
Andrew Dixon
Change Manager
Tuesday, 13 March 2012