You are on page 1of 1

DATA PROGRESS PROYEK

Proyek : Biogas PT Multi Persada Gatra Megah Lokasi : Muara Teweh - Kalteng
Dimensi Kolam : 159m x 69m x 11m Start : 04 Des 2018
Personil Team : Sobirin, Slamet, Syamrodin, Aris B

JENIS QUANTITY BOBOT AKUMULATIF PROGRESS FEB-MAR (m²)


NO JENIS PEKERJAAN
MATERIAL (m²) (%) 28/02/19 07/03/19 14/03/19 21/03/19
1 Wrapping Concrete Wheel HDS 100 1517,34 5,43 1517,34 1517,34 1517,34 1517,34
2 Skirt HDS 100 6523,02 23,36 6523,02 6523,02 6523,02 6523,02
3 HDPE Pocket Skirt HDS 100 29,36 0,11 29,36 29,36 29,36 29,36
Strapping for Gas
4 HDS 100 887,73 3,18 712,47 887,73 887,73 887,73
Collection Pipe
5 Baffle Curtain HDS 100 257,04 0,92 257,04 257,04 257,04 257,04
Baffle PS Floater
6 HDS 100 62,83 0,23 62,83 62,83 62,83 62,83
Wrapping
Pocket for Baffle
7 HDS 100 3,40 0,01 3,40 3,40 3,40 3,40
Concrete Block
Strapping for Baffle
8 HDS 100 31,92 0,11 31,92 31,92 31,92 31,92
Holder
9 Corner Strapping HDS 100 135,59 0,49 70,00 98,00 98,00 98,00
Float Construction
10 HDS 100 2278,71 8,16 0,00 0,00 1337,50 2278,71
Wrapping
11 Gas Vent HDS 100 29,48 0,11 29,48 29,48 29,48 29,48
12 Lidah Cover HDS 150 2366,06 8,47 1771,00 2366,06 2366,06 2366,06
13 Digester Cover HDS 150 13042,58 46,71 0,00 0,00 0,00 0,00
14 Scrubber Tank Linning HDS 150 539,99 1,93 0,00 0,00 0,00 0,00
15 Scrubber Cover HDS 150 145,00 0,52 0,00 0,00 0,00 0,00
16 Recirculation Tank HDS 150 73,25 0,26 0,00 0,00 0,00 0,00
TOTAL 27923,30 100,00 11007,86 11806,18 13143,68 14084,89
Akumulatif (%) 39,42 42,28 47,07 50,44

KURVA PROGRESS

120,00%

100,00%

80,00%

60,00%
50,44% Rencana
40,00%
42,28% 47,07% Realisasi
39,42%
20,00%

0,00%

CATATAN PENTING

- Kegiatan minggu ini fabikasi sarung floater dengan panjang 31m x 19 pcs dan pengisian styrofoam sebanyak 29 floater.

21/03/2019