TIME SCHEDULE ( REV-1 )

WASHING STATION + RELOCATION SERVICE WATER PIPE at 910 BUILDING


Preod : July 17 - 23, 2023

NO LEVEL BOBOT May-23 Jun-23 Jul-23


PRIODE 2-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 10-16 17-23 24-31

PREPARTION WORK 6,760 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52 0,52
CONCRETE FLOOR ACCESS INCLUDE WASHING PAD HEAVY
A.
EQUIPMENT

1 EARTH WORKS 13,993 2,00 2,00 2,00 2,00 2,00 2,00 2,00

2 PAVEMENT STRUCTURE WORKS 37,019 6,17 6,17 6,17 6,17 6,17 6,17

3 SOIL TEST 0,294 0,29

4 MECHANICAL, ELECTRICAL AND PLUMBING OF WASHING 6,037 1,01 1,01 1,01 1,01 1,01 1,01
PAD
5 OIL SEPARATOR 21,103 3,01 3,01 3,01 3,01 3,01 3,01 3,01

B STEEL FLOOR 13,080 3,27 3,27 3,27 3,27

C. RE-INSTAL SERVICE WATER PIPE at 910 BUILDING 1,713 0,43 0,43 0,43 0,43

TOTAL PROGRESS PLAN 100,0 0,52 2,52 2,52 2,52 2,52 2,81 6,54 13,14 11,14 14,41 14,41 13,98 12,97

COMULATIVE PROGRESS PLAN - 0,52 3,04 5,56 8,08 10,60 13,41 19,95 33,09 44,23 58,64 73,04 87,03 100,00

INPLEMENTATION PROGRESS 1,16 1,59 0,95 4,75 6,60 2,94 6,03 11,17 11,63 17,06 9,93 13,04

COMULATIVE INPLEMENTATION PROGRESS 1,16 2,75 3,70 8,45 15,05 17,99 24,02 35,19 46,82 63,89 73,82 86,86

DEVIATION 0,64 (0,29) (1,86) 0,37 4,46 4,58 4,07 2,10 2,60 5,25 0,77 -0,17

PT. SARANA STEEL ENGINEERING

PARNO