Professional Documents
Culture Documents
Civil Engineers
Geotechnical Engineering 156
July 2003 Issue GE3
Pages 147–158
Paper 13218
Received 13/12/2002
Accepted 07/04/2003
Keywords: Andy R. Pickles Siew Wei Lee Brian A. W. Norcliffe
excavation/geotechnical Director, Geotechnical Geotechnical Engineer, Geotechnical Engineer, Bachy
engineering/groundwater Consulting Group (Asia) Ltd, Geotechnical Consulting Soletanche Group Ltd, Hong
Hong Kong Group (Asia) Ltd, Hong Kong
Kong
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 147
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Northern
approach tunnel
Station
Southern
approach tunnel
GL 50
Sea
GL S1 Old reclamation
TWB
GL 50
: PZ
: VPZ
: INC
: MPX 100 m
: New reclamation area
C: Culvert
PS: Pumping station
TWB: Tsuen Wan Bypass
Fig. 3. Plan view of schematic details and instrumentation locations at Tsuen Wan site: P2,
piezometer; VP2, vibrating wire piezometer; INC, inclinometer; MPX, magnetic probe
extensometer
subsurface settlement due to pre-trenching and diaphragm wall Hong Kong marine environment, and although some variation
installation, and deep excavation and dewatering. is exhibited the following general features are apparent.
2. BACKGROUND INFORMATION (a) The new reclamation fill on the seaward side of the site is
vibro-compacted marine sand, which was hydraulically
2.1. Ground conditions placed. The soft marine clay that blankets the seabed in
The ground conditions at the site are shown in Fig. 4 Hong Kong was removed prior to placement of the fill.
(subsurface geological profiles along the landward (eastern) (b) The fill in the older reclamation comprises mostly general
diaphragm walls). The ground conditions are typical of the fill and is more variable than the newer marine sand fill.
148 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
contract) to 26 m where it joins the station. The level of the
Distance: m
underside of the base slab varies from 13 mPD to 17 mPD.
Location of seawall
The NAT is 315 m long. The tunnel width varies from 18 m at
0 100 200 300 400 500 600 700 800 900 1000
Ground level
the northern end (where it joins a tunnel from another
5
6 Tunnel
contract) to 28 m where it joins the station. The level of the
0 Fill Fill
Fill underside of the base slab varies from 13 mPD to 15 mPD.
⫺5 13
MD The tunnels were constructed between diaphragm walls. The
⫺10 13
All. All. MD All.
walls are 1·2 m thick where they form the permanent side walls
All.
⫺15 22
Level: mPD
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 149
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Construction of the diaphragm walls commenced in February
Before DWall After DWall: level controlled by
2000. Work continued on a number of fronts, and at any time completion pumping tests, dewatering and
diaphragm walling, dewatering and excavation were ongoing seasonal variation
at different areas within the site. 4.0
3.0
3. PIEZOMETRIC LEVEL RESPONSE AT DEPTH
2.0
level outside the excavation for the station and approach ⫺2.0
tunnels during dewatering. The piezometric level at depth was
⫺3.0
influenced by fluctuation of the tidal water level, seasonal
variation of water level in the fill, and the effects of ⫺4.0
Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
dewatering. The response of the piezometric level at depth was
also complicated in areas where the marine clay was left in
place, effectively forming an aquiclude between the upper fill
materials and the underlying granular alluvial deposits and Fig. 6. Daily piezometric level variation of VPZ 429 on
CDG. landward side
1.5 variations at the southern end of the SAT and the northern end
of the NAT. Fig. 7 shows that after completion of the
1.0
diaphragm walls most of the piezometers show no significant
0.5
reduction to the daily piezometric variation, as the piezometers
0.0 Variation
before DWall were still subject to seawater recharge. The piezometric
⫺0.5 reduction is denoted by the downward-pointing arrows in the
⫺1.0 figure.
⫺1.5
Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00
May 01
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
150 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
SAT Station NAT SAT Station NAT
2.2 0
Before DWall After DWall
Range of daily piezometric variation: m 2.0 ⫺1
1.8 ⫺2
1.6 ⫺3
Max. drawdown: m
1.4 ⫺4
1.2 ⫺5
1.0 ⫺6
0.8 ⫺7
0.6 ⫺8
0.4 ⫺9
0.0 ⫺11
0 100 200 300 400 500 600 700 800 900 1000
0
1000
100
200
300
400
500
600
700
800
900
Northward distance from gridline S1: m
Northward distance from gridline S1: m
1000
100
200
300
400
500
600
700
800
900
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 151
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Level of diaphragm wall toe: mPD Northward distance from gridline S1: m
0 ⫺5 ⫺10 ⫺15 ⫺20 ⫺25 ⫺30 ⫺35 ⫺40 ⫺45
1000
100
200
300
400
500
600
700
800
900
0
0
Seaward ⫺0
⫺1
Landward SAT Station NAT
⫺2 ⫺1
Best fit
⫺3 ⫺2 TWB
Max. drawdown: m
⫺4
Drawdown: m
⫺3
⫺5 SAT and
⫺4 station
⫺6
⫺7 ⫺5
⫺8 ⫺6
⫺9
⫺7
⫺10
VPZ 113 VPZ 436 VPZ 450 PZ 409 PZ 404 PZ 407
⫺11
shallower drawdown was measured at a deeper diaphragm wall the selected section. The period for diaphragm wall pre-
and vice versa. The length of seepage path behind the trenching or installation is illustrated as two periods: for
diaphragm wall might control the observed relationship. A instruments close to the wall the period for construction of the
deeper diaphragm wall represents a longer seepage path, and three panels closest to the instrument, and for instruments at
the drawdown caused by dewatering is expected to be less. The the furthest distance from the wall the period for construction
scatter in the data points could be caused by different distances of the panels within a 458 spread from the instrument location.
between the piezometers and the diaphragm walls, and by
ground condition variations. Figure 12 summarises the following instrumentation
monitoring data obtained at instruments located on the
Based on the data for the landward piezometers in Fig. 9 the seaward side of the station at gridline 50
average reduction of the piezometric level at rockhead was
approximately 5·5 m, 3·5 m and 7·5 m below the mean (a) the settlement recorded at deformation monitoring points
sea level for the SAT, station and NAT respectively. All these DMPs 594, 595, 596, 597 and 598, which are located at
piezometers were located within approximately 5 m of the back distances of 44 m, 34 m, 24 m, 14 m and 4 m respectively
face of the diaphragm walls in the zone where any flow from the seaward face of the diaphragm wall
beneath the wall is concentrated, and therefore a relatively (b) the movement of the top of inclinometer INC 452 and at a
large drawdown can be expected. It is therefore of interest to depth of approximately 11 m (i.e. 6 mPD), the level at
consider the drawdown at rockhead level at greater distances which the maximum wall movement was recorded (see
from the diaphragm wall. Fig. 3)
(c) the piezometric level recorded at VPZ 449, which was
Figure 11 compares the drawdown measured at the various located at rockhead level approximately 5 m behind the
standpipe piezometers (PZs, shown as open symbols) located at diaphragm wall (see Fig. 3).
rockhead close to the TWB with the adjacent VPZs (shown as
solid symbols) located close to the landward diaphragm wall The main stages of the construction sequence are also shown in
for the SAT and station. The horizontal axis of the figure Fig. 12 for this area of the site. Diaphragm walling was
shows the locations of the instruments along the SAT and the undertaken between the middle of February and the middle of
station. Fig. 3 shows the exact location of the instruments. The June 2000. The first pumping test was carried out between 14
drawdown at rockhead level adjacent to the landward and 21 July 2000, and the second test between 7 and 14
diaphragm wall was between 3·5 m and 6·0 m, and the September 2000. Excavation and dewatering for the station
equivalent drawdown close to the TWB was between 2·0 m was carried out between early August and early December
and 3·0 m. On average, the drawdown adjacent to the TWB 2000. The following points can be observed from the
was about 45% of the drawdown adjacent to the wall. instrumentation data presented.
However, the drawdown did not cause significant
displacements to the TWB. (a) A settlement of approximately 5 mm was recorded at all
the settlement points (DMPs) during the first week of
4. SETTLEMENT BEHAVIOUR AT STATION monitoring. This settlement was also observed at the
GRIDLINE GL 50 settlement points on the landward side of the station, and
Cross-section gridline 50 (see Fig. 3) has been selected to may indicate movement of the settlement benchmark
illustrate construction events affecting various instruments on rather than settlement of all monitoring points.
152 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
May 00
May 01
Aug 00
Sep 00
Nov 00
Dec 00
Aug 01
Sep 01
Nov 01
Feb 00
Mar 00
Feb 01
Mar 01
Jan 00
Jun 00
Jan 01
Jun 01
Apr 00
Oct 00
Apr 01
Oct 01
Jul 00
Jul 01
3p
45° spread
⫺5
2nd pump
1st pump
⫺10
⫺15
EXC
⫺0
⫺20
Vertical deformation: mm
⫺40
⫺120
P
50 Top
INC 452
11 m deep
40
Displacement: mm
30
EXC
20
P
10
0
3p
P P
2.5
45° spread VPZ 449
2.0
Piezometric level: mPD
1.5
1.0
0.5
0.0
⫺0.5
⫺1.0
⫺1.5
Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
Fig. 12. Monitoring data for various instruments on seaward side of station GL 50: 3p, 3 panels;
P, pumping test; EXC, excavation and dewatering
(b) Significant settlements were observed during installation of resulted in a small inward movement of the top of the
the diaphragm wall, varying from approximately 50 mm diaphragm wall (INC 452) by approximately 5 mm.
within approximately 5 m of the wall to approximately (d ) The second pumping test between 7 and 14 September
15 mm at a distance of approximately 35 m behind the 2000 resulted in a large and almost immediate movement
wall. The settlement was cumulative owing to construction of the diaphragm wall, varying from approximately 35 mm
of adjacent panels rather than a sudden drop due to the at the top of the wall to 10 mm at 11 m deep. This
construction of a single panel. pumping test was responsible for the maximum step in the
(c) The first pumping test between 14 July and 21 July 2000 wall displacement. The DMPs correspondingly showed
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 153
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
some increased settlements during and after the pumping commissioning of the dewatering wells in this station area.
tests. A pumping test carried out in the middle of July 2000
(e) It is reasonable to assume that settlement due to caused some piezometric drawdown. A more significant
dewatering was minimal in this area as a result of the drawdown was observed at the beginning of September
recharge by seawater. The ground settlement due to 2000, as a result of the second pumping test.
excavation of the station therefore varied from (d ) The piezometric level is maintained at a low level during
approximately 40 mm close to the back of the wall to excavation to the final level and then rises slightly during
approximately 12 mm at a distance of approximately 24 m December 2000, when the pumps are required only to
behind the wall. This settlement was associated with an maintain rather than lower the water level in the station
inward movement of the diaphragm wall of approximately box.
40 mm. (e) The ground outside the excavation commenced to settle as
( f ) Very little movement of the diaphragm wall was observed a result of both dewatering and excavation within the
at a depth of 11 m after the beginning of April 2001, station. In particular, the reduction of the water level
following completion of the track-level slab. In addition, during and after the second pumping test caused an
subsequent ground settlement of the new reclamation immediate settlement of approximately 5 mm close to the
outside the diaphragm wall was reduced to a very slow rate wall, reducing to about 2 mm adjacent to the TWB.
of approximately 0·5–1·0 mm/month. This continuing (f) The magnitude of settlement appears to be controlled by
settlement was probably due to ongoing creep within the both the excavation depth and the drawdown. The
reclamation fill. maximum settlement of 30 mm adjacent to the wall (DMP
(g) The piezometric level (VPZ 449) at rockhead remained tidal 601) and 15 mm adjacent to the TWB (DMP 605) coincides
throughout the construction sequence, as it was constantly with the maximum depth of excavation.
recharged by seawater. A small piezometric level reduction (g) The ground surface shows elastic rebound by
of less than 1 m was observed during August to October approximately 2 mm in response to the reduced level of
2000, possibly as a result of the pumping tests and drawdown between November 2000 and January 2001.
excavation-related dewatering. Following completion of (h) Minor additional settlement (, 5 mm) is observed close to
the station excavation the piezometric level returned to its the wall between February and May 2001, possibly as a
original groundwater level. result of consolidation. Ground settlement was stable after
May 2001.
Figure 13 summarises the following instrumentation (i) By the middle of October 2001 the piezometric level at
monitoring data obtained at instruments located on the rockhead had increased and was only approximately 2 m
landward side of the station at gridline 50 below the mean sea level.
(a) the settlement recorded at DMPs 601, 602, 603, 604 and 5. SUBSURFACE SETTLEMENT
605, which were located at distances of 4 m, 14 m, 24 m, Two magnetic probe extensometers have been selected to
31 m and 41 m from the landward face of the diaphragm investigate the subsurface settlement behaviour for the new
wall respectively and old reclamation on the landward side of the site. They are
(b) the piezometric level recorded at VPZ 450 (see Fig. 3), MPX 107, which was located within the new reclamation of the
which was located at rockhead level approximately 3 m SAT, and MPX 415, which was located within the old
behind the diaphragm wall (unfortunately the inclinometer reclamation of the station. The locations of both the MPXs are
in the diaphragm wall at this location was damaged during shown in Fig. 3.
excavation).
Figure 14 shows the settlement of the magnets of MPX 107
The main stages of the construction sequence are also shown in during diaphragm wall construction, and SAT excavation and
Fig. 13 for this area of the site. The following points can be strutting. Magnet M1 is located nearest to the ground surface
observed in the data. and magnet M10 is located in rock. Fig. 15 shows the ground
conditions of the borehole of MPX 107, SPT N profile, levels of
(a) A settlement of approximately 4 mm was recorded at all the magnets within the borehole, and the normalised settlement
the settlement points during the first week of monitoring. within an individual soil layer, which is measured by two
This settlement was also observed at the settlement points consecutive magnets. The normalised settlement is the ratio of
on the seaward side of the station, and may indicate settlement or compression within a soil layer (difference in
movement of the settlement benchmark rather than settlement between two consecutive magnets) over the
settlement of all the monitoring points. thickness of the layer. The units are millimetres per metre
(b) Relatively small settlements were observed during (mm/m), and the ‘’ sign represents compression of the soil
installation of the diaphragm wall, varying from layers. The normalised settlement is divided into the settlement
approximately 10 mm within approximately 5 m of the measured during diaphragm walling and pre-trenching
wall to approximately 5 mm at a distance of 40 m behind (denoted by ‘DWall’) and during tunnel excavation and
the wall. Most of this settlement occurred during strutting (denoted by ‘EXC’) (see Fig. 14). The total settlement,
construction of the first panel, but small additional which is summation of the settlement measured during both
settlements can be seen during construction of the adjacent the DWall and EXC, is denoted by ‘Total’.
panels.
(c) The piezometric level (VPZ 450) at rockhead drops slowly It can be seen from Fig. 15 that a significant thickness of
during both June and July 2000, presumably in response to cobbles and boulders from the former seawall was encountered
154 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
May 00
May 01
Aug 00
Sep 00
Nov 00
Dec 00
Aug 01
Sep 01
Nov 01
Feb 00
Mar 00
Feb 01
Mar 01
Jan 00
Jun 00
Jan 01
Jun 01
Apr 00
Oct 00
Apr 01
Oct 01
Jul 00
Jul 01
3p
prop
⫺0
⫺5
1st pump
2nd pump
⫺10
⫺15
3p
EXC
⫺0
45° spread P P
⫺5
⫺10
Vertical deformation: mm
⫺15
DMP
⫺20
601
⫺25 602
⫺30 603
604
⫺35
605
⫺40
3p
1
P
0
⫺1
⫺2
⫺3
⫺4
⫺5
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
Feb 00
Mar 00
Jan 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Fig. 13. Monitoring data for various instruments on landward side of station GL50: 3p, 3 panels;
P, pumping test; EXC, excavation and dewatering
between levels 3·5 mPD and 11·5 mPD. Pre-trenching was the piezometric drawdown in the CDG layer during dewatering
carried out between these levels. The column ‘DWall’ in Fig. 15 for the tunnel excavation. The piezometric drawdown could
shows that after diaphragm walling and pre-trenching the layer have caused some consolidation settlement in the CDG layer.
of cobbles and boulders showed the largest normalised
settlement, of between 3·6 mm/m and 4·4 mm/m. The column Figure 16 shows data for subsurface settlement at MPX 415
‘EXC’ shows that, in general, the normalised settlement located within the old reclamation of the station. The MPX
increases with depth for the settlement induced by the station data were missing from early May to early July 2000, as access
excavation and strutting. The column ‘Total’ shows that the to the instrument was obstructed. The time periods for
majority of the total settlement occurred in the cobble and diaphragm walling (DWall) and station excavation and
boulder layer, followed by the underlying CDG and then the fill strutting (EXC) are also shown in the figure. No former seawall
layer above, which is predominantly vibro-compacted medium was encountered at the MPX location, although there was a
dense sand. The reasons why the CDG layer shows a larger thin layer of fill (cobbles) between levels 4·0 mPD and
magnitude of settlement than the fill (medium dense sand) 6·0 mPD (see Fig. 17). The column ‘DWall’ in Fig. 17 shows
layer could be the structure of the extremely weak CDG silt and that, after diaphragm walling, the alluvium layer showed the
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 155
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
0
⫺10
⫺20
⫺30
Vertical deformation: mm
⫺40
⫺50
⫺60
Diaphragm
walling and
⫺70 pre-trenching
(DWall)
Tunnel
⫺80 excavation and
strutting (EXC)
⫺90
Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
M1 M2 M3 M4 M5 M6 M7
M8 M9 M10
Fig. 14. Subsurface settlement data for MPX 107 located in new reclamation
156 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
0
⫺5
⫺10
⫺25
⫺30
Station
excavation and
⫺35 strutting
(EXC)
⫺40
Mar 00
Mar 01
Jan 00
Feb 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
M1 M2 M3 M4 M5 M6 M7
Fig. 16. Subsurface settlement data for MPX 415 located in the old reclamation
6. CONCLUSIONS
SPT N The completion of the diaphragm walls effectively cut off the
0 5 10 15 20 hydraulic connection between the landward piezometers and
4
Wash boring the sea, as evidenced by the daily variation in piezometric level
M1 DWall EXC Total
2 being significantly reduced. As expected, the seaward
Fill (firm
clay) ⫺0.2 ⫺0.2 ⫺0.4 piezometers showed negligible changes in daily piezometric
0 M2 level variation after completion of the diaphragm walls because
Fill (firm
⫺2 silt) seawater recharge was unaffected.
⫺0.7 ⫺0.8 ⫺1.5
Fill (sand) M3
⫺4
Dewatering for excavation of the station and tunnels resulted
Fill (cobbles) ⫺0.2 ⫺1.7 ⫺1.9
Level: mPD
Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 157
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
pre-trenching and diaphragm walling. After pumping tests REFERENCES
there was a sharp increase in the ground settlement and 1. GAMMON J., HILL S., MALKA D. and CARAYOL S. Real time
displacement of the diaphragm wall. It is believed that the monitoring of highway viaduct close to deep excavation.
settlement induced during the deep excavation and dewatering Geotechnical Deformations and Movements: Proceedings of
was predominantly caused by the wall deflection. During the 21st Annual Seminar of Geotechnical Division Hong
excavation dewatering, the groundwater drawdown on the Kong Institution of Engineers, Hong Kong, 2001, 217–225.
seaward side was less than that on the landward side, as the 2. NORCLIFFE B. A. W., PICKLES A. R. and LEE S. W. The use of
seawater recharged the seaward area. recharge wells to mitigate ground settlement on KCRC
contract CC300 Tsuen Wan Station and approach tunnels.
The MPX data show that the pre-trenching in the cobbles Geotechnical Aspects of Mass Transportation Systems:
and boulders layer resulted in large settlements. The Proceedings of the 22nd Annual Seminar of Geotechnical
reduced settlement in the CDG layer on the landward side Division Hong Kong Institution of Engineers, Hong Kong,
of the station (as compared with settlement on the 2002, 123–130.
landward side of the SAT) is attributed to the reduced 3. THORLEY C. B. B. and FORTH R. A. Settlement due to
piezometric drawdown, which in turn induced less diaphragm wall construction in reclaimed land in Hong
consolidation settlement. Kong. Journal of Geotechnical and Geoenvironmental
Engineering, ASCE, 2002, 128, No. 6, 473–478.
7. ACKNOWLEDGEMENTS 4. COWLAND J. W. and THORLEY C. B. B. Ground and building
The authors express their gratitude to KCRC for their kind settlement associated with adjacent slurry trench
permission to publish this paper. Contributions from the site excavation. Proceedings of the 3rd International Conference
staff, and in particular Ir Jonathan Gammon, are highly on Ground Movements and Structures (GEDDES J. D. (ed.)).
appreciated. Pentech Press, London, 1985, pp. 723–738.
Please email, fax or post your discussion contributions to the secretary by 1 January 2004: email: mary.henderson@ice.org.uk;
fax: þ44 (0)20 7799 1325; or post to Mary Henderson, Journals Department, Institution of Civil Engineers, 1–7 Great George Street,
London SW1P 3AA.
158 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.
Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.