You are on page 1of 12

Proceedings of the Institution of

Civil Engineers
Geotechnical Engineering 156
July 2003 Issue GE3
Pages 147–158
Paper 13218
Received 13/12/2002
Accepted 07/04/2003
Keywords: Andy R. Pickles Siew Wei Lee Brian A. W. Norcliffe
excavation/geotechnical Director, Geotechnical Geotechnical Engineer, Geotechnical Engineer, Bachy
engineering/groundwater Consulting Group (Asia) Ltd, Geotechnical Consulting Soletanche Group Ltd, Hong
Hong Kong Group (Asia) Ltd, Hong Kong
Kong

Groundwater and ground movement around deep excavation


A. R. Pickles, S. W. Lee and B. A. W. Norcliffe

The Tsuen Wan West Station of Kowloon Canton


Railway Corporation was constructed on both previously Mainland China

and recently reclaimed land. The project comprised


approximately 600 m of cut-and-cover approach tunnels
and a 400 m long station structure constructed in a 20 m
New Territories
deep excavation. Extensive instrumentation monitoring N
was carried out to monitor groundwater levels, ground
movements and displacement of adjacent structures
KCRC
during the course of construction. This paper presents West Rail
background information on the construction site and the
monitoring results. It was found that the groundwater Tsuen Wan
regime on the seaward side was strongly influenced by West Station

tidal movements throughout the monitoring period,


whereas the landward groundwater regime showed a
HK New Kowloon
diminished tidal influence soon after construction of the Airport
diaphragm wall. Rock grouting carried out beneath the
diaphragm wall was effective in mitigating drawdown of HK Island
piezometric level outside the wall. The magnitude of the
drawdown was found to be a function of diaphragm wall
depth. Data on ground settlement, diaphragm wall Fig. 1. Tsuen Wan West Station of KCRC West Rail project,
Hong Kong
deflection and groundwater were interactively discussed
as the construction progressed. Finally subsurface
settlement data were reviewed to highlight the adverse
effect of pre-trenching for diaphragm wall construction
and excessive drawdown in the weak rock layer. soils (marine deposit), the formation of seawalls, and hydraulic
placement of sand fill, which was vibro-compacted.
1. INTRODUCTION
The Kowloon Canton Railway Corporation (KCRC) has Various existing structures are located adjacent to the station
undertaken construction of a railway linking the western area and tunnels. These include: the elevated four-lane Tsuen Wan
of the New Territories to Kowloon, known as ‘West Rail’ (see Bypass (TWB), which runs parallel to the site at a distance of
Fig. 1). Contract CC-300 for the construction of Tsuen Wan approximately 40 m from the landward diaphragm wall; the
West Station comprised approximately 600 m of cut-and-cover Tsuen Wan central salt water pumping station adjacent to the
approach tunnels and a 400 m long station structure NAT; and gas and water mains and culverts that cross over
constructed in a deep excavation (Fig. 2). Construction of the the site (Fig. 3). Dewatering and excavation for the station,
northern and southern approach tunnels and station required tunnels and culvert diversions inevitably resulted in ground
excavation to a depth of up to approximately 20 m below movements that had some influence on these adjacent
ground level within a concrete diaphragm cut-off wall. structures and utilities. In anticipation of these movements, a
comprehensive set of geotechnical instrumentation was
The station and the southern approach tunnel (SAT) are installed to monitor the variation of groundwater levels,
1
constructed partly on previously reclaimed land (old ground movements and displacement of adjacent structures.
reclamation) and partly on new reclamation (Fig. 3). The
northern approach tunnel (NAT) is constructed entirely on This paper presents a review of the groundwater data in order
previously reclaimed land. The old reclamation was constructed to establish the effectiveness of the cut-off wall in mitigating
more than ten years ago. Construction of the new reclamation drawdown outside the diaphragm wall. Movements of the
commenced in March 1999 and was completed in October ground surface and diaphragm wall at a particular section of
2000. The reclamation works involved dredging of soft seabed the station will be discussed. Finally the paper reviews the

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 147

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Northern
approach tunnel

Station

Boundary of new Tsuen Wan


reclamation Bypass

Southern
approach tunnel

Fig. 2. Aerial photograph of Tsuen Wan West Station construction site

Southern approach tunnel (SAT) Station Northern approach tunnel (NAT)

GL 50
Sea

New reclamation 428 449 Sea


452
113 107
C 409 C 415 429 436 450 PS
404 407 C

GL S1 Old reclamation
TWB
GL 50
: PZ
: VPZ
: INC
: MPX 100 m
: New reclamation area
C: Culvert
PS: Pumping station
TWB: Tsuen Wan Bypass

Fig. 3. Plan view of schematic details and instrumentation locations at Tsuen Wan site: P2,
piezometer; VP2, vibrating wire piezometer; INC, inclinometer; MPX, magnetic probe
extensometer

subsurface settlement due to pre-trenching and diaphragm wall Hong Kong marine environment, and although some variation
installation, and deep excavation and dewatering. is exhibited the following general features are apparent.

2. BACKGROUND INFORMATION (a) The new reclamation fill on the seaward side of the site is
vibro-compacted marine sand, which was hydraulically
2.1. Ground conditions placed. The soft marine clay that blankets the seabed in
The ground conditions at the site are shown in Fig. 4 Hong Kong was removed prior to placement of the fill.
(subsurface geological profiles along the landward (eastern) (b) The fill in the older reclamation comprises mostly general
diaphragm walls). The ground conditions are typical of the fill and is more variable than the newer marine sand fill.

148 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
contract) to 26 m where it joins the station. The level of the
Distance: m
underside of the base slab varies from 13 mPD to 17 mPD.
Location of seawall
The NAT is 315 m long. The tunnel width varies from 18 m at
0 100 200 300 400 500 600 700 800 900 1000
Ground level
the northern end (where it joins a tunnel from another
5
6 Tunnel
contract) to 28 m where it joins the station. The level of the
0 Fill Fill
Fill underside of the base slab varies from 13 mPD to 15 mPD.
⫺5 13
MD The tunnels were constructed between diaphragm walls. The
⫺10 13
All. All. MD All.
walls are 1·2 m thick where they form the permanent side walls
All.
⫺15 22
Level: mPD

CDG for the tunnels within approximately 50 m of the station,


Rock CDG
⫺20 CDG 19 Rock designated as the transition tunnels. Elsewhere the diaphragm
⫺25 65 walls are 0·8 m thick and are essentially temporary works,
⫺30
although they have been left in place after completion of the
Rock 97
structure. The box of the tunnels within the temporary
⫺35 6: SPT N
diaphragm walls is a ‘floating’ structure, which was constructed
⫺40
below water table but not anchored down to rockhead. The
⫺45 SAT Station NAT
maximum diaphragm wall panel length was 6·4 m. Within the
tunnels five levels of temporary props were generally required.
Fig. 4. Geological profiles of Tsuen Wan West Station: MD,
marine deposit; All., alluvium; CDG, completely decomposed
granodiorite. Marine deposit was fully dredged during new 2.3. Construction method
reclamation This paper concerns the construction stage up to October 2001,
when the main structural elements for the station and tunnels
were essentially complete. Pre-trenching was required prior to
General fill is a non-cohesive material with maximum diaphragm wall construction in areas where the fill and
particle size less than 200 mm. As a result of the relatively alluvium contained significant cobble and boulder layers. The
loose specification requirements general fill can have a pre-trenching comprised excavation of the panel to the base of
very variable composition but typically contains a large the cobble and boulder layer using bentonite/cement slurry to
proportion of completely decomposed rock. Although most temporarily support the excavation. The slurry was then left to
of the old fill is granular, silty and clayey material was set prior to re-excavation for construction of the wall.
often encountered. A significant thickness of boulders or
rockfill was encountered, particularly in the area of former Where the diaphragm wall was founded on rock, contact
seawalls. grouting was used both to improve the bearing capacity and
(c) The ground level is typically at 4·0 to 5·0 mPD and the reduce the local permeability of the rock. The contact grouting
base of the fill is typically at a level between 8 mPD and comprised cement grouting to a depth of approximately 1 m
10 mPD. The term ‘PD’ refers to principal datum, and below the toe of the wall. In addition, rock grouting using a
0 mPD is 1·3 m above mean sea level in Hong Kong. In the micro-fine cement to a depth of 5 m below the toe of the wall
area of the station and northern approach tunnel the older was carried out below the landward station diaphragm wall.
reclamation fill is generally underlain by approximately This was adopted in order to reduce the permeability of the
2–5 m of soft marine clay. rock and thereby reduce the potential for drawdown of the
(d ) The alluvium that underlies the fill or marine deposits is piezometric level outside the station on the landward side of
generally granular and has a thickness typically in the the site. There was no concern over the drawdown on the
range 2–5 m. Alluvial clay has been encountered at some seaward side of the site, as there were no sensitive structures
locations. The base of the alluvium is typically at a depth on the seaward side and the groundwater regime was
of 12 mPD to 15 mPD. continually recharged by the sea.
(e) A variable thickness of completely decomposed
granodiorite (CDG) underlies the alluvium. The level of the For construction purposes the station and tunnels were divided
rockhead at the site is extremely variable, ranging from into shorter sections either by bentonite cement slurry cut-off
approximately 12 mPD to 40 mPD. The rock underlying walls or by sheet pile walls with bottom grouting, or by a
the site is highly fractured in some areas. combination of slurry walls and sheet piles. Prior to excavation
within any section of the approach tunnels or station a series
2.2. Description of structure design of pumping tests were carried out to demonstrate the
The station is 390 m long and 42 m wide. The level of the effectiveness of the water cut-off around the proposed
underside of the base slab is 12·5 mPD. The station was excavation.
constructed between 1·2 m thick diaphragm walls, which form
the permanent side walls. The diaphragm walls are load Excavation-related dewatering was controlled to ensure that at
bearing and are founded on the underlying bedrock. The any time the water level was approximately 1 m below the
station is a two-level structure with the base slab, concourse- excavation level. In order to prevent flotation of the structure
level slab and ground-level roof slab forming the permanent the dewatering had to be maintained until the structure and
props between the walls. backfilling to ground surface were complete. The station and
tunnels were constructed ‘bottom up’, requiring full-depth
The SAT is 285 m long. The tunnel width varies from 21 m at excavation prior to casting the base slab as the lowest-level
the southern end (where it joins a tunnel from another permanent strut.

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 149

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Construction of the diaphragm walls commenced in February
Before DWall After DWall: level controlled by
2000. Work continued on a number of fronts, and at any time completion pumping tests, dewatering and
diaphragm walling, dewatering and excavation were ongoing seasonal variation
at different areas within the site. 4.0

3.0
3. PIEZOMETRIC LEVEL RESPONSE AT DEPTH
2.0

Piezometric level: mPD


Two rows of vibrating wire piezometers (VPZs) were installed
within approximately 5 m of the outside face of the seaward 1.0
and landward diaphragm walls, with their tips located
0.0 Variation after
approximately 0·3 m above the rockhead. The primary function Variation DWall
of the VPZs was to monitor the drawdown of the piezometric ⫺1.0 before DWall

level outside the excavation for the station and approach ⫺2.0
tunnels during dewatering. The piezometric level at depth was
⫺3.0
influenced by fluctuation of the tidal water level, seasonal
variation of water level in the fill, and the effects of ⫺4.0

Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
dewatering. The response of the piezometric level at depth was
also complicated in areas where the marine clay was left in
place, effectively forming an aquiclude between the upper fill
materials and the underlying granular alluvial deposits and Fig. 6. Daily piezometric level variation of VPZ 429 on
CDG. landward side

3.1. Response of the piezometric level to tidal


fluctuation
Most of the VPZs show some piezometric level fluctuation due The smaller daily level fluctuation at VPZ 429 is attributed
to tidal effects. The magnitude of the response is a function of to the fact that this piezometer was located approximately
the distance of the piezometer from the seawall, the state of the 50 m further from the sea than VPZ 428.
hydraulic connection through the ground between the sea and (b) The diaphragm walls in this area were completed around
the piezometer tip, and the presence of the diaphragm walls. To the beginning of August 2000, and it can be seen that the
illustrate this it is worth comparing the data recorded at VPZ daily level variation at VPZ 429 immediately decreased to
428 (5 m) and VPZ 429 (+6 m), which are on opposite sides approximately 0·3 m. This demonstrates the effectiveness of
of the station. The ‘’ and ‘+’ symbols in the brackets indicate the diaphragm walls in insulating against tidal effects. The
the seaward and landward offset from the diaphragm wall daily level variation at VPZ 428 remained relatively
respectively. The locations of VPZ 428 and VPZ 429 are shown unchanged, however, as it was still subject to seawater
in Fig. 3 and the data obtained from them are shown in Figs 5 recharge.
and 6 respectively. The following points can be observed. (c) After completion of the diaphragm walls the piezometric
levels of both the VPZs were lowered owing to pumping
(a) Prior to construction of the diaphragm wall the daily tests, excavation-related dewatering and seasonal or
piezometric level response at VPZ 428 varied by rainfall variation. These issues will be discussed later.
approximately 1·5 m, whereas the daily piezometric level
response at VPZ 429 varied by only approximately 1·2 m. The typical ranges of daily piezometric level variation for the
seaward and landward piezometers are shown in Figs 7 and 8
respectively. The horizontal axis of the figures shows the
locations of the piezometers along the station and tunnels. The
Before DWall After DWall: level controlled by pumping solid and open symbols are for data before and after
completion tests, dewatering and seasonal variation
completion of the adjacent diaphragm wall respectively. It can
3.0 be seen from Fig. 7 that the maximum daily level variation on
Variation after
2.5 the seaward side of the site occurred towards the north end of
DWall
2.0 the station box and the adjacent NAT, with much smaller
Piezometric level: mPD

1.5 variations at the southern end of the SAT and the northern end
of the NAT. Fig. 7 shows that after completion of the
1.0
diaphragm walls most of the piezometers show no significant
0.5
reduction to the daily piezometric variation, as the piezometers
0.0 Variation
before DWall were still subject to seawater recharge. The piezometric
⫺0.5 reduction is denoted by the downward-pointing arrows in the
⫺1.0 figure.
⫺1.5
Jan 00
Feb 00
Mar 00
Apr 00
May 00
Jun 00
Jul 00

May 01
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00
Jan 01
Feb 01
Mar 01
Apr 01

Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01

Figure 8 compares the landward daily fluctuation of


piezometric level before and after completion of the diaphragm
walls. The daily level variation on the landward side prior to
construction of the diaphragm walls was generally less than
Fig. 5. Daily piezometric level variation of VPZ 428 on
seaward side that measured on the seaward side. Upon completion of the
diaphragm walls the daily level variation on the landward side

150 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
SAT Station NAT SAT Station NAT
2.2 0
Before DWall After DWall
Range of daily piezometric variation: m 2.0 ⫺1
1.8 ⫺2
1.6 ⫺3

Max. drawdown: m
1.4 ⫺4

1.2 ⫺5

1.0 ⫺6

0.8 ⫺7

0.6 ⫺8

0.4 ⫺9

0.2 ⫺10 Seaward Landward

0.0 ⫺11
0 100 200 300 400 500 600 700 800 900 1000
0

1000
100

200

300

400

500

600

700

800

900
Northward distance from gridline S1: m
Northward distance from gridline S1: m

Fig. 9. Maximum drawdown outside the seaward and


Fig. 7. Range of piezometric level variation for seaward landward diaphragm walls, caused by dewatering
piezometers, before and after completion of diaphragm walls

In reviewing the results shown in Fig. 9 it is worth noting that


contact grouting was only carried out below the landward
SAT Station NAT
diaphragm walls for the station and NAT, and rock grouting
2.2
Before DWall After DWall
was only carried out below the landward station diaphragm
2.0
Range of daily piezometric variation: m

walls. Based on Fig. 9 the following conclusions can be drawn.


1.8
1.6 (a) The seaward piezometers adjacent to the SAT recorded
1.4 drawdown between 4 m and 8 m, the station between
1.2 0·0 m and 4·5 m and the NAT between 0·3 m and
1.0 7·0 m.
0.8 (b) The landward piezometers adjacent to the SAT recorded
0.6 drawdown between 2·5 m and 10 m, the station
0.4
between 2·5 m and 5·0 m and the NAT between 4·0 m
and 10·0 m.
0.2
(c) The drawdown on the seaward side was slightly less than
0.0
that on the landward side. This was due to seawater
0

1000
100

200

300

400

500

600

700

800

900

recharge experienced by the seaward piezometers.


Northward distance from gridline S1: m
(d ) The average drawdown at rockhead level was less at the
station than at the NAT and SAT. This gives an indication
Fig. 8. Range of piezometric level variation for landward of the benefit of the rock grouting carried out beneath the
piezometers, before and after completion of diaphragm walls
landward station walls. Artificial recharge of groundwater
was adopted at the north end of the station box, and this
2
had an influence on the results in this area. Norcliffe et al.
discussed the use of recharge wells in mitigating ground
was significantly reduced but not entirely eliminated. The walls settlement on this project.
largely isolated the landward piezometers from the tidal effect (e) Although there was no rock grouting on the seaward side
of seawater. of the station, the drawdown was relatively minor owing to
the rapid recharge of groundwater from the sea, indicating
3.2. Piezometric level at rockhead due to dewatering a relatively high permeability path in this area of the site.
The piezometric level at rockhead responded to the dewatering ( f ) The contact grouting beneath the NAT appears to have had
carried out for excavation of the station and tunnels. The only a relatively small effect on the magnitude of the
magnitude of the reduction was a function of various factors, drawdown when compared with the results for the SAT.
including the level of drawdown and pumping rate from within
the excavation, the localised ground conditions, and the extent Figure 10 plots the maximum piezometric drawdown against
and effectiveness of the contact and rock grouting below the the level of the diaphragm wall toe. The diaphragm walls were
toe of the diaphragm wall. The maximum drawdown recorded founded on bedrock. The figure excludes the data points from
at all the rockhead piezometers adjacent to both the seaward the landward station area that was subject to rock grouting
and landward diaphragm walls is summarised in Fig. 9. The ‘’ beneath the diaphragm walls. It appears that there is a
sign on the vertical axis of the figure represents drawdown correlation between the drawdown and the depth of the
below the mean sea water level. diaphragm wall, which is controlled by rockhead level. A

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 151

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Level of diaphragm wall toe: mPD Northward distance from gridline S1: m
0 ⫺5 ⫺10 ⫺15 ⫺20 ⫺25 ⫺30 ⫺35 ⫺40 ⫺45

1000
100

200

300

400

500

600

700

800

900
0

0
Seaward ⫺0
⫺1
Landward SAT Station NAT
⫺2 ⫺1
Best fit
⫺3 ⫺2 TWB
Max. drawdown: m

⫺4

Drawdown: m
⫺3
⫺5 SAT and
⫺4 station
⫺6

⫺7 ⫺5

⫺8 ⫺6
⫺9
⫺7
⫺10
VPZ 113 VPZ 436 VPZ 450 PZ 409 PZ 404 PZ 407
⫺11

Fig. 11. Comparison of maximum drawdown between VPZs


Fig. 10. Maximum drawdown as a function of diaphragm wall close to diaphragm walls of SAT and station and those close
depth, which is related to rockhead level to TWB

shallower drawdown was measured at a deeper diaphragm wall the selected section. The period for diaphragm wall pre-
and vice versa. The length of seepage path behind the trenching or installation is illustrated as two periods: for
diaphragm wall might control the observed relationship. A instruments close to the wall the period for construction of the
deeper diaphragm wall represents a longer seepage path, and three panels closest to the instrument, and for instruments at
the drawdown caused by dewatering is expected to be less. The the furthest distance from the wall the period for construction
scatter in the data points could be caused by different distances of the panels within a 458 spread from the instrument location.
between the piezometers and the diaphragm walls, and by
ground condition variations. Figure 12 summarises the following instrumentation
monitoring data obtained at instruments located on the
Based on the data for the landward piezometers in Fig. 9 the seaward side of the station at gridline 50
average reduction of the piezometric level at rockhead was
approximately 5·5 m, 3·5 m and 7·5 m below the mean (a) the settlement recorded at deformation monitoring points
sea level for the SAT, station and NAT respectively. All these DMPs 594, 595, 596, 597 and 598, which are located at
piezometers were located within approximately 5 m of the back distances of 44 m, 34 m, 24 m, 14 m and 4 m respectively
face of the diaphragm walls in the zone where any flow from the seaward face of the diaphragm wall
beneath the wall is concentrated, and therefore a relatively (b) the movement of the top of inclinometer INC 452 and at a
large drawdown can be expected. It is therefore of interest to depth of approximately 11 m (i.e. 6 mPD), the level at
consider the drawdown at rockhead level at greater distances which the maximum wall movement was recorded (see
from the diaphragm wall. Fig. 3)
(c) the piezometric level recorded at VPZ 449, which was
Figure 11 compares the drawdown measured at the various located at rockhead level approximately 5 m behind the
standpipe piezometers (PZs, shown as open symbols) located at diaphragm wall (see Fig. 3).
rockhead close to the TWB with the adjacent VPZs (shown as
solid symbols) located close to the landward diaphragm wall The main stages of the construction sequence are also shown in
for the SAT and station. The horizontal axis of the figure Fig. 12 for this area of the site. Diaphragm walling was
shows the locations of the instruments along the SAT and the undertaken between the middle of February and the middle of
station. Fig. 3 shows the exact location of the instruments. The June 2000. The first pumping test was carried out between 14
drawdown at rockhead level adjacent to the landward and 21 July 2000, and the second test between 7 and 14
diaphragm wall was between 3·5 m and 6·0 m, and the September 2000. Excavation and dewatering for the station
equivalent drawdown close to the TWB was between 2·0 m was carried out between early August and early December
and 3·0 m. On average, the drawdown adjacent to the TWB 2000. The following points can be observed from the
was about 45% of the drawdown adjacent to the wall. instrumentation data presented.
However, the drawdown did not cause significant
displacements to the TWB. (a) A settlement of approximately 5 mm was recorded at all
the settlement points (DMPs) during the first week of
4. SETTLEMENT BEHAVIOUR AT STATION monitoring. This settlement was also observed at the
GRIDLINE GL 50 settlement points on the landward side of the station, and
Cross-section gridline 50 (see Fig. 3) has been selected to may indicate movement of the settlement benchmark
illustrate construction events affecting various instruments on rather than settlement of all monitoring points.

152 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
May 00

May 01
Aug 00

Sep 00

Nov 00

Dec 00

Aug 01
Sep 01

Nov 01
Feb 00

Mar 00

Feb 01

Mar 01
Jan 00

Jun 00

Jan 01

Jun 01
Apr 00

Oct 00

Apr 01

Oct 01
Jul 00

Jul 01
3p

Excavation level: mPD


prop
0

45° spread
⫺5

2nd pump
1st pump
⫺10

⫺15
EXC
⫺0

⫺20
Vertical deformation: mm

⫺40

⫺60 3p DMP 594


DMP 595
⫺80
DMP 596
45° spread P
DMP 597
⫺100
P DMP 598

⫺120
P

50 Top
INC 452
11 m deep
40
Displacement: mm

30

EXC
20
P

10

0
3p
P P
2.5
45° spread VPZ 449
2.0
Piezometric level: mPD

1.5
1.0
0.5
0.0
⫺0.5
⫺1.0
⫺1.5
Jan 00

Feb 00

Mar 00

Apr 00

May 00

Jun 00

Jul 00

Aug 00

Sep 00

Oct 00

Nov 00

Dec 00

Jan 01

Feb 01

Mar 01

Apr 01

May 01

Jun 01

Jul 01

Aug 01

Sep 01

Oct 01

Nov 01

Fig. 12. Monitoring data for various instruments on seaward side of station GL 50: 3p, 3 panels;
P, pumping test; EXC, excavation and dewatering

(b) Significant settlements were observed during installation of resulted in a small inward movement of the top of the
the diaphragm wall, varying from approximately 50 mm diaphragm wall (INC 452) by approximately 5 mm.
within approximately 5 m of the wall to approximately (d ) The second pumping test between 7 and 14 September
15 mm at a distance of approximately 35 m behind the 2000 resulted in a large and almost immediate movement
wall. The settlement was cumulative owing to construction of the diaphragm wall, varying from approximately 35 mm
of adjacent panels rather than a sudden drop due to the at the top of the wall to 10 mm at 11 m deep. This
construction of a single panel. pumping test was responsible for the maximum step in the
(c) The first pumping test between 14 July and 21 July 2000 wall displacement. The DMPs correspondingly showed

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 153

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
some increased settlements during and after the pumping commissioning of the dewatering wells in this station area.
tests. A pumping test carried out in the middle of July 2000
(e) It is reasonable to assume that settlement due to caused some piezometric drawdown. A more significant
dewatering was minimal in this area as a result of the drawdown was observed at the beginning of September
recharge by seawater. The ground settlement due to 2000, as a result of the second pumping test.
excavation of the station therefore varied from (d ) The piezometric level is maintained at a low level during
approximately 40 mm close to the back of the wall to excavation to the final level and then rises slightly during
approximately 12 mm at a distance of approximately 24 m December 2000, when the pumps are required only to
behind the wall. This settlement was associated with an maintain rather than lower the water level in the station
inward movement of the diaphragm wall of approximately box.
40 mm. (e) The ground outside the excavation commenced to settle as
( f ) Very little movement of the diaphragm wall was observed a result of both dewatering and excavation within the
at a depth of 11 m after the beginning of April 2001, station. In particular, the reduction of the water level
following completion of the track-level slab. In addition, during and after the second pumping test caused an
subsequent ground settlement of the new reclamation immediate settlement of approximately 5 mm close to the
outside the diaphragm wall was reduced to a very slow rate wall, reducing to about 2 mm adjacent to the TWB.
of approximately 0·5–1·0 mm/month. This continuing (f) The magnitude of settlement appears to be controlled by
settlement was probably due to ongoing creep within the both the excavation depth and the drawdown. The
reclamation fill. maximum settlement of 30 mm adjacent to the wall (DMP
(g) The piezometric level (VPZ 449) at rockhead remained tidal 601) and 15 mm adjacent to the TWB (DMP 605) coincides
throughout the construction sequence, as it was constantly with the maximum depth of excavation.
recharged by seawater. A small piezometric level reduction (g) The ground surface shows elastic rebound by
of less than 1 m was observed during August to October approximately 2 mm in response to the reduced level of
2000, possibly as a result of the pumping tests and drawdown between November 2000 and January 2001.
excavation-related dewatering. Following completion of (h) Minor additional settlement (, 5 mm) is observed close to
the station excavation the piezometric level returned to its the wall between February and May 2001, possibly as a
original groundwater level. result of consolidation. Ground settlement was stable after
May 2001.
Figure 13 summarises the following instrumentation (i) By the middle of October 2001 the piezometric level at
monitoring data obtained at instruments located on the rockhead had increased and was only approximately 2 m
landward side of the station at gridline 50 below the mean sea level.

(a) the settlement recorded at DMPs 601, 602, 603, 604 and 5. SUBSURFACE SETTLEMENT
605, which were located at distances of 4 m, 14 m, 24 m, Two magnetic probe extensometers have been selected to
31 m and 41 m from the landward face of the diaphragm investigate the subsurface settlement behaviour for the new
wall respectively and old reclamation on the landward side of the site. They are
(b) the piezometric level recorded at VPZ 450 (see Fig. 3), MPX 107, which was located within the new reclamation of the
which was located at rockhead level approximately 3 m SAT, and MPX 415, which was located within the old
behind the diaphragm wall (unfortunately the inclinometer reclamation of the station. The locations of both the MPXs are
in the diaphragm wall at this location was damaged during shown in Fig. 3.
excavation).
Figure 14 shows the settlement of the magnets of MPX 107
The main stages of the construction sequence are also shown in during diaphragm wall construction, and SAT excavation and
Fig. 13 for this area of the site. The following points can be strutting. Magnet M1 is located nearest to the ground surface
observed in the data. and magnet M10 is located in rock. Fig. 15 shows the ground
conditions of the borehole of MPX 107, SPT N profile, levels of
(a) A settlement of approximately 4 mm was recorded at all the magnets within the borehole, and the normalised settlement
the settlement points during the first week of monitoring. within an individual soil layer, which is measured by two
This settlement was also observed at the settlement points consecutive magnets. The normalised settlement is the ratio of
on the seaward side of the station, and may indicate settlement or compression within a soil layer (difference in
movement of the settlement benchmark rather than settlement between two consecutive magnets) over the
settlement of all the monitoring points. thickness of the layer. The units are millimetres per metre
(b) Relatively small settlements were observed during (mm/m), and the ‘’ sign represents compression of the soil
installation of the diaphragm wall, varying from layers. The normalised settlement is divided into the settlement
approximately 10 mm within approximately 5 m of the measured during diaphragm walling and pre-trenching
wall to approximately 5 mm at a distance of 40 m behind (denoted by ‘DWall’) and during tunnel excavation and
the wall. Most of this settlement occurred during strutting (denoted by ‘EXC’) (see Fig. 14). The total settlement,
construction of the first panel, but small additional which is summation of the settlement measured during both
settlements can be seen during construction of the adjacent the DWall and EXC, is denoted by ‘Total’.
panels.
(c) The piezometric level (VPZ 450) at rockhead drops slowly It can be seen from Fig. 15 that a significant thickness of
during both June and July 2000, presumably in response to cobbles and boulders from the former seawall was encountered

154 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
May 00

May 01
Aug 00
Sep 00

Nov 00
Dec 00

Aug 01
Sep 01

Nov 01
Feb 00
Mar 00

Feb 01
Mar 01
Jan 00

Jun 00

Jan 01

Jun 01
Apr 00

Oct 00

Apr 01

Oct 01
Jul 00

Jul 01
3p
prop
⫺0

Excavation level: mPD


45° spread

⫺5

1st pump

2nd pump
⫺10

⫺15
3p
EXC
⫺0
45° spread P P
⫺5

⫺10
Vertical deformation: mm

⫺15
DMP
⫺20
601
⫺25 602

⫺30 603

604
⫺35
605
⫺40
3p

3 45° spread EXC


P VPZ 450
2
Piezometric level: mPD

1
P
0

⫺1

⫺2

⫺3

⫺4

⫺5
Jan 01
Feb 01
Mar 01
Apr 01
May 01
Jun 01
Jul 01
Aug 01
Sep 01
Oct 01
Nov 01
Feb 00
Mar 00
Jan 00

Apr 00
May 00
Jun 00
Jul 00
Aug 00
Sep 00
Oct 00
Nov 00
Dec 00

Fig. 13. Monitoring data for various instruments on landward side of station GL50: 3p, 3 panels;
P, pumping test; EXC, excavation and dewatering

between levels 3·5 mPD and 11·5 mPD. Pre-trenching was the piezometric drawdown in the CDG layer during dewatering
carried out between these levels. The column ‘DWall’ in Fig. 15 for the tunnel excavation. The piezometric drawdown could
shows that after diaphragm walling and pre-trenching the layer have caused some consolidation settlement in the CDG layer.
of cobbles and boulders showed the largest normalised
settlement, of between 3·6 mm/m and 4·4 mm/m. The column Figure 16 shows data for subsurface settlement at MPX 415
‘EXC’ shows that, in general, the normalised settlement located within the old reclamation of the station. The MPX
increases with depth for the settlement induced by the station data were missing from early May to early July 2000, as access
excavation and strutting. The column ‘Total’ shows that the to the instrument was obstructed. The time periods for
majority of the total settlement occurred in the cobble and diaphragm walling (DWall) and station excavation and
boulder layer, followed by the underlying CDG and then the fill strutting (EXC) are also shown in the figure. No former seawall
layer above, which is predominantly vibro-compacted medium was encountered at the MPX location, although there was a
dense sand. The reasons why the CDG layer shows a larger thin layer of fill (cobbles) between levels 4·0 mPD and
magnitude of settlement than the fill (medium dense sand) 6·0 mPD (see Fig. 17). The column ‘DWall’ in Fig. 17 shows
layer could be the structure of the extremely weak CDG silt and that, after diaphragm walling, the alluvium layer showed the

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 155

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
0

⫺10

⫺20

⫺30
Vertical deformation: mm

⫺40

⫺50

⫺60
Diaphragm
walling and
⫺70 pre-trenching
(DWall)
Tunnel
⫺80 excavation and
strutting (EXC)

⫺90
Jan 00

Feb 00

Mar 00

Apr 00

May 00

Jun 00

Jul 00

Aug 00

Sep 00

Oct 00

Nov 00

Dec 00

Jan 01

Feb 01

Mar 01

Apr 01

May 01

Jun 01

Jul 01

Aug 01

Sep 01
M1 M2 M3 M4 M5 M6 M7

M8 M9 M10

Fig. 14. Subsurface settlement data for MPX 107 located in new reclamation

largest normalised settlement ratio. The alluvium layer has the


SPT N
lowest SPT N values. The column ‘EXC’ shows a significant
0 10 20 30 increase in the normalised settlement in the fill (cobbles) layer
4 Fill (cobbles) for the settlement caused by the station excavation and
M1 DWall EXC Total strutting (from 0·2 mm/m to 1·7 mm/m). The settlement
2
⫺0.2 ⫺0.2 ⫺0.4 ratios in the alluvium and CDG layers were also increased. The
Fill (medium M2
0 column ‘Total’ shows that the profile of the total settlement
dense sand)
⫺1.0 ⫺0.4 ⫺1.4
⫺2 M3 ratios seems to follow the SPT N profile. The largest settlement
occurred in the alluvium layer, which has the lowest SPT N
⫺4 ⫺2.2 ⫺0.2 ⫺2.4
M4 values, followed by the extremely weak CDG silt and fill (firm
Level: mPD

⫺6 ⫺3.6 ⫺1.2 ⫺4.8 clay and sand).


Fill (cobbles and M5
⫺8 boulders)
⫺4.0 ⫺1.2 ⫺5.2 When comparing Figs 14 and 15 with Figs 16 and 17 it is
M6
⫺10 apparent that the settlement of the new reclamation was about
⫺4.4 ⫺1.4 ⫺5.8
⫺12 M7 twice that of the old reclamation. This is due mainly to the
⫺2.4 ⫺1.6 ⫺4.0
pre-trenching that was carried out in the former seawall layer
⫺14 M8
CDG (extremely (cobbles and boulders in MPX 107) in the SAT. Thorley and
3 4
⫺16 weak silt)
⫺2.6 ⫺1.6 ⫺4.2 Forth and Cowland and Thorley have also highlighted the
M9
⫺18
adverse effect of pre-trenching for deep excavation in Hong
⫺0.6 ⫺1.4 ⫺2.0 Kong. The settlement in the CDG layer was less in the old
Rock M10
⫺20
reclamation within the station area than in the SAT area, as
Magnet Normalised shown by the normalised settlement of 1·7 mm/m for MPX
level settlement: 415 as opposed to 4·0 mm/m for MPX 107. This demonstrates
mm/m
the effectiveness of rock grouting carried out on the landward
side of the station. The piezometric drawdown in the CDG layer
Fig. 15. Ground profile and ratios of settlement over layer
due to dewatering was reduced by the rock grouting, resulting
thickness at different depths of MPX 107: CDG, completely
decomposed granodiorite; M1, magnet 1 in a correspondingly reduced consolidation settlement at
MPX 415.

156 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
0

⫺5

⫺10

Vertical deformation: mm ⫺15


Diaphragm walling
(DWall)
⫺20

⫺25

⫺30
Station
excavation and
⫺35 strutting
(EXC)

⫺40
Mar 00

Mar 01
Jan 00

Feb 00

Apr 00

May 00

Jun 00

Jul 00

Aug 00

Sep 00

Oct 00

Nov 00

Dec 00

Jan 01

Feb 01

Apr 01

May 01

Jun 01

Jul 01

Aug 01

Sep 01
M1 M2 M3 M4 M5 M6 M7

Fig. 16. Subsurface settlement data for MPX 415 located in the old reclamation

6. CONCLUSIONS
SPT N The completion of the diaphragm walls effectively cut off the
0 5 10 15 20 hydraulic connection between the landward piezometers and
4
Wash boring the sea, as evidenced by the daily variation in piezometric level
M1 DWall EXC Total
2 being significantly reduced. As expected, the seaward
Fill (firm
clay) ⫺0.2 ⫺0.2 ⫺0.4 piezometers showed negligible changes in daily piezometric
0 M2 level variation after completion of the diaphragm walls because
Fill (firm
⫺2 silt) seawater recharge was unaffected.
⫺0.7 ⫺0.8 ⫺1.5
Fill (sand) M3
⫺4
Dewatering for excavation of the station and tunnels resulted
Fill (cobbles) ⫺0.2 ⫺1.7 ⫺1.9
Level: mPD

⫺6 in a significant reduction in piezometric level recorded at


M4
All. (silt) rockhead level close to the outer face of the diaphragm walls.
⫺8 ⫺0.8 ⫺1.5 ⫺2.3
All. (clay)
The comparatively smaller drawdown at the station is thought
M5
⫺10 to be due to the additional rock grouting that was carried out
CDG ⫺0.5 ⫺1.2 ⫺1.7 to a depth of approximately 5 m below the landward station
⫺12 M6
(extremely diaphragm walls. Contact grouting to a depth of approximately
weak silt) 1 m below the base of the landward NAT diaphragm walls was
⫺14 ⫺0.3 ⫺0.5 ⫺0.8
M7 found to be ineffective at cutting off water seepage below the
⫺16 Rock walls. The magnitude of drawdown outside the diaphragm
Magnet
⫺18 level
Normalised walls was found to be a function of diaphragm wall depth,
settlement: which was related to rockhead level. The piezometers close to
mm/m
the TWB showed an average of 45% of the drawdown
experienced by the piezometers within 5 m of the landward
Fig. 17. Ground profile and ratios of settlement over layer
diaphragm walls.
thickness at different depths of MPX 415: All., alluvium; CDG,
completely decomposed granodiorite; M1, magnet 1
A significant amount of settlement was observed during

Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al. 157

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
pre-trenching and diaphragm walling. After pumping tests REFERENCES
there was a sharp increase in the ground settlement and 1. GAMMON J., HILL S., MALKA D. and CARAYOL S. Real time
displacement of the diaphragm wall. It is believed that the monitoring of highway viaduct close to deep excavation.
settlement induced during the deep excavation and dewatering Geotechnical Deformations and Movements: Proceedings of
was predominantly caused by the wall deflection. During the 21st Annual Seminar of Geotechnical Division Hong
excavation dewatering, the groundwater drawdown on the Kong Institution of Engineers, Hong Kong, 2001, 217–225.
seaward side was less than that on the landward side, as the 2. NORCLIFFE B. A. W., PICKLES A. R. and LEE S. W. The use of
seawater recharged the seaward area. recharge wells to mitigate ground settlement on KCRC
contract CC300 Tsuen Wan Station and approach tunnels.
The MPX data show that the pre-trenching in the cobbles Geotechnical Aspects of Mass Transportation Systems:
and boulders layer resulted in large settlements. The Proceedings of the 22nd Annual Seminar of Geotechnical
reduced settlement in the CDG layer on the landward side Division Hong Kong Institution of Engineers, Hong Kong,
of the station (as compared with settlement on the 2002, 123–130.
landward side of the SAT) is attributed to the reduced 3. THORLEY C. B. B. and FORTH R. A. Settlement due to
piezometric drawdown, which in turn induced less diaphragm wall construction in reclaimed land in Hong
consolidation settlement. Kong. Journal of Geotechnical and Geoenvironmental
Engineering, ASCE, 2002, 128, No. 6, 473–478.
7. ACKNOWLEDGEMENTS 4. COWLAND J. W. and THORLEY C. B. B. Ground and building
The authors express their gratitude to KCRC for their kind settlement associated with adjacent slurry trench
permission to publish this paper. Contributions from the site excavation. Proceedings of the 3rd International Conference
staff, and in particular Ir Jonathan Gammon, are highly on Ground Movements and Structures (GEDDES J. D. (ed.)).
appreciated. Pentech Press, London, 1985, pp. 723–738.

Please email, fax or post your discussion contributions to the secretary by 1 January 2004: email: mary.henderson@ice.org.uk;
fax: þ44 (0)20 7799 1325; or post to Mary Henderson, Journals Department, Institution of Civil Engineers, 1–7 Great George Street,
London SW1P 3AA.

158 Geotechnical Engineering 156 Issue GE3 Groundwater and ground movement in deep excavation Pickles et al.

Downloaded by [ York University] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.

You might also like