Professional Documents
Culture Documents
CONSEQUENCES
S/N HAZARD OR EVENT POSSIBLE CAUSES (Harm - Who/What might be harmed
how)
1) Improper assessment of
Demobilizing and Good vehicles. Supervisor –Operator –Labour Public
6
housekeeping 2) Inexperienced driver.
Notes:
1- Pre shift safety briefing should to be held to discuss hazards and associated control measures and to consider
2- All work to be carried out by competent persons, suitably trained
3- Standard PPE should be worn at all times. Only additional PPE, for the task being carried out, is specified in
SEV
Incident
Severity
1
Negligible
2
Low
3
Medium
4
High
5
Major
RISK ASSESSMENT
DATE:
D BY: RA No: 01
Risk Rating
CONSEQUENCES
(Classification
ho/What might be harmed and CONTROL MEASURES:
according to Risk
how)
Matrix)
4). Conduct, HSE Inductions, Toolbox meeting and review the JSA to all
personnel invovled in the work activities
5). Responsible person will conduct inspection,
monitor the work activities and ensure that safety standards and
procedures are strictly followed
1).Ensure uncoiled hoses will not be a tripping hazard. Ensure there are
no kinks, cracks or damage to hoses. Ensure all torch valves are closed
–Operator –Labour Public D3 and inspect for possible leaks.
2). Ensure adjustment screws on regulators are
backed off so no tension is present for both acetylene and oxygen.
2). Do not weld near flammable materials (3)Use lock out/tag out when
–Operator –Labour Public D4 welding near electrical devices (4) Use welding curtain to shield other
employees and visitors from arc rays (5) Make use of PPE like nose
mask, face shield, helmet, coveralls, handgloves and safety boots) (6).
Proper inspection of welding equipment before usage (7). Provision of
fire estinguisher while the welding task is ongoing
–Operator –Labour Public D4 Ensure safe positioning of fingers and make use of PPE
1). Before, during and after task, the area must be clear of all types of
waste and combustible materials.
–Operator –Labour Public D4 2). Work site must be returned to a safe condition upon completion of
the project
3). Proper disposal of waste materials must be ensured
rol measures and to consider additional hazards present due to surrounding work
SEVERITY LIKELIHOOD
Minor
Local
damage
environmenta
Minor injury or Health Brief
l damage.
effects (Medical disruption
Within the A2 B2 C2 D2
Treatment or Work (cost >
fence and
Restricted Case) N100,000 but
within
<N1M. 1day
systems
downtime)
damage
Contaminatio
Major injury or Health Partial
n Damage
effects shutdown
sufficient to A3 B3 C3 D3
(cost >1M but
(Lost Time Injury) attack the
<N10M), 1-7
environment.
days
Major
Limited loss damage
of discharges Partial
Single fatality or of known operation
Permanent Total toxicity. loss( cost A4 B4 C4 D4
Disability Affecting >10M but
neighbourhoo <N100M)
d. 2weeks
shutdown
Extensive
Major
damage
environmenta
Substantial or
l damage.
total
Extended
Multiple fatalities operation A5 B5 C5 D5
measures to
loss (cost > N
restore the
100M)more
contaminated
than 2weeks
environment.
shutdown
RESIDUAL RISK
RATING (Classification Action Party
L MEASURES:
according to Risk
Matrix)
d playing
personnels must be allowed to carry
C1 Supervisor
lbox meeting and review the JSA to all
ivities
le person will conduct inspection,
sure that safety standards and
o starting work
C1 Supervisor
wheel
es while grinding
fore undergoing the task.
ELIHOOD
5.-E
Very Likely
E1
E2
E3
E4
E5