Professional Documents
Culture Documents
Boqs For Pit Latrine Final
Boqs For Pit Latrine Final
1 PRELIMINARIES
Clear site of shrub, Trees etc. and excavate over site to remove top
1.02 vegetable soil average depth of 300mm, remov the tree stumps, cart away m2 68.0 2,000 136,000
to atleast 30M from site.
Excavate for the latrine pit commencing at reduced level to depth not
exceeding 4.0m i.e 7.70m long, 1.90m wide and 4.0m deep and not less
2.01 than 1.50m above the water table including all earth work support, m3 59.0 4,000 236,000
keeping the excavation free from water and spreading excavated materials
away inclusive of any rock areas.
Excavate for foundations Plinth walling, curtain wall and urinal to a firm
2.03 m3 16.0 4,000 64,000
level not exceeding 1.0m deep return refill and ram.
3 SUB-STRUCTURE
Anti-termite treatment
Provide anti-termite treatment to sides of excavation and at intervals of
3.01 sum 1.0 150,000 150,000
every 300mm layer during back filling
Concrete Works
3.02 Cast 230mm thick concrete (1:3:6/38mm) at the base of pit. m3 3.4 300,000 1,020,000
Ditto but 230mm thick by 690mm wide foundation for curtail walls and
3.03 m3 3.6 25,000 90,000
urinal
3.05 Ditto but 230x230mm ground beam and slab beam m3 2.0 25,000 50,000
Ditto but 100mm thick oversite and suspended slabs. Squat holes and
3.06 m3 2.8 25,000 70,000
inspection chambers (600x600mm) should be provided.
3.08 20mm thick concrete (1:2) APC ready to received DPC m 52.0 10,000 520,000
25mm thick cement/sand (1:4) plaster applied in two layers and finished
3.1 m2 63.0 8,000 504,000
with a steel float applied to the internal surface of pit
Backfills
Imported marrum fill to sides of excavations compacted in 200mm layers
3.11 m3 26.0 5,000 130,000
to 95% MDD ready to received hardcore
200mm thick stone hardcore, well spread and Leveled, consolidated and
3.12 m2 15.0 7,500 112,837
blinded with crushed stone at the bottom of the pit.
Brick Works
230mm thick well burnt clay brick walls approved by engineer with metal
strips at every 3 courses bedded in cement/sand mortar 1:4 and atleast
3.14 200mm well above ground on ditto (detailed in drawing) to be used as m2 67.0 18,000 1,206,000
containment for Latrine with two separate chambers and intermediate
brickwork from the bottom of pit to slab level
Ditto but 230mm well burnt clay brick plinth wall to curtain wall and
3.15 m2 20.0 18,000 360,000
urinal
Reinforcement Works
High yield tensile steel bar reinforcement size 12mm diameter to BS 4461
3.16 as described including cutting to lengths, bending, hoisting and fixing Kg 171.0 5,000 855,000
including all necessary tying wire and spacers to columns and beams.
3.17 Ditto but 10mm diameter in cobweb 200mm centers to suspended slab Kg 73.0 5,000 365,000
Steel fabric mesh reinforcement ref no. A98 weighing 1.58kg/m2: in floor
3.2 m2 28.0 8,000 224,000
bed: including tying wire and distance blocks
Form works
Sawn formworks to sides of columns beams and soffits of beams and
3.22 m2 23.0 9,000 207,000
slabs completed with all accessories
3.23 Ditto but to side of slabs size 75-150mm wide m 27.0 3,000 81,000
COLLECTION
Page 3 2,979,000
Page 4 3,787,838
Page 5 387,000
4 SUPER STRUCTURE
150mm thick wall of well burnt clay bricks with metal strips placed every
4.01 three course in cement mortar mix 1:4 including screen walls and urinal to m2 106.0 18,000 1,908,000
the specified heights with metal strip placed at every alternate course
4.03 150x150mm reinforced concrete (1:2:4/19mm aggregates) beam m3 0.6 300,000 180,000
High yield tensile steel bar reinforcement size 12mm diameter to BS 4461
as described including cutting to lengths, bending, hoisting and fixing
4.04 Kg 94.0 5,000 470,000
including all necessary tying wire and spacing blocks to columns and
beams.
5 ROOF CONSTRUCTION
5.01 Well treated timber size 50 x 75mm as purlins (pine) m 31.0 2,000 62,000
5.02 Ditto but 50x100mm as rafters approximately at 1.5m centers m 16.0 2,200 35,200
6 DOORS
Purpose made steel door size 1000x2200mm (D1) with 250mm high
permanent vent fabricated from 40x40x1.0mm SHS as shutter frames,
1.2mm thick mild steel plate panel and 1.2mm mild steel louvres.
6.01 Completed with door frames fabricated from 1.2mm thick standard door No 1.0 500,000 500,000
frame section, fixing lugs to walls, hinges and locking mechanisms with
tri-circle locks size 265 and 3 keys. All pre-approved by engineers and
primed with red-oxide before delivery to site.
6.02 Ditto but door size 900x2200mm (D2) No 4.0 400,000 1,600,000
7 FINISHES
7.01 35mm thick cement sand floor screed (1:3) finished smooth. m2 21.0 8,000 168,000
7.02 Ditto but disabled persons' ramp finished rough m2 11.0 8,000 88,000
20mm cement, sand (1:4) wall plaster in two coats steel trowled hard and
7.03 m2 93.0 8,000 744,000
smooth on walls internally. Finish smooth with cement lime slurry
15mm cement and sand (1:3) skirting 150mm high on plastered walls in
7.04 two coats steel troweled hard and smooth on walls internally and m 43.0 2,900 124,700
externally.
Inverted V shape well finished copping to be done top of the curtain wall
7.05 m 12.0 2,900 34,800
and Urinal for boys
15mm cement, sand (1:4) wall render trowled hard and smooth on walls
7.06 m2 54.0 8,000 432,000
externally. Finish smooth with cement lime slurry
15mm cement and sand (1:3) skirting 150mm high on plastered walls in
7.07 two coats steel troweled hard and smooth on walls internally and m 24.0 2,900 69,600
externally.
Ditto but rough cast rendered walls externally side and rear walls to
7.08 m2 38.0 8,000 304,000
height of 1.5 m from skirting level.
75mm thick concrete (grade 15) splash apron on 100mm hardcore base
well rammed and apron finished with 25mm thick cement and sand (1:3)
screed trowelled smooth to gentle falls with division strips every 2.00
8.01 metre length and including 150mm brick edge wall average 500mm deep m3 1.5 300,000 450,000
rendered on and including 450mm x 50mm thick concrete grade 10
foundation and all necessary excavations and disposal of spoil and
formwork to edge of apron
Fabricate and Install PWD standard supports (hand rails, Toilet seats,
8.02 LS 1.0 300,000 300,000
hand support) etc as provided annex to drawings
Construct urinary channel with gentle slope and install floor trap
connected with 100mm diameter uPVC to soak pit 2m diameter and 1.5 m
8.03 No. 1.0 90,000 90,000
deep, fill in clean selected hard core and covered with polythene sheeting
and backfill
Supply and install standard sitting toilet pan with bottom part cut to allow
8.04 direct defecation into the pit and with no cistern but cast firm into the No. 1.0 275,000 275,000
toilet floor using concrete and finished smooth as in the drawing
Supply and installed 100mm diameter uPVC vent pipe complete with cap,
8.05 No. 5.0 40,000 200,000
fly screen and painted black. Allow to pass over roof covering by 1M.
8.06 Clear the site of all construction debris and level the site Sum 1.0 250,000 250,000
9 PAINTING
Prepare, prime and paint one undercoat and 2 subsequent coats of vinyl
9.01 silk emulsion cream sodolin paint on internal wall 1500mm above floor m2 28.0 4,000 112,000
level
Ditto but 3 coats of high gloss paint upto 1500mm from floor level or as
9.02 m2 65.0 6,000 390,000
will be direected by the site engineer
Prepare, prime and paint one undercoat and 2 subsequent coats of tobacco
9.04 high gloss paint up to 200mm above the floor as skirting both internally m 67.0 4,000 268,000
and externally
Prepare, prime and paint one undercoat and 2 subsequent coats of cream
9.05 weather guard paint on all rendered walls above 1500, (above roughcast), SM 16.0 4,000 64,000
the front and the interior of the curtain walls
Prepare touch up primer and apply one undercoat and two finishing coats
9.06 m2 24.0 4,000 96,000
of gloss oil paint: glazed metal doors
Prepare, prime and paint an undercoat and three coats of colour Weather
9.07 m 12.0 5,000 60,000
guard paint on the copping surface
100mm thick concrete (grade 15) slab as base for 750L tank on 100mm
hardcore base well rammed and apron finished with 25mm thick cement
and sand (1:3) screed trowelled smooth and including 230mm brick edge
10.01 wall average 500mm deep and 600mm above ground rendered on and Sum 1.0 400,000 400,000
including 450mm x 50mm thick concrete grade 10 foundation and all
necessary excavations and disposal of spoil and formwork to edge of
apron
Supply and install 250L plastic tank from approved supplier inclusive of
6m long plastic gutter, stop ends, spout, down pipes, bends, gutter
10.02 No. 1.0 120,000 120,000
washout and its protective structure as detailed in the drawings and all
accessories.
Allow for plumbing works for water supply to hand washing basins inside
10.03 Sum 1.0 150,000 150,000
disable persons' stance and infront of the curtain water
SUMMARY TO BOQ
1 PRELIMINARIES 1,036,000
3 SUB-STRUCTURE 7,153,838
4 SUPERSTRUCTURE 2,910,500
6 DOORS 3,100,000
7 FINISHES 1,965,100
9 PAINTING 1,142,000