Page 1 BOQS FOR PIT LATRINE

BOQ FOR 5- STANCE DRAINABLE LATRINE AND URINAL

No Description Unit Qty Rate Ushs

1 PRELIMINARIES

Mobilization and demobilization of equipment, tools, personnel to and


1.01 Sum 1.0 900,000 900,000
from the site

Clear site of shrub, Trees etc. and excavate over site to remove top
1.02 vegetable soil average depth of 300mm, remov the tree stumps, cart away m2 68.0 2,000 136,000
to atleast 30M from site.

Total Preliminary to Summary>>>>>>>>>>>>>>>> 1,036,000

Page 1 BOQS FOR PIT LATRINE


Page 2 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

2 EXCAVATION AND EARTH WORKS

Excavate for the latrine pit commencing at reduced level to depth not
exceeding 4.0m i.e 7.70m long, 1.90m wide and 4.0m deep and not less
2.01 than 1.50m above the water table including all earth work support, m3 59.0 4,000 236,000
keeping the excavation free from water and spreading excavated materials
away inclusive of any rock areas.

2.02 Provide form work support to ditto m2 77.0 3,000 231,000

Excavate for foundations Plinth walling, curtain wall and urinal to a firm
2.03 m3 16.0 4,000 64,000
level not exceeding 1.0m deep return refill and ram.

Load wheel and deposit surplus excavated materials and deposit at


2.04 m3 85.0 2,000 170,000
distance not less than 1 km from the site as directed by site Engineer.

Total Excavation and Earth Works to Summary>>>>>>>>>>>>>>>> 701,000

Page 2 BOQS FOR PIT LATRINE


Page 3 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

3 SUB-STRUCTURE

Anti-termite treatment
Provide anti-termite treatment to sides of excavation and at intervals of
3.01 sum 1.0 150,000 150,000
every 300mm layer during back filling

Concrete Works
3.02 Cast 230mm thick concrete (1:3:6/38mm) at the base of pit. m3 3.4 300,000 1,020,000

Ditto but 230mm thick by 690mm wide foundation for curtail walls and
3.03 m3 3.6 25,000 90,000
urinal

230x690x690mm reinforced concrete (1:2:4/19mm aggregate) footing at


3.04 m3 0.5 300,000 150,000
the bottom of pit and 230x230 colunms.

3.05 Ditto but 230x230mm ground beam and slab beam m3 2.0 25,000 50,000

Ditto but 100mm thick oversite and suspended slabs. Squat holes and
3.06 m3 2.8 25,000 70,000
inspection chambers (600x600mm) should be provided.

3.07 Ditto but 100mm thick ramps m2 11.0 15,000 165,000

3.08 20mm thick concrete (1:2) APC ready to received DPC m 52.0 10,000 520,000

Lay 150mm wide bituminous felt or other approved materials as DPC on


3.09 m 52.0 2,500 130,000
APC with 200mm overlaps ready to receive super structural walls

25mm thick cement/sand (1:4) plaster applied in two layers and finished
3.1 m2 63.0 8,000 504,000
with a steel float applied to the internal surface of pit

Backfills
Imported marrum fill to sides of excavations compacted in 200mm layers
3.11 m3 26.0 5,000 130,000
to 95% MDD ready to received hardcore

Total Carried to Collection>>>>>>>>>>>>>>> 2,979,000

Page 3 BOQS FOR PIT LATRINE


Page 4 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

200mm thick stone hardcore, well spread and Leveled, consolidated and
3.12 m2 15.0 7,500 112,837
blinded with crushed stone at the bottom of the pit.

Supply and instal 1000mm gauge Polythene sheeting as tanking to the


3.13 m2 74.0 2,500 185,000
excavated pit

Brick Works

230mm thick well burnt clay brick walls approved by engineer with metal
strips at every 3 courses bedded in cement/sand mortar 1:4 and atleast
3.14 200mm well above ground on ditto (detailed in drawing) to be used as m2 67.0 18,000 1,206,000
containment for Latrine with two separate chambers and intermediate
brickwork from the bottom of pit to slab level

Ditto but 230mm well burnt clay brick plinth wall to curtain wall and
3.15 m2 20.0 18,000 360,000
urinal

Reinforcement Works

High yield tensile steel bar reinforcement size 12mm diameter to BS 4461
3.16 as described including cutting to lengths, bending, hoisting and fixing Kg 171.0 5,000 855,000
including all necessary tying wire and spacers to columns and beams.

3.17 Ditto but 10mm diameter in cobweb 200mm centers to suspended slab Kg 73.0 5,000 365,000

Mild steel bar reinforcement size 8mm diameter to BS 4461at 200mm


3.18 Kg 90.0 5,000 450,000
centers for columns and beams

Provide lockable 600mmx600mm cast iron air tight prefabricated covers


3.19 No. 1.0 30,000 30,000
with frame as inspection covers or as directed by engineer.

Steel fabric mesh reinforcement ref no. A98 weighing 1.58kg/m2: in floor
3.2 m2 28.0 8,000 224,000
bed: including tying wire and distance blocks

Page 4 BOQS FOR PIT LATRINE


Page 5 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

Total Carried to Collection >>>>>>>>>>>>>>>>>>>>>>> 3,787,838

Page 5 BOQS FOR PIT LATRINE


Page 6 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

3.21 Ditto but in concrete ramps m2 11.0 9,000 99,000

Form works
Sawn formworks to sides of columns beams and soffits of beams and
3.22 m2 23.0 9,000 207,000
slabs completed with all accessories

3.23 Ditto but to side of slabs size 75-150mm wide m 27.0 3,000 81,000

Total Carried to Collection >>>>>>>>>>>>>>>>>>>>>>> 387,000

COLLECTION

Page 3 2,979,000

Page 4 3,787,838

Page 5 387,000

Page 6 BOQS FOR PIT LATRINE


Page 7 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs


Total Substructure to Summary>>>>>>>>>>>>>>>> 7,153,838

Page 7 BOQS FOR PIT LATRINE


Page 8 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

4 SUPER STRUCTURE

150mm thick wall of well burnt clay bricks with metal strips placed every
4.01 three course in cement mortar mix 1:4 including screen walls and urinal to m2 106.0 18,000 1,908,000
the specified heights with metal strip placed at every alternate course

Approved Kajjansi burnt clay vent bricks or equivalent in cement mortar


4.02 Pcs 30.0 1,950 58,500
1:4

4.03 150x150mm reinforced concrete (1:2:4/19mm aggregates) beam m3 0.6 300,000 180,000

High yield tensile steel bar reinforcement size 12mm diameter to BS 4461
as described including cutting to lengths, bending, hoisting and fixing
4.04 Kg 94.0 5,000 470,000
including all necessary tying wire and spacing blocks to columns and
beams.

Mild steel bar reinforcement size 8mm diameter to BS 4461at 200mm


4.05 Kg 42.0 5,000 210,000
centers for columns and beams

Sawn formworks to sides of columns beams and soffits of beams and


4.06 m2 12.0 7,000 84,000
slabs completed with all accessories

Total Super Structure to Summary>>>>>>>>>>>>>>>> 2,910,500

Page 8 BOQS FOR PIT LATRINE


Page 9 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

5 ROOF CONSTRUCTION

5.01 Well treated timber size 50 x 75mm as purlins (pine) m 31.0 2,000 62,000

5.02 Ditto but 50x100mm as rafters approximately at 1.5m centers m 16.0 2,200 35,200

5.03 Ditto but 75x100mm as wall plates m 15.0 2,500 37,500

5.04 Ditto but 50x150mm as tie beams m 6.0 2,800 16,800

5.06 Ditto but 20x225mm as fascia boards m 25.0 10,000 250,000

28 G Prepainted corrugated roofing iron sheets as per drawings (colour to


5.07 m2 25.0 18,600 465,000
be determined by SMC)

5.08 Ditto but ridge caps m 3.0 10,000 30,000

5.09 Ditto but gutters m 6.0 12,000 72,000

Total Roof Construction to Summary>>>>>>>>>>>>>>>> 896,500

Page 9 BOQS FOR PIT LATRINE


Page 10 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

6 DOORS

Purpose made steel door size 1000x2200mm (D1) with 250mm high
permanent vent fabricated from 40x40x1.0mm SHS as shutter frames,
1.2mm thick mild steel plate panel and 1.2mm mild steel louvres.
6.01 Completed with door frames fabricated from 1.2mm thick standard door No 1.0 500,000 500,000
frame section, fixing lugs to walls, hinges and locking mechanisms with
tri-circle locks size 265 and 3 keys. All pre-approved by engineers and
primed with red-oxide before delivery to site.

6.02 Ditto but door size 900x2200mm (D2) No 4.0 400,000 1,600,000

Ditto but grill size 1000x1600mm (D3) fabricated from 40x25x1.0mm


SHS as shutter frames, 20x20x1.2mm SHS as grills. Completed with door
frames fabricated from 1.2mm thick standard door frame section, fixing
6.03 No 2.0 500,000 1,000,000
lugs to walls, hinges and locking mechanisms with tri-circle locks size
265 and 3 keys. All pre-approved by engineers and primed with red-
oxide before delivery to site.

Page 10 BOQS FOR PIT LATRINE


Page 11 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs


Total Doors to Summary>>>>>>>>>>>>>>>> 3,100,000

Page 11 BOQS FOR PIT LATRINE


Page 12 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

7 FINISHES

7.01 35mm thick cement sand floor screed (1:3) finished smooth. m2 21.0 8,000 168,000

7.02 Ditto but disabled persons' ramp finished rough m2 11.0 8,000 88,000

20mm cement, sand (1:4) wall plaster in two coats steel trowled hard and
7.03 m2 93.0 8,000 744,000
smooth on walls internally. Finish smooth with cement lime slurry

15mm cement and sand (1:3) skirting 150mm high on plastered walls in
7.04 two coats steel troweled hard and smooth on walls internally and m 43.0 2,900 124,700
externally.

Inverted V shape well finished copping to be done top of the curtain wall
7.05 m 12.0 2,900 34,800
and Urinal for boys

15mm cement, sand (1:4) wall render trowled hard and smooth on walls
7.06 m2 54.0 8,000 432,000
externally. Finish smooth with cement lime slurry

15mm cement and sand (1:3) skirting 150mm high on plastered walls in
7.07 two coats steel troweled hard and smooth on walls internally and m 24.0 2,900 69,600
externally.

Ditto but rough cast rendered walls externally side and rear walls to
7.08 m2 38.0 8,000 304,000
height of 1.5 m from skirting level.

Total Finishes to Summary>>>>>>>>>>>>>>>> 1,965,100

Page 12 BOQS FOR PIT LATRINE


Page 13 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

8 OTHER EXTERNAL WORK

75mm thick concrete (grade 15) splash apron on 100mm hardcore base
well rammed and apron finished with 25mm thick cement and sand (1:3)
screed trowelled smooth to gentle falls with division strips every 2.00
8.01 metre length and including 150mm brick edge wall average 500mm deep m3 1.5 300,000 450,000
rendered on and including 450mm x 50mm thick concrete grade 10
foundation and all necessary excavations and disposal of spoil and
formwork to edge of apron

Fabricate and Install PWD standard supports (hand rails, Toilet seats,
8.02 LS 1.0 300,000 300,000
hand support) etc as provided annex to drawings

Construct urinary channel with gentle slope and install floor trap
connected with 100mm diameter uPVC to soak pit 2m diameter and 1.5 m
8.03 No. 1.0 90,000 90,000
deep, fill in clean selected hard core and covered with polythene sheeting
and backfill

Supply and install standard sitting toilet pan with bottom part cut to allow
8.04 direct defecation into the pit and with no cistern but cast firm into the No. 1.0 275,000 275,000
toilet floor using concrete and finished smooth as in the drawing

Supply and installed 100mm diameter uPVC vent pipe complete with cap,
8.05 No. 5.0 40,000 200,000
fly screen and painted black. Allow to pass over roof covering by 1M.

8.06 Clear the site of all construction debris and level the site Sum 1.0 250,000 250,000

Total Other External Works to Summary>>>>>>>>>>>>>>>> 1,565,000

Page 13 BOQS FOR PIT LATRINE


Page 14 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

9 PAINTING

Prepare, prime and paint one undercoat and 2 subsequent coats of vinyl
9.01 silk emulsion cream sodolin paint on internal wall 1500mm above floor m2 28.0 4,000 112,000
level

Ditto but 3 coats of high gloss paint upto 1500mm from floor level or as
9.02 m2 65.0 6,000 390,000
will be direected by the site engineer

Prepare, prime and paint one undercoat and 2 subsequent coats of of


9.03 beetlenut weather guard paint on roughcasted wall surface as will be m2 38.0 4,000 152,000
directed by the engineer

Prepare, prime and paint one undercoat and 2 subsequent coats of tobacco
9.04 high gloss paint up to 200mm above the floor as skirting both internally m 67.0 4,000 268,000
and externally

Prepare, prime and paint one undercoat and 2 subsequent coats of cream
9.05 weather guard paint on all rendered walls above 1500, (above roughcast), SM 16.0 4,000 64,000
the front and the interior of the curtain walls

Prepare touch up primer and apply one undercoat and two finishing coats
9.06 m2 24.0 4,000 96,000
of gloss oil paint: glazed metal doors

Prepare, prime and paint an undercoat and three coats of colour Weather
9.07 m 12.0 5,000 60,000
guard paint on the copping surface

Total Carried to Summary>>>>>>>>>>>>>>>> 1,142,000

Page 14 BOQS FOR PIT LATRINE


Page 15 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

10 RAIN WATER HARVESTING AND HAND WASHING FACILITY

100mm thick concrete (grade 15) slab as base for 750L tank on 100mm
hardcore base well rammed and apron finished with 25mm thick cement
and sand (1:3) screed trowelled smooth and including 230mm brick edge
10.01 wall average 500mm deep and 600mm above ground rendered on and Sum 1.0 400,000 400,000
including 450mm x 50mm thick concrete grade 10 foundation and all
necessary excavations and disposal of spoil and formwork to edge of
apron

Supply and install 250L plastic tank from approved supplier inclusive of
6m long plastic gutter, stop ends, spout, down pipes, bends, gutter
10.02 No. 1.0 120,000 120,000
washout and its protective structure as detailed in the drawings and all
accessories.

Allow for plumbing works for water supply to hand washing basins inside
10.03 Sum 1.0 150,000 150,000
disable persons' stance and infront of the curtain water

Supply and intall Vitreous china Wash Basin approximately


380×330x185mm with plastic bottle trap, taps and all accessories as
10.04 No 2.0 60,000 120,000
Armitage Shanks htm64 contour washbasin S2290 or equal approved.
Including connection of waste water to soak pits

Total Carried to Summary>>>>>>>>>>>>>>>> 790,000

Page 15 BOQS FOR PIT LATRINE


Page 16 BOQS FOR PIT LATRINE

No Description Unit Qty Rate Ushs

SUMMARY TO BOQ

1 PRELIMINARIES 1,036,000

2 EXCAVATION AND EARTH WORKS 701,000

3 SUB-STRUCTURE 7,153,838

4 SUPERSTRUCTURE 2,910,500

5 ROOFING CONSTRUCTION 896,500

6 DOORS 3,100,000

7 FINISHES 1,965,100

8 OTHER EXTERNAL WORK 1,565,000

9 PAINTING 1,142,000

10 RAIN WATER HARVESTING AND HAND WASHING FACILITY 790,000

SUMMARY TOTAL 21,259,938


VAT 18% 3,826,789

GRANDA TOTAL 25,086,726