You are on page 1of 11

AJMER SMART CITY LIMITED AJMER

Abstract of 1St R.A Bill


Name of Name :- Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Billing :- 14.02.2021
Date of
Name of Contractor :- M/s MLA NBCC ( A Joint Venture) Commenceme :- 18.12.2020
nt
Date of
LoA No:- ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020 Completion
:- 17.06.2021
Amount of Contract:- 62982048.06
Qty upto This Bill Upto date
S. No BoQ No. Item Description Unit Rate Amount Remark
Last Bill Qty. Gross Qty

G-Schudule

1 21 Dismantling of flexible pavements and disposal of


dismantledmaterials up to a lead of 50 metres as directed by
Engineer. Bituminous courses : Divider

Brought from Comp.MB -Construction of divider and widening of road from


50.40
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -1

Brought from Comp.MB -Construction of divider and widening of road from


36.00
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -3

Brought from Comp.MB -Construction of divider and widening of road from


22.20
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -6

Total cum 0.00 108.60 108.60 296.00 32145.60

2 22 Dismantling of flexible pavements and disposal of dismantled


materials up to a lead of 50 metres as directed by Engineer.
Granular courses : Divider

Brought from Comp.MB -Construction of divider and widening of road from


235.20
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -1

Brought from Comp.MB -Construction of divider and widening of road from


168.00
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -3

Total cum 0.00 403.20 403.20 206.00 83059.20

3 23 Providing and laying lean cement concrete 1:4:8 in Sub- base


over a prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not exceeding
25 mm, aggregate cement ratio not to exceed 15:1, aggregate
gradation after blending to be as per table 600-1, cement content
not to be less than 150 kg/ cum,

Brought from Comp.MB -Construction of divider and widening of road from


50.40
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -1

Brought from Comp.MB -Construction of divider and widening of road from


36.00
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -4

Total cum 0.00 86.40 86.40 2300.00 198720.00

4 Reinforcement for R.C.C. work at all levels including straightening,


cutting, bending, placing in position and binding all complete.

27 Brought from Comp.MB -Construction of divider and widening of road from


6.79
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -2

Brought from Comp.MB -Construction of divider and widening of road from


4.86
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -4

Total Tonne 0.00 11.65 11.65 51400.00 598861.40

Sign. of PMC Engr. MAKARWALI ROAD/1st R.Bill/Abst./Page No:-1 Sign. of Contractor


AJMER SMART CITY LIMITED AJMER
Abstract of 1St R.A Bill
Name of Name :- Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Billing :- 14.02.2021
Date of
Name of Contractor :- M/s MLA NBCC ( A Joint Venture) Commenceme :- 18.12.2020
nt
Date of
LoA No:- ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020 Completion
:- 17.06.2021
Amount of Contract:- 62982048.06
Qty upto This Bill Upto date
S. No BoQ No. Item Description Unit Rate Amount Remark
Last Bill Qty. Gross Qty

5 Providing and laying structural plain/ reinforced cement concrete (design mix) of
specified grade in substructure at all levels using batching plant, transit mixer, concrete
pump and vibrater including cost of form work complete as per drawing and clause
1500, 1700 and 2200 of MoRT&H specification including all scaffolding, material,
labour, machinery etc.
RCC Grade M -20

25
Brought from Comp.MB -Construction of divider and widening of road from
180.60
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -2

Brought from Comp.MB -Construction of divider and widening of road from


129.00
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -4

Total cum 0.00 309.60 309.60 4700.00 1455120.00 F.R.= 5180

6 Earth work in excavation for roadway, including trimming bottom and side slopes
in accordance with requirement of line, grades and cross sections, including disposal
of surplus material with all lift and lead upto 1000 metre as per MoRT&H
specification clause 301.
In all type of soil cum

Brought from Comp.MB -Construction of divider and widening of road from


794.77
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -2

3
Brought from Comp.MB -Construction of divider and widening of road from
713.98
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -5

Brought from Comp.MB -Construction of divider and widening of road from


1050.72
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -6

Total Cum 0.00 2559.47 2559.47 145.00 371123.15

7 Providing, laying, spreading and compacting of granular sub-base by providing


close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed
Material to work site, spreading in uniform layers with motor grader on prepared
surface and compacting with vibratory power roller to achieve the desired density,
complete as per MoRT&H specification clause - 401 including all material, labour,
machinery, lighting, guarding and maintenance of diversion.
: Grading - I Material cum

Brought from Comp.MB -Construction of divider and widening of road from


244.02
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -2
4

Brought from Comp.MB -Construction of divider and widening of road from


216.49
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -5

Brought from Comp.MB -Construction of divider and widening of road from


398.49
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -7

Total Cum 0.00 859.00 859.00 1070.00 919130.00

Sign. of PMC Engr. MAKARWALI ROAD/1st R.Bill/Abst./Page No:-2 Sign. of Contractor


AJMER SMART CITY LIMITED AJMER
Abstract of 1St R.A Bill
Name of Name :- Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Billing :- 14.02.2021
Date of
Name of Contractor :- M/s MLA NBCC ( A Joint Venture) Commenceme :- 18.12.2020
nt
Date of
LoA No:- ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020 Completion
:- 17.06.2021
Amount of Contract:- 62982048.06
Qty upto This Bill Upto date
S. No BoQ No. Item Description Unit Rate Amount Remark
Last Bill Qty. Gross Qty

8 Providing, laying, spreading (with paver finisher only) and


compacting wet mix macadam (WMM) base course comprising of graded stone
aggregate and granular material conforming to MORT&H specifications (Table 400-
II) in layers of equal compacted thickness each consolidated, including pre-mixing the
material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed
material by tippers to site, laying in uniform layers in base course on a well prepared
sub-base/ base course and compacting with power vibratory-roller to achieve the
desired density complete as per MoRT&H specification clause - 406 including all
material, labour, machinery, lighting, guarding and maintenance of diversion.

5 Brought from Comp.MB -Construction of divider and widening of road from


402.90
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. - 3

Brought from Comp.MB -Construction of divider and widening of road from


366.98
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -6

Brought from Comp.MB -Construction of divider and widening of road from


656.81
charan sansthan to Bheru Bada Makarwali road/1st R.Bill/RM/Page No. -7

Total Cum 0.00 1426.69 1426.69 1000.00 1426690.00 Full Rate-1360

Gross Total (G.Schedule + Extra) 5,084,849.35


less T.p. @ 34.71% (Below) 1,764,951.21
Net Grand Total 3,319,898.14
Total Net Amount paid upto last Bill -
Net Amount of 5th Running Bill 3,319,898.14
Say in Rs. 3,319,898.00
Verified for :- Rs. Thirty Three Lakh Nineteen Thousand Eight Hundred and Ninety Eight Only
Certified that
1 work is satisfactory.
2 work has been carried out as per specification & contract agreement & found satisfactory.
3 Nothing is out standing against the contractor up to this bill.
4 Quality control test has been conducted as per specification and enclosed.
5 Photograph has been enclosed before execution of work during and after execution of work and verified.
6 Bill recommendation for payment Rs. 33,19,898.00/-

Sign of Contractor Civil Engg (PMC) Road Engg. (PMC) Team Leader (PMC)

AEN ACE CE

Sign. of PMC Engr. MAKARWALI ROAD/1st R.Bill/Abst./Page No:-3 Sign. of Contractor


Ajmer Smart City Limited
Name of Work
Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Commencement :- 18.12.2020
:-
Name of
M/S MLA - NBCC ( A Joint Venture) Date of completion :- 17.06.2021
Contractor
LoA No :-
ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020
:-
W.O. Amount :- 62982048.06
Computerised MEASUREMENT Book of : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
G.Sch.
S.No. Item Item Description No. L B H Qty Unit C.F. to Page Remark
Code
Record Entry Date :- 10.1.2021
Dismantling of flexible pavements and disposal of dismantled
1 21 materials up to a lead of 50 metres as directed by Engineer.
Bituminous courses : Divider
RHS & LHS divider from CH-3/370 to 3/570 ; L = 200 m 2 200 0.4 0.15 24
RHS & LHS divider from CH-3/130 to 3/350 ; L = 220 m 2 220 0.4 0.15 26.4

Total= 50.4 Cum

Dismantling of flexible pavements and disposal of dismantled


2 22 materials up to a lead of 50 metres as directed by Engineer.
Granular courses : Divider
RHS & LHS divider from CH-3/370 to 3/570 ; L = 200 m 2 200 1.4 0.2 112
RHS & LHS divider from CH-3/130 to 3/350 ; L = 220 m 2 220 1.4 0.2 123.2

Total= 235.2 Cum

Providing and laying lean cement concrete 1:4:8 in Sub- base over a
prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the
3 23 size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table 600-1,
cement content not to be less than 150 kg/ cum,
RHS & LHS divider from CH-3/370 to 3/570 ; L = 200 m 2 200 0.4 0.15 24
RHS & LHS divider from CH-3/130 to 3/350 ; L = 220 m 2 220 0.4 0.15 26.4 440

Total= 50.4 Cum


Reinforcement for R.C.C. work at all levels including straightening, cutting,
bending, placing in position and binding all complete. No. of Bar Per Wt per
4 27 Cut L Total Wt
Elem. elem. unit L

RHS & LHS divider from CH-3/370 to 3/570 ; L = 200 m. TMT Bar = 8ø;
2 1001 2.05 0.395 1621.12
N=(200/.20)=1000 , i.e. 1000 +1=1001 Nos
Longitudinal TMT Bar = 8ø; 10 Nos 2 10 200 0.395 1580
Laps = 200/12 =16.66 i.e. ( 16 -6 (Expans. Joint) = 10 lapping Point) &
2 10 4 0.395 31.6
Cum. Lap Length for one Bar= 10x.4=4.0m
RHS & LHS divider from CH-3/130 to 3/350 ; L = 220 m. TMT Bar = 8ø;
2 1101 2.05 0.395 1783.07
N=(220/.20)=1100 , i.e. 1100 +1=1101 Nos
Longitudinal TMT Bar = 8ø; 10 Nos 2 10 220 0.395 1738
Laps = 220/12 =18.33 i.e. ( 18 -6 (Expans. Joint) = 12 lapping Point) &
2 10 4.8 0.395 37.92
Cum. Lap Length for one Bar= 12x.4=4.8m

Total= 6791.71 Kg

Providing and laying structural plain/ reinforced cement concrete (design


mix) of specified grade in substructure at all levels using batching plant, transit
mixer, concrete pump and vibrater including cost of form work complete as per
5 25 drawing and clause 1500, 1700 and 2200 of MoRT&H specification including
all scaffolding, material, labour, machinery etc.
RCC Grade M -20

RHS & LHS divider from CH-3/370 to 3/570 ; L = 200 m 2 200 0.15 0.4 24.00
2 200 0.25 0.20 20.00
2 200 0.30 0.35 42.00
RHS & LHS divider from CH-3/130 to 3/350 ; L = 220 m 2 220 0.15 0.4 26.40
2 220 0.25 0.20 22.00
2 220 0.30 0.35 46.20

Total= 180.60 Cum


Earth work in excavation for roadway, including trimming bottom and side
slopes in accordance with requirement of line, grades and cross sections,
including disposal of surplus material with all lift and lead upto 1000 metre as
3 per MoRT&H specification clause 301.
In all type of soil cum

LHS Ch 3/450 to 3/570 ; L 110 m ; W : Avg (3.30+2.90+3.20)(3.10+3.00+3.20)


(3.10+3.30+2.90)(3.40+3.30+2.90) 110 3.13 0.49 168.89

LHS Ch 3/240 to 3/450 ; L 180 m ; W : Avg (3.40+3.30+2.90)(2.90+3.40+3.40)


(3.40+3.50+3.70)(3.10+3.50+3.70)(3.40+3.40+3.10)(3.40+3.30+3.00)
(3.00+3.60+3.50) 180 3.33 0.49 293.71

LHS Ch 3/180 to 3/240 ; L 60 m ; W : Avg (4.00+3.90+3.60)(4.70+4.00+3.70)


40 3.98 0.49 78.01

LHS Ch 2/910 to 3/060 ; L 150 m ; W : Avg (4.70+3.40+3.60)(4.10+4.40+3.60)


(4.10+3.30+3.80)(3.90+3.30+3.90)(4.40+4.60+4.70) 130 3.99 0.49 254.16

Total= 794.77 Cum

Sign. of PMC Engr. Widening of Road from Ambedkar Circle to MDS Tiraha/2nd R.Bill/RM/Page No.-4 Sign. of Contractor
Ajmer Smart City Limited
Name of Work
Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Commencement :- 18.12.2020
:-
Name of
M/S MLA - NBCC ( A Joint Venture) Date of completion :- 17.06.2021
Contractor
LoA No :-
ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020
:-
W.O. Amount :- 62982048.06
Computerised MEASUREMENT Book of : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
G.Sch.
S.No. Item Item Description No. L B H Qty Unit C.F. to Page Remark
Code

Providing, laying, spreading and compacting of granular sub-base by


providing close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform layers with motor
grader on prepared surface and compacting with vibratory power roller to
achieve the desired density, complete as per MoRT&H specification clause -
4
401 including all material, labour, machinery, lighting, guarding and
maintenance of diversion.
: Grading - I Material cum

LHS Ch 3/450 to 3/570 ; L 110 m ; W : Avg (3.30+2.90+3.20)(3.10+3.00+3.20)


110 3.13 0.15 51.70
(3.10+3.30+2.90)(3.40+3.30+2.90)
LHS Ch 3/240 to 3/450 ; L 180 m ; W : Avg (3.40+3.30+2.90)(2.90+3.40+3.40)
(3.40+3.50+3.70)(3.10+3.50+3.70)(3.40+3.40+3.10)(3.40+3.30+3.00) 180 3.33 0.152 91.11
(3.00+3.60+3.50)
LHS Ch 3/180 to 3/240 ; L 60 m ; W : Avg (4.00+3.90+3.60)(4.70+4.00+3.70)
40 3.98 0.147 23.40
LHS Ch 2/910 to 3/060 ; L 150 m ; W : Avg (4.70+3.40+3.60)(4.10+4.40+3.60)
(4.10+3.30+3.80)(3.90+3.30+3.90)(4.40+4.60+4.70) 130 3.99 0.15 77.81

Total= 244.02 Cum

Providing, laying, spreading (with paver finisher only) and


compacting wet mix macadam (WMM) base course comprising of graded
stone aggregate and granular material conforming to MORT&H specifications
(Table 400-II) in layers of equal compacted thickness each consolidated,
including pre-mixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tippers to site, laying in uniform layers in
5 base course on a well prepared sub-base/ base course and compacting with
power vibratory-roller to achieve the desired density complete as per MoRT&H
specification clause - 406 including all material, labour, machinery, lighting,
guarding and maintenance of diversion.

LHS Ch 3/450 to 3/570 ; L 110 m ; W : Avg (3.30+2.90+3.20)(3.10+3.00+3.20)


110 3.13 0.25 86.17
(3.10+3.30+2.90)(3.40+3.30+2.90)
LHS Ch 3/240 to 3/450 ; L 180 m ; W : Avg (3.40+3.30+2.90)(2.90+3.40+3.40)
(3.40+3.50+3.70)(3.10+3.50+3.70)(3.40+3.40+3.10)(3.40+3.30+3.00) 180 3.33 0.247 148.05
(3.00+3.60+3.50)
LHS Ch 3/180 to 3/240 ; L 60 m ; W : Avg (4.00+3.90+3.60)(4.70+4.00+3.70)
40 3.98 0.245 39.00
LHS Ch 2/910 to 3/060 ; L 150 m ; W : Avg (4.70+3.40+3.60)(4.10+4.40+3.60)
(4.10+3.30+3.80)(3.90+3.30+3.90)(4.40+4.60+4.70) 130 3.99 0.25 129.68

Total= 402.90 Cum

Record Entry Date :- 25.1.2021


Dismantling of flexible pavements and disposal of dismantled
1 21 materials up to a lead of 50 metres as directed by Engineer.
Bituminous courses : Divider
RHS & LHS divider from CH-3/000 to 3/120 ; L = 120 m 2 120 0.4 0.15 14.4
RHS & LHS divider from CH-2/560 to 2/740 ; L = 180 m 2 180 0.4 0.15 21.6

Total= 36 Cum

Dismantling of flexible pavements and disposal of dismantled


2 22 materials up to a lead of 50 metres as directed by Engineer.
Granular courses : Divider
RHS & LHS divider from CH-3/000 to 3/120 ; L = 120 m 2 120 1.4 0.2 67.2
RHS & LHS divider from CH-2/560 to 2/740 ; L = 180 m 2 180 1.4 0.2 100.8

Total= 168 Cum

Providing and laying lean cement concrete 1:4:8 in Sub- base over a
prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the
3 23 size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table 600-1,
cement content not to be less than 150 kg/ cum,
RHS & LHS divider from CH-3/000 to 3/120 ; L = 120 m 2 120 0.4 0.15 14.4
RHS & LHS divider from CH-2/560 to 2/740 ; L = 180 m 2 180 0.4 0.15 21.6 360
0

Total= 36 Cum

Sign. of PMC Engr. Widening of Road from Ambedkar Circle to MDS Tiraha/2nd R.Bill/RM/Page No.-5 Sign. of Contractor
Ajmer Smart City Limited
Name of Work
Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Commencement :- 18.12.2020
:-
Name of
M/S MLA - NBCC ( A Joint Venture) Date of completion :- 17.06.2021
Contractor
LoA No :-
ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020
:-
W.O. Amount :- 62982048.06
Computerised MEASUREMENT Book of : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
G.Sch.
S.No. Item Item Description No. L B H Qty Unit C.F. to Page Remark
Code
Reinforcement for R.C.C. work at all levels including straightening, cutting,
bending, placing in position and binding all complete. No. of Bar Per Wt per
4 27 Cut L Total Wt
Elem. elem. unit L

RHS & LHS divider from CH-3/000 to 3/120 ; L = 120 m. TMT Bar = 8ø;
2 601 2.05 0.395 973.32
N=(120/.20)=600 , i.e. 600 +1=601 Nos
Longitudinal TMT Bar = 8ø; 10 Nos 2 10 120 0.395 948
Laps = 120/12 =10 i.e. ( 10 -2 (Expans. Joint) = 8 lapping Point) &
2 10 3.2 0.395 25.28
Cum. Lap Length for one Bar= 8x.4=3.2m
RHS & LHS divider from CH-2/560 to 2/740 ; L = 180 m. TMT Bar = 8ø;
2 901 2.05 0.395 1459.17
N=(180/.20)=900 , i.e. 900 +1=901 Nos
Longitudinal TMT Bar = 8ø; 10 Nos 2 10 180 0.395 1422
Laps = 180/12 =15 i.e. ( 15 -5 (Expans. Joint) = 10 lapping Point) &
2 10 4 0.395 31.6
Cum. Lap Length for one Bar= 10x.4=4.0m

Total= 4859.37 Kg

Providing and laying structural plain/ reinforced cement concrete (design


mix) of specified grade in substructure at all levels using batching plant, transit
mixer, concrete pump and vibrater including cost of form work complete as per
5 25 drawing and clause 1500, 1700 and 2200 of MoRT&H specification including
all scaffolding, material, labour, machinery etc.
RCC Grade M -20

RHS & LHS divider from CH-3/000 to 3/120 ; L = 120 m 2 120 0.15 0.4 14.40
2 120 0.25 0.20 12.00
2 120 0.30 0.35 25.20
RHS & LHS divider from CH-2/560 to 2/740 ; L = 180 m 2 180 0.15 0.4 21.60
2 180 0.25 0.20 18.00
2 180 0.30 0.35 37.80

Total= 129.00 Cum

Earth work in excavation for roadway, including trimming bottom and side
slopes in accordance with requirement of line, grades and cross sections,
including disposal of surplus material with all lift and lead upto 1000 metre as
3 per MoRT&H specification clause 301.
In all type of soil cum

LHS Ch 2/760 to 2/910 ; L 150 m ; W : Avg (3.60+3.90+4.70)(3.60+3.90+4.20)


(3.60+3.10+4.20)(3.60+3.90+3.60)(3.60+3.50+3.60) 135 3.770 0.49 249.39

LHS Ch 2/640 to 2/760 ; L 120 m ; W : Avg (3.60+3.40+3.60)(3.70+3.70+3.60)


100 3.600 0.49 176.40
(3.70+3.10+3.40)(3.90+3.10+4.40)
LHS Ch 2/520 to 2/640 ; L 120 m ; W : Avg (4.10+4.10+4.40)(5.3+4.10+4.50)
(5.3+5.70+5.70)(4.7+4.60+5.70) 90 4.200 0.49 185.22
LHS Ch 2/460 to 2/520 ; L 60 m ; W : Avg (4.7+4.50+4.60)(4.5+4.50+4.60)
45 4.670 0.49 102.97
Total= 713.98 Cum

Providing, laying, spreading and compacting of granular sub-base by


providing close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform layers with motor
grader on prepared surface and compacting with vibratory power roller to
achieve the desired density, complete as per MoRT&H specification clause -
4
401 including all material, labour, machinery, lighting, guarding and
maintenance of diversion.
: Grading - I Material cum

LHS Ch 2/760 to 2/910 ; L 150 m ; W : Avg (3.60+3.90+4.70)(3.60+3.90+4.20)


(3.60+3.10+4.20)(3.60+3.90+3.60)(3.60+3.50+3.60) 135 3.770 0.15 76.34

LHS Ch 2/640 to 2/760 ; L 120 m ; W : Avg (3.60+3.40+3.60)(3.70+3.70+3.60)


100 3.600 0.146 52.56
(3.70+3.10+3.40)(3.90+3.10+4.40)
LHS Ch 2/520 to 2/640 ; L 120 m ; W : Avg (4.10+4.10+4.40)(5.3+4.10+4.50)
90 4.200 0.15 56.70
(5.3+5.70+5.70)(4.7+4.60+5.70)
LHS Ch 2/460 to 2/520 ; L 60 m ; W : Avg (4.7+4.50+4.60)(4.5+4.50+4.60)
45 4.670 0.147 30.89
Total= 216.49 Cum

Providing, laying, spreading (with paver finisher only) and


compacting wet mix macadam (WMM) base course comprising of graded
stone aggregate and granular material conforming to MORT&H specifications
(Table 400-II) in layers of equal compacted thickness each consolidated,
including pre-mixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tippers to site, laying in uniform layers in
5 base course on a well prepared sub-base/ base course and compacting with
power vibratory-roller to achieve the desired density complete as per MoRT&H
specification clause - 406 including all material, labour, machinery, lighting,
guarding and maintenance of diversion.

LHS Ch 2/760 to 2/910 ; L 150 m ; W : Avg (3.60+3.90+4.70)(3.60+3.90+4.20)


(3.60+3.10+4.20)(3.60+3.90+3.60)(3.60+3.50+3.60) 135 3.770 0.254 129.27

LHS Ch 2/640 to 2/760 ; L 120 m ; W : Avg (3.60+3.40+3.60)(3.70+3.70+3.60)


100 3.600 0.25 90.00
(3.70+3.10+3.40)(3.90+3.10+4.40)
LHS Ch 2/520 to 2/640 ; L 120 m ; W : Avg (4.10+4.10+4.40)(5.3+4.10+4.50)
90 4.200 0.254 96.01
(5.3+5.70+5.70)(4.7+4.60+5.70)
LHS Ch 2/460 to 2/520 ; L 60 m ; W : Avg (4.7+4.50+4.60)(4.5+4.50+4.60)
45 4.670 0.246 51.70

Sign. of PMC Engr. Widening of Road from Ambedkar Circle to MDS Tiraha/2nd R.Bill/RM/Page No.-6 Sign. of Contractor
Ajmer Smart City Limited
Name of Work
Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer Date of Commencement :- 18.12.2020
:-
Name of
M/S MLA - NBCC ( A Joint Venture) Date of completion :- 17.06.2021
Contractor
LoA No :-
ASCL/NIT-62/2020-21/4408 Dated :- 18.12.2020
:-
W.O. Amount :- 62982048.06
Computerised MEASUREMENT Book of : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
G.Sch.
S.No. Item Item Description No. L B H Qty Unit C.F. to Page Remark
Code
Total= 366.98 Cum
Record Entry Date :- 14.2.2021

Dismantling of flexible pavements and disposal of dismantled


2 21 materials up to a lead of 50 metres as directed by Engineer.
Bituminous Coursecourses : Divider
RHS & LHS divider from CH-2/400 to 2/545 ; L = 145 m 2 145 0.4 0.15 17.4
RHS divider from CH-2/320 to 2/400 ; L = 80 m 1 80 0.4 0.15 4.8
Total= 22.20 Cum

Earth work in excavation for roadway, including trimming bottom and side
slopes in accordance with requirement of line, grades and cross sections,
including disposal of surplus material with all lift and lead upto 1000 metre as
3 per MoRT&H specification clause 301.
In all type of soil cum

LHS Ch 2/280 to 2/460 ; L 180 m ; W : Avg (4.5+4.70+5.40)(5.8+5.80+5.40)


(5.8+4.80+4.80)(4.7+4.80+4.90)(4.7+4.50+4.70)(4.6+4.90+4.80) 160 4.983 0.4 318.91

LHS Ch 2/160 to 2/280 ; L 120 m ; W : Avg (4.6+4.80+4.80)(4.10+4.50+4.80)


100 4.475 0.4 179.00
(4.10+4.40+4.50)(4.00+4.60+4.50)
LHS Ch 2/040 to 2/160 ; L 120 m ; W : Avg (4.00+4.60+4.20)(5.20+4.60+5.50)
90 4.708 0.4 169.49
(5.20+4.50+4.70)(4.80+4.50+4.70)
LHS Ch 1/890 to 2/040 ; L 150 m ; W : Avg (4.70+4.50+4.70)(4.70+4.60+4.70)
(4.80+4.60+4.50)(4.30+4.60+4.50)(4.30+4.40+4.60) 140 4.567 0.4 255.75
LHS Ch 1/800 to 2/890 ; L 90 m ; W : Avg (4.70+4.40+4.50)(4.50+4.80+4.50)
70 4.556 0.4 127.57
(4.40+4.70+4.50)
Total= 1050.72 Cum

Providing, laying, spreading and compacting of granular sub-base by


providing close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform layers with motor
grader on prepared surface and compacting with vibratory power roller to
achieve the desired density, complete as per MoRT&H specification clause -
4
401 including all material, labour, machinery, lighting, guarding and
maintenance of diversion.
: Grading - I Material cum

LHS Ch 2/280 to 2/460 ; L 180 m ; W : Avg (4.5+4.70+5.40)(5.8+5.80+5.40)


(5.8+4.80+4.80)(4.7+4.80+4.90)(4.7+4.50+4.70)(4.6+4.90+4.80) 160 4.983 0.154 122.78

LHS Ch 2/160 to 2/280 ; L 120 m ; W : Avg (4.6+4.80+4.80)(4.10+4.50+4.80)


100 4.475 0.15 67.13
(4.10+4.40+4.50)(4.00+4.60+4.50)
LHS Ch 2/040 to 2/160 ; L 120 m ; W : Avg (4.00+4.60+4.20)(5.20+4.60+5.50)
90 4.708 0.15 63.56
(5.20+4.50+4.70)(4.80+4.50+4.70)
LHS Ch 1/890 to 2/040 ; L 150 m ; W : Avg (4.70+4.50+4.70)(4.70+4.60+4.70)
(4.80+4.60+4.50)(4.30+4.60+4.50)(4.30+4.40+4.60) 140 4.567 0.154 98.46

LHS Ch 1/800 to 2/890 ; L 90 m ; W : Avg (4.70+4.40+4.50)(4.50+4.80+4.50)


70 4.556 0.146 46.56
(4.40+4.70+4.50)
Total= 398.49 Cum

Providing, laying, spreading (with paver finisher only) and


compacting wet mix macadam (WMM) base course comprising of graded
stone aggregate and granular material conforming to MORT&H specifications
(Table 400-II) in layers of equal compacted thickness each consolidated,
including pre-mixing the material with water at OMC in mechanical mixer (Pug
Mill), carriage of mixed material by tippers to site, laying in uniform layers in
5 base course on a well prepared sub-base/ base course and compacting with
power vibratory-roller to achieve the desired density complete as per MoRT&H
specification clause - 406 including all material, labour, machinery, lighting,
guarding and maintenance of diversion.

LHS Ch 2/280 to 2/460 ; L 180 m ; W : Avg (4.5+4.70+5.40)(5.8+5.80+5.40)


(5.8+4.80+4.80)(4.7+4.80+4.90)(4.7+4.50+4.70)(4.6+4.90+4.80) 160 4.983 0.25 199.32

LHS Ch 2/160 to 2/280 ; L 120 m ; W : Avg (4.6+4.80+4.80)(4.10+4.50+4.80)


100 4.475 0.25 111.88
(4.10+4.40+4.50)(4.00+4.60+4.50)
LHS Ch 2/040 to 2/160 ; L 120 m ; W : Avg (4.00+4.60+4.20)(5.20+4.60+5.50)
90 4.708 0.254 107.62
(5.20+4.50+4.70)(4.80+4.50+4.70)
LHS Ch 1/890 to 2/040 ; L 150 m ; W : Avg (4.70+4.50+4.70)(4.70+4.60+4.70)
(4.80+4.60+4.50)(4.30+4.60+4.50)(4.30+4.40+4.60) 140 4.567 0.25 159.85

LHS Ch 1/800 to 2/890 ; L 90 m ; W : Avg (4.70+4.40+4.50)(4.50+4.80+4.50)


70 4.556 0.245 78.14
(4.40+4.70+4.50)
Total= 656.81 Cum

Sign. of PMC Engr. Widening of Road from Ambedkar Circle to MDS Tiraha/2nd R.Bill/RM/Page No.-7 Sign. of Contractor
Government of Rajasthan
Ajmer Smart City Limited, Ajmer.
Name of work : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
Name of contrator : M/s MLA NBCC ( A Joint Venture)
ASCL/NIT-62/2020-21/4408
LOA No :
Dated :- 18.12.2020
Amount of Contract : 62982048.06
RA Bill No. & date of this RA Bill : 1st Running / 14.2.2021 Total Amount up to date: 3692800.00
RA Bill No. of his last Bill : None Amount of this Bill: 3692800.00
Stipulated Date of commencement : 18.12.2020
Stipulated date of completion ( Design & Build) 17.06.2021
Actual Commencement Date : 18.12.2020
Actual Date of completion : Work in progress
I. Account of Work Executed
TABLE - 1
Quantity executed as per Measurment Book Amount on the basis of actual measurments
BOQ Quantity as per
S.No Description Unit BOQ Rate Remarks
S.No BOQ As per Previous Since Previous Upto date As per Previous
Upto date As per this Bill
Running bill Bill Quantity Running bill

Dismantling of flexible
pavements and disposal of
dismantledmaterials up to a lead
1 21 cum 360.0000 296.00 108.60 108.60 32145.60 0 32145.60
of 50 metres as directed by
Engineer. Bituminous courses :
Divider

Dismantling of flexible
pavements and disposal of
dismantled materials up to a lead
2 22 cum 400.000 206.00 403.20 403.20 83059.20 0 83059.20
of 50 metres as directed by
Engineer. Granular courses :
Divider

Providing and laying lean


cement concrete 1:4:8 in Sub-
base over a prepared sub-grade
with coarse and fine aggregate
conforming to IS: 383, the size of
3 23 coarse aggregate not exceeding cum 420.000 2300.00 86.40 86.40 198720.00 0 198720.00
25 mm, aggregate cement ratio
not to exceed 15:1, aggregate
gradation after blending to be as
per table 600-1, cement content
not to be less than 150 kg/ cum,

Reinforcement for R.C.C. work


at all levels including
4 27 straightening, cutting, bending, Tonne 190.000 51400.00 11.651 11.651 598861.40 0 598861.40
placing in position and binding all
complete.

Providing and laying structural


plain/ reinforced cement
concrete (design mix) of
specified grade in substructure at
all levels using batching plant,
transit mixer, concrete pump and
Full Rate-
5 25 vibrater including cost of form cum 1920.000 4700.00 309.60 309.60 1455120.00 0 1455120.00
5180
work complete as per drawing
and clause 1500, 1700 and 2200
of MoRT&H specification
including all scaffolding, material,
labour, machinery etc.
RCC Grade M -20

Earth work in excavation for


roadway, including trimming
bottom and side slopes in
accordance with requirement of
line, grades and cross sections,
6 3 including disposal of surplus cum 21600.000 145.00 2559.47 2559.47 371123.15 0 371123.15
material with all lift and lead upto
1000 metre as per MoRT&H
specification clause 301.
In all type of soil cum

Makarwali Road/1st R. Bill/Bill Form/Page No:-8


Government of Rajasthan
Ajmer Smart City Limited, Ajmer.
Name of work : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
Name of contrator : M/s MLA NBCC ( A Joint Venture)
ASCL/NIT-62/2020-21/4408
LOA No :
Dated :- 18.12.2020
Amount of Contract : 62982048.06
RA Bill No. & date of this RA Bill : 1st Running / 14.2.2021 Total Amount up to date: 3692800.00
RA Bill No. of his last Bill : None Amount of this Bill: 3692800.00
Stipulated Date of commencement : 18.12.2020
Stipulated date of completion ( Design & Build) 17.06.2021
Actual Commencement Date : 18.12.2020
Actual Date of completion : Work in progress
I. Account of Work Executed
TABLE - 1
Quantity executed as per Measurment Book Amount on the basis of actual measurments
BOQ Quantity as per
S.No Description Unit BOQ Rate Remarks
S.No BOQ As per Previous Since Previous Upto date As per Previous
Upto date As per this Bill
Running bill Bill Quantity Running bill

Providing, laying, spreading


and compacting of granular
sub-base by providing close
graded Material, mixing in a
mechanical mix plant at OMC,
carriage of mixed Material to
work site, spreading in uniform
layers with motor grader on
prepared surface and
7 4 cum 5386.500 1070.00 859.00 859.00 919130.00 0 919130.00
compacting with vibratory power
roller to achieve the desired
density, complete as per
MoRT&H specification clause -
401 including all material, labour,
machinery, lighting, guarding and
maintenance of diversion.
: Grading - I Material cum

Providing, laying, spreading (with


paver finisher only) and
compacting wet mix macadam
(WMM) base course comprising
of graded stone aggregate and
granular material conforming to
MORT&H specifications (Table
400-II) in layers of equal
compacted thickness each
consolidated, including pre-
mixing the material with water at
OMC in mechanical mixer (Pug Full Rate-
8 5 cum 5630.625 1000.00 1426.69 1426.69 1426690.00 0 1426690.00
Mill), carriage of mixed material 1360
by tippers to site, laying in
uniform layers in base course on
a well prepared sub-base/ base
course and compacting with
power vibratory-roller to achieve
the desired density complete as
per MoRT&H specification clause
- 406 including all material,
labour, machinery, lighting,
guarding and maintenance of
diversion.
Total Amount 5084849.35 0.00 5084849.35
Less T.P.@34.71 -1764951.21 0.00 -1764951.21
Net Amount 3319898.14 0.00 3319898.14
Say in Rs. 3,319,898.00

I- Verified for Rs. 33,19,898 only.


( In words :Rs. Thirty Three Lakh Nineteen Thousand Eight Hundred and Ninety Eight Only)

II-Certificate and signature


1 The measurements were made & Checked by PMC Engineers .
2 The material has been supplied as per specifications.
3 The inspection, tests report , photographs of work executed is enclosed.
4 All T&P and materials have been arranged by the contractor on his own level.
5 Nothing is outstanding against the contractor.

Signature of contractor Signature of PMC Engg. Road Engg. (PMC) Signature of PMC Team Leader

JEN AEN (Civil) ACE CE

Makarwali Road/1st R. Bill/Bill Form/Page No:-9


Government of Rajasthan
Ajmer Smart City Limited, Ajmer.
Name of work : Construction of divider and widening of road from charan sansthan to Bheru Bada Makarwali road Ajmer
Name of contrator : M/s MLA NBCC ( A Joint Venture)
ASCL/NIT-62/2020-21/4408
LOA No :
Dated :- 18.12.2020
RA Bill No. & date of this RA Bill : 1st Running / 14.2.2021 Amount of Contract : 62982048.06
RA Bill No. of his last Bill : None Total Amount up to date: 3692800.00
Stipulated Date of commencement : 18.12.2020 Amount of this Bill: 3414104.00
Stipulated date of completion ( Design & Build) : 17.06.2021
Actual Commencement Date : 18.12.2020
Actual Date of completion : Work in progress

Excess Item Slip Up to 1st R.A Bill


BOQ ITEM Qty As Per G- Qty As Per Site Excess Qty Excess Qty Unit Rate Amount Remarks
S.No Schedule %
Dismantling of flexible pavements
and disposal of dismantled
materials up to a lead of 50 metres
22 as directed by Engineer. Granular 400.00 403.20 3.20 0.80% Cum 206.00 659.20
courses : Divider

GRAND TOTAL 659.20


Less TP @34.71% 228.81
Net Amount 430.39

Contractor Civil Engg (PMC) Team Leader (PMC)

JEN AEN EE ACE CE