Professional Documents
Culture Documents
1. Executive Summary 3
2. Test Prerequisites 3
3. Test Information 6
3.1. Overview 6
4. Instrumentation 6
5. Staffing 7
7. Appendices 8
Page 2 of 7
1. EXECUTIVE SUMMARY
This Black Building IST Testing Method Statement has been prepared by AE ARMA-ELEKTROPANC for
the MEP works undertaken by BAKU BOULEVARD HOTEL PROJECT.
This Method Statement has been prepared to record the operation, performance and integration of the
installed fire life safety systems during an emergency or electrical failure / part failure scenario.
The testing will consist of a number of different subsequent tests under various power configurations. The
testing that will be carried out ensures that the generator backed systems function correctly during a power
failure, and also that all the various systems restart after mains power restoration without going into alarm
or fault mode.
Once a test is completed, the attached sample test sheet can be filled out with the test data gathered from
the logs exported.
2. TEST PREREQUISITES
The Contractor’s T&C for Mechanical/Electrical Group has the overall responsibility for the implementation
of this Method Statement.
The Contractor’s T&C MEP Coordinator will ensure that the resources are available to carry out the works
as per approved drawings, method of statement, and work as scheduled.
The Contractor’s Site Engineer/Supervisor is responsible to ensure that the work has been carried out as
per approved drawings, method statements and assist inspection.
The Contractor’s commissioning technician/s is responsible to ensure that they are abiding the method of
statement to achieve the required data as per equipment schedule and project specification.
The Contractor Safety Officer will assist in all issues related to the HSE.
All of the system documentation and record drawings shall be available for reference, additionally there
should be back up of the latest system configurations of all fire panels.
AE Arma-Elektropanc – Electrical
Page 3 of 7
Emerson – UPS
Schindler – Lifts
Preaction System
Preaction system in generator room functional and interfaced with Fire Alarm.
Any required keys/tools available.
Page 4 of 7
3. TEST INFORMATION
3.1 OVERVIEW
The information provided in the appendix is a guide to the required state of all of the building assets during
the following different conditions simulated for this test, as listed below:
TEST 1
TEST 2
TEST 3
TEST 4
TEST 5
TEST 1
TEST 2
Until the generator kicks off, check the emergency lighting on escape routes during 20 seconds
synchronisation.
After 20 seconds complete, verify that two generator sets take over the power.
Verify that only one generator runs according to low load demand.
Page 5 of 7
TEST 3
TEST 4
Perform random Cause & Effect tests in the building while still on generator power. Verify that fire alarm
system and all integrated systems perform as per the latest Cause & Effect Matrix:
2. Activate a manual call point in ground floor fire detection / evacuation zones
Alarm on Fire Alarm panel
All strobes and sounders in zone activate
HVAC serving zone stops
Access Control on doors releases
Solenoid valve closes
Background music stops
Lighting control activates
Door openers activate
Smoke extract fans start
TEST 5
Restore MV. Verify that MV takes over the power. Verify that all systems are healthy and building is back
in normal condition.
4. INSTRUMENTATION
Radio Communication
Smoke Detector Tester Pole
Smoke Test Sprays (sufficient amount of cans)
Heat Detector Tester Pole
Key for Manual Call Points
Page 6 of 7
5. STAFFING
During tests, the personnel involved could be exposed to risks of electrocution or other dangers related
with live working. All personnel will have valid Site Induction and Supervisor signed Permit to Work. Permit
to work or operate the systems will be on place before starting the work.
A team of experienced and well qualified safety officers will be assigned to implement and control the Health
Safety & Environment Plan on site.
7. APPENDICES
Page 7 of 7