You are on page 1of 11

Energy Conversion and Management: X 20 (2023) 100490

Contents lists available at ScienceDirect

Energy Conversion and Management: X


journal homepage: www.sciencedirect.com/journal/energy-conversion-and-management-x

An eco-friendly remote sensing assisted development procedure to install


renewable energy infrastructure for highest techno-economic gain
Reza Fardi Asrami , Ali Sohani , Mona Zamani Pedram , Hoseyn Sayyaadi *
Optimization of Energy Installations Lab., Faculty of Mechanical Engineering-Energy Division, K.N. Toosi University of Technology, P.O. Box: 19395-1999, No. 15-19,
Pardis St., Mollasadra Ave., Vanak Sq., Tehran 1991 943344, Iran

A R T I C L E I N F O A B S T R A C T

Keywords: By taking socio-economic, terrain, and meteorological impacts into account, an eco-friendly methodology to sort
Geographic information system the potential locations for installation of renewable energy infrastructure has been proposed, which is also able to
Eco-friendly technology address the most important challenge in the field, i.e., determination of the best contribution of the renewable
Renewable energy
energy sources. For this purpose, three advanced approaches, namely, remote sensing by geographic information
Techno-economic gain
Clean energy production
system (GIS), optimization, and weighted decision-making are employed. Moreover, a sensitivity analysis is
conducted to evaluate the influence of land prices, nominal capacity, and relative importance of technical and
economic indicators in decision-making. Iran is chosen as the case study because it has significant solar and wind
energy potential and also has serious energy, economic, and environmental issues. The findings indicate an
optimal land price of $200 per m2, a hub nominal capacity of 50 MW, and an equal weighting of objective
functions for the case study. The average energy generation, levelized cost of energy (LCOE), PV ratio, and land
utilization are projected to reach 288.5 GWh.year− 1, 0.3260 $.(kWh)-1, 4.15 %, and 2362334 m2, respectively
when the optimal procedure is applied. The sensitivity study also shows that relative to PV, the contribution of
wind turbines increases with plant size.

demand in low radiation days, while PV panels can maintain the energy
1. Introduction flow in case the wind turbine is not working [19–21].
Choosing the location of a wind-PV hybrid system is of great
Environmental pollutions have been on a steady rise in past decades, importance [22]. A minimum of annual radiation and average wind
caused by heavy dependency of energy sector to fossil fuels [1–3]. speed should be considered, since a location with low wind speed not
Renewable energies are reasonable alternatives to not only reduce the only can cause damage to the turbines [23], but it also will not produce
dependency on limited fossil fuels, but also manage the ever-growing enough energy to make the investment justifiable from economic aspects
environmental problems [4–6]. The growth rate for renewable energy [24]. Different factors affect the generated energy of solar and wind
usage between 2009 and 2019 have been 13.4 % per annum, while this farms e.g., radiation, wind speed, terrain slope, elevation, and orienta­
growth rate for 2020 was 9.7 % [7]. Solar and wind energies are tion of the panels [25]. A hybrid system should have a minimum dis­
considered as the main sources of renewable energy production, with tance to residential areas to avoid inconvenience to human life, and it
wind and PV farms producing 50 % and 27 % of the total, respectively should not be located too far from main roads for ease of availability
[8–10]. PV panels are noiseless, can be used in small scales, and are [26]. Using a Geographic information system (GIS) approach for site
functional if one of them gets damaged, while wind turbines are mostly selection of hybrid power plants can provide the opportunity to exclude
used in large scales, and produce a more constant energy [11–13]. On unsuitable locations based on the geographical restrictions [27].
the other hand, both of these two energy sources have their own dis­ Furthermore, on-site configuration of PV panel and wind turbine is of
advantages [14–16]. PV farms are dysfunctional in sunless days, and great importance, since the optimized energy production is dependent
wind turbines can get damaged if the wind speed drops below a certain on the ratio of PV/wind potential of each location [28].
amount, which can cause fluctuation in energy production flow [17]. A Saraswat et al. [29] used GIS and MCDM to find the locations of solar
wind-PV hybrid system can overcome these obstacles, and improve the and wind farms in India. Evaluation criteria are divided into technical,
reliability of the power plant [18]. The wind turbines can meet the socio-environmental, and economic factors. Investigated locations are

* Corresponding author.
E-mail address: sayyaadi@kntu.ac.ir (H. Sayyaadi).

https://doi.org/10.1016/j.ecmx.2023.100490
Received 30 July 2023; Received in revised form 15 October 2023; Accepted 14 November 2023
Available online 15 November 2023
2590-1745/© 2023 The Author(s). Published by Elsevier Ltd. This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/).
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

Nomenclature Abbreviations
AHP Analytic hierarchy process
Ap Panel’s area (m2) BOS Balance of system
At Turbine’s swept area (m2) CRF Capital recovery factor
Ccap Initial capital cost ($) GIS Geographical information system
Co&m Cost of operation and maintenance ($) LCOE Levelized cost of energy
Ctotal Total annualized cost ($) MCDM Multi-criteria decision-making
d Discount rate MDBP Minimum distance between panels
D Rotor diameter (m) NOCT Nominal operating cell temperature
G Annual radiation STC Standard test condition
GSTC Radiation under STC (W.m-2) TOPSIS Technique for order of preference by similarity to ideal
n Life span of hybrid farm (years) solution
PPV Produced energy from PV panels (kWh) PV Photovoltaic
Ptotal Total produced energy from hybrid farm (kWh)
Greek symbols
Pw Produced energy from wind turbine (kWh)
α Altitude angle (Degrees)
T Panel temperature (℃)
η Panel’s efficiency
Ta Ambient temperature (℃)
ηm Modified efficiency of panel
Tcoeff Temperature coefficient of panel (%.K-1)
θ Tilt angle of panel (Degrees)
TSTC Temperature under STC (℃)
ρ Air density (kg.m− 3)
V Average wind speed (m.s-1)
Wp Width of the panel
z Azimuth angle

grouped into five categories of highly suitable, suitable, moderately urban areas, and land-use were attributes for infrastructure and envi­
suitable, less suitable, and not suitable, but the site-selection was done ronment criteria. A weight was assigned to all of the criteria for optimum
separately for PV and wind farms. site selection using the rank-sum method.
On another study, Ali et al. [30] explored suitable areas to set hybrid Table 1 contains other recently conducted studies for hybrid, solar,
PV-wind farms, by multi-criteria GIS modeling techniques. A minimum and wind farms site selection. Based on the criteria in Table 1, gap of
wind velocity of 4 m.s− 1, irradiance of 3.5 kW.m− 2.day− 1, and other knowledge in the previous studies is outlined as:
factors like slope and residential buffers has been considered to exclude
unsuitable locations. Furthermore, AHP approach was used as a MCDM • Using GIS for site selection of solar, wind, or hybrid power plants can
to evaluate the remaining location. help eliminate unsuitable locations. In some cases, a location was
Effat et al. [31] used geospatial data for optimum selection of hybrid considered as case study, without considering the geographical
solar-wind energy sites in Egypt. Solar radiation, panel orientation, and limitation of renewable power plants.
slope were selected as limiting criteria for solar energy, while wind • A hybrid power plant can improve the reliability of the power pro­
speed, slope, and elevation were considered as wind energy criteria. duction and avoid fluctuation in energy flow. PV and wind criteria
Distance to conversion stations, distance to main roads, distance to

Table 1
Recent conducted studies.
Study Summary & approach GIS Hybrid site- Techno- Optimized on-site PV-
approach? selection? economic wind configuration?
analysis?

Dalwadi et al. Optimize stand-alone solar-wind hybrid power system and to maximize use of No No Yes No
[32] renewable energy generation system while minimizing the total system cost
Hatata et al. An optimization method for sizing a solar/wind/battery hybrid power system No No Yes No
[33] based on the artificial immune system
Ara et al. Two-level planning to assess the techno-economic feasibility of hybrid offshore No Yes Yes Yes
[34] wind-solar PV power plants
Tercan [35] Develop a GIS-Best Worst Method based Eco mentalist land suitability model to Yes No No No
identify optimal locations for wind farms
Tercan et al. Contribute to the growth, expansion, advancement, and location selection of Yes No No No
[36] PV farms using GIS, AHP, Weighted Linear Combination, and Inverse Distance
Weighting approaches
Cunden et al. A MCDM process together with GIS to analyze multiple constraints that affect Yes No No No
[37] the siting of wind farms
Xu et al. [38] A novel method integrating GIS, interval AHP and stochastic VIKOR was Yes No No No
proposed to tackle site selection issue of wind farms in the Wafangdian region,
China
Ifaei et al. An algorithm-based data processing, sizing, optimization, sensitivity analysis Yes Yes Yes No
[39] and clustering approach is proposed as an efficient simultaneous solar/wind
assessment methodology
Dhunny et al. Identification of optimal wind, solar and hybrid wind-solar farming sites using No Yes Yes No
[40] fuzzy logic modelling
Jahangiri Find the ideal locations for construction of hybrid solar-wind power stations in Yes Yes No No
et al. [41] Middle-East using Boolean model in GIS software

2
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

should be considered simultaneously for site selection, while most should be considered to avoid disruption of geographical development.
studies did not consider them at the same time. On the other hand, high distance to urban or rural areas creates acces­
• The produced energy affects the economic aspects of power plant, sibility issues, which makes the selected site less economically and so­
and justifiability of power plant from economic aspects can incen­ cially justifiable. For this study, a minimum and maximum distance of 2
tivize the investors. A techno-economic analysis of each location can and 10 km are selected, respectively.
be incredibly useful for optimized site-selection, but this analysis was Distance to main roads. A high distance with main roads makes
neglected in some of the studies. equipment and material transportation very hard. A minimum distance
• Annual radiation, average wind speed, elevation, and annual mean of 1 km is considered to avoid accidents, while a maximum of 10 km
temperature are different for each location, so the optimized distance is chosen for ease of transportation.
configuration of PV panels and wind turbines will be variable. The Distance to railways and airports. PV panels can cause problems
PV/wind energy production ratio should be calculated in each for the pilot’s vision, or there can be adverse effect on airplanes, caused
location, but only one of the recent studies carried out this by wind turbines. To avoid this and any other accident, hybrid sites
calculation. should have a considerable distance to airports and railways. Based on
the literature, the minimum distance is considered to be 3 km.
Based on the gap of knowledge from previous studies, which could be Distance to natural resources. To avoid any harmful activity for
detected by checking the answers to the questions in Table 1, the nov­ natural resources e.g., forests, protected areas, etc., a minimum distance
elties of current study are covering all the indicated items at the same of 4 km to natural resources is considered for hybrid power plants, based
time: on previous studies.
Distance to waterbodies. Areas close to rivers, damns, or lakes are
• A GIS approach has been outlined to eliminate unsuitable locations potential flood zones in bad weather, while being usually crowded. The
for hybrid power plant establishment based on socio-economic, minimum distance to water bodies in this study is considered to be 2 km.
meteorological, and terrain properties of each location.
• PV and wind farms minimum requirements have been applied on GIS 2.1.2. Terrain restrictions
approach to only investigate locations that are suitable for hybrid The Terrain situation has direct effect on the efficiency of power
power plant installation. plant. In this section, three important factors for land suitability are
• With considering different PV panel and wind turbine models, the pointed out.
generated energy and economic parameters are calculated for each Slope. Smoothness of the land is defined as slope. A higher slope
possible location, providing the chance to investigate each location indicates that the land has more ups and down, which hardens the
from techno-economic point of view, and usage of MCDM with en­ installation of PV panels and wind turbine. Based on the previous
ergy and economic parameters as objective functions. studies, a maximum slope of 10 % for wind turbine and 5 % for PV
• A computer code is developed to find the best configuration and best panels is selected. In this study, a 5 % slope is chosen as the threshold for
PV/wind ratio for each location by finding the closest configuration this property.
to the ideal answer. Elevation. As indicated on previous studies, e.g., Zoghi et al. [42],
• A sensitivity analysis is carried out to analyze the effect of variation higher altitude location receive better radiation due to thin atmosphere,
in land price, nominal capacity, and weight of objective functions in while having less flora and fauna species [43]. On the other hand, higher
TOPSIS. altitude locations have higher transmission and transportation costs
[44]. For this study, a maximum elevation of 2000 m from sea level is
2. Methodology considered as exclusion criteria.
Land cover. Installation of PV panels or wind turbines on a land with
This section shows the steps in finding the best locations for hybrid unsuitable vegetation not only can cause problem for contractors, but it
power plant. also can harm the vegetation or even destroy it. Based on the literature,
the suggested area for PV and wind farm installation are mostly bare
2.1. GIS approach areas and lands with short vegetations. To be more specific, according to
[45] and [29], European Space Agency (ESA) specifies 4 suitable
In order to utilize GIS approach, ArcMap software from ESRI is used. vegetation from globe cover map for PV farm installation, i.e., mosaic
The software provides the user with multiple tools to eliminate, edit, or vegetation, close to open vegetation, sparse vegetation and bare areas.
create maps. For the purpose of this study, the maps of annual radiation, Mosaic and close to open vegetations consists of croplands, shrublands,
annual mean wind speed, annual mean temperature, and topography of and grass lands which are indication of short vegetation. The acceptable
case study are merged to create a unified layer for analysis. Each loca­ land covers are extracted from globe cover using ArcGIS and applied to
tion in this map contains geographical coordinates alongside elevation the base layer.
from sea level and other characteristics, and based on the implied re­
strictions, unsuitable points are eliminated from the map. A Boolean 2.1.3. Meteorological limitations
strategy is used in this study to classify the investigated locations. Based Meteorological characteristics of each location are the most impor­
on the previous works and potentials of study area, a threshold is tant factors in hybrid farm site selection. These characteristics are
specified for socio-environment, terrain, and meteorological properties, measured annually and presented as average values throughout the
which indicates if a location has the minimum specifications to be year.
considered as a hybrid power plant site. Radiation. Locations with high radiation are obvious choices for PV
farm installation. Different studies consider a radiation higher than 1500
2.1.1. Socio-economic restrictions kWh.m− 2.year− 1 as moderately suitable radiation for PV utilization
All locations with high population density or high traffic can become [29,31,43,46]. Current study considers 1700 kWh.m− 2.year− 1 as the
prone to danger if renewable power generation sites are established too minimum radiation for site selection, since the study area has high po­
close to them. Furthermore, environmentally sensitive areas should have tential for solar energy.
a safe distance with wind and PV farms to avoid any conflict or harmful Wind speed. As indicated in Table 2, previous studies consider any
impact on each other. Therefor a minimum or maximum distance is wind speed below 4 m.s− 1 unsuitable for wind turbine operation, which
considered for locations of high interest. is the cut-in speed in which the turbine stops working.
Distance to settlements. A minimum distance to residential areas In this study, the minimum wind speed for exclusion areas is

3
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

Table 2
Exclusion criteria in previous conducted studies.
Exclusion criteria Saraswat et al. [29] Ali et al. [30] Effat Tercan et al. [35,36] Günen Anwarzai [47] Current study
et al. [46]
[31]

Radiation (kWh. 1600 1300 1500 1200 1600 1300 1700


m− 2.year− 1)
Wind speed (m.s− 1) 4 4 6 4.4 – 6 6
Slope (%) Max of 5 % Max of 5 Maxx of Max of 10 Max of 5 Max of 5 Max of 5
5
Annual temperature – – – Max of 10.5 Max of – Max of 15
(℃) 12.7
Elevation (m) Max of 1500 Max of 200 Min of Min of 3000 – Max of 2000
400
Distance to Min of 10 Min of 1 Min of 5 Min of 1 Min of 2 Min of 2 Min of 2
settlements (km) Max of Max of 10 Max of 10 Max of 10
50
Distance to main Max of 10 Max of 10 Min of 1 Min of 0.15 Min of 2 Max of 10 Min of 1
roads (km) Min of 0.5 k Max of Max of 10
10
Distance to railways Min of 7 Min of 3 – Min of 0.1 Min of 2 Min of 3.5 Min of 3
and airports (km)
Distance to natural Min of 10 Min of 1.5 – Min of 4 – – Min of 4
resources (km)
Distance to water Min of 7 Min of 0.4 Min of 1 Min of 1 Min of 4 Min of 0.4 Min of 2
bodies (km)
Land Cover Barren or sparsely Bare land, Bare Avoid urban, industrial, – Bare soil, Sand Mosaic, close to open, and
vegetated, mosaic, shorter land, commercial, vegetated, and covered area sparse vegetation, and
grassland, and shrubland vegetation desert transport areas bare areas

considered to be 6 m.s− 1. making it one of the richest countries in the world for average received
Mean Temperature. PV panels are affected by the ambient tem­ radiation. Although Iran is not as rich in wind speed as it is for solar
perature. Based on the panel’s characteristics, as the temperature of radiation, the country has locations with high potential for wind farm
panel exceeds the temperature of standard test condition (STC), its ef­ installations with wind speed up to 17 m.s− 1. Fig. 1 shows the average
ficiency reduces with a constant ratio, i.e., temperature coefficient of wind speed and radiation of Iran [51].
panel. Locations with high mean temperature are not suitable for hybrid Iran has a low efficiency (30 %) in centralized power systems,
energy harvesting. Based on the range of mean annual temperature of transmission, and distribution system, and is ranked 10th in emission
case study, and previous study investigation, a maximum temperature of production worldwide [39]. These reasons have motivated the govern­
15 ℃ is selected as exclusion limit. ment to increase the share of renewables in the total energy production,
Table 2 consists of considered exclusion criteria in the previous study making the country an ideal case study for this investigation.
and the selected limits for current study. Applying these restrictions on After careful implementation of exclusion criteria, 696 locations
the base layer maps, eliminates locations that are not suitable for hybrid have been identified as possible sites for hybrid farm establishment.
power plant establishment. Fig. 2 shows the distribution of possible locations for Iran.

2.2. Case study 2.3. Energy modelling

Iran is selected as the case study of the current research. The country The produced energy of PV and wind farms is dependent on different
is one the largest energy producers in the middle east, which is heavily factors, e.g., efficiency of panel, mean temperature, wake area, etc. In
dependent in fossil fuel energy [48–50]. The average annual solar ra­ this section, the generated energy of both PV panels and wind turbine
diation in the country is between 1650 and 2000 kWh.m− 2.year− 1, are modelled and calculated.

Fig. 1. Maps of the average annual wind speed and radiation of Iran [52].

4
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

sin(z)
MDBP = Wp sin(θ) (6)
tan(α)

In Eq. (6), Wp is width of the panel, and θ is panel’s tilt angle, while z and
α are azimuth and altitude angles, respectively. As a common estimation
and based on previous studies, the tilt angle of panel is equal to latitude
of the location [56,57].
Different factors should be considered for wind turbine placement.
Visual influence and noise of the turbines require a distance between
farms and residential areas, which is suggested to be 1000 to 1200 m in
[58]. Based on the applied geographical restrictions, this distance is
considered for hybrid farm site.
For distance between turbines, wake effect of turbines should be
minimized [59]. Choi et al. [60] conducted a numerical study on hori­
zontal axis wind turbines. Distance between turbines in the prevailing
wind direction was changed from 3 rotor diameter (D) to 7D, and ratio of
generated power by upstream turbine to downstream turbine was
calculated in each case. Based on the results, there was a non-linear
Fig. 2. Possible sites for hybrid farm establishment. relationship between power ratio and separation distance, but beyond
the distance of 5D increase in the power ratio was not significant. Hence,
2.3.1. Produced energy the optimal distance between wind turbines in the prevailing wind di­
Solar energy production by PV panels is dependent on received ra­ rection is selected to be 5 times of turbines blade diameter.
diation, panel’s area, and panel’s efficiency [53]: For distance perpendicular to wind direction, Panaitescu et al. [61]
suggests a distance of 2–5 times of rotor diameter, while Schwanz et al.
PPV = ηm × Ap × G (1) [62] and Gupta [63] propose a 5D and 3-5D distance would be suitable.
In this study, a minimum distance of 3D is considered for the distance
In Eq. (1), ηm , Ap , and G represent panel’s modified efficiency, panel’s
between wind turbines in perpendicular direction of wind. Fig. 3 shows
area, and received radiation respectively. Depending on the number of
the schematic of a hybrid power plant.
panels, the total produced energy from PV panels can be obtained.
Panel’s temperature has a direct effect on its efficiency. Eq. (2) and (3)
2.3.3. PV panels and wind turbine: Model selection
shows the calculation of modified efficiency [33]:
For a constant area, changing the size of wind turbine leads to a
(NOCT − 20) drastic change in farm’s layout and generated power, while a change in
T = Ta + GSTC (2)
800 the solar panel would not affect the layout significantly. For the purpose
of this study, three different large-scale turbines from Vestas Company
ηm = η + (T − Tstc ) × Tcoeff (3) are selected, which are presented on Table 3. Vestas company is the
leading manufacturer in wind turbines, covering 16 % of installed ca­
In Eq. (2), T is panel’s temperature, Ta is ambient temperature, NOCT is pacity worldwide [64].
nominal operating cell temperature from data sheet, and GSTC is the For PV panel model, Hi-Mo5 PV panel from LONGi company is
radiation under STC. In Eq. (3) η is the efficiency of the panel under STC, selected for simulation (see Table 4 for the specifications) [65].
Tstc is STC which is equal to 25 ℃, and Tcoeff is the temperature coeffi­
cient of selected PV panel. A similar energy model has been used in [54],
in which a comparison was made between the model and real PV farms, 2.4. Economic modelling
which indicated the validity of the current model. In order not to make
the work lengthy by providing repetitive information, that reference has For economic evaluation of hybrid power plant, Levelized cost of
been cited for more information. energy (LCOE) is considered as the economic objective function. LCOE
The produced energy from wind turbine can be modeled through Eq. indicates the cost of the produced electricity, which is independent of
(4) [37]: the production source, making it a valuable parameter for comparison.
Ctotal
1
Pw = ρ A t V 3 (4) LCOE = (7)
2 Ptotal

where ρ is the air density, At is the swept area by turbine blades, and V is In Eq. (7), Ctotal is the total annualized cost, and Ptotal is the total
the average wind speed in the location of installation. The total gener­ generated energy per year by hybrid farm. Ctotal is illustrated in (8).
ated energy from hybrid power plant obtained by Eq. (5). Ctotal = Ccap ⋅CRF + CO&M (8)
Ptotal = PPV + Pw (5)
where Ccap is the initial capital cost, CO&M is the annual cost of operation
and maintenance, and CRF is capital recovery factor which in other
2.3.2. Optimal spacing
word is annualizing factor based on the discount rate. CRF is calculated
A low distance between rows of solar panels can cause shading in
through Eq. (9),
certain times during the day, which leads to power loss. In order to avoid
this, an optimal distance should be considered between PV panels [55]. d(1 + d)n
As suggested in [48], PV panels receive the most energy between 9 A.M. CRF = (9)
[(1 + d)n − 1]
to 3P.M., and the longest shadow is created in winter solstice. Based on
this, minimum distance between panels (MDBP) is calculated through where d is the discount f actor, and n is the life span of power plant,
Eq. (6). which is considered to be 20 years. Ccap consists of costs of wind tur­
bines, PV panels, and balance of system (BOS) costs, which refers to all
of the components except wind turbines and solar panels, e.g., support

5
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

Fig. 3. Schematic of a hybrid power plant.

aspect of the project is more valuable than the quantity of produced


Table 3
energy, more weight should be given to LCOE, and if the amount of
Selected wind turbine models.
produced energy is more important than producing a cheaper energy,
Turbine Rated Power Rotor Diameter (m) Swept Area (m2) the generated energy should be given more weight in TOPSIS decision
model (MW)
making. This matter is investigated in this paper and the results are
V100 2 100 7854 discussed in the next section.
V136 3.45 136 14,527
Fig. 4 is a demonstration of how the code is implemented to choose
V172 7.2 172 23,235
the best configurations for each possible point. It should be noted that
large computations are required in this project, since the code loops
through every possible configuration of all possible locations.
Table 4
Selected PV module.
3. Results and discussion
PV Panel Rated Size (mm) Efficiency at Temperature
Model power (W) STC (%) coefficient (%.℃-1)
In this section the results of the current project are analyzed. The best
Hi-Mo5 545 2256 × 21.3 − 0.340 configurations for each possible location are obtained using the devel­
1133 × 35
oped computer code. Total nominal power of the hybrid farm, land cost,
and weight of objective functions in TOPSIS are three variables that
structure, connection cable, inverters and transformers. Wind turbine affect the results. The total nominal power of hybrid power plant is
costs comprises 70 % of the wind farm costs, while 30 % of the total is considered to be 30 MW, while cost of 1 square meter of land is 30 $ and
dedicated to BOS [66,67]. On the other hand, PV module cost about 35 LCOE and GE are given same weight in TOPSIS calculations. These
% of the total PV farm expenditure, while the rest is dedicated to BOS values are considered as base characteristics of the power plant, but a
[68]. At the last quarter of 2021, the average price of wind turbines for sensitivity analysis should be applied to each of these values to under­
Vestas company was 810 $.kW− 1, while the selected PV panel costs stand how they affect the results.
around 0.23 $.W− 1 [69]. GE, LCOE, PV ratio and Land use provide useful and sufficient in­
formation about the hybrid power plant. GE is necessary for demand
load analysis, LCOE determines if the project is economically feasible,
2.5. Optimized layout PV ratio shows the dependency to wind and PV sources, and amount of
the occupied land would be practical knowledge in order to assess the
Based on each location, hybrid farm’s layout can vary. Three economic justifiability of project.
different wind turbines and one model of PV panel are selected for For the base variables, Table 5 demonstrates the average of total
obtaining the optimized layout of each location using a developed generated energy, LCOE, PV ratio and land use of all possible points.
computer code. Geographical specifications, annual radiation, average Table 5 shows that establishing a 30 MW hybrid power plant in each
wind speed, annual mean temperature, and characteristics of panel and of the possible points, would result in 196.4 GWh of produced energy on
wind turbines are given as input to the code, and the optimized PV/wind average in each location, with 0.122 $ per kWh of electricity.
ratio is calculated for each location as the output using multi-criteria Different scenarios can be defined to analyze the results of this study.
decision making. TOPSIS is used to find the closest solution to the Any change in nominal capacity of power plant, land cost, and weight of
ideal answer, which is maximum generated energy and minimum LCOE. objective functions in MCDM can change the results drastically, so
The code loops through every possible combination of PV and wind different scenarios are introduced in this section to help the stakeholders
turbines, calculating the generated energy and LCOE of each layout as for policy making.
objective functions.
Different weight can be given to these objective functions which will
affect the results, based on the priority of stakeholders. If the economic

6
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

3.2. Nominal Capacity: How does the size of hybrid farm affect the
configurations?

The produced energy from a hybrid farm is dependent on nominal


capacity of the farm and geographical suitability. Nominal capacity
determines the size of power plant, and how many panels or wind tur­
bines should be installed in it.
The nominal capacity of the hybrid farm changes from 10 MW to 100
MW for the case study in Fig. 6. By increasing the size of hybrid farm, the
generated energy and land usage rises with a constant slope. As can be
seen from Eq. (1) and Eq. (4), number of PV panels and wind turbines are
directly involved in generated energy calculation, and with growth in
the size of the farm the number of panels and turbines increases which
leads to more generated energy and more land usage. Fig. 6b and 6c
indicate that higher nominal capacity generally leads to higher average
LCOE and lower PV ratio. In other words, increasing the share of wind
turbines in large scale hybrid farms leads to lower cost per unit of pro­
duced electricity. It should also be noted that LCOE is not very sensitive
to size variation of hybrid farm and it only changes 0.01 $ per kWh. For
50 MW farms and larger the PV ratio drops below 5 %, meaning that PV
panels act as back up for large scale power plants.

3.3. Land cost: What is the best strategy for higher priced lands?

The average land prices have a direct effect on LCOE and economic
justifiability of the farm (Fig. 7).
In this study, the possible points are locations that are suitable from
geographical and meteorological points of views, but land prices cannot
be investigated in large scale studies, since many different factors like
economic stability and landowner’s willingness to sell are involved.
For the base value, price of 1 m2 of land is assumed and calculations
and suggested configuration are carried out. In this part, GE, LCOE, PV
ratio, and Land use are analyzed for different land prices.
For locations with higher land prices, LCOE increases with a constant
slope. As the cost of lands rises, more PV panels should be used in order
Fig. 4. Steps of the implemented code. to mitigate the land cost effect on LCOE. Wind turbines occupy more
spaces and that is why PV ratio rises for more expensive land to avoid
very high LCOE and keep the farm economically justifiable. A higher PV
Table 5 ratio leads to less generated energy and land use.
Average values for the base variables.
GE (GWh.year− 1) LCOE ($.kWh− 1) PV ratio (%) Land use (m2) 3.4. Policy-making: How to utilize this study?
196.4 0.122 4.96 2,066,870
Iran is a vast country with high potentials for both solar and wind
farm installation. Although there are numerous locations that are suit­
3.1. More output or cheaper energy? able for hybrid farm installations, the land price is relatively high in the
country due to economic instability. As reported by [70], the average
For the base values, the weight of LOCE and generated energy of the price of each square meter of land in the capital city is $354.6.
farm are considered equal, meaning that both of these objective func­ Considering a lower price for other cities and locations still shows a high
tions have the same importance in decision making. If a cheaper energy price for land costs.
is desirable, more weight should be given to LCOE in TOPSIS, but if the Furthermore, based on the report of Renewable energy organization
amount of generated energy is more important, GE should have more of Iran [71], only 0.6 % of total generated energy in the country is
weight in MCDM. produced by renewable energy sources. PV and wind farms installed
As anticipated, as the weight of LOCE in TOPSIS is increased, average capacity is around 519 MW and 332 MW, respectively.
generated energy and LCOE decrease. Fig. 5c indicates that PV ratio is Based on the fact that fossil energy produced in Iran is heavily sub­
very sensitive to LCOE weight and dramatically rises with increase of it. sidized by the government, installation of large-scale hybrid farms in
In other words, increasing the share of PV panels in hybrid power plants possible locations with equal weight for LCOE and generated energy not
leads to cheaper energy production. Fig. 5d shows a down trend for Land only can reduce fossil energy dependency, but it also provides the
use with the rise of LCOE weight. Wind turbines produce more energy, country with the opportunity to reduce its environmental emissions.
but they need more space compared to PV panels and cost more which Table 6 shows the average generated energy, LCOE, PV ratio and land
results in higher LCOE. When the LCOE weight is set to 0.7 instead of use for installation of 50 MW hybrid farm in each of possible locations
0.5, the developed code chooses a configuration with more PV ratio. with average land cost of $200 and equal weights for objective functions
Although the generated energy declines, average LCOE drops around in MCDM.
0.08 $.kWh− 1 which makes the configuration closest to the ideal answer. Based on the result of this study, there are only 696 locations in the
whole country which have been found suitable for PV-wind hybrid farm
establishment. These locations are mainly located in east-north and
west-northern parts of the country, which usually are not densely

7
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

Fig. 5. Effect of LCOE weight variation on (a) average GE, (b) average LCOE, (c) PV ratio, and (d) Land use.

Fig. 6. Changes in the nomical capacity by variation of (a) average GE, (b) average LCOE, (c) PV ratio, and (d) Land use.

populated. Based on the discussed points in sections 3.1, 3.2, and 3.3, 4. Conclusion
Table 7 could be presented as an explicit policy-recommendation for
stakeholders. This table has been provided by considering farms with This study aimed at answering three questions about hybrid PV-wind
nominal capacity above 30 MW as large-scale farms and land prices farms, which were 1. Why hybrid farms should be used?, 2. What would
above $ 30 per m2 as expensive lands. be the best location to deploy them?, and 3. What is the best condition to
install them? A GIS approach was employed to eliminate unsuitable
locations for installation of hybrid PV-wind farms based on socio-
economic, terrain, and meteorological restrictions. Remaining

8
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

Fig. 7. Changes in the land cost by variation of (a) average GE, (b) average LCOE, (c) PV ratio, and (d) Land use.

• Although southern parts of Iran receive more annual average radi­


Table 6
ation, the possible points are mostly located on northern-east and
Results of the suggested strategy for case study.
northern-west parts of the country. This can be justified by the fact
GE (GWh.year− 1) LCOE ($.kWh− 1) PV ratio (%) Land use (m2) that southern part of the country has lower average wind speed, and
288.5339 0.326026 4.15 2,362,334 higher average temperature which would affect the modified effi­
ciency of the panels.
• It is up to the stakeholders to decide the weight of objective function
Table 7 for the optimal establishment of hybrid farm. If the farm is estab­
Policy-recommendation based on the obtained results of this study. lished in a location with high demand where quantity of generated
energy is more important than producing cheap energy, weight of
Expensive lands Cheap lands
LCOE should decrease in the developed code. Otherwise, higher
Cheap energy Small-scale hybrid farm with Large-scale hybrid farm LCOE weight would create a set-up where cheaper energy is
production high PV-ratio with high PV-ratio
High energy Small-scale hybrid farm with Large-scale hybrid farm
produced.
production low PV-ratio with low PV-ratio
CRediT authorship contribution statement

locations were considered possible points for installation. Energy and Reza Fardi Asrami: Conceptualization, Methodology, Investigation,
economic modelling of the farm was carried out, while calculating the Software, Writing – original draft, Writing – review & editing, Visuali­
optimal spacing between PV panels and wind turbines to avoid occu­ zation. Ali Sohani: Conceptualization, Investigation, Methodology,
pying unnecessary land. Generated energy and LCOE were calculated as Writing – original draft, Writing – review & editing. Mona Zamani
energy and economic objective functions for MCDM. A computer code Pedram: Methodology, Writing – review & editing. Hoseyn Sayyaadi:
was developed to find the best layout for hybrid farm, calculating the Methodology, Writing – review & editing.
generated energy, LCOE, PV ratio, and land use for each location. The
code used the GIS data and wind turbine and PV panel models as the Declaration of Competing Interest
inputs to find the best configuration for each possible location. The most
important findings of the work could be itemized as follows: The authors declare that they have no known competing financial
interests or personal relationships that could have appeared to influence
• Land prices are very important in the scale of the hybrid farm and the work reported in this paper.
configuration of panels and turbines. As the land prices increase,
smaller scale farms with higher PV ratio are recommended to make Data availability
up for the land costs.
• For cheaper areas, large-scale farms with less PV ratio produce more Data will be made available on request.
energy with lower LCOE.

9
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

References [29] Saraswat SK, Digalwar AK, Yadav SS, Kumar G. MCDM and GIS based modelling
technique for assessment of solar and wind farm locations in India. Renew Energy
2021;169:865–84.
[1] Osorio-Aravena JC, Rodríguez-Segura FJ, Frolova M, Terrados-Cepeda J, Muñoz-
[30] Ali S, Taweekun J, Techato K, Waewsak J, Gyawali S. GIS based site suitability
Cerón E. How much solar PV, wind and biomass energy could be implemented in
assessment for wind and solar farms in Songkhla, Thailand. Renew Energy 2019;
short-term? A Multi-Criteria GIS-Based Approach Applied to the Province of Jaén,
132:1360–72.
Spain. J Clean Prod 2022;366:132920.
[31] Effat HA, El-Zeiny AM. Geospatial modeling for selection of optimum sites for
[2] Gao J, Wang Y, Huang N, Wei L, Zhang Z. Optimal site selection study of wind-
hybrid solar-wind energy in Assiut Governorate, Egypt, The Egyptian Journal of
photovoltaic-shared energy storage power stations based on GIS and multi-criteria
Remote Sensing and Space. Science 2022.
decision making: A two-stage framework. Renew Energy 2022;201:1139–62.
[32] Dalwadi P, Shrinet V, Mehta C, Shah P. Optimization of solar-wind hybrid system
[3] Elkadeem MR, Younes A, Mazzeo D, Jurasz J, Elia Campana P, Sharshir SW, et al.
for distributed generation. In: 2011 Nirma University International Conference on
Geospatial-assisted multi-criterion analysis of solar and wind power geographical-
Engineering. IEEE; 2011. p. 1–4.
technical-economic potential assessment. Appl Energy 2022;322:119532.
[33] Hatata A, Osman G, Aladl M. An optimization method for sizing a solar/wind/
[4] Odoi-Yorke F, Adu TF, Ampimah BC, Atepor L. Techno-economic assessment of a
battery hybrid power system based on the artificial immune system. Sustainable
utility-scale wind power plant in Ghana. Energy Convers Manage X 2023;18:
Energy Technol Assess 2018;27:83–93.
100375.
[34] Ara SR, Paul S, Rather ZH. Two-level planning approach to analyze techno-
[5] Kocabaldır C, Yücel MA. GIS-based multicriteria decision analysis for spatial
economic feasibility of hybrid offshore wind-solar pv power plants. Sustainable
planning of solar photovoltaic power plants in Çanakkale province, Turkey. Renew
Energy Technol Assess 2021;47:101509.
Energy 2023;212:455–67.
[35] Tercan E. Land suitability assessment for wind farms through best-worst method
[6] Xenitidis K, Ioannou K, Tsantopoulos G. An innovative methodology for the
and GIS in Balıkesir province of Turkey. Sustainable Energy Technol Assess 2021;
determination of wind farms installation location characteristics using GIS and
47:101491.
Delaunay Triangulation. Energy Sustain Dev 2023;75:25–39.
[36] Tercan E, Eymen A, Urfalı T, Saracoglu BO. A sustainable framework for spatial
[7] bp Statistical Review, Statistical Review of World Energy, 2021. https://www.bp.
planning of photovoltaic solar farms using GIS and multi-criteria assessment
com/en/global/corporate/energy-economics/statistical-review-of-world-energy.
approach in Central Anatolia, Turkey. Land Use Policy 2021;102:105272.
html.
[37] Cunden TS, Doorga J, Lollchund MR, Rughooputh SD. Multi-level constraints wind
[8] Aghaloo K, Ali T, Chiu Y-R, Sharifi A. Optimal site selection for the solar-wind
farms siting for a complex terrain in a tropical region using MCDM approach
hybrid renewable energy systems in Bangladesh using an integrated GIS-based
coupled with GIS. Energy 2020;211:118533.
BWM-fuzzy logic method. Energ Conver Manage 2023;283:116899.
[38] Xu Y, Li Y, Zheng L, Cui L, Li S, Li W, et al. Site selection of wind farms using GIS
[9] Barbiero T, Grillenzoni C. Planning a novel regional methane network: Demand
and multi-criteria decision making method in Wafangdian, China. Energy 2020;
forecasting and economic evaluation. Energy Convers Manage X 2022;16:100294.
207:118222.
[10] Demir A, Dinçer AE, Yılmaz K. A novel method for the site selection of large-scale
[39] Ifaei P, Karbassi A, Jacome G, Yoo C. A systematic approach of bottom-up
PV farms by using AHP and GIS: A case study in İzmir, Türkiye. Sol Energy 2023;
assessment methodology for an optimal design of hybrid solar/wind energy
259:235–45.
resources–Case study at middle east region. Energ Conver Manage 2017;145:
[11] Xu X, Zhang Z, Yuan J, Shao J. Design and multi-objective comprehensive
138–57.
evaluation analysis of PV-WT-BG-Battery hybrid renewable energy systems in
[40] Dhunny A, Doorga J, Allam Z, Lollchund M, Boojhawon R. Identification of optimal
urban communities. Energy Convers Manage X 2023;18:100357.
wind, solar and hybrid wind-solar farming sites using fuzzy logic modelling.
[12] Das TK, Kundu D. Feasibility and sensitivity analysis of a self-sustainable hybrid
Energy 2019;188:116056.
system: A case study of a mountainous region in Bangladesh. Energy Convers
[41] Jahangiri M, Ghaderi R, Haghani A, Nematollahi O. Finding the best locations for
Manage X 2023;20:100411.
establishment of solar-wind power stations in Middle-East using GIS: A review.
[13] Icaza-Alvarez D, Jurado F, Tostado-Véliz M, Arevalo P. Design to include a wind
Renew Sustain Energy Rev 2016;66:38–52.
turbine and socio-techno-economic analysis of an isolated airplane-type organic
[42] Zoghi M, Houshang Ehsani A, Sadat M, javad Amiri M, Karimi S. Optimization solar
building based on a photovoltaic/hydrokinetic/battery. Energy Convers Manage X
site selection by fuzzy logic model and weighted linear combination method in arid
2022;14:100202.
and semi-arid region: A case study Isfahan-IRAN. Renew Sustain Energy Rev 2017;
[14] Rekik S, El Alimi S. Optimal wind-solar site selection using a GIS-AHP based
68:986–96.
approach: A case of Tunisia. Energy Convers Manage X 2023;18:100355.
[43] Giamalaki M, Tsoutsos T. Sustainable siting of solar power installations in
[15] A. Ngila Mulumba, H. Farzaneh, Techno-economic analysis and dynamic power
Mediterranean using a GIS/AHP approach. Renew Energy 2019;141:64–75.
simulation of a hybrid solar-wind-battery-flywheel system for off-grid power
[44] Siyal SH, Mörtberg U, Mentis D, Welsch M, Babelon I, Howells M. Wind energy
supply in remote areas in Kenya, Energy Convers Manage X 18 (2023) 100381.
assessment considering geographic and environmental restrictions in Sweden: A
[16] Gabbar HA, Siddique AB. Technical and economic evaluation of nuclear powered
GIS-based approach. Energy 2015;83:447–61.
hybrid renewable energy system for fast charging station. Energy Convers Manage
[45] Huang T, Wang S, Yang Q, Li J. A GIS-based assessment of large-scale PV potential
X 2023;17:100342.
in China. Energy Procedia 2018;152:1079–84.
[17] Wang C-N, Dang T-T, Wang J-W. A combined Data Envelopment Analysis (DEA)
[46] Günen MA. A comprehensive framework based on GIS-AHP for the installation of
and Grey Based Multiple Criteria Decision Making (G-MCDM) for solar PV power
solar PV farms in Kahramanmaraş, Turkey. Renew Energy 2021;178:212–25.
plants site selection: A case study in Vietnam. Energy Rep 2022;8:1124–42.
[47] Anwarzai MA, Nagasaka K. Utility-scale implementable potential of wind and solar
[18] Al-Masri HMK, Dawaghreh OM, Magableh SK. Optimal configuration of a large
energies for Afghanistan using GIS multi-criteria decision analysis. Renew Sustain
scale on-grid renewable energy systems with different design strategies. J Clean
Energy Rev 2017;71:150–60.
Prod 2023;414:137572.
[48] Fardi Asrami R, Sohani A, Saedpanah E, Sayyaadi H. Towards achieving the best
[19] Vega-Garita V, Alpizar-Gutierrez V, Alpízar-Castillo J. A practical method for
solution to utilize photovoltaic solar panels for residential buildings in urban areas.
considering shading on photovoltaics systems energy yield. Energy Convers
Sustain Cities Soc 2021;71:102968.
Manage X 2023;20:100412.
[49] Afkhami P, Zarrinpoor N. The energy-water-food-waste-land nexus in a GIS-based
[20] Ibrahim O, Bakare MS, Amosa TI, Otuoze AO, Owonikoko WO, Ali EM, et al.
biofuel supply chain design: A case study in Fars province. Iran, J. Clean. Product.
Development of fuzzy logic-based demand-side energy management system for
2022;340:130690.
hybrid energy sources. Energy Convers Manage X 2023;18:100354.
[50] Ghasemipour N, Izanlou P, Jahangir MH. Feasibility study on utilizing oscillating
[21] Shezan SA, Ishraque MF, Muyeen SM, Arifuzzaman SM, Paul LC, Das SK, et al.
wave surge converters (OWSCs) in nearshore regions, case study: Along the
Effective dispatch strategies assortment according to the effect of the operation for
southeastern coast of Iran in Oman sea. J Clean Prod 2022;367:133090.
an islanded hybrid microgrid. Energy Convers Manage X 2022;14:100192.
[51] DTU Wind Energy, Global Wind Atlas, 2021. https://globalwindatlas.info/.
[22] Wu Y, Zhang T, Xu C, Zhang B, Li L, Ke Y, et al. Optimal location selection for
[52] Global Solar Atlas, Solar Raster Map of Iran, 2019. https://globalsolaratlas.info/
offshore wind-PV-seawater pumped storage power plant using a hybrid MCDM
download/iran.
approach: a two-stage framework. Energ Conver Manage 2019;199:112066.
[53] Saedpanah E, Fardi Asrami R, Sohani A, Sayyaadi H. Life cycle comparison of
[23] Deveci M, Cali U, Pamucar D. Evaluation of criteria for site selection of solar
potential scenarios to achieve the foremost performance for an off-grid
photovoltaic (PV) projects using fuzzy logarithmic additive estimation of weight
photovoltaic electrification system. J Clean Prod 2020;242:118440.
coefficients. Energy Rep 2021;7:8805–24.
[54] Asrami RF, Sohani A, Sayyaadi H, Moradi MH. Geographical information system as
[24] Asadi M, Ramezanzade M, Pourhossein K. A global evaluation model applied to
an approach for PV power plants allocation with 3E criteria. Sol Energy 2023;264:
wind power plant site selection. Appl Energy 2023;336:120840.
111966.
[25] Zhou X, Huang Z, Wang H, Yin G, Bao Y, Dong Q, et al. Site selection for hybrid
[55] Yang Q, Huang T, Wang S, Li J, Dai S, Wright S, et al. A GIS-based high spatial
offshore wind and wave power plants using a four-stage framework: A case study in
resolution assessment of large-scale PV generation potential in China. Appl Energy
Hainan, China. Ocean Coast Manag. 2022;218:106035.
2019;247:254–69.
[26] Raza MA, Yousif M, Hassan M, Numan M, Kazmi SAA. Site suitability for solar and
[56] Yadav AK, Chandel S. Tilt angle optimization to maximize incident solar radiation:
wind energy in developing countries using combination of GIS-AHP; a case study of
A review. Renew Sustain Energy Rev 2013;23:503–13.
Pakistan. Renew Energy 2023;206:180–91.
[57] Pillot B, Al-Kurdi N, Gervet C, Linguet L. An integrated GIS and robust optimization
[27] Moltames R, Naghavi MS, Silakhori M, Noorollahi Y, Yousefi H, Hajiaghaei-
framework for solar PV plant planning scenarios at utility scale. Appl Energy 2020;
Keshteli M, et al. Multi-Criteria Decision Methods for Selecting a Wind Farm Site
260:114257.
Using a Geographic Information System (GIS). Sustainability 2022;14(22):14742.
[58] Salomon H, Drechsler M, Reutter F. Minimum distances for wind turbines: A
[28] Aghajani J, Farnia P, Velayati AA. Impact of geographical information system on
robustness analysis of policies for a sustainable wind power deployment. Energy
public health sciences. Biomed Biotechnol Res J (BBRJ) 2017;1(2):94.
Policy 2020;140:111431.

10
R. Fardi Asrami et al. Energy Conversion and Management: X 20 (2023) 100490

[59] European Wind Energy Association, Wind Energy - The Facts, 2009. https://www. [65] EnergySage, Top 10 solar companies and manufacturers in 2022, 2022. https://
wind-energy-the-facts.org/home–about-the-project.html. news.energysage.com/best-solar-panel-manufacturers-usa/#:~:text=The%20top
[60] Choi NJ, Hyun Nam S, Hyun Jeong J, Chun Kim K. Numerical study on the %2010%20solar%20panel%20companies%20globally%20with%20the%
horizontal axis turbines arrangement in a wind farm: Effect of separation distance 20highest,%2C%20Suntech%2C%20and%20First%20Solar.
on the turbine aerodynamic power output. J Wind Eng Ind Aerodyn 2013;117: [66] Mohamadi H, Saeedi A, Firoozi Z, Sepasi Zangabadi S, Veisi S. Assessment of wind
11–7. energy potential and economic evaluation of four wind turbine models for the east
[61] Panaitescu F-V, Panaitescu M, Anton I-A, Anton C, Turof M. New solutions to of Iran. Heliyon 2021;7(6):e07234.
protect the Romanian coastline. In: Advanced Topics in Optoelectronics, [67] T. Stehly, P. Beiter, P. Duffy, 2019 cost of wind energy review, National Renewable
Microelectronics, and Nanotechnologies IX. SPIE; 2018. p. 513–21. Energy Lab.(NREL), Golden, CO (United States), 2020.
[62] Schwanz D, Henke RE, Leborgne RC. Wind power integration in Southern Brazil: [68] IRENA, Renewable Power Generation Costs in 2020, 2020.
Steady-state analysis, Sixth IEEE/PES Transmission and Distribution: Latin [69] Keiron Greenhalgh, More wind turbine price increases on the way: OEMs, 2022.
America Conference and Exposition (T&D-LA). IEEE 2012;2012:1–6. https://cleanenergynews.ihsmarkit.com/research-analysis/more-wind-turbine-
[63] Gupta N. A review on the inclusion of wind generation in power system studies. price-increases-on-the-way-oems.html.
Renew Sustain Energy Rev 2016;59:530–43. [70] Statistical Center of Iran, Iran’s Q3 Real-Estate Market in Urban Areas Reviewed,
[64] Counsil GWE. Global Wind Report 2021:2021. https://gwec.net/global-wind-rep 2021.
ort-2021/. [71] SATBA, Installed renewable energy sources in Iran, 2022.

11

You might also like