Professional Documents
Culture Documents
Energy
journal homepage: www.elsevier.com/locate/energy
a r t i c l e i n f o a b s t r a c t
Article history: One of the main challenges of e-mobility roll-out is securing the required charging demand without
Received 29 March 2021 stressing the existing power grid. The electrical source must be non-conventional to achieve the ultimate
Received in revised form eco-friendly goal. This study conducts a techno-economic assessment for a novel stand-alone renew-
19 October 2021
ables-based charging station to determine the optimal configuration to generate the required daily
Accepted 22 December 2021
charging demand. The optimization is accomplished through modeling and simulating of the proposed
Available online 27 December 2021
design using HOMER software in four cities of Qatar to investigate various geographical locations and
metrological conditions. The optimal solution is compared with the grid extension option in each
Keywords:
Ammonia
location using a comprehensive economic criterion. The results showed that 250 kW wind turbine with
Energy Storage 60 m hub height, 450 kWp CPV/T system, 500 kW electrolyzer, 100 kW H2 and NH3 FCs, 15 kW bio-
Environmental generator, 200 kg chemical storage tank, 304e324 kW Li-ion battery storage and 299e335 kW con-
Hydrogen verter combination is the optimal stand-alone configuration for the selected sites. The optimum cases'
Solar net present cost ranges between $2.53 M to $2.92 M, and the cost of electricity ranges between $0.285 to
Wind $0.329 per kWh. The proposed optimization methodology is suitable for applications in any location,
considering the metrological conditions of the site under study.
© 2021 The Authors. Published by Elsevier Ltd. This is an open access article under the CC BY license
(http://creativecommons.org/licenses/by/4.0/).
https://doi.org/10.1016/j.energy.2021.123008
0360-5442/© 2021 The Authors. Published by Elsevier Ltd. This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/).
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
but when they are employed separately, their intermittent nature break-even grid extension distance was calculated and found
makes them unreliable sources of energy with relatively high 2.87 km for the case of Mbuji-Mayi. Similarly, this study did not
capital costs [14]. Mixing two or more RES such as wind turbine cover the payback period, PI, and IRR.
(WT), concentrated photovoltaic thermal (CPV/T), or hydro pro- Hafez and Bhattacharya investigated the optimal RES-based
vides a steady energy supply compared to single RES [15]. Hy- configuration and sizing for designing an on-grid and off-grid
bridization of multiple RES and energy storage options increases EVCS with both electrical and thermal loads, targeting minimum
the overall proposed system's production capacity, reliability, and lifecycle cost and harmful emissions [1]. Using HOMER to assess
efficiency. The net present cost (NPC) and cost of energy (COE) both cases' optimal techno-economic design, multiple configura-
should be competitive compared to fossil fuel-based systems to tions consisting of PV, battery storage, and a diesel generator were
promote the penetration of RES in the transport sector [16]. examined. The break-even grid extension distance was calculated
Due to RES’ dependence on renewable resources, which vary by to serve as an economic reference for selecting among the option of
location, the main challenge remains in devising a comprehensive connecting the EVCS to the grid or going for a RES-based stand-
techno-economic approach to determine the optimal location, alone option. Their results showed that a configuration consisting
configuration, and operation strategy for a hybrid EVCS. Therefore, of PV, battery storage, and a diesel generator is the optimal
the objective of this study is to develop a novel techno-economic configuration for the stand-alone case where the NPC and COE
methodology to determine the optimal site-specific stand-alone were found as $945,000 and 0.625 $/kWh, respectively. The same
EVCS configuration to increase the pace of integrating RES with EV design was found for the grid-connected case as the optimal one
charging infrastructure in an eco-friendly and cost-effective where NPC and COE were found as $835,000 and 0.551 $/kWh,
manner. respectively. The break-even grid extension distance for diesel
generator-based EVCS, RES-based EVCS, and mix RES and diesel
1.1. Literature review generator-based EVCS were found 69.9 km, 125 km, and 36.6 km,
respectively. The payback period, PI, and IRR were not included in
Different studies were conducted in the literature to assess on- that study.
grid and off-grid hybrid systems to generate electricity using
different techno-economic methods and tools. Among many works 1.2. Motivation and inspiration
that investigated the off-grid generation options, only a few have
considered calculating the break-even grid extension distance, Despite the importance of off-grid charging stations, they have
which is the minimum grid distance that makes the RES-based not yet been thoroughly studied and modeled, which requires more
stand-alone electricity generation option more feasible than grid investigation [32]. Based on the literature review, few studies have
extension. Out of 85 stand-alone papers presented by Bahramara assessed and optimized EVCS from technical and economic per-
et al., only 12 listed in Table 1 have calculated the break-even grid spectives. Most of the studies in the literature predominantly
extension distances where Hybrid Optimization Model for Electric focused on the technical aspects of EVCS infrastructure. Therefore,
Renewable (HOMER) software was used [14]. more optimization studies are needed to promote the integration of
Both grid-connected and stand-alone charging stations (CS) RES with EVCS as grid isolated systems to boost EV penetration in
composed of photovoltaic (PV) for EV charging are well established, the transport sector and increase the RES share in global electricity
however, at a relatively smaller scale with moderate reliability [28]. generation without impacting the grid. This paper's motivation is to
Few studies have investigated the deployment of large-scale off- propose a technically and economically balanced optimal off-grid
grid hybrid RES to supply electricity for EVCS [29]. Those studies micropower system consisting of RES and various energy storage
have emphasized the positive technical advantages of deploying technologies to fulfill the daily electricity demand of a fast EVCS.
stand-alone EVCS to safeguard the existing network with less focus The State of Qatar possesses a large portion of the world's nat-
on economic feasibility [1]. Limited combined technical and eco- ural gas reserve; nevertheless, the government has committed
nomic optimization studies were conducted for off-grid configu- through its national vision 2030 to expand renewable energy
rations, out of which rare have calculated the break-even grid sources and reduce reliance on conventional resources aiming for
extension distance. None have included the payback period, prof- social, economic, and environmental sustainability. Since Qatar is
itability index (PI), and internal rate of return (IRR). located within the Sun Belt region of the world, it receives plentiful
Ekren et al. used HOMER software to design and optimize an off- solar radiation throughout the year, which supports the utilization
grid hybrid solar PV and WT to generate electricity for an EVCS in of solar technology widely. Moreover, based on previous studies, it
Izmir city in Turkey [2]. Their results showed that 250 kW solar PV was proven that utilizing small to mid-range wind turbines for
and a 200 kW WT are the optimal sizings for the proposed electricity generation is viable [33]. This fact gives great potential
configuration where COE and NPC were found 0.064 $/kWh and for solar and wind technologies deployment expansion in Qatar for
$697,704, respectively. Domínguez-Navarro et al. used the Monte electricity generation purposes.
Carlo method to model and simulate EV demand and RES output. Transport sector decarbonization to reduce greenhouse gases
The Genetic Algorithm optimization technique was used to assess (GHG) emissions by promoting electric mobility penetration has
the feasibility of integrating hybrid solar PV and WT RES with a been one of Qatar's main objectives for the last five years. In May
storage system to generate electricity for a fast EVCS [30]. Based on 2017, the “Green Car Initiative” was launched to encourage EVs'
the calculated NPC, they concluded that the integration of RES and adoption [34]. It was announced that 400 EVCS would be installed,
battery system decreases the stress on the grid and increases the and EVs share will reach 2e4% by 2022 [35]. Qatar will be hosting
economic feasibility of the EVCS. The payback period, profitability FIFA World Cup Qatar 2022, and it was declared that 25% of the
index, and internal rate of return were not considered in this study. buses would be electric by 2022 to serve as a sustainable transfer
Vermaak and Kusakana developed a stand-alone RES-based means during the championship. By 2030 all public transport buses
EVCS for rural areas in the Democratic Republic of Congo [31]. are projected to be electric [36].
Different configurations consisting of PV, WT, battery, and diesel Since the successful deployment of EVs is predominantly reliant
generator were simulated using HOMER. PV, WT with batteries on establishing an efficient and reliable EVCS infrastructure to
were found to be the most economical design where NPC and COE facilitate the smooth transition to electric mobility, it is essential to
were calculated as $39,705 and 0.499 $/kWh, respectively. The devise a comprehensive optimization methodology to propose a
2
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Table 1
Breakeven grid distance calculated in previous literature.
Stand-alone hybrid configuration Location Break-even grid distance (km) LCOE Reference
sustainable EVCS design and investigate it technically and each step is elaborated subsequently.
economically.
The main novelties and objectives of the present work are
summarized below:
2.1. Proposed preliminary design
Introducing a robust methodology to assess the optimal techno-
economic configuration and sizing of a stand-alone fast EVCS A novel stand-alone EVCS design consisting of integrated RES
with hybrid RES and multiple energy storage options capable of with alternative storage systems was proposed by the author in
fulfilling daily EV charging demand reliably. previous studies [29,37], where the thermodynamic analysis was
Modeling, simulating and optimizing the proposed hybrid sys- conducted for the proposed design, and the energy and exergy ef-
tem using technical and economic data of the incorporated ficiencies were found 45% and 19%, respectively. The proposed
components and site-specific metrological inputs for four design is configured of the following main components:
different locations in the State of Qatar to assess the optimal
cost-effective and technically feasible configurations. Integrated solar CPV/T and WT systems as two main RES.
Conducting sensitivity analysis to examine the resilience of the Proton Exchange Membrane (PEM) electrolyzer to produce H2
selected configuration against selected uncertain parameters. from water.
Devising economic comparative analysis method to assist in
favoring stand-alone or grid connection options on a case-by-
case basis.
2. Methodology
This study's methodology flow is demonstrated in Fig. 1, where Fig. 1. Methodology flowchart.
3
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Air separator to produce N2 from the air through the cryogenic PWTG;STP ¼ the WT power output at standard temperature and
process. pressure [kW]
Haber-Bosch plant for NH3 synthesis through the produced H2 r ¼ the actual air density [kg/m3]
and N2. r0 ¼ the air density at standard temperature and pressure
Lithium-ion (Li-ion) battery storage system (BSS) and chemical (1.225 kg/m3).
storage system. Biodiesel generator is integrated into the proposed design as a
H2 and NH3 fuel cells (FC) produce electricity during nighttime backup source in case main energy sources and storage systems fail
and unfavorable weather conditions. to meet demand. Biodiesel has a higher heating value (HHV) of
DC-DC, AC-DC, and DC-AC converters. 40,700 kJ/kg, which is only 9% less than petroleum diesel. Restau-
Back up biodiesel generator for use during energy cases only rant waste oil and animal fat can be processed locally to produce
when the other energy sources are not available. the required quantities instead of using conventional diesel.
In addition to the batteries, H2 and NH3 chemical storage sys-
Since Qatar is located on the Sun Belt, solar technology is inte- tems are incorporated to diversify surplus energy storage methods
grated into the proposed design to harvest solar energy throughout and increase battery lifetime by reducing its charging and dis-
the year for electricity generation. Moreover, space requirements charging cycles. Compared to Li-ion batteries, H2 and HN3 have
are low for small scale generation plants. Compared to other relatively higher gravimetric and volumetric energy densities. H2
renewable energy options, construction time is short as well. In and NH3 fuel cells units are incorporated since small-scale H2 FC
recent years, solar technology has become competitive due to its and NH3 FC is already implemented.
efficiency and dramatic cost reduction. In Qatar, geothermal energy (hot water/steam) and hydropower
The following equation is used to calculate the output of the are unavailable due to the country's geography and its site-specific
CPV/T [14]: conditions.
The authors conducted a technical assessment of the proposed
GT design in another study [38]. The technical viability of the proposed
PPV ¼ YPV fPV 1 þ ap Tc Tc;STC (1) design for fast charging 50 EVs per day in Qatar was examined. The
GT;STC
results showed that the proposed design could fulfill the daily
where. charging demand throughout the year reliably.
YPV ¼ the rated capacity of the PV array [kW] Since it is vital to assess the proposed system's economic
fPV ¼ the PV derating factor [%] feasibility and compare it to the alternative grid-connected option,
this study's scope covers the above uninvestigated essential
GT ¼ the solar radiation incident on the PV array [kW/m2]
elements.
GT;STC ¼ the incident radiation at standard test conditions
[1 kW/m2]
aP ¼ the temperature coefficient of power [%/ C] 2.2. Techno-economic and optimization tool selection
TC ¼ the PV cell temperature [ C]
TC;STC ¼ the PV cell temperature under standard test conditions Based on the literature reviewed in this study, HOMER software
[25 C] developed by National Renewable Energy Laboratory (NREL) is a
A wind turbine is incorporated in the proposed design to sup- powerful and reliable tool used by many researchers to conduct
plement the solar system during night times and overcast days. techno-economic assessment studies for optimal sizing of the
With an average wind speed of 5.6 m/s in Qatar, there are enough components containing in their proposed hybrid RES systems.
wind turbine models on the market to generate electricity at lower HOMER modeling and simulation can provide accurate and reliable
wind speed ranges. Space requirement for the small-scale plant is results having similar charecteristics with RETScreen [39] software,
low. Compared to other renewable energy options, construction based on which profound decisions can be made [40]. Also, it avoids
time is short. Globally, wind turbine efficiency has increased, and needless, complex, lengthy calculations used by PV DesignPro [41],
the cost has reduced in recent years. PV*SOL [42], and Hybrid2 [43] software which increases the
The following equation is used to calculate the wind speed at simulation process timing dramatically with negligible result
hub height [14]: improvement [40]. As per review paper results conducted by
Bahramara et al., HOMER is a commonly applied tool by many re-
Zhub a searchers, particularly in developing countries, to assess RES sys-
Uhub ¼ Uanem , (2) tem configurations [14].
Zanem
5
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
associated costs within the project lifetime are reflected in Table 2, 3. Results and discussions
where the project lifetime is considered 25 years and a 5.7% dis-
count rate with a 0.55% inflation rate are used in this study [48]. In this section of the study, the modeling, simulation, and
optimization process in HOMER Pro will be elaborated, based on
which the results will be analyzed and discussed.
Values of certain factors beyond control may vary throughout 3.1. Load demand and metrological data modeling
the plant's life cycle, alternating the optimal solution under those
scenarios. Hence, it is essential to examine the range of possible HOMER performs hourly modeling for all the inputs for an entire
values for those factors through simulation and optimization and year based on the data either fed into HOMER or selected from the
determine the optimal solutions under those circumstances. Wind HOMER library. This stage is essential to simulate all possible sys-
speed and solar radiation are two examples where changes in their tem combinations to reach the configuration that meets the de-
values will directly impact incorporated RES, affecting the config- mand and technical requirements at the lowest lifecycle cost.
uration mix, equipment sizing, and optimal results. Therefore, Accordingly, the EVCS load demand is modeled in HOMER Pro,
sensitivity analysis must be conducted to examine the system's as illustrated in Fig. 4, where the daily and seasonal stochastic EV
resilience under investigation where the best configuration would demand profiles are indicated.
be the one with optimal results under most circumstances. The average monthly solar Global Horizontal Irradiance (GHI)
In this study, sensitivity analysis is conducted against wind and clearness index for the four selected locations are modeled in
speed considering different WT hub heights. However, other un- HOMER. Solar radiation is found available throughout the year in
certain parameters can be evaluated following the same method as Qatar, where a significant quantity of solar energy can be acquired.
found appropriate by the assessor. In some cases, the optimal Moreover, the four selected locations' annual solar radiation and
configuration might change if the system is examined under a clearness index are found similar, where the average annual solar
range of uncertain parameters. Still, the overall optimal design is radiation is found 5.33 kWh/m2 per day.
considered the one with minimum NPC and COE under most Likewise, the temperature of the four selected locations is
circumstances. modeled where the four selected locations' temperature is
While investigating the economic feasibility of a stand-alone observed similar throughout the year with an annual average
RES EVCS against grid-connected EVSC, it is essential to calculate temperature of 27.48 C.
the break-even grid extension distance limit. If the grid infra- Similarly, the four selected locations' annual wind resource data
structure is available closer than this limit, it is more economical to is modeled. The yearly average wind speed in the four selected
go for the grid-connected EVCS option but not from technical or locations is similar and equals 5.61 m/s at 50 m height.
environmental perspectives. However, if the grid is available Based on the obtained modeling results from HOMER, the four
beyond this limit, the off-grid option would be technically, selected sites' metrological data are similar throughout the year
economically, and environmentally optimal. despite being located in four different zones because Qatar's total
The proposed methodology has numerous advantages, such as: land size is relatively small, with a total area not exceeding 11,500
km2 [53].
1. A systematic approach to comprehensively examine the techno-
economic aspects of the proposed novel stand-alone fast EVCS
with precise results.
2. Flexibility to investigate different technologies within a system 3.2. System design configuration in HOMER
to determine the optimal combination that meets technical re-
quirements cost-effectively. The initial step is constructing the proposed design in HOMER,
3. Hourly-based modeling and simulation capability to precisely for which the values of the decision variables under investigation
analyze the amount of energy generated and consumed by in- must be specified. The incorporated components’ values used in the
tegrated subsystems and components throughout the project's HOMER simulation process are shown in Table 3. The decision
lifecycle. variables for each component and uncertain parameters against
4. Accessibility to rich technical and metrological data from reli- which the sensitivity analysis is conducted are indicated.
able resources embedded in the HOMER library. Few components have predefined parameters, others have a
5. Sensitivity analysis by changing the values of selected inputs range of parameters to be investigated, and the HOMER optimizer
and observing the performance of the subsystems and overall determines others. The proposed design configuration is built in
system. HOMER and reflected in Fig. 5.
Table 2
Life cycle cost of main components.
Component Capital Cost ($) Replacement Cost ($) O&M Cost ($) Fuel Cost ($/L) Lifetime Reference
6
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Table 3
Components and parameters investigated in the study.
CPV/T 450 kWp Determined using PVSyst [54] software based on space limitation of 1500 m2
WT 250 kW Determined considering space limitation and WT blade dimensions
H2 and NH3 FCs 100 kW/200 kW Both sizes are simulated for each FC
BSS and Converter e Calculated and selected by HOMER Optimizer
Bio Generator 15 kW Small capacity used as a backup emergency supply
Electrolyzer 100 kW/500 kW Both sizes are simulated
Chemical storage tank 50 kg/100 kg/200 kg Both sizes are simulated
BSS charging strategy LF/CC Both strategies are simulated
WT Hub Height 40 m/50 m/60 m Sensitivity analysis is carried out
Table 4
Optimal configuration for each WT hub height in east location.
WT Hub Hight Electro-lyzer Chemical Storage Dispatch Li-Ion Battery Con-verter H2 FC NH3 FC Bio Gen NPC (Mill- COE Un-met load
(m) (kW) Tank (kg) Strategy (kWh) (kW) (kW) (kW) (kW) ion $) ($) (%)
Similar modeling, simulation, and optimization exercise are FCs. It is observed that the bio generator contributes throughout the
conducted using HOMER on the remaining three locations. The year with only 1.10%, 0.04%, 1.54%, and 1.10% in east, west, north,
optimal configurations with minimum NPC and COE for each WT and south locations, respectively, to backup during emergencies.
hub height in west, north, and south locations are given in Table 5, It is noticed by comparing the monthly generation profiles, and
Table 6, and Table 7, respectively. volumes of all the four locations are similar due to the similarity in
Accordingly, the overall optimal configuration with minimum the metrological resources driving the integrated RES in the system,
NPC, COE and unmet demand percentage for all the four locations which have the majority generation share.
comprises of 60 m hub height WT, 450 kWp CPV/T system, 500 kW It can be concluded that the overall proposed off-grid RES-based
electrolyzer, 100 kW H2 and NH3 FCs, 15 kW bio-generator, 200 kg system is technically viable, and the daily EVCS charging demand is
chemical storage tank, Li-ion battery storage, and converter com- fulfilled reliably in all four locations.
bination. The optimal configurations operate on the CC dispatch
strategy in east, north, and south locations, while the west location 3.7. Comparative analysis with grid connectivity option
operates on the LF dispatch strategy.
Specifications of CPV/T, wind turbine, batteries, inverter, and Although a bulk number of fast EVCS connections to the existing
storage tank selected for the proposed configuration are reflected grid will stress the network and negatively impact the power
in Table 8. supply's security, it is worth analyzing from the economic
perspective whether it is feasible to go for a stand-alone or grid-
3.5. Optimal configurations’ NPC assessment connected EVCS. Therefore, the break-even distance is calculated
in all the four selected locations to determine the maximum
The optimal configuration component level NPC breakdown allowable network distance beyond which stand-alone EVCS would
based on expenditure type for east location is illustrated in Table 9. be more feasible.
The overall system NPC is calculated by summing up the NPC of Distance-based sensitivity analysis is performed in HOMER Pro
each. to calculate the NPC for connecting to the grid considering multiple
The optimal configuration’ NPC at the east location is $2.53 M. distances ranging from 0 to 30 km. Table 12 indicates the param-
Similarly, the optimal configurations’ NPC at west, north, and south eters used in the grid-based EVCS simulation and optimization
locations are $2.63 M, $2.92 M, and $2.53 M, respectively. process in HOMER. The indicated grid costs are actual costs ob-
Fig. 6 is a graphical illustration of the NPC amount of each tained from Qatar's sole power utility service provider [57], while
expenditure type of the optimal configurations selected for east, the carbon price is assumed to start with US $10 per ton in the first
west, north, and south locations. year and reach the US $30 per ton in ten years [58].
Unlike NPC of a stand-alone EVCS, which depends on the inte-
3.6. Optimal design's technical analysis grated components associated lifetime costs to generate the
required electricity to meet the demand, NPC of grid-tied EVCS
Based on the results obtained from HOMER and reflected in depends on the associated cost to secure the required power
Table 4, Table 5, Table 6, and Table 7, the detailed technical com- infrastructure inclusive of cable extension cost from the grid to the
ponents capacities of the most optimal configuration for each of the EVCS, power purchase cost, and carbon emission prices. Since
four locations are extracted and reflected in Table 10. The four lo- natural gas is the sole grid electricity generation source, HOMER
cations have identical values for most components with minimal found CO2 emissions from grid-connected configurations equals
variance in Li-ion battery and converter capacities. 418 tons per year.
The total electricity produced by the system throughout the year Table 13 illustrates the break-even distance at which both grid-
at east, west, north, and south locations is 1.003 GWh, 967 MWh, connected and off-grid optimal design EVCS NPCs are the same for
984 MWh, and 1.003 GWh. The detailed contribution of each of the each of Qatar's four selected locations based on the results obtained
energy sources in each location is illustrated in Table 11. from HOMER.
It is observed that WT has the dominant production contribu- From the economic perspective, if the distance between the
tion followed by the CPV/T system with a total of 77.9%, 79.2%, selected EVCS location and the available grid is equal to or more
77.2%, and 77.9% for east, west, north, and south locations, respec- than the break-even distance, then RES based hybrid stand-alone
tively, while the rest 22.1%, 20.8%, 22.8%, and 22.1% are distributed system option is preferred. On the other hand, if it is less, then
among the remaining incorporated multiple storage systems and the grid-connected EVCS option is preferred more.
Table 5
Optimal configuration for each WT hub height in west location.
WT Hub Hight Electro-lyzer Chemical Storage Dispatch Li-Ion Battery Con-verter H2 FC NH3 FC Bio Gen NPC (Mill- COE Un-met load
(m) (kW) Tank (kg) Strategy (kWh) (kW) (kW) (kW) (kW) ion $) ($/kWh) (%)
8
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Table 6
Optimal configuration for each WT hub height in north location.
WT Hub Hight Electro-lyzer Chemical Storage Dispatch Li-Ion Battery Con-verter H2 FC NH3 FC Bio Gen NPC (Mill- COE Un-met load
(m) (kW) Tank (kg) Strategy (kWh) (kW) (kW) (kW) (kW) ion $) ($/kWh) (%)
Table 7
Optimal configuration for each WT hub height in south location.
WT Hub Hight Electro-lyzer Chemical Storage Dispatch Li-Ion Battery Con-verter H2 FC NH3 FC Bio Gen NPC (Mill- COE Un-met load
(m) (kW) Tank (kg) Strategy (kWh) (kW) (kW) (kW) (kW) ion $) ($/kWh) (%)
Table 8
Technical specifications of main integrated components.
Table 9
East location optimal configuration components’ NPC breakdown.
9
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Fig. 6. Optimal configuration total lifetime cost (a) east, (b) west, (c) north, and (d) south.
Table 10
Optimal configuration components capacities in each of the four locations.
Component East location West location North location South location Unit
Table 11
Annual electricity system production per source.
Table 12 Table 13
Grid connection-associated costs. Optimal design break-even distance for each of the selected four locations in Qatar.
Description Value Unit Optimal design location NPC ($) COE ($) Break-even distance (km)
Fig. 7 is a graphical illustration of break-even distance where the NPC and stand-alone NPC intersect. Beyond this point, a stand-
NPC is relatively low if the grid is available at the EVCS location but alone EVCS option would be more feasible.
gets high and high as the distance increases. Additional economic assessment tools such as payback period,
At a break-even distance, the lines representing grid-connected PI, and IRR must be calculated and compared for stand-alone and
10
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Fig. 7. Distance break-even distance for each of the four locations in Qatar.
grid-connected scenarios to achieve a comprehensive economic over the initial investment as per the below equation:
analysis. In addition to the cash outflows indicated in Tables 9 and
12, the selling price of EV charging must be known to calculate the
cash inflows. Since Qatar has a limited number of EVs and EVCS, the PN CFt
t¼0 ð1þrÞt
EV selling price is still not declared. As the unit cost of purchasing PI ¼ (6)
power from the grid in Qatar is 0.1 $/kWh, EV charging selling price I0
is assumed 0.25 $/kWh in this study.
The payback period is a tool to determine the required time for where:
an investment's cash inflows to become equal to cash outflows. CFt ¼ future cash flow [$]
Cumulative cash outflows and inflows for a stand-alone and grid- I0 ¼ initial investment [$]
connected at 5 km and 10 km EVCS are calculated and reflected r ¼ discount rate [%]
in Table 14. t ¼ number of time periods.
The results show that a stand-alone EVCS payback period is 14 Since the calculated PI for a stand-alone EVCS project is more
years, while payback periods for grid-connected EVCS at 5 km than one and equal to 1.2, it is feasible to invest in this project.
distance and 10 km distance from the grid are 16 and 23 years, Similarly, PI for grid-connected EVCS at 5 km distance and 10 km
respectively. distance from the grid are calculated and found 0.97 and 0.70,
PI is calculated by dividing the present value of future cash flows respectively.
The following equation is used to calculate IRR:
Table 14
Stand-alone and grid connected EVCS payback calculations.
11
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
Author contributions
4. Conclusions and future work
Conceptualization, Yusuf Bicer; Methodology, Yusuf Bicer,
This study performs a comprehensive techno-economic Abdulla Al Wahedi.; Software, Abdulla Al Wahedi; Formal analysis,
assessment of a novel hybrid renewable energy-based stand- Yusuf Bicer, Abdulla Al Wahedi; Investigation, Abdulla Al Wahedi;
alone fast electric vehicle charging station. The novel design con- Resources, Yusuf Bicer; Data curation, Abdulla Al Wahedi, Yusuf
sists of a concentrated PV system, wind turbine, converter, elec- Bicer; Writing e original draft Preparation, Abdulla Al Wahedi;
trolyzer, backup bio generator, H2 and NH3 fuel cells hybridized Writing e review & editing, Abdulla Al Wahedi, Yusuf Bicer; Su-
with electrochemical and chemical storage facilities. pervision, Yusuf Bicer.
Based on the minimum cost of energy and net present cost,
HOMER Pro microgrid optimization software is used to model and Funding
simulate multiple system configurations at four diverse
geographical locations in Qatar to determine the optimal combi- The APC of this article was funded by the Qatar National Library.
nation, components sizing, and energy management strategy. This research was funded by Qatar Foundation with student num-
Sensitivity analysis is performed by simulating a range of values ber 210009262.
for selected crucial parameters such as sizes of H2 and NH3 FCs,
electrolyzers and chemical storage tanks, wind turbine hub heights, Declaration of competing interest
and battery storage charging strategies. The HOMER optimizer se-
lects the sizes of the battery storage systems and the converters. The authors declare that they have no known competing
Out of 4236 solutions simulated by HOMER, 908 were found financial interests or personal relationships that could have
feasible from which the optimal stand-alone configuration for each appeared to influence the work reported in this paper.
site is determined.
A comprehensive economic criterion is applied to compare the Acknowledgments
proposed optimal stand-alone system against a grid-connected
option. Cable extension costs from the grid to the EVCS selected Authors acknowledge Hamad Bin Khalifa University (HBKU),
location, power purchase cost, and carbon emission prices were Qatar support, Qatar Foundation (QF), Qatar and the help from Engr.
considered while calculating a grid-connected option's NPC and Mazan Al Masri at Qatar Electricity and Water Corporation (KAH-
COE. The payback period, profitability index, and internal rate of RAMAA). The Qatar National Library funded the publication fee of
return were calculated for both options. this article.
The main results of the present work can be summarized as:
Nomenclature
System configuration consisting of 60 m hub height wind tur-
bine, 450 kWp CPV/T system, 500 kW electrolyzer, 100 kW H2 BSS Battery Storage System
and NH3 FCs, 15 kW bio-generator, 200 kg chemical storage tank, CC Cycle Charging
Li-ion battery storage, and converter is found as the optimal COE Cost of Energy
solution based on minimum NPC, COE and unmet demand. CPV/T Concentrated Photovoltaic Thermal
The annual electricity generated by the optimal configurations CS Charging Station
in east, west, north, and south locations is 1.003 GWh, EV Electric Vehicle
967 MWh, 984 MWh, and 1.003 GWh. EVCS Electric Vehicle Charging Station
The optimal combinations in east, north, and south locations FC Fuel Cell
operate on CC dispatch strategy while on west location it GHG Greenhouse gases
operates on LF dispatch strategy. GHI Global Horizontal Irradiance
The NPC of optimal configurations at east, west, north, and south HHV Higher Heating Value
locations is $2.53 M, $2.63 M, $2.92 M, and $2.53 M, respectively. HOMER Hybrid Optimization Model for Electric Renewable
Simultaneously, the COE is $0.285, $0.296, $0.329, and $0.285, IRR Internal Rate of Return
respectively. LF Load Following
Wind turbine and CPV/T production contribution is 77.9%, 79.2%, LHV Lower Heating Value
77.2%, and 77.9% for east, west, north, and south locations, Li-ion Lithium Ion
respectively. NPC Net Present Cost
12
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
13
A. Al Wahedi and Y. Bicer Energy 243 (2022) 123008
14