Er.R.M.Dinakar,B.Tech., The General Manager Operation,


Superintending Engineer, M/s Cheyyar SEZ Developers Pvt Ltd.,
General Construction Circle, Plot No.3-A, SIPCOT Industrial park,
230/110 KV GIS SS Campus, 3rd floor, Mangal Village, Mathur post,
A-10, Thiru-vi-ka Industrial Estate, Vembakkam Taluk,
Guindy, Chennai – 32. Thiruvannamalai D.T.
sekar.kuppusamy@fengtay.com
Lr. No. SE/GCC-I/CNI/AEE/GL/AE/GL/F.Cheyyar SEZ/D. 1371 /2023, dt: 04.11.2023.
Sir,
Sub: GCC-I/Chennai – Extension of 1no New 110KV EHT Service at Pelakuppam
Village for a maximum demand of 10500KVA to M/s Cheyyar SEZ Developers,
Near Plot No:A1, Sipcot Industrial Park, Pelakuppam Village, Tindivanam,
Villupuram District by making LILO arrangements for carrying out the entire
extension works under Self-Execution – Inspection wavier- Reg.
Ref: 1.Circular Memo No.CFC.TR/FC/GL/DFC/Fin/TR/D.No.728/2022,Dt:11.08.2022.
2. Memo No: CE/Coml/SE/EE2/AEE2/F.M/s Cheyyar–New EHT/D:410/23,
dt: 08.08.2023.
3. Memo.No.SE/VEDC/VPM/AEE/GL/CHD/TA/F.EHT Cheyyar /D.181/23-24,
dt. 11.08.2023.
4. M/s Cheyyar SEZ Developers Pvt Ltd.,Lr.No.Nil, dt:13.10.2023.
5.Lr.No.EE/SSE/CNI/F.M/s.SEZ Cheyyar/D.No.581/223,Dt:26.10.2023.
********
Based on the letter reference (4), the inspection waiver for the following materials are
furnished as follows.
Sl.No Description Quantity Make

1 Isolator with/Without Earth 8 Nos GR power

2 110 KV LAS 12 Nos CGL

3 Battery Charger 2 Nos Voltech

4 Battery 1 Set Voltech

5 DCDB 1 No Voltech

The test certificate as per norms and the test report of the factory may be furnished
before dispatch.

This approval does not absolve you from your contractual obligations/terms and
conditions of letter of award. S/d..Er.R.M.Dinakar, B.Tech.,
dt:04.11.2023
SUPERINTENDING ENGINEER
GCC-I/CHENNAI
Copy submitted to the Chief Engineer/Transmission Projects-I/Chennai. -For kind information
please. (By mail only)
Copy to the Executive Engineer/SSE/Chennai. (By mail only)

You might also like