You are on page 1of 1

::TANTRANSCO::

From To

Er.R.M.Dinakar,B.Tech., The General Manager Operation,


Superintending Engineer, M/s Cheyyar SEZ Developers Pvt Ltd.,
General Construction Circle, Plot No.3-A, SIPCOT Industrial park,
230/110 KV GIS SS Campus, 3rd floor, Mangal Village, Mathur post,
A-10, Thiru-vi-ka Industrial Estate, Vembakkam Taluk,
Guindy, Chennai – 32. Thiruvannamalai D.T.

Lr. No. SE/GCC-I/CNI/AEE/GL/AE/F.Cheyyar SEZ/D. 034/2024, dt: 09.01.2024.


Sir,

Sub: GCC-I/CNI– Extension of 1no New 110KV EHT Service at Pelakuppam Village for
a maximum demand of 10500KVA to M/s Cheyyar SEZ Developers, Near Plot
No:A1, Sipcot Industrial Park, Pelakuppam Village, Tindivanam, Villupuram District
by making LILO arrangements for carrying out the entire extension works under
Self-Execution – Tower Parts - Inspection report - Reg.
Ref: 1. M/s Cheyyar SEZ Developers Pvt Ltd.,Lr.No.Nil, dt:13.10.2023
2.Lr.No.AEE/TLC/thiruvallur/Inspection/D.Camp/ dt:15.12.2023
********
Based on the letter reference (1), the inspection was carried out for the following Tower
Parts at the factory premises of M/s.S.M.Tower Technology, Vichoor. The details of the materials
are given below.

Sl. No Description Qty

1 KCO Tower 1 set

The test results are found generally in order.

Encl: Test report S/d…Er.R.M.Dinakar, B.Tech., dt:09.01.2023


SUPERINTENDING ENGINEER,
GCC-I/CHENNAI.
Copy submitted to the Chief Engineer/Transmission Projects-I/Chennai for kind information
please. (By mail only)
Copy to the Executive Engineer/TLC/Poonamallee. (By mail only