It is submitted that 04 x air conditioners having cooling capacity i.e. (3 x 7.5 installed and 01
x 10 Ton) at NTC MSU Multan are being used for the proper control of the temperature of the EWSD
switch Room & smooth working of the system. These air conditioners are being used around the clock
for the temperature control of the EWSD switch room.
2. A pair of air conditioners will be used with the start of the summer season for the proper
control of the temperature of the EWSD switch room as the most sensitive equipment i.e. EWSD MSU
complete, Banning Rectifier, Soft Switch with Rectifier, UMG/NGN, and DWDM, BRAS, MX104
Router and data equipment has been installed in the switch room.
3. At present 02 x air conditioners are faulty the log book of the air conditioners of MSU
Multan is attached. The air conditioner Technician was called to find out the cause and he has asked
that compressors of 02 x Air Conditioners (Having Capacity 7.5 Ton i.e Air conditioner no 01 & 02) have
been burnt. For the repair of 01 x air conditioner following is required: -
Repairing of Compressor (Motor, Pistons)
R-22 Gas 8 Kg
Compressor Oil 4 Liter
Dry Filter
Gas Accumulator
JUSTIFICATION
Central Telephone Exchange Dera Adda Multan
061-9200004 061-9200011
NATIONAL TELECOMMUNICATION CORPORATION Ministry of Information
Technology & Telecom
Office of the Assistant Divisional Engineer (Int/Sw)) NTC Multan
Present Status
04 x air conditioners having cooling capacity i.e (3 x 7.5 installed and 01 x 10 Ton) at NTC MSU Multan
are being used for the proper control of temperature of EWSD switch Room & smooth working of the
system. These air conditioners are being used round the clock for the temperature control of EWSD
switch room. It is pertinent to mention here that said Air conditioners units were installed on
01-06-2001, so the air conditioners have completed the useful life.
Routine Maintenance
The complete service of air conditioners is essentially required interest of NTC for the proper control
of temperature of EWSD switch room as the most sensitive equipment i.e EWSD MSU complete,
Baning Rectifier, Soft Switch with Rectifier, UMG/NGN, DWDM, BRAS, MX104 Router and data
equipment is also installed in switch room. The proper control of temperature is quite essential for the
smooth functioning above mentioned equipment as the summer season has to be started.
No technical difficulty is being anticipated during the execution of work
WORK ORDER
For Routine Maintenance of Air Conditioners 2 x7.5 Ton & 01 x 10 Ton Cabinet Type
Installed at EWSD Switch Room NTC MSU Multan
To:
M/s Al-Khair Enterprises,
Near Jamia Masjid Zikrya, Neelam Street,
Vehari Road Multan
Copy to: -
Assistant Director (Accounts) NTC Multan.
It is to inform that M/s Al-Khair Enterprises, Multan Cantt has completed work
for “Routine Maintenance of Air Conditioners 2 x 7.5 Ton & 01 x 10 Ton Cabinet Type Installed at
EWSD Switch Room NTC MSU Multan” on dated 31-03-2022.
Submitted for information, please
Regards,
Kindly find enclosed herewith bill no. 08, Dated: 31-03-2022 amounting to
Rs.24,952/- from M/s Al-Khair Enterprises, Multan on account of Routine Maintenance of Air
Conditioners 2 x 7.5 Ton & 01 x 10 Ton Cabinet Type Installed at EWSD Switch Room NTC MSU
Regards,