Republic of the Philippines

Department of Education
REGION I
SCHOOLS DIVISION OFFICE I
PANGASINAN
BINMALEY, I District

SABANGAN ELEMENTARY SCHOOL


101321

CONTINGENCY
PLAN FOR
EARTHQUAKE

SEPTEMBER 2022
PREFACE
T his 2022 Contingency Plan covers SABANGAN ELEMENTARY SCHOOL/SCHOOLS DIVISION
OFFICE I OF PANGASINAN/REGION.

The goal of the contingency plan is to provide effective, efficient, timely and well-
coordinated response mechanisms in the event of the occurrence of a earthquake in Municipality of
Binmaley. such mechanisms shall help to protect lives, properties and the environment, and restore
the immediate needs of the affected communities.

It focuses on building collaboration among various sectors and stakeholders to respond


to disasters and hazards that beset the community. Thus, the school aims to:

1. To clearly identify the different responsibilities and to pre-determine the immediate course of
action of the School’s DRRM team in the conduct of response operations for the given
emergency situation.
2. To identify person(s) of authority in giving commands and other relevant directives during
disaster response operations
3. To create awareness for school administrators to initiate the integration of Disaster Risk
Reduction and Management (DRRM) programs specifically disaster preparedness and
mitigation in school’s curricula, learning materials and teaching manuals.
4. To ensure maximum care, assistance and services to affected learners
5. Encourage community involvement which certainly helps to achieve collaborations;
6. Ensured that the whole range of resources in the community is used to the full for the good of
its area.
TABLE OF CONTENTS

Chapter 1: BACKGROUND
A. Introduction……………………………………………………………………………………..1-11

Baseline Data on Infrastructure……………………………………………… 12

Baseline Data on Non-Infrastructure……………………………………… 12-15

Baseline Data on Personnel………………………………………………...... 16

Baseline Data on Learners…………………………………………………..... 16

B. Hazard analysis………………………………………………………………………………. 17

Historical Data……………………………………………………………………….. 17

Hazard Prioritization…………………………………………………………….. 18

Anatomy of Hazards……………………………………………………………….19

Chapter 2: CAPACITIES AND VULNERABILITIES…………………………….…………..… 20-23

Chapter 3: RESPONSE AND ARRANGEMENT………………………………..………..…… 24

A. Scenario Building……………………………………………………………..........…..24-25

B. Resource Inventory………………………………………………….………..…... ……27-26

C. Response Actions…………………………………………………….…………...........28

D. SDRRM Team Directory…………………………………………….…….…….... ….29

E. Binmaley Emergency Directory…………………………………………….…..… .30

Chapter 4: ACTIVATION AND DEACTIVATION……………………………….…………….. 31

Effectivity………………………………………...……………………………..……………. 32
CHAPTER 1: BACKGROUND
A.INTRODUCTION

B inmaley is a coastal municipality in the province of Pangasinan facing the Lingayen gulf in
between Lingayen and Dagupan City. It has 33 barangays and it is classified as a first-class municipality.
The municipality has a land area of 118.50 square kilometers or 45.75 square miles which constitutes
2.17% of Pangasinan's total area. Its population as determined by the 2020 Census was 86,881. This
represented 2.75% of the total population of Pangasinan province, or 1.64% of the overall population of
the Ilocos Region. Based on these figures, the population density is computed at 733 inhabitants per
square kilometer or 1,899 inhabitants per square mile. Binmaley’s Climate is tropical the average
temperature is 27.5 the average rainfall is 2,333 mm. Flooding is a top priority hazard.

Binmaley derived its name from the Pangasinan phrase “nanmaliw ya baley”, meaning, a place or
territory that has been converted into a town because it is believed that the municipality was formerly a
part of the town of Binalatongan, now known as San Carlos City.

The town is famous for its bangus (milkfish) aquaculture due to the existence of its numerous
fishponds (pokok in the Pangasinan language). Binmaley has a land area of 11, 850 hectares and a
population of 83,052. Based from the Bureau of Local Government Finance, the annual regular revenue
of Binmaley for the fiscal year of 2016 was P160, 401,850.71.

According to the 2015 Census, the age group with the highest population in Binmaley is 5 to 9,
with 8,858 individuals. The median age of 25 indicates that half of the entire population of Binmaley are
aged less than 25 and the other half are over the age of 25. The latest census figures in 2015 denote a
positive growth rate of 1.03%, or an increase of 4,350 people from the previous population of 78,702 in
2010.

General Douglas McArthur used the town’s beach, designated as “yellow beach” alongside the
beaches of Lingayen, Dagupan and San Fabian, in their landing operations to liberate Luzon from
Japanese occupation during World War II. Binmaley’s town center has a Neo-classical church dating
back to the 17th century. It also became famous throughout the Philippines for the outstanding
academic achievements of students. Its name roughly means “the place which became a town or went
to town in the Pangasinan language.

The Philippines is among top five high-risk countries which experienced natural disasters such as
earthquake, flashfloods, mudslides, typhoon and volcanic eruptions. In the World Risk Report 2013, the
country is ranked third as the most disaster-prone country in the world for having the greatest number
of hazards, damages, and fatalities every year (AND, 2014, p.64). This was made more apparent after
the devastation caused by Super Typhon (ST) Yolanda (a.k.a., “Haiyan”) in Region VIII on November 8,
2013. Based on Department of Environment and Natural Resources, Mines and Geo-Science Bureau
(DENR0MGB), Pangasinan is among the top flood prone provinces. In a study on Vulnerability
Assessment of Pangasinan province to typhoons, floods and landslides, exposure, sensitivity, adaptive
capacity and overall vulnerability of each city and municipality were assessed and ranked from most
vulnerable to the least. Binmaley is categorized as mild vulnerable.
1

SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

“It’s always best to be prepared even before a disaster strikes,” former Mayor Simplicio L.
Rosario told the Philippine Information Agency.
The above statement is in line with the adaptive capacity of Municipality during disasters. In
case a calamity strikes, the local government of Binmaley wants to be sure that it has enough
evacuation centers for affected residents. Aside from the evacuation centers, Rosario said that the local
government has also procured new rescue vehicle as well as rescue equipment and conducted basic life
support training as part of its disaster risk reduction and management programs.
Sabangan is a barangay in the municipality of Binmaley, in the province of Pangasinan. Its
population as determined by the 2020 Census was 768. This represented 0.88% of the total population
of Binmaley.Sabangan is situated at approximately 16.0521, 120.2956, in island of Luzon. Elevation at
these coordinates is estimated at 5.9 meters or 19.4 feet above sea level and situated at the center of an
ocean connected to Lingayen Gulf and a river.
The population of Sabangan grew from 614 in 1990 to 768 in 2020, an increase of 154 people over
the course of 30 years. The latest census figures in 2020 denote a positive growth rate of 0.59%, or an
increase of 21 people, from the previous population of 747 in 2015. According to the 2015 Census, the
age group with the highest population in Sabangan is 20 to 24, with 90 individuals. Conversely, the age
group with the lowest population is 80 and over, with 3 individuals. Combining age groups together,
those aged 14 and below, consisting of the young dependent population which include infants/babies,
children and young adolescents/teenagers, make up an aggregate of 27.31% (204). Those aged 15 up to
64, roughly, the economically active population and actual or potential members of the work force,
constitute a total of 67.20% (502). Finally, old dependent population consisting of the senior citizens,
those aged 65 and over, total 5.49% (41) in all. The computed Age Dependency Ratios mean that among
the population of Sabangan, there are 41 youth dependents to every 100 of the working age population;
there are 8 aged/senior citizens to every 100 of the working population; and overall, there are 49
dependents (young and old-age) to every 100 of the working population.
The median age of 25 indicates that half of the entire population of Sabangan are aged less than 25 and
the other half are over the age of 25. https://www.philatlas.com/luzon/r01/pangasinan/binmaley/sabangan.html

Sabangan shares a common border with the following barangay(s):


 Buenlag, Binmaley, Pangasinan
 Pugaro Suit, Dagupan, Pangasinan
 Salapingao, Binmaley, Pangasinan

SABANGAN BINMALEY MAP


SCHOOL CONTINGENCY PLAN
2 FOR EARTHQUAKE

EARTHQUAKE

An earthquake is a weak to violent shaking of the ground produced by the sudden movement
of rock materials below the earth’s surface.

The earthquakes originate in tectonic plate boundary. The focus is point inside the earth where
the earthquake started, sometimes called the hypocenter, and the point on the surface of the earth
directly above the focus is called the epicenter.

There are two ways by which we can measure the strength of an earthquake: magnitude and
intensity. Magnitude is proportional to the energy released by an earthquake at the focus. It is
calculated from earthquakes recorded by an instrument called seismograph. It is represented by
Arabic Numbers (e.g. 4.8, 9.0). Intensity on the other hand, is the strength of an earthquake as
perceived and felt by people in a certain locality. It is a numerical rating based on the relative effects to
people, objects, environment, and structures in the surrounding. The intensity is generally higher near
the epicenter. It is represented by Roman Numerals (e.g. II, IV, IX). In the Philippines, the intensity of
an earthquake is determined using the PHIVOLCS Earthquake Intensity Scale (PEIS).

Types of earthquakes

There are two types of earthquakes: tectonic and volcanic earthquakes. Tectonic earthquakes are
produced by sudden movement along faults and plate boundaries. Earthquakes induced by rising lava
or magma beneath active volcanoes is called volcanic earthquakes.

Earthquake Monitoring System

At present, PHIVOLCS operates 108 (as of December 2020) seismic monitoring stations all over
the Philippines. These stations are equipped with seismometers that detect and record earthquakes.
Data is sent to the PHIVOLCS Data Receiving Center (DRC) to determine earthquake parameters such
as magnitude, depth of focus and epicenter. Together with reported felt intensities in the area (if any),
earthquake information is released once these data are determined.
3

SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

This Contingency Plan focuses on earthquakes-the 3 rd priority hazard. The Philippines’ geographical and
geological setting makes it prone to earthquakes as it is situated within the Pacific Ring of Fire, where two
major tectonic plates of the world meet. This would explain the occurrence of twenty (20) earthquakes
recorded per day and that makes up to 100 to 200 earthquakes felt every year some of which could cause
tsunamis. The Philippines is likewise home to 300 volcanoes, 22 of which are active and 24 are potentially active.
The image below depicts documented earthquake occurrences in the Philippines, their Magnitude (the energy
generated by the earthquake) and Depth of the earthquake from sea level.

EARTHQUAKE HAZARD MAP


4
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE
5

SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

FIVE AREAS IN THE PHILIPPINES WITH HIGH RISK IN


EARTHQUAKE.
The ten provinces most at risk of earthquakes – due to the presence of or their nearness
to active faults and trenches – include Surigao del Sur, La Union, Benguet, Pangasinan, Tarlac,
Pampanga, Ifugao, Davao Oriental, Nueva Vizcaya and Nueva Ecija (Manila

PRIMER ON THE 27 July 2022 MAGNITUDE (Mw) 7.0


Northwestern Luzon EARTHQUAKE
At 08:43 AM Philippine Standard Time (PST), 27 July 2022, a major earthquake
with magnitude (Mw) 7.0 shook the provinces in northwestern Luzon and adjacent areas including
Metro Manila. The earthquake has an epicenter located at 17.63°N, 120.63°E – 3 km N 50° W of Tayum
(Abra) with a depth of 15 kilometers
6
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

E ach year, approximately 232 million people are affected by natural disasters, 100,000 people are died and
more than US$100 billion global in harm between 2001 and 2010.
Natural hazard is hydrological, atmospheric and geophysical incident such as tsunami,
earthquake, drought, flood or windstorm which caused damage or loss and natural disaster is severe
hazardous incident which affected the natural and built environment of affected regions. The Philippines
is among top five high-risk countries which experienced natural disasters such as earthquake,
flashfloods, mudslides, typhoon and volcanic eruptions. The Philippines had experienced five floods,
eight storms in form of tropical cyclones and earthquake in 2013. The landslides occurred in the areas
which surrounded by the mountains and coastlines.
Besides, Pangasinan province also listed as flood and typhoon prone province and located in the
west central area of Luzon, proved to be vulnerable to those disasters. Pangasinan is third biggest
province in the Philippines which constituted almost 42% of the region and 2% of total Philippine area.
There are 28% or 49 of of 175 typhoons that entered the Philippine area of responsibility directly
affected the province. The Pangasinan’s Provincial Disaster Risk Reduction and Management Council
(PDRRMC) had reported total of 405 casualties due to typhoons which 188 were reported died, 183
people injured and 34 people were missing.
7
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

A vulnerability map of the Pangasinan province had been created to accentuate the
vulnerability of the cities and municipalities. The different vulnerability levels were assigned specific
colour codes as shown in Fig. 1. The city of Dagupan is the most vulnerable and is also the only town
that was categorized as “Highly Vulnerable.” The municipalities Calasiao, Santa Barbara, Sual, and
Bolinao closely follow as “Moderately Vulnerable” areas.

Earthquake Hazards
8
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE
9
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

https://www.phivolcs.dost.gov.ph/index.php/earthquake/earthquake-hazards

Tips To Survive an Earthquake


No one wants to be taken by surprise when an earthquake hits. However, it’s impossible to
know when the next deadly tremor will occur. It might happen during the most mundane moment of
the day or while you’re sleeping.
Here are some tips to keep in mind before, during, and after an earthquake to ensure your
safety and of your loved ones when this disaster happens:
1. Before an Earthquake
Know the nearest evacuation site. If you’re living in a house made of light materials and located along
a fault line, it’s best to adhere to your local government’s evacuation guidelines. Thus, it’s important
to know the exact location of the nearest evacuation site and the safest route toward it.
Know your home’s “safe spots.” These are the spots where you can take cover in case a quake
happens, such as under a sturdy table.

10
SCHOOL CONTINGENCY PLAN FOR EARTHQUAKE

Create an earthquake plan. This includes delegating to your family members specific tasks that will be
accomplished when an earthquake occurs (e.g., where to meet when a quake hits, who will carry the
emergency kits, who will call emergency contacts, etc.)
Prepare an emergency kit. The kit must include ready-to-eat food, bottled water, a first aid kit,
charger, flashlight, batteries, and important documents.
Address potential home hazards. Heavy furniture (e.g., shelves and cabinets) and appliances must be
secured by strapping or hooking them to the wall. Don’t put heavy items near your home’s exit.
2. During an Earthquake
 Drop, cover, and hold. If possible, do this until the shaking stops. This is the best precaution in
case you’re in a high-rise building. Refrain from rushing to the exit (if there are many people) or
using an elevator. If there’s no available cover, protect your head and neck using pillows,
books, or arms.
 Move away from hazards such as windows, wires, fuel lines, trees, or sinkholes.
 Stop the vehicle if you’re inside it but make sure you’re far from any hazard.
 Go to the high ground if the shaking continues for more than 20 seconds. A tsunami might
ensue because of the persisting quake.
 Walk swiftly if you’re evacuating. This is faster than driving to the evacuation site and will keep
you from falling debris.
 Lock your wheelchair if you’re sitting on it.
 If you’re trapped, make noise using metals or any available material. Shouting should be your
last resort as it may drain your energy and make you inhale the dust.
3. After an Earthquake
Prepare for aftershocks. Although these are weaker than the main shaking, they might still
impose a risk to your safety and lead to further damage to infrastructure. Thus, stay alert and look out
for your loved ones. In case of an aftershock, be ready to practice safety measures just like you did
during the main quake.
Look for cracks in your home’s walls and roof. Don’t forget to check electrical and water lines
as well. If you find broken electrical lines, avoid using appliances and turning on the lights. Report
immediately to the local government unit or any concerned agency in case of faulty electrical or water
line.
Stay tuned for authorities’ announcements when it’s safe to return home in case you’re in an
evacuation sit.
11

Table 1. Baseline Data on Infrastructure

Table 2. Baseline Data on Non-Infrastructure


Name of Year Source Condition No. of Classrooms
Structure/ Constructed
Facility Instructional Non-
Instructional

USAide 1992/2018 NGO/DepEd Newly- 5 1


Renovated

Public Private 2018 DepEd Newly- 3 1


Partnership Renovated
(PPP)

Total 8 2

12
A. Furniture QUANTITY REMARKS

Armchairs 41 (wood) Good Condition

Set of Table & Chair 0 N/A

Table 0 N/A

Teachers’ Desk 0 N/A

Teachers’ Chair 4 Good Condition

Cabinets 2 Good Condition

Blackboard 16 Good Condition

Others N/A N/A

B. Equipment QUANTITY REMARKS

DCP Package 3 Good Condition

Computer/Desktop/ 5 Good Condition


Laptop

Television 6 PTA Funded

Radio 1 Good Condition

Aircon 1 Good Condition

Stand Fan 0 N/A

Wall Fan 0 N/A

Water Dispenser 1 Good Condition

Others N/A N/A

C. Laboratory

i. Science N/A N/A

ii. TVL N/A N/A

D. Learning Resources

i. Library Books N/A N/A

ii. Textbooks
15
Table 3. Baseline Data on Personnel
Teaching Non-Teaching GRAND
TOTAL
School Personnel
Mal Female SUB- Male Female SUB-
e
TOTAL TOTAL

Excluding IP, Muslim and with 1 7 8 1 1 2 10


Special Needs

IP 0 0 0 0 0 0 0

Muslim 0 0 0 0 0 0 0

Teaching Hearing 0 0 0 0 0 0 0
Personnel Impaired
with Special
Needs Visually 0 0 0 0 0 0 0
Impaired

Others 0 0 0 0 0 0 0
(Physical)

TOTAL 1 7 8 1 1 1 10

Table 4. Baseline Data on Learners


Grade Level

Learners
Male Female TOTAL

Excluding IP, Muslim and with Special Needs 55 45 100

IP 0 0 0

Muslim 0 0 0

Teaching Hearing Impaired 0 0 0


Personnel
with Special Visually Impaired 0 0 0
Needs

Others (Physical/Mental/Intellectual) 0 0 0

TOTAL 55 45 100

B. HAZARD ANALYSIS

TEMPLATE 3: HISTORICAL DATA ON DISASTERS


Affected EFFECTS ON:
Population INFRASTRUCTURE NON-INFRASTRUCTURE
No. of No. of No. of No. of non- No. of No. of No. of No. of
Learn Personnel Instructiona instructiona WASH damaged damage damaged
ers l Classroom l Facilities DepEd d school Learning
Estimate
classrooms Computerizatio furniture resources
d Total Other
Name of Type of n Project
Year Cost of effects/dama
Hazard Hazard (DCP)
Damage ges
M M T M M T M M T d
I A O I A O I A O
N J T N J T N J T
O O A O O A O O A
R R L R R L R R L
L L L
Y Y Y
Luzon Earthqu 1990 - -
Earthqu ake
ake 1990
Luzon Earthqu 2022 112 9 0 0 0 0 0 0 0 0 0 0 0 0 0 All
Earthqu ake Governme
ake 2022 nt are
Work
Suspended

Overview of 2022 Earthquake in Luzon

On July 27, 2022, at 8:43:24 a.m. (PHT), an earthquake struck the island of Luzon in
the Philippines. The earthquake had a magnitude of 7.0 Mw , with an epicenter
in Abra province. Eleven people were reported dead and 615 were injured. At least 35,798 homes,
schools and other buildings were damaged or destroyed, resulting in ₱1.88 billion (US$34 million)
worth of damage.

17 PRIORITIZATION
TEMPLATE 5: HAZARD

HAZARD PROBABILITY IMPACT AVERAGE RANK

RATE
PROBABI
REMARKS RATE REMARKS
* ** LITY +
IMPACT
2

1.Typhoon 4 Typhoon and 4 Significant lost or 4 2


weather damage to property
disturbances
frequently
occur thru the
area

2. Hightide 5 Hightide is 4 It affects the motion of 4.5 1


frequently people within the area
occurring thru because hightide
the area. It all within the road might
start last June cause diseases such
2022 as Leptospirosis
caused by virus that
9
comes from rats and
stagnant waters might
cause Dengue.

3. Earthquake 3 Area seldom 2 Catastrophic loss of 2.5 4.5


experiences
earthquakes property
but last July 27,
2022 shaken
the place

4. Covid 3 The event is 3 Delay in Operations / 3 3


expected to work
occur in most
and many
cases

5. Tsunami 3 The Area is 2 Catastrophic loss of 2.5 4.5


surrounded by property
bodies of
water.

10

C. Anatomy of18the Hazard

HAZARD TO PLAN
Resurgence of EARTHQUAKE
FOR

EARLY WARNING TRIGGERING EXISTING


ROOT CAUSES
SIGNS FACTORS MITIGATING MEASURES
Sudden movement
along faults within
the Earth.
Activate SDRRM Team
Erratic animal
Coordinate within the
The movement behaviors such as
LGU for class suspension
releases stored-up scared or confused Sudden release of stress
‘elastic strain’ energy pets or birdcalls not along faults in the
in the form of seismic usually heard during earth's crust. Monitor the schools on
waves, the night. the preparedness
measures as per DO 83
s. 2011 and DM 108 s.
Continuous motion of
2016
Ground surface to Sudden water level tectonic plates
shake. changes in wells or Monitor the situation of
artesian bores the school for any
incidents may happen like
Long-term falling debris
deformation and the
buildup of stress.

https://www.bgs.ac.uk/discovering-geology/earth-hazards/earthquakes/what-causes-earthquakes/#:~:text=Earthquakes%20are%20the%20result%20of,the%20ground%20surface
%20to%20shake.

19

CHAPTER II: CAPACITIES AND VULNERABILITIES AND KEY DRRM MEASURES

T his part provides a summary of the school’s different capacities and vulnerabilities or gaps in
terms of different key areas of preparedness to response.
Key Areas for Details Capacities Gaps Vulnerabilities
Preparedness
Risk Understanding 1. Understanding of Trainings and Implementation Geohazard location
Hazards and its Workshops
characteristics
2. Conduct of Risk Hazard mapping Implementation School Site
Assessment Development Plan
3. Planning and Drafting plan of Continuity if the Action Action Plan
Undertaking Action Plan Assessment &
Actions based on completion
risk assessment
results
Contingency Plan 1. Contingency plan Meetings and Limited manpower Time Constraint
and Dissemination Coordination
2. IEC Printing Content & Layout Familiarization of the
content
1. Understanding of Capacity Building Accessibility to Poor Connectivity
Communication advisory including Information
warning signals
2. Understanding Upkeep Limited Materials Lack of Funds
and Information know
Implementation of how
DO 21 s. 2015
3. Equipment Intact contact Hotline nos. Poor signal
numbers
1. Division Office Radar Reporting Poor signal Poor Connectivity
2. P/M/CDRRMC Intact contact Hotline nos. Poor signal
Coordination numbers
3. LGU’s Mdrrmc personnel Hotline nos. Immediate action on
contacts certain situation
4. Partners Barangay Officials Hotline nos. Poor signal
and parents contact
5. DepEd CO Rapid Assessment Hotline nos. Poor signal
Monitoring 1. Monitoring of Municipal Officials, Hotline numbers Late response in case
preparedness/ Barangay officials of emergency
contingency plan and PTA Officials
of school
2. Monitoring of Maintenance and Accessibility Late response in case
hazard situation, posting of contact of emergency
including numbers/hotline
numbers posted
communicating
20 with school
officials,
district/division
office and LGU
3. Monitoring Quick response of Internet Late submission of
RADaR SH and SDRRMC connectivity/non- Report
completion, availability of
Communication
validation and
submission to
Central Office
4. Monitoring of Monitoring and Availability of Data in Improper filling of
Implementation Assessment Review the School Data and Reporting
of support for
learning
continuity
5. Tracking of Maintenance of Access to the Records Records are handed
Learners and Contact numbers of to Advisers and
Personnel parents and School Disaster
teachers Coordinator
6. Transportation Readily Available Lack of Coordination Observance of Safety
Protocols
1. Interfere among Hotline numbers Poor connection No Signal
Convergence Offices within the were posted
School
2. Existence of Creation of SDRRM Coordination Hesitation to
DRRM Team response
3. Command System Open connection Coordination Availability of
Manpower
4. Twinning with Coordination Collaboration Hesitation to
other Divisions Response

Support for 1. Implement and Local Officials are Coordination Functionality


Learning Monitor the ones in-charge
Continuity Temporary
Learning Space
(TLS)
2. Buffer stocks for Requisition from Availability Shipping/Trucking
learning the LRMDS in- Transportation
materials charge
3. Alternative Intact modules in No Printed copy Availability of hard
Delivery Modes ADM Copy
4. Psychosocial Open Lack of Coordination Hesitation to
Support Communication Response
System to Parents
5. Emergency Open Inability of parents to Hesitation to
School Feeding Communication to attend regularly in the Response
Parents preparation of Foods
for the SBFP
6. Learner’s Kit Open Parents are not aware Irresponsible in using
Communication to of pupil’s needs in the the kits
parents and school
Learners
21 7. Teacher’s Kit Limited/others still Intact Wasteful used
purchase
8. Hygiene Kit Limited Limited Wasteful used
9. Provisions of Intact and still Lack of budget for Improper used
Water Sanitation updating maintenance
and Hygiene
Services
10. Updated Data and Master list Lack of Information Poor attendance
disaggregated are always updated Dissemination
data on learners
and master list of
students in school
and alternative
learning schools
(ALS)
11. Clean up Drives Coordination to Limited of human Availability of
stakeholders resources/manpower manpower materials
12. Signed Availability of Funds Time Constraint None inclusion to
Memorandum of and Resources Peps
Agreement
(MOA)

Support for 1. Signed Submission of Proper identification of Topographical area is


Schools Used as memorandum of Proper available evacuation the same with the
Evacuation Centers Agreement communication to area identified evacuation
respective offices in area located within
(MOA) between
charge the barangay.
LGU and School
on the use of
schools as
evacuation center
including the roles
and
responsibilities of
both institutions;
2. Repair, Coordinate with Lack of Funds Availability of
maintenance and stakeholders Manpower
replacement of
schools identified
as evacuation
center by the LGU
3. Resumption Intact and still Update the existing Absence of multiple
Strategies improving emergency Operation risks assessment
including Plan
Assessment of
Readiness of the
Schools
4. Establish Intact and Available Resettlement and Hesitation to
functional Complimentary Response
referral pathways Pathways
to respond to
22 child protection
concerns using
the existing PNP
and DSWD
operational
guidelines
5. Feedback Open Time constraint Hesitation to
mechanism to communication Response
report gaps in system to parents
the delivery of
services,
grievances and
other needs to
improve
education
interventions
6. Twinning of School coordinate Time Constraint Absence of Multiple
schools for with District Office risks Assessment
teacher-
volunteers for
deployment in the
affected schools
that need
additional
volunteers
7. LGU’s preposition Coordinate with the Hotline numbers Lack of funds
additional stakeholders
Temporary
Learning Spaces
(TLS)
1. Regular conduct Conduct Seminars Proper Implementation Hesitate to join the
of Drills and Drills for Different Drills
Drills Disaster
Orientation on the
NSED & Fire Drill Conduct of NSED and
fire Drill must be
done.
2. Existence of Open Lack of Coordination Late Response in
Protocols – Communication case of Emergency
command system, System to Parents
evacuation route,
safe place, family
reunification
3. Coordination with Proper Orientation Hotline numbers Poor Signal
and participation on the Conduct of
of parents, the Drill to the Simulation drills must
students & the be taken seriously by
relevant agencies
employees the people involved
and partners communication especially the
during drills Letters/SMS are SDRRM Team
sent to the PTA, through the
PNP, BFP, MDRRMC leadership of the
23 & PDRRMC & incident
Messages through Commander/Principal
group chats of and the SDRRM
students & teachers Coordinator
for the conduct of
the Drill
Coordinate with
stakeholders
Fund Sources MOOE, LGU, PTA, Coordinate with the Hotline Numbers Lack of Funds
Private Donations Stakeholders

School is an
Implementing Unit
(Direct released of
MOOE Fund)

CHAPTER III: RESPONSE ARRANGEMENTS

This section will show the possible future situations after the earthquake hits the school.

A. SCENARIO BUILDING
SITUATION BAD WORSE WORST

SCENARIO ground shaking ground rupture, tsunamis, and


landslides, liquefaction.

IMPACT ON HUMAN LIVES

No. of Death/s 0 0 1-2

No. of Injured 0 1-2 3 more

Percentage of 0% 1-3 % 4%
Displacement

AFFECTED POPULATION

No. of Learners 100 100 100

No. of Teaching 8 8 8
Personnel

No. of Non-Teaching 2 2 2
Personnel

EFFECTS ON

Learners none Injury, trauma Injury, trauma, death

Teachers none Injury, trauma Injury, trauma, death

Educational Continuity Delayed (1 week) Delayed (minimum of1 Delayed (until the
day and maximum of 1 repair of school has
month)
24 been done)

Instructional None Minor damages Heavy to severe


Classrooms damage

WaSH Facilities None None Minor damages

Perimeter Fence and None None Minor damages


Gate

School Furniture None Minor damages Heavy to severe


damage

Power Lines None Minor damages Heavy to severe


damage
Water Utilities None Minor damages Heavy to severe
damage

Roads and Bridges (to None None Minor damages


and from school)

● Description of the Event

Pangasinan is one of the provinces which experienced natural disasters such as earthquake,
floods, mudslides, typhoon and volcanic eruptions. Pangasinan had experienced flooding, storms in
form of tropical cyclones and earthquakes. Because of these natural disasters, our school has
experienced from minor damages to severe damages in facilities and some areas of our school are
under water.

● Impact on human lives

Since our town Binmaley is near coastal area, it has an impact on human lives that can lead to
injury or even death.

● Affected population

Based on the current data or existing records of the school, there are 100 learners, 10 teaching
and non-teaching personnel that will be affected by a earthquake.

● Effects on based on the capacity of the school

Based on the above data, it shows that there will be school property and facilities will be
affected by these calamities due to the school’s capacity of monitoring, early warning, forecasting and
hazard identification were very much strengthened.

25

B. RESOURCE INVENTORY AND NEEDS PROJECTION

This part serves as an inventory of all existing human resources, supplies and equipment of the
school that can be mobilized in preparing for response and during response and early recovery after the onslaught
of a Earthquakes. The tables below identify the projected needs in terms of human resources and supplies &
equipment and determine possible sources of funds to fill in the gaps in training or procurement of equipment and
supplies. Table 4 lists down all human resources needed to prepare and respond to Tropical Cyclone. Table 5
includes inventory of supplies and equipment in the school.

HUMAN RESOURCES

Human Resources Capacity No. of Projected Needs (e.g. Possible Timeline


(certification, skills, staff/persons training needs) Write N/A sources of
etc) available if not needed funding
No. of Cost for (MOOE, SEF,
staff Training Local DRRM
needing Fund, Partners,
etc)
training
Internal
Local DRRM
Basic Life Support 9 9 n/a Year Round
(e.g. GCs, Teachers, Fund/partners
Staff. Etc)
External Resources Basic Life Support

(e.g. Partners, PNP, (Rural Health Unit


Year Round
BFA, etc) Binmaley,
Philippine Red
Cross)
Search and
Rescue Year Round
(MDRRMO)
Fire Management
and Control – BFP Year Round
Binmaley
Equipment’s

Projected Needs Possible


Equipment’s/Supplies Condition Units Units Unit Cost sources of Timeline
Available Needed funding
(e.g. fire extinguishers, (e.g. fully
body board, siren, functional, (MOOE, SEF,
comms radio) nearing expiry, Local DRRM
etc.) Fund,
Partners,
etc.)
Fire Extinguishers Nearing expiry 3 2 Php 1,700 MOOE Jan.-Dec.
Communication Functional 1 2 Php 5,000 MOOE Jan.-Dec.
equipment
First aid kit Functional 6 26 2 Php 1,500 Partners Jan.-Dec.
sirens Fully functional 1 0 0 n/a n/a
26
LEARNING RESOURCES

Grade Level Title Language Available Quantity Needed Quantity


English 1 English 11 4
Filipino 1 Filipino 11 4
Araling Panlipunan 1 Mother tongue 11 4
Grade 1
Mathematics 1 Mother tongue 11 4
ESP 1 Mother tongue 11 4
MAPEH 1 Mother tongue 11 4
MTB-MLE 1 Mother tongue 11 4

Grade Level Title Language Available Quantity Needed Quantity


English 2 English 12 3
Filipino 2 Filipino 12 3
Araling Panlipunan 2 Mother tongue 12 3
Grade 2 Mathematics 2 Mother tongue 12 3
ESP 2 Mother tongue 12 3
MAPEH 2 Mother tongue 12 3
MTB-MLE 2 Mother tongue 12 3

Grade Level Title Language Available Quantity Needed Quantity


English 3 English 15 5
Filipino3 Filipino 15 5
Araling Panlipunan 3 Mother tongue 15 5
Mathematics 3 Mother tongue 15 5
Grade 3
ESP 3 Mother tongue 15 5
Science 3 Mother tongue 15 5
MAPEH 3 Mother tongue 15 5
MTB-MLE 3 Mother tongue 15 5

Grade Level Title Language Available Quantity Needed Quantity


English 4 English 12 3
Filipino 4 Filipino 12 3
Araling Panlipunan 4 Filipino 12 3
Mathematics 4 English 12 3
Grade 4
ESP 4 Filipino 12 3
Science 4 English 12 3
MAPEH 4 Filipino 12 3
EPP 4 Filipino 12 3

Grade Level Title Language Available Quantity Needed Quantity


English 5 English 25 0
Filipino 5 Filipino 25 0
Araling Panlipunan 5 Filipino 25 0
Mathematics 5 English 25 0
Grade 5
ESP 5 Filipino 25 0
Science 5 English 25 0
MAPEH 5 Filipino 25 0
TLE 5 Filipino 25 0

27
Grade Level Title Language Available Quantity Needed Quantity
English 6 English 15 5
Filipino 6 Filipino 15 5
Araling Panlipunan 6 Filipino 15 5
Mathematics 6 English 15 5
Grade 6
ESP 6 Filipino 15 5
Science 6 English 15 5
MAPEH 6 Filipino 15 5
TLE 6 Filipino 15 5
C. RESPONSE ACTIONS
This part focuses on the school’s response if and when Earthquake will hit the school. The table
below summarizes the said responses:

The table below presents the actions of the school if the chosen priority hazard occurs.

TABLE 6: RESPONSE ACTIONS FOR PRIORITY HAZARD

TIMELINE RESPONSE ACTIONS


BEFORE Make an Emergency Plan: Create a family emergency
communications plan that has an out-of-state
contact. Plan where to meet if you get separated.
Make a supply kit that includes enough food and
water for several days, a flashlight, a fire extinguisher
and a whistle.

Prepositioning pf resources (books, learning


resources, adherence to suspension of classes based
on EO 66 s. 2012
DURING Cover your head and neck with your arms. If a sturdy
table or desk is nearby, crawl underneath it for
shelter. If no shelter is nearby, crawl next to an
interior wall (away from windows). Crawl only if you
can reach better cover without going through an
area with more debris.
AFTER Monitor the School’s Situation and gather
information for reporting.

Check yourself and others for injuries....


Check water, gas, and electric lines for damage. ...
Turn on the radio. ...
Stay out of damaged buildings.
Be careful around broken glass and debris. ...
Be careful of chimneys (they may fall on you).
Stay away from beaches. ...
Stay away from damaged areas.

0-24 hours Observe Safety measures


24-48 hours Monitoring and checking for damages
72 hours Submission of RADAR
96 hours validation
5-10 days Clean-Up Drive

28
D. SDRRM TEAM DIRECTORY
E. BINMALEY/SCHOOL EMERGENCY DIRECTORY
The following are required clusters, with their corresponding lead and members and their
responsibilities that must be activated in response to the typhoon.

Role Name/Cluster Lead Contact Number Responsibility


Over-all Coordinator Dr. Emma C. Cerezo In-charge of the CP
process; monitors the
progress of CP; initiates
the conduct of meetings
to review, evaluate and
update the Contingency
Plan
Communication and Rochelle B. Torres 09383250472 In-charge of the
Warning dissemination of the
information regarding
the hazard.
Evacuation Mercedes B. Torres 09091471463 Assists with the
evacuation and acts as
communication liaisons
with on-scene
responders (police,
firefighters, etc)
Security Manny V. Dela Cruz 09954039482 Prevents crime of theft,
and protect the general
welfare during the
typhoon/hazard.
Supply Mylyn D. Tomaquin 09666453144 Monitors and make sure
that there is enough
supply of equipment,
medical supplies and
other relief goods during
the typhoon.
Medical Maricris C. Acosta 09156651992 Responds on on-scene
treatment
Relief and Registration Catalina Antonia Y. 09209124216 Monitors and assess the
Ferrer/Juanita S. 09084942347 relief operation.
Fernandez
Technical Jonathan V. 09093403458 Checks the electrical
Villanueva/Marivic F. 09073722592 support in school and
Castro other safety equipment.

29

Partnership is necessary to ensure continuity and expansion of resources not readily found
within the existing capacity of the school.
1. MDRRMC/LGU/BFP/PNP as member of the medical and rescue team if there is an untoward incident
happen.
2. Barangay Councils as part of the implementing partner of the school as a member of the safety and
security team, psychological and support team, evacuation team and technical working group.
3. Barangay health workers to support our medical and rescue team if needed.
4. PTA Officers headed by the President, Charina Bruan as a member of the evacuation Team.

PARTNERS SPECIFIC ROLE/SUPPORT OF PARTNER CONTACT


PERSON/NUMBER
MDRRMO Monitors and assist in relief operation, search and 094996144842
rescue and other assistance needed.
BINMALEY FIRE STATION To provide security to resources and assist in 09171854611
relief operation and search and rescue.
BINMALEY PNP To provide security to resources and assist in 09499400713
relief operation and search and rescue.
AMBULANCE Providing care and safe transport and rescue. 09159063375
BARANGAY COUNCIL Assist in relief operation and search and rescue Brgy. Captain Cezar D.
and other assistance needed. Francisco/ Educ.Chairman
Hon. Salcedo Erfe
BARANGAY HEALTH UNIT Support our medical and rescue team if needed. Mrs. Baby Ramos
PTA OFFICERS Assist in relief operation and search and rescue Mrs. Charina Bruan
and other assistance needed.

30
CHAPTER VI: ACTIVATION/NON-ACTIVATION

The procedures for activating the Contingency Plan shall adhere to the flow chart below:
PDRA- Pre-Disaster Risk Assessment Alert Status- level of readiness
RDANA- Rapid Damage Assessment START of the agency, offices or field
units in prevention for
PAGASA forecast Typhoon

DRRMC conducts PDRA

1 Typhoon makes landfall, DRRMC 2


conducts RDANA

EOC on blue alert


EOC on red alert status YES NO status
Activate
Contingency Plan?
Responders conduct
RO convenes the normal operations
clusters at the EOC using ICS

Clusters provide
RO mobilizes and continuous support to
deploys MT responders

NO
Clusters and IMT
operate based on 1 Situation Normalize

Contingency Plan

NO IC recommends
Situation demobilization
Approved? 1
RO approves recommendation
IMT recommends for demobilization
deactivation of
Contingency Plan Responders and clusters demobilize.
Clusters for early recovery operate.
RO directs
deactivation of
Contingency Plan EOC returns to white status

2 31 END
The decision whether or not to activate the contingency plan (CP) will be based on the findings of the
Pre-Disaster Risk Assessment (PDRA) by the SDRRMC. If CP is activated, all clusters will convene at the Incident
Command Post. The incident Management Team (IMT) will be mobilized, who, together with the clusters shall
implement the CP.

The Contingency Plan shall be deactivated once the situation has improved and when heightened alert
is no longer required. Upon deactivation, operation will still remain to until a “White Alert” is finally declared.
EFFECTIVITY
This contingency plan for Earthquake shall be effective and upon publication. The plan shall
be considered as “working document” and be subjected to continuous review and enhancement by the DepEd
Technical Working Group based on latest scientific studies about geological hazards, risk assessment findings
and innovations in DRRM policies and standards.

Prepared by: Checked and Validated by:

ROCHELLE B. TORRES EMMA C. CEREZO, EdD


SDRRM Focal Person Principal II

--END—