PROJECT TITLE: RENOVATION OF CNHS COMFORT ROOMS

PROJECT LOCATION: CALATAGAN BATANGAS


PROJECT OWNER:

Total Cost
Estimated Direct
WORK DESCRIPTION Quantity Unit Estimated Unit
Cost
Item No. Cost

GENERAL REQUIREMENTS
PERMITS AND OTHER DOCUMENTARY REQUIREMENTS 1 LOT 20,000.00 20,000.00

20,000.00

I BOY'S COMFORT ROOM RIGHT WING (FRONT) 10.25 sq.m


SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 10.25 SQ.M 2,500.00 25,625.00 25,625.00
INSTALLATION OF NEW OF WATER CLOSET AND URINAL 1 LOT 28,875.00 28,875.00 28,875.00
INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 25,000.00 25,000.00 25,000.00
INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 15,000.00 15,000.00 14,000.00
PAINTING WORKS 1 LOT 14,000.00 14,000.00 12,000.00

105,500.00

II BOY'S COMFORT ROOM RIGHT WING (REAR) 7.58sq.m


TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 7.58 SQ.M 2,500.00 18,950.00 18,950.00
SUPPLY AND INSTALLATION OF NEW 1 UNIT OF WATER CLOSET AND 3
UNITS OF URINAL 1 LOT 40,200.00 40,200.00
NSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 8,000.00 8,000.00
INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 12,000.00 12,000.00
PAINTING WORKS 1 LOT 13,000.00 13,000.00 13,000.00
92,150.00

III GIRL'S COMFORT ROOM RIGHT WING (REAR) 7.58sq.m


TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 7.58 SQ.M 2,500.00 18,950.00 18,950.00
INSTALLATION OF NEW UNIT OF WATER CLOSET 1 LOT 25,000.00 25,000.00
SUPPLY AND INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 8,000.00 8,000.00
INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 12,000.00 12,000.00
PAINTING WORKS 1 LOT 13,000.00 13,000.00 13,000.00
76,950.00

IV BOY'S,GIRL'S AND TEACHER'S COMFORT ROOM LEFT WING (REAR) 11.11 sq.m
TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 11.09 SQ.M 2,500.00 27,725.00 27,725.00
INSTALLATION OF NEW UNIT OF WATER CLOSET AND 2 UNITS OF URINAL 1 LOT 40,000.00 40,000.00

INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 5,000.00 5,000.00

INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 8,000.00 8,000.00
PAINTING WORKS 1 LOT 14,000.00 14,000.00 14,000.00
94,725.00

V COMFORT ROOM LEFT WING (NEAR CLINIC) 13.63sq.m

TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 11.09 SQ.M 2,500.00 27,725.00 27,725.00
INSTALLATION OF NEW WATER CLOSET 1 LOT 25,000.00 25,000.00
INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 15,000.00 15,000.00
INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 29,000.00 29,000.00
PAINTING WORKS 1 LOT 15,000.00 15,000.00 15,000.00
111,725.00

VI COMFORT ROOM LEFT WING (FRONT) 14.06 sq.m (FACULTY)


TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 14.06 SQ.M 2,500.00 35,150.00 35,150.00
SUPPLY AND INSTALLATION OF NEW 5 UNIT OF WATER CLOSET 1 LOT 35,000.00 35,000.00
SUPPLY AND INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 25,000.00 25,000.00
SUPPLY AND INSTALLATION OF TOILET PARTITIONS 1 LOT 23,000.00 23,000.00
PAINTING WORKS 1 LOT 11,000.00 11,000.00 11,000.00
129,150.00

VII COMFORT ROOM WITH WASHING AREA


TILE WORKS
SUPPLY AND INSTALLATION OF 30X30 CERAMIC NON SKID FLOOR TILES 14.06 SQ.M 2,500.00 35,150.00 35,150.00
SUPPLY AND INSTALLATION OF NEW 5 UNIT OF WATER CLOSET 1 LOT 35,000.00 35,000.00
SUPPLY AND INSTALLATION OF NEW LAVATORY WITH MIRROR 1 LOT 25,000.00 25,000.00
INSTALLATION OF TOILET CHB PARTITIONS WITH PANEL DOORS 1 LOT 35,000.00 35,000.00
PAINTING WORKS 1 LOT 8,000.00 8,000.00 8,000.00
138,150.00

TOTAL PROJ.COST 768,350.00