You are on page 1of 2

TSO TOP TUNNEL & CONSTRUCTION SDN BHD JOB SAFETY ANALYSIS FORM (JSA FORM)

Manual Lifting (using chain block, sling belt, & shackle) &
Activity: Positioning for tank, Kettle DSC02-KET01 RA Team: Tinesh, Iqbal & Wagar Ali
Location: Biocon 1814 (SRP) Reviewed By : Iqbal
Date: 17-Feb-24
Prepared By: Waqar Ali and Iqbal
Approved By:

Step Description of Task Step Potential Hazard / Who or What Might be Control Measures/Recovery Action / Responsible
No Risk Harmed Measures Party
1 Application of work permit 1. Miscommunication and lack of 1. Body injury 1. Work permit to be secured before any works commence
information
Work Supervisor Safety
2. Exposed to unknown hazard at 2. Pre-start meeting shall be discussed during daily toolbox
Supervisor
workplace meeting before work commence
3. Tool/Equipment inspection must be carried out
2 Inspection of tools, equipment and lifting 1. Slip, trip and fall 1. Body injury 1. Pic to check the power tool for faults before inspect and do not
gears before commence work 2. Electrocution use a tool that has any defects such as damage to the casing, faulty
switch, torn or crack. Work Supervisor Safety
2. Wear appropriate PPE (safety helmet, shoes, jacket, glass, Supervisor
gloves, etc)
3. Ensure workers not involved with the inpection at a safe
distance rom the work area
3 Confirming the location of 1. Miscommunication and lack of 1. Property damage 1. Communicate with project team the correct location of the tank to be Work Supervisor Safety
moving/positioning the equipment/tank information installed Supervisor

4 Mobilisation of material and equipment 1. Heavy / large machinery equipment 1. Property damage 1. Supervisor to brief crew on the ground of all the
2. Body injury activities related to work.
2. Obstruction in access way 3. Vehicle and machinery stuck 2. Survey and ascertain that the allocated area is
Work Supervisor Safety
3. Uncontrolled vehicle movement / enough for the mobilization of machinery
traffic flow Supervisor
3. Clear area of unnecessary obstruction
4. Unstable ground due to bad weather 4. Assign a man to guide or
condition escort if required to bring it to the location.
5 Setting up for manual lifting using C- 1. Incompetent person 1. Property damage 1- Conduct toolbox meeting before start work
Channel, I-Beam , lifting belt and chain 2. Unauthorized personnel 2. Body injury 2. Only competent person to carry out manual lifting.
block. 3. Presence of other / situational 3. Provide barricade and lifting signage.
hazard 4. Work area inspection prior to start work activity.
4. Restricted / limited work Work Supervisor Safety
5. Permit to work (PTW) shall applied as required.
space. Supervisor
6. Ensure chain block was inspect and certified before used.
5. Ergonomics hazards (strains, sprains, 7. Ensure ground is stable, and nobody work below the lifting load.
back injuries and body injury 8. Ensure adequate space is available to work.

Page 1 of 2
TSO TOP TUNNEL & CONSTRUCTION SDN BHD JOB SAFETY ANALYSIS FORM (JSA FORM)

Manual Lifting (using chain block, sling belt, & shackle) &
Activity: Positioning for tank, Kettle DSC02-KET01 RA Team: Tinesh, Iqbal & Wagar Ali
Location: Biocon 1814 (SRP) Reviewed By : Iqbal
Date: 17-Feb-24
Prepared By: Waqar Ali and Iqbal
Approved By:

6 Manual lifting / pulling the kettle using 1. Improper ringging / slingging method 1. Property 1. Permit to work (PTW) shall applied as required
chain block damage 2. Ensure chain block, anchor hook, lifting gear shall have valid
2. Incorrect hook attachment resulting in 2. Body injury inspection tag and inspected by inspector before entering the site.
dislodging of hook 3. Ensure rigger use the proper ringging and slingging method
3. Unsuitable use of lifting gears before lifting operation and properly tie the lifting gears.
4. Mechanic failure of resulting in loss 4. Ensure ringging been carried out by qualified and competent
load rigger.
5. Communication failure 5. Barricade work area, avoid standing under suspended load.
6. Ergonomics 6. Never use undue effort to force a chain block to operate.
7. Swaying & falling of load 7. Ensure the chain block must always be rigged to lift in a straight line
form hook to hook. The chain block must always be free to swivel on
the upper hook. Under no conditions should the chain block frame be
allowed to bear on any support when in use as this would cause bending
of the hook or frame and damage the unit.
8. Ensure to not exceed SWL of chain block, wire rope and lifting gears.
9. Proper use of tag line allowing hoisting material to not swing out
Work Supervisor Safety
of control.
Supervisor
10. The set-up area shall be inspected to determine the suitability

11. Ensure rigger hand free from pinch point are and follow up the
signal by signalman only
12. Follow lifting plan which consists of all the important information
that must be considered in this lifting operation
13. Regular maintenance and servicing are to be carried out according to
manufacturer’s specification
14. Check for gouged, twisted, distorted links and foreign
material. Do not operate chain blocks with twisted, kinked or damaged
chain links.
15. Communication with hand signal or walkie talkie with low frequency.

16. Wear suitable PPE


8 Environment 1. Exposure to extreme temperature 1. Heat stress 1. Drink water regularly.
2. Bad weather condition 2. Dehydration Work Supervisor Safety
2. Provide rest shelter for workers
(heavy/rain/lighting/strong wind) 3. Strike by lightning Supervisor
3. Stop work immediately in occurrence of bad weather
9 Housekeeping 1. Pinch point 1. Hand injury 1. Ensure all the workers are fit to work.
2. Sharp Edge 2. Wear suitable work gloves appropriate to the task Work Supervisor Safety
must be work Supervisor
3. Perform good housekeeping practices.

Page 2 of 2

You might also like