You are on page 1of 7

PEAKE TECHNOLOGIES LIMITED

JOB HAZARD ANALYSIS

Location: National Cycling Centre - SPORTT Date: 14/06/22 JHA #: SPORTT-NCC-001 Site Visited: Yes No Permit #:
Job Description: Maintenance Service on Cooling Towers
Has consideration been given to weather conditions: Are written job procedures discussed and attached: Are there SIMOPS: Yes No Emergency Response Plan Made &
Yes No Yes No Discussed:
Was Toolbox meeting held: Yes No Yes No

Sequence of Basic Job Steps Potential Accidents / Hazards Corrective Measures / Recommendations Action By
1. Mobilization of manpower, tool and 1.Poor Lifting causing back injuries, strains 1. Ensure PPE is worn at all times (Safety helmet, steel toed boots, Peake’s Supervisor
equipment 2. Pinch Points, lacerations vest, glasses, gloves). Is another critical person on site
3. Sharp edges 2. Assess loads before lifting. Use of proper lifting techniques. to ensure that the controls are
4. Slips, Trips, Falls Seek assistance to lift or lower heavy loads. implemented?
5. COVID-19 Contamination 3. Cordon off the work area.
4. Pay attention to environment/surfaces particularly in wet
conditions. Ensure soles of Safety boots are not smooth.
5. Inspect all tools and equipment before mobilization to ensure
that they are in good condition.
6. Scheduling of work are to be conducted in such a way to limit
the number of persons coming into contact with one another.
Employees are required to practice social distancing and keep 2m
away from others. Frequent washing of hands with soap and water;
use of hand sanitizer in the absence of soap and water. Refrain
from touching hands, face and mouth. Use of facemask.
Supervision of employees to enforce restriction of gatherings.
Adhere to Client’s COVID-19 Procedures.
2. Isolate Cooling Tower Electricals 1. Electrical shock, burns 1. Use LO/TO isolate the electrical to prevent tampering. Peake Personnel
Complete Client’s Lock out/Tag form if available.
Is testing of the electrical system
to confirm that the system is
de-energized taking place?

Is the assigned person conducting


LOTO certified?

In the event client does not have a


LOTO form what is your
process?
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS
3. Isolate Water Supply 1. Sharp edges/Pinch Points 1. Be mindful of hand and body placement, ensure use of Peake’s Supervisor
2. Awkward positioning appropriate PPE (gloves)
3. Slips/trips/falls 2. Practice situational awareness, properly analyze work area for
best plan of action.
3. Watch where you are walking especially in wet areas, ensure
proper housekeeping is maintained in work area.

4. Inspection/replacement of Fan Belts 1. Use of Hand/Power tools 1. Inspect all tools and power cords before use, do not disable or Peake’s supervisor
2. Pinch points/Sharp edges remove any safety devices on tools, ensure only trained and
competent personnel are used, only use tools for their intended
purpose, ensure use of appropriate PPE (gloves safety glasses,
safety boots)
2. Be mindful of hand and body placement, ensure use of
appropriate PPE (gloves)
5.Inspection and Cleaning of Fan Blades 1. Working at heights 1. Cordon off work area to prevent unauthorized personnel, ensure Peake’s Supervisor
2. Use of Hand/Power tools scaffolding is inspected and certified before use, ensure capacity
3. Pinch points/Sharp Edges limit of scaffolding is not exceeded, ensure use of appropriate fall Scaffold to be appropriately
4. Slip, trips and falls protection devices when working at heights 6ft and above, tagged after erection.
properly secure all tools and equipment on scaffolding to avoid
dropped objects Certs provided.
2. Inspect all tools and power cords before use, do not disable or
remove any safety devices on tools, ensure only trained and
competent personnel are used, only use tools for their intended
purpose, ensure use of appropriate PPE (gloves safety glasses,
safety boots)
3. Be mindful of hand and body placement, ensure use of
appropriate PPE (gloves)
4. Watch where you are walking especially in wet areas, ensure
proper housekeeping is maintained in work area
6. Greasing of all Bearings, shaft and hubs 1. Working at heights 1. Cordon off work area to prevent unauthorized personnel, ensure Peake’s Supervisor
2. Pinch Points/Sharp Edges scaffolding is inspected and certified before use, ensure capacity
3. Slips, trips and falls limit of scaffolding is not exceeded, ensure use of appropriate fall
protection devices when working at heights 6ft and above,
properly secure all tools and equipment on scaffolding to avoid
dropped objects
2. Be mindful of hand and body placement, ensure use of
appropriate PPE (gloves)
3. Watch where you are walking especially in wet areas, ensure
proper housekeeping is maintained in work area
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS

7. Cleaning/Power Washing of Necessary Parts 1. Working at Heights 1. Cordon off work area to prevent unauthorized personnel, ensure Peake’s Supervisor
and Components 2. Use of Hand/Power Tools scaffolding is inspected and certified before use, ensure capacity
3. slips, trips and falls limit of scaffolding is not exceeded, ensure use of appropriate fall
protection devices when working at heights 6ft and above,
properly secure all tools and equipment on scaffolding to avoid
dropped objects
2. Inspect all tools and power cords before use, do not disable or
remove any safety devices on tools, ensure only trained and
competent personnel are used, only use tools for their intended
purpose, ensure use of appropriate PPE (gloves safety glasses,
safety boots)
3. Watch where you are walking especially in wet areas, ensure
proper housekeeping is maintained in work area

8. Treatment/Painting of Exposed Metals as 1. Use of Hazardous Chemical 1. Consult MSDS for all hazardous substances before use, MSDS to be provided to HSES
Necessary 2. Working at Heights ensure work area is properly ventilated where possible, Dept.
3. Slips, trips and falls ensure use of appropriate PPE (face covering, gloves, long
sleeve clothing
2. Cordon off work area to prevent unauthorized personnel, ensure
scaffolding is inspected and certified before use, ensure capacity
limit of scaffolding is not exceeded, ensure use of appropriate fall
protection devices when working at heights 6ft and above,
properly secure all tools and equipment on scaffolding to avoid
dropped objects
3. Watch where you are walking especially in wet areas, ensure
proper housekeeping is maintained in work area
8. Putting system back into operation 1. Incorrect wiring. Electrical damage to unit. 1. Use of competent personnel. Check operation of unit and Peake’s Supervisor
record readings. Follow appropriate work procedure.
Technician certificates required.
9. Housekeeping Trips, slips, fall resulting in abrasions, lacerations. 1. Cover items which cannot be moved prior to start of task. Store Peake’s Supervisor
Serious bodily injury tools and materials to one (1) side away from the working area.
Leptospirosis 2. Clean up work area and place trash in garbage bags and
dispose of in designated areas at the end of the work period.
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS

SAFETY EQUIPMENT REQUIRED:


Safety Hard Hat  Safety Glasses Face Shield Hearing Protection Goggles Cotton Gloves Fire Blanket Lock Out

Safety Harness  Barricades Vessel Entry Fire Resistant Clothing Leather Gloves Chemical Resistant Gloves Tag Out Fire Extinguishers
Permit
Rope Off Area  Hot Work Permit Fire Watch Scaffolding Gas Detectors Lifting Precaution Dust Mask Chemical Mask

Other (Please specify) Safety Boots Excavation Permit


HAZARD CHECKLIST:
Falls From Heights Falling Objects Collision Access/Egress Moving Machinery Liquid Or Gas Under Pressure
Noise Chemical Exposure Illumination Flammable Materials Flaring / Hydrocarbon Gas Release Electricity
Oil/ Chemical Competence Of Personnel Confine Space Corrosive Material Manual Handling Naked Flames
Other (Please
specify)
PREPARED BY APPROVED BY APPROVED BY APPROVED BY APPROVED BY
Job Title: HSEQ OFFICER Job Title: MANAGER Job Title: Job Title: Job Title:
Name: ANDRE FRANCO Name: MURREN GEORGE Name: Name: Name:
(Please Print) (Please Print) (Please Print) (Please Print) (Please Print)
Signature: Signature: Signature: Signature: Signature:
Date: Date: Date Date Date

\
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS

Sequence of Basic Job Steps Potential Accidents / Hazards Corrective Measures / Action By
Recommendations
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS

Please write your name clearly (valid for 5 consecutive days)


Date: Date: Date: Date: Date:
Names Signature Names Signature Names Signature Names Signature Names Signature
PEAKE TECHNOLOGIES LIMITED
JOB HAZARD ANALYSIS