1 Prepare the format for structural audit including complains reported by the user. COI602.6
Marking Scheme 6mk
Sr.no. Type of information/Criteria Information Status Remark
1 Name of users Name:
Mobile/Whats App No.
Alternative No.:
E-Mail:
Address:
Answer 2 Status of user Owner/Tenant/Lease
3 Address of site Detailed address of site
4 Total area, number of floors Plot area:
Built up area:
Carpet area:
Number of wings/building:
Number of floors:
Number of flats:
Number of flats:
Flat No:
5 Water leakage problem
a) From water tank Yes/No
b) Walls Yes/No
c) Inside area Yes/No
d) Outside area Yes/No
10. Formation/Identification of
cracks
a) Slab Yes/No
b) Column Yes/No
c) Beams Yes/No
d) Walls Yes/No
e) Foundation Yes/No
11. Functioning problem of doors Yes/No
and windows
12. Feel of vibration while using
structure
13. Termite problem if any Yes/No
14. Any alteration carried out Yes/No if yes the details
15. Any other specific complaint
2 Write the necessity of performing structural audit of existing structure. COI602.6
Answer 1.To provide a realistic estimate of imcome expenses for a period and of financial position at close
of period.
2. To maximize the useful life of an asset, as well as equipment uptime
3. To minimizing percentage of operating costs
4. used to control expenditure
5. used to establish proprieties.
5. To Provide direction for selection of materials as per their cost.
4. Write down necessity/Importance of budget. COI602.6
Marking Scheme 6mk
Answer 1.To create a spending plan for your money
2.To ensures that you will always have enough money for things you need
3.To keep you out of debt or help you work your way out of debt.
4.To control project costs within approved budget and deliver expected project goals.
5.Used to narrow down a choice in contractor
6.To avoid spending on unnecessary fees, services and products that are cutting into your financial
goals.
5. Write short note on detailed inspection. Or Checklist for detailed inspection. COI602.6
Marking Scheme
Answer While repair/strengthening on has to reach the distress part of structure , detailed inspection for
repair of any part of structure includes.
1.Check the accessibility of place where repairs is required.
2.Removal of material of distress area.
3.Any special tools required
4.Manpower required
5.Alternative methods of repair
6.Strengthening method if required
7.Duration of curing of repair material
8.List of test to be carried out
9.loading /transporting of removed material.
6. Write down steps involved in structural audit. COI602.6
Marking Scheme 6mk
Answer Step 1- It is imperative that we must have architectural and structural plans of bld. It will be helpful
if we have detailed structural calculations including assumptions for the structural design.
Step 2- If the architectural plans and structural plans are not available , the same can be prepared by
any engineer.
Step 3- Inspection of the bld- A detailed inspection of the bld. Can reveal the following
1.Any settlements in foundations
2. Cracks in columns, beams and slabs
3.Concrete disintegration and exposed steel rif. Photographs can be helpful.
4.slight tapping using hammer can reveal deterioration in concrete.
5.corrosion in rif.
6.status of balconies- sagging, deflection, cracks
7.status of architectural freatures, chhajjas.
8.Cracks in wall indiacation swelling in RCC members or deflection or corrosion
9.leakages from terrace and toilet blocks.
10. leakages and dampness in wall
11.status of repairs and last repaired.
12.What was repaired?
13.Who was the agency?
14.How much was spent for repairs?
15.Building plans are available? When approved?
Step 4-Preparation of audit report:on the basis of inspection of building an audit report is prepared.
Step 5- Tests recommended: It is important that various tests are carried out in old buildings. This
will give an idea about extent of corrosion, distress and loss of strength in concrete and steel.
Step 6- Highlight the critical areas and how to go for repairs.
7. Describe in brief any four importance of visual observations for damage. COI602.6
Marking Scheme
Answer 1.The technique of visual observations in which visual appearances of damages or defects in
structure gives the first alertness about problems to the owner.
2.It is very powerful NDT method. Its efficiency, however, is to a large extent governed by
experience and knowledge of investigator.
3.A broad knowledge of structural behavior, materials and construction methods is desirable.
4.This variable and localized damage is a phenomenon of interest and therefore attending this
localized damage is relatively easy and permits to carry out localized repairs effectively.
5.This controls restoration costs and duration of activity.
6.The observations or investigation must be recorded in a systematic manner to ascertain whether