GEODETIC EXPERT SCHEDULE

ID ITEM Start Duration Finish DETAIL ACTION 2024


January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 20
14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08
0 GEODETIC 31/01/24 298 23/11/24 31/01 23/11
ACTIVITY days
1 CONSTRUCTION31/01/24 298 days 23/11/24 31/01 23/11
ITEM
2 ITEM 1 31/01/24 25 days 24/02/24 Geometric and Elevasi 31/01 24/02
Checking
3 ITEM 2 25/02/24 35 days 30/03/24 Geometric and Elevasi 25/02 30/03
Checking
4 ITEM 3 25/02/24 9 days 04/03/24 PDA pile position checking 25/02 04/03

5 ITEM 4 05/03/24 3 days 07/03/24 Elevasi Checking finish 05/03 07/03


Ground
6 ITEM 5 08/03/24 16 days 23/03/24 Pile cut elevation checking 08/03 23/03

7 ITEM 6 24/03/24 10 days 02/04/24 Geometric and Elevasi 24/03 02/04


Checking
8 ITEM 7 03/04/24 5 days 07/04/24 Elevasi Checking finish 03/04 07/04
Ground
9 ITEM 8 31/03/24 10 days 09/04/24 PDA pile position checking 31/03 09/04

10 ITEM 9 10/04/24 3 days 12/04/24 Elevasi Checking finish 10/04 12/04


Ground
11 ITEM 10 13/04/24 22 days 04/05/24 Pile cut elevation checking 13/04 04/05

12 ITEM 11 05/05/24 25 days 29/05/24 Geometric and Elevasi 05/05 29/05


Checking
13 ITEM 12 30/05/24 8 days 06/06/24 Elevation check 30/05 06/06

14 ITEM 13 08/04/24 2 days 09/04/24 Elevation check 08/04 09/04

15 ITEM 14 10/04/24 3 days 12/04/24 Geometric and Elevasi 10/04 12/04


Checking
16 ITEM 15 13/04/24 11 days 23/04/24 Geometric and Elevasi 13/04 23/04
Checking
17 ITEM 16 07/06/24 5 days 11/06/24 Elevation check 07/06 11/06

18 ITEM 17 12/06/24 7 days 18/06/24 Geometric and Elevasi 12/06 18/06


Checking
19 ITEM 18 19/06/24 14 days 02/07/24 Geometric and Elevasi 19/06 02/07
Checking
20 ITEM 19 03/07/24 72 days 12/09/24 Geometric and Elevasi 03/07 12/09
Checking
21 ITEM 20 13/09/24 72 days 23/11/24 Geometric and Elevasi 13/09 23/11
Checking

Note :
1. Item Name (See Contractor Schedule)
2. Start duration and finish folow Contractor Schedule
3. The Contractor Schedule is Attached
4. Geometric checking (Verticality, Dimension part of struktur)
5. elevation checking ( Elevation Excavation, Gravel,LC, Rebar,
Concrete of each stage of work

31/01/24 - 23/11/24