COMPANY NAME PROJECT NAME WRITTEN BY

NTISANE HOLDINGS Bund wall maintanance plan (83m³) Adrian

CLIENT

ESKOM

DATE Task DESCRIPTION EXPECTED RESULT ACTUAL RESULT PASSED TESTED BY COMMENTS
Break bund wall and rebuild it
1 according to SANS small currently in progress
Breaking of the walls buildings standard
Drainage of contaminated water water drained and disposed in
2 water was drained and disposed
from sumps an environmentally safe way

3 Filling and repair of cracks wall free from cracks pending

4 Sand blasting even surface pending

neat and Aesthecally acceptable


5 Painting of wall pending
standard