Republic of the Philippines

Province of Samar
Municipality of Daram

NAME/LOCATION OF PROJECT: Project Cost: ₱631,178.75


Source of Funds: SEF
SPECIAL EDUCATION FUND DARAM I DISTRICT SCHOOLS Project Duration: 240 C.D.
Desirable Starting Upon Approval
DARAM, SAMAR Date:
Description:

MINIMUM EQUIPMENT REQUIREMENT TECHINICAL PERSONNEL REQUIREMENT


Description No. Description No.
Skilled 2
Laborer 4

LOT NO. Description Location

Wash in School Project ArawanI, Astorga, Campelipa, Guintampilan,


I
Implementation/Improvement Pondang

Unit Quantity Cost Unit Cost


I.A REINFORCED CONCRETE 1.12 cu.m 21,136.50 18,871.88

I.B METAL STRUCTURES 430.02 kg 59,022.85 137.26

I.C METAL ROOFING 7 sq.m. 5,879.79 839.97

PAINTING, VARNISHING AND


I.D 20.5 sq.m. 12,010.15 585.86
OTHER RELATED WORKS
FORMWORKS AND
I.E 180 bd.ft 30,013.83 166.74
FALSEWORKS

I.F PLUMBING WORKS 144 m 13,787.16 95.74

I.G CERAMIC/GRANITE TILES 13.5 sq.m. 17,408.79 1,289.54

I.H MASONRY WORKS 10.8 sq.m. 36,385.53 3,369.03

I.I WATER SYSTEM 1 unit 4,355.40 4,355.40

TOTAL COST ₱200,000.00

LOT NO. Description Location

II School Library Program Improvement PARASAN, POBLACION 1, RIZAL

Unit Quantity Cost Unit Cost


II.A CARPENTRY & JOINERY WORKS 104 bd.ft. 50,000.00 480.77
II.A CARPENTRY & JOINERY WORKS 104 bd.ft. 50,000.00 480.77

II.B CABINETRY AND WOODWORKS 34.56 sq.m. 85,755.28 2,481.34

PAINTING, VARNISHING AND


II.C 34.56 sq.m. 14,244.72 412.17
OTHER RELATED WORKS
TOTAL COST ₱150,000.00

LOT NO. Description Location

SBM Hub Improvement and Other Needs in


III Baclayan, Poblacion 1
Preparation for Division Evaluation

Unit Quantity Cost Unit Cost


III.A CARPENTRY & JOINERY WORKS 136 bd.ft. 30,628.71 225.21

III.B CABINETRY AND WOODWORKS 17.28 sq.m. 42,877.64 2,481.34

PAINTING, VARNISHING AND


III.C 59.08 sq.m. 13,734.89 232.48
OTHER RELATED WORKS

III.D METAL ROOFING 41.8 sq.m. 12,758.76 305.23

TOTAL COST ₱100,000.00

LOT NO. Description Location

District Office Improvement or Repair for the


IV Poblaccion 1
Division PAGDUAWA Program Implementation

Unit Quantity Cost Unit Cost


IV.I CARPENTRY & JOINERY WORKS 160 bd.ft. 89,253.68 557.84

IV.B JALOUSIE WINDOWS 112 bd.ft. 67,828.95 605.62

PAINTING, VARNISHING AND


IV.C 94.8 sq.m. 24,096.12 254.18
OTHER RELATED WORKS
TOTAL COST ₱181,178.75

Prepared by: Recommending Approval:

ENGR. MARK JOSEPH B. CABANGANAN ENGR. GERARDO P. MUSTACISA


Engineer I MPDC/
Enineering
M.E. Staff
(Designate)

Approved:

PHILIP MARTIN L. ASTORGA


Municipal Mayor