BOQ For FOB span 42m

Total length = 50 m
Span = 42 m
Width of FOB = 3 m
Width of ramp/staircase = 2 m
Centre to centre spacing between girders = 2.75 m
Height of FOB = 6 m
Length of ramp = 71.25 m

Total length
2 3
Main span No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISWB 600(H) 2 50 100 185 1.850 14.52
ISMB 200 26 2.75 71.5 30.8 0.220 1.73
ISMB 400 7 2.75 19.25 78.5 0.151 1.19
PIPE 100 (M) NB 38 2.9 110.2 15.5 0.171 1.34
PIPE 100 (M) NB 2 50 100 15.5 0.155 1.22
PIPE 80 (M) NB 19 3.03 57.50 10.7 0.062 0.48
TUBE 50x50x5 4 50 200 9 0.180 1.41
PIPE 350x10 14 6 84 106.8 0.897 7.04
PIPE 150 (M) NB 8 3 24 22.3 0.054 0.42
PIPE 150 (M) NB 8 2 16 22.3 0.036 0.28
ISMB 450 8 3 24 92.3 0.222 1.74
ISMB 450 8 2 16 92.3 0.148 1.16
Bracings 75x75x10 64 3.35 214.66 14 0.301 2.36

Thk (m)
Base plate C1 24 0.04 2500 0.240 1.884
Base plate C2 4 0.04 2500 0.040 0.314

Total length
2 3
Ramp No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISMB 300 4 71.25 285 58.7 1.673 13.13
PIPE 200(M) 36 3.25 117 37.6 0.440 3.45
ISMB 150 88 2 176 19.1 0.336 2.64
PIPE 100 (M) NB 20 2 40 15.5 0.062 0.49
PIPE 100 (M) NB 108 2.9 313.2 15.5 0.485 3.81
PIPE 100 (M) NB 4 71.25 285 15.5 0.442 3.47
PIPE 80 (M) NB 54 2.04 110.14 10.7 0.118 0.93
TUBE 50x50x5 8 70.5 564 9 0.508 3.98

Thk (m)
Chequered plate 6mm 2 0.006 1425000 1.710 13.42
Base plate C4 72 0.03 2500 0.540 4.24

Total length
2 3
Stairs No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISMB 450 12 5 60 92.3 0.554 4.35
ISMB 450 14 2 28 92.3 0.258 2.03
PIPE 200(M) NB 8 5 40 37.6 0.150 1.18
PIPE 150(M) NB 8 2 16 22.3 0.036 0.28
PIPE 150(M) NB 4 4 16 22.3 0.036 0.28
PIPE 100 (M) NB 8 2.9 23.2 15.5 0.036 0.28
PIPE 100 (M) NB 4 5 20 15.5 0.031 0.24
PIPE 80 (M) NB 4 4.00 16 10.7 0.017 0.13
TUBE 50x50x5 8 5.00 40 9 0.036 0.28
Bracings 75x75x10 8 2.83 22.63 14 0.032 0.25
ISA 50x50x6 180 0.34 60.37 4.79 0.029 0.23
ISA 50x50x6 90 2.0 180.0 4.79 0.086 0.68

Thk (m)
Chequered plate 6mm 6 0.006 100000 0.360 2.83
2 0.006 80000 0.096 0.75
2 0.006 120000 0.144 1.13
Base plate C3 16 0.02 2500 0.080 0.63
Total length
2 3
Railing No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
Main span 2 50 100 20.92 0.209 1.64
Ramp 4 71.25 285 20.92 0.596 4.68
Stairs 2 48 96 20.92 0.201 1.58

Weight of structural steel = 110.102 tonnes


Weight of connection say 20 %
Total Weight of structural steel = 132.12 tonnes

Concrete (Quantity)
Reinforcement Reinforcement
Components 3
No. L B H Volume (m ) (kg/cum) (in tons)
Deck slab 120mm thk 1 50 3 0.12 18 100 1.8
Pedestal
Main span 14 0.7 0.7 2.1 14.41 210 3.025
Stairs 8 0.7 0.7 2.1 8.23 210 1.729
Ramp 36 0.7 0.7 2.1 37.04 210 7.779
Footing
Main span (for C1) 2 6 5 0.4 24 130 3.120
Main span (for C2) 1 2 5 0.4 4 130 0.520
Stairs 4 2 4 0.4 12.8 130 1.664
Ramp 36 1.5 1.5 0.4 32.4 150 4.860

3
Volume of concrete = 150.9 m
Reinforcement (HYSD Fe 500) = 24.5 tonnes
BOQ For FOB span 50m

Total length = 58 m
Span = 50 m
Width of FOB = 3 m
Width of ramp/staircase = 2 m
Centre to centre spacing between girders = 2.72 m
Height of FOB = 6 m
Length of ramp = 71.25 m

Total length
2 3
Main span No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISMB 750 2 58 116 252 2.923 22.95
ISMB 300 32 2.72 87.04 58.7 0.511 4.01
ISMB 450 7 2.72 19.04 92.3 0.176 1.38
PIPE 100 (M) NB 44 2.9 127.6 15.5 0.198 1.55
PIPE 100 (M) NB 2 58 116 15.5 0.180 1.41
PIPE 80 (M) NB 22 3.03 66.58 10.7 0.071 0.56
TUBE 50x50x5 4 58 232 9 0.209 1.64
PIPE 350x10 14 6 84 146.3 1.229 9.65
PIPE 150 (M) NB 8 3 24 22.3 0.054 0.42
PIPE 150 (M) NB 8 2 16 22.3 0.036 0.28
ISMB 450 8 3 24 92.3 0.222 1.74
ISMB 450 8 2 16 92.3 0.148 1.16
Bracings 75x75x10 76 3.35 254.91 14 0.357 2.80

Thk (m)
Base plate C1 24 0.05 2500 0.300 2.355
Base plate C2 4 0.05 2500 0.050 0.393

Total length
2 3
Ramp No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISMB 300 4 71.25 285 58.7 1.673 13.13
PIPE 200(M) 36 3.25 117 37.6 0.440 3.45
ISMB 150 88 2 176 19.1 0.336 2.64
PIPE 100 (M) NB 20 2 40 15.5 0.062 0.49
PIPE 100 (M) NB 108 2.9 313.2 15.5 0.485 3.81
PIPE 100 (M) NB 4 71.25 285 15.5 0.442 3.47
PIPE 80 (M) NB 54 2.04 110.14 10.7 0.118 0.93
TUBE 50x50x5 8 70.5 564 9 0.508 3.98

Thk (m)
Chequered plate 6mm 2 0.006 1425000 1.710 13.42
Base plate C4 72 0.03 2500 0.540 4.24

Total length
2 3
Stairs No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
ISMB 450 12 5 60 92.3 0.554 4.35
ISMB 450 14 2 28 92.3 0.258 2.03
PIPE 200(M) NB 8 5 40 37.6 0.150 1.18
PIPE 150(M) NB 8 2 16 22.3 0.036 0.28
PIPE 150(M) NB 4 4 16 22.3 0.036 0.28
PIPE 100 (M) NB 8 2.9 23.2 15.5 0.036 0.28
PIPE 100 (M) NB 4 5 20 15.5 0.031 0.24
PIPE 80 (M) NB 4 4.00 16 10.7 0.017 0.13
TUBE 50x50x5 8 5.00 40 9 0.036 0.28
Bracings 75x75x10 8 2.83 22.63 14 0.032 0.25
ISA 50x50x6 180 0.34 60.37 4.79 0.029 0.23
ISA 50x50x6 90 2.0 180.0 4.79 0.086 0.68

Thk (m)
Chequered plate 6mm 6 0.006 100000 0.360 2.83
2 0.006 80000 0.096 0.75
2 0.006 120000 0.144 1.13
Base plate C3 16 0.02 2500 0.080 0.63
Total length
2 3
Railing No. Length (m) (m) Area (cm ) Volume(m ) Wt (tons)
Main span 2 58 116 20.92 0.243 1.90
Ramp 4 71.25 285 20.92 0.596 4.68
Stairs 2 48 96 20.92 0.201 1.58

Weight of structural steel = 125.567 tonnes


Weight of connection say 20 %
Total Weight of structural steel = 150.68 tonnes

Concrete (Quantity)
Reinforcement Reinforcement
Components 3
No. L B H Volume (m ) (kg/cum) (in tons)
Deck slab 120mm thk 1 58 3 0.12 20.88 100 2.088
Pedestal
Main span 14 0.7 0.7 2 13.72 210 2.881
Stairs 8 0.7 0.7 2 7.84 210 1.646
Ramp 36 0.7 0.7 2 35.28 210 7.409
Footing
Main span (for C1) 2 6 5 0.5 30 170 5.100
Main span (for C2) 1 2 5 0.5 5 170 0.850
Stairs 4 2 4 0.5 16 170 2.720
Ramp 36 1.5 1.5 0.5 40.5 200 8.100

3
Volume of concrete = 169.22 m
Reinforcement (HYSD Fe 500) = 30.8 tonnes