Professional Documents
Culture Documents
CII 280 - 3 Whats The Risk
CII 280 - 3 Whats The Risk
Probability
Poor soil conditions may Cost
Probability
furnished to CII. D L M M H H 0.08
Available to non-members by purchase; however, no require deep foundations,
copies may be made or distributed and no modifications C L L M M H 0.06
may be made without prior written permission from CII. resulting in cost increase.
Contact CII at http://construction-institute.org/catalog.
htm to purchase copies. Volume discounts may be B L L L M M 0.04
available.
Utility relocation delay could Schedule
0.02
All CII members, current students, and faculty at a
college or university are eligible to purchase CII products result in longer schedule. A L L L L M
at member prices. Faculty and students at a college or 0.00
university may reproduce and distribute this work without a b c d e 640 650 660 670 680 690 700 710 720
modification for educational use.
Printed in the United States of America.
Impact Distribution for Cost to Completion ($ million)
Interpreting Probabilistic Outputs
What is the range of cost or schedule? What risks have the greatest impact, and
Cost/Time Probability Mass Function where should I focus mitigation efforts?
Sensitivity Analysis
Distribution for Total Project Costs Distribution for Project Schedule
(Current $million) (Year) Tornado Diagram
0.025
Mean = 3.6 Years
0.025 Mean = $22.5
Unmitigated Mean Severity
80% Confidence
0.020 0.020 = 3.8 Years Risk Event 0.00 .1 0.20 .3 0.40 .5 0.60 .7
Probability
Probability
What it means: Illustrates a range of project cost from $15–30 million, with a mean cost What it means: Illustrates that the risk events “Historic site” and “Replaced culvert over
of $22.5 million. Illustrates a range of project schedule from 2.7–4.2 years, with a mean Wandering Creek” have the greatest impact on cost uncertainty. Mitigation efforts should
duration of 3.6 years. focus on these two risk events.
approval
0.80 0.80
3
Mean = $22.5 Mean = 3.6 Years RFP delay
0.60 0.60 resolved
0.40
2
0.40
What it means: Illustrates that the project’s cost and schedule will not exceed $26 million What it means: Illustrates that the “Historic site” risk event will be resolved after
or 3.8 years (at an 80-percent confidence level). approximately one year, at which time its contingency can be released.