Table of Milestones:

Sl.No Description of Milestone (Physical) Time % age amount to be


allowed in with-held in case of
Months non-achievement of
(from milestone
date of
start)
1 Appointment of Architectural consultant, design
consultant and services consultants, Appointment of 1.5 0.07
GRIHA Consultant.
2 Preparation of all architectural working drawings,
LOP, landscape drawings, structural drawings and
services drawings of all components along-with Level-
4 BIM model including obtaining all approval of all
local bodies/ statutory bodies, all other concerned
authorities as may be applicable for the work, all
complete as per direction of engineer-in-charge to start 4 0.33
the construction activities.
Setting up of site office, site testing lab, batching plant,
approval of design mix, initial setting out, required
barricading, pollution control program, work program
with material and resource scheduling in MS project/
primavera, steel yard, cement go-down.
3 i. All Building except Hospital Building:
Completion of RCC work of foundation up to plinth
8 0.17
level.
ii. Completion of Boundary wall
4 Hospital Building:
Completion of RCC work of foundation up to plinth 8 0.30
level
5 Misc. Non-Residential Building except Hospital
Building:
Completion of RCC work in Superstructure & all 10 0.18
masonry work for all floors including conduiting work
6 Hospital Building & other Non-Residential
10 0.10
Buildings:

AE & M (C) /UKP AE & M (E)/UKP EE & SM (C)-1/UKP EE & SM(E)/ UKP Page-74
Placing supply order for E&M equipments like
substation, DG Set, HVAC plant, CSSD equipments,
Laundry equipments, Kitchen equipments, MGPS
equipments, STP equipments, Firefighting & Fire
alarm equipment, CCTV, drinking water pump related
equipments, Pneumatic tube transport system
equipment, Automated Laundry & waste management
System equipment, Nurse call system equipment,
Lifts, Modular OT equipment, Solar water heating
equipment, IBMS equipment, LAN & EPABX
equipments, Audio-Visual equipment & other misc.
Medical and E&M equipment.
7 Sample Quarters/ Suites:
Completion of 01 No. sample quarter for Type-4 and
completion of 01 No. sample room/ suites (including 10 0.01
toilet & kitchen) for SR Hostel & Nurses Hostel
Building including all E&M related works, fittings &
fixtures.
8 All Residential Buildings:
Completion of RCC work in Superstructure & all
masonry work for all floors including conduiting work
& placing supply order for E&M equipments like 15 0.15
rising mains, LT panels, firefighting and fire alarm
system equipments & VRF equipments, lifts etc.
9 Hospital Building:
Completion of Pre-fabricated Composite Steel 15 1.50
Structure work in Superstructure.
10 Hospital Building:
Completion of masonary work including conduiting 17 0.15
work for all floors.
11 Misc. Non-Residential Buildings except Hospital
Building:
Completion of plastering, flooring, doors, windows,
false ceiling, finishing works, internal water supply,
sanitary & sewerage etc. in all respect including wiring
work, installation of all equipments related to
substation building, HVAC plant, CSSD equipments, 20 0.16
Laundry equipments, Kitchen equipments, MGPS
equipments, STP equipments, Firefighting and
drinking water pump house related equipments
including all other misc. internal & external works
pertaining to buildings as mentioned in this NIT to
make the buildings functional in all respect.
12 All Residential Buildings: 20 0.18

AE & M (C) /UKP AE & M (E)/UKP EE & SM (C)-1/UKP EE & SM(E)/ UKP Page-75
Completion of plastering, flooring, doors, windows,
false ceiling, finishing works, internal water supply,
sanitary & sewerage etc., including wiring, installation
of Residential Furniture, Electrical fitting & fixtures
including all other misc. internal & external works
pertaining to buildings as mentioned in this NIT to
make the buildings functional in all respect.
13 Hospital Building:
Completion of plastering, flooring, doors, windows,
false ceiling, finishing works, etc. including all internal
& external works, installation of all Hospital Furniture,
E&M related works, fittings & fixtures, wire, cables,
rising mains work, panels works and other fixtures,
medical equipment, firefighting, fire alarm, lifts, VRF 21 1.30
and AHU related works including supply and return
water line, ducting works, cooling tower works, Solar
water heating system work and all other works
complete etc. including all other misc. internal &
external works pertaining to buildings as mentioned in
this NIT to make the building functional in all respect.
14 All external development works pertaining to Civil,
Electrical & Mechanical and Horticulture complete in
all respect with testing and commissioning of services,
clearances from local body/ completion certificates 22 0.40
etc. required to declare buildings and campus
authorized for occupation.

NOTE:

Withheld amount shall be released if subsequent milestone is achieved within respective time
specified. However, in case milestones are not achieved by the Bidder for the work, the amount shown
against milestone shall be withheld.

Intending bidder may submit phasing of activities/ milestones based on their resources and
methodology at the time of bidding corresponding to physical milestones/stages indicated in the above
table. These shall be formed part of the agreement after approval of the accepting authority,
otherwise it would be assumed that agency agrees with the above-mentioned physical milestones.

Authority to decide:

(i) Extension of time : Superintending Engineer cum Project Director, Uttarakhand


Projects CPWD, Rishikesh or his successor thereof.

(ii) Rescheduling of components : Superintending Engineer cum Project Director, Uttarakhand


Projects, CPWD, Rishikesh or his successor thereof

AE & M (C) /UKP AE & M (E)/UKP EE & SM (C)-1/UKP EE & SM(E)/ UKP Page-76