You are on page 1of 1

LIFTING PLAN Date : ……………………

Project No : 425841
Permit No : ……………….......
Crane ID No :………………………
S.NO Description Unit Value
1 Weight of the lifting load (Load) ton
2 Lifting Beam ton
m
3 Hook blocks weight ton
4 Lifting Gears & Appliances ton
Total weight ton

S.NO Description Unit Value


1 Total weight as per above * ton
2 Main boom length m
SWL
3 Radius m
4 Safe working Load of crane ton
5 Safety Factor*
m 6 Utilization Rate* %
* % of chart capacity used = Weight of the lifted load/Net crane capacity. It shouldbe less
than 75%.
Verified & Checked by: Lifting Supervisor (Name/Sign). Site Supervisor (Name/Sign)

GGME/CX-393/LPF/01 Lifting Plan