BULLDOZER D 85 SS

PRODUCTIVITY LAND CLEARING


PRODUCTIVITY
❑ Untuk menghitung productivity bulldozer 85 aktivitas land clearing

Q = N x 60 x e x E x 1000 N= W
CM LB - LO
Dimana : Dimana :
Q = Productivity per jam (m²/jam) N = Jumlah trip
N = Jumlah trip W = Total lebar kerja area (meter)
CM = Cycle time (menit) LB = Lebar balde D85 (meter)
e = Grade factor LO = Lebar overlap blade (meter)
E = Job efficiency
PRODUCTIVITY
• Spesifikasi DZ 85 SS

• Lebar blade (LB) & Lebar overlap blade (LO)


1. Lebar blade (LB) DZ 85 SS = 3,725 mm / 3,7 meter
2. Lebar overlap blade (LO)
0% = 0 mm
25 % = 0,93 mm
50 % = 1,8625 mm
75 % = 2,793 mm
100 % = 3,725 mm
PRODUCTIVITY
• Cycle time (CM) • Job efficiency (E)

• Grade factor (e)