PEKERJAAN JALAN BETON

PEKERJAAN PERBAIKAN JALAN INDESSO CILEUNGSI - BOGOR

NO PEKERJAAN TITIK
VOLUME SATUAN
LOKASI

1 Mob Demob AREA ICI 1 Ls


2 Galian tanah, sedalam 20 cm + buang ke luar lokasi AREA ICI 51.19 M3
3 Perbaikan tanah dasar + Pemadatan, tebal 200 cm AREA ICI 2.57 M3
4 Plastik Cor beton AREA ICI 255.97 m2
5 Begesteng AREA ICI 20.78 m2
6 Pembesian wiremesh M.8 + dowel AREA ICI 255.97 m2
7 Pekerjaan Beton, K.350 AREA ICI 51.19 m3

JUMLAH TOTAL
DI BULATKAN
Terbilang :

NOTE Wire mesh M.8 11.34


Dowel besi D.22
HARGA SATUAN JUMLAH
( Rp ) ( Rp )

IDR 7,500,000 IDR 7,500,000


IDR 400,000 IDR 20,477,840
IDR 1,500,000 IDR 3,852,000
IDR 20,000 IDR 5,119,460
IDR 150,000 IDR 3,117,150
IDR 125,000 IDR 31,996,625
IDR 1,500,000 IDR 76,791,900

IDR 148,854,975
IDR 148,800,000
AREA ICI PEKERJAAN BETON

N VOLUME P L VOL SAT


N = = 255.97 M2
area.1 = 12.95 x 13.20 = 170.97
area.2 = 10.00 x 6.30 = 63.00
area.3 = 5.50 x 4.00 = 22.00
Perbaikan tanah dasar = 12.84
AREA.3
area.1 = 2.40 x 3.10 = 7.44 m2
area.2 = 0.80 x 3.00 = 2.40 m2
area.3 1.2 x 2.5 = 3.00 m2

VOLUME TOTAL beton = 255.97 M2


volume perbaikan tanah dasar = 12.84 M2

AREA.2 AREA.1