Volume Pekerjaan

Pembangunan Rumah Type 36

No. Uraian Pekerjaan Volume Satuan Ket.


1. PEKERJAAN PERSIAPAN
1.1 Pembersihan Lahan 66 m2
Luas = Panjang x Lebar
= 6 m x 11 m
= 66 m2

1.2 Pemasangan Bowplank


Luas = Panjang x Lebar 26,5 m
7,25 m + 7,25 m + 6 m +
= 6m
= 26,5 m

2. PEKERJAAN STRUKTUR
Horizontal = 21 m
vertikal = 29.25 m
Volume = 50.25 m3

1.1 Pekerjaan Pondasi


2.1.1 Pekerjaan galian tanah 32.6625 m3
panjang urugan pasir &
aanstamping = 50.25 m
lebar = 0.8 m
tinggi = 0.25 m
volume galian aanstamping = pxlxt
= 50.25m x 8.0m x 0.25m

= 10.05 m3
= 0.45 m2
Luas penampang pondasi
panjang galian pondasi = 50.25 m
volume = L penampang x p galian
= 0.45m2 x 50.25m
= 22.6125 m3

volume total galian pondasi = V galian + V Pondasi


= 10.05m3 + 22.6125m3
= 32.6625 m3

1.1.2 Urugan Pasir 2.01 m3


Panjang = 50.25 m
lebar = 0.8 m
tinggi = 0.05 m
volume = pxlxt
= 50.25m x 0.8m x 0.05m
= 2.01 m3

1.1.3 Aanstamping 8.04 m3


panjang = 50.25 m
lebar = 0.8 m
tinggi = 0.2 m
volume = pxlxt
= 50.25m x 0.8m x 0.2m
= 8.04 m3

1.1.4 Pemasangan batu kali 22.6125 m3


luas permukaan = 0.45 m2
panjang = 50.25 m
volume = L Permukaan x P
= 0.45m2 x 50.25m
= 22.6125 m3
1.2 Pekerjaan Beton bertulang
2.2.1 Pekerjaan sloff 15/20 1.5075 m3
panjang = 50.25 m
lebar = 0.15 m
tinggi = 0.2 m
volume = pxlxt
= 50.25m x 0.15m x 0.2m
= 1.5075 m3

Volume Bekesting
2 x p sloff = 2 x 50.25m
= 100.5 m

volume besi diameter 8


4 x panjang sloof = 4 x 50.25m
= 201 m
volume besi sengkang diameter 6
jumlah sengkang = 336 buah
volume sengkang = 218.4 m3

1.2.2 Pekerjaan kolom 15/15 1.0998 m3


jumlah kolom = 13 buah
tinggi kolom = 3.76 m
total tinggi seluruh kolom = jumlah x tinggi kolom
= 13 buah x 3.76m
= 48.88 m

panjang = 0.15 m
lebar = 0.15 m
volume kolom = pxlxt
= 0.15m x 0.15m x 48.88m
= 1.0998 m3
volume bekesting = 195.52 m3

volume tulangan kolom


panjang besi diameter 8 = 195.52 m

volume sengkang
jumlah sengkang = 326.8667 buah
panjang sengkang = 0.45 m
volume besi sengkang = jumlah x p sengkang
= 326.8667 buah x 0.45m

= 147.09 m3

1.2.3 Pekerjaan ring balk 15/15 0.945 m3


panjang = 42 m
lebar = 0.15 m
tinggi = 0.15 m
volume ring balok = pxlxt
= 42m x 0.15m x 0.15m
= 0.945 m3
Volume Bekisting = 84 m3

2. PEKERJAAN DINDING
2.1 Pekerjaan Dinding
luas dinding 132.7075 m2
panjang = 39.5 m
tinggi = 3.75 m
Luas = pxt
= 39.5m x 3.75m
= 148.125 m2
Luas Pintu utama + kusen
Kusen Pintu:
panjang = 1 m
lebar = 2.1 m
Luas kusen pintu = pxl
= 1m x 2.1m
= 2.1 m2

panjang = 1.95 m
lebar = 1.75 m
Maka, Luas kusen jendela = pxl
utama = 1.95m x 1.75m
= 3.4125 m2
luas kusen pintu (P1) 2 unit
panjang = 0.9 m
lebar = 2.1 m
Maka, Luas kusen pintu (P1) = 2xpxl
= 2 x 0.9m x 2.1m
= 3.78 m2
Kusen pintu geser (P2)
panjang = 1 m
lebar = 2.1 m
Luas kusen pintu geser = pxl
= 1m x 2.1m
= 2.1 m2
kusen pintu + daun pintu P3
panjang = 0.8 m
lebar = 2.1 m
= Pxl
volume = 0.8m x 2.1m m2
volume = 1.68 m2
jendela + kusen J1 (2 unit)
panjang = 0.67 m
lebar = 1.75 m
Maka, luasnya = 2xpxl
= 2 x 0.67m x 1.75m
= 2.345 m2
2.2 Pekerjaan plesteran
3.2.1 Plesteran 1:2 483.955 m2
2
Luas dinding total = 265.415 m
Luas dinding toilet = 23.4375 m2
panjang = 6.25 m
tinggi = 3.75 m

2.2.2 Plesteran Dinding 1:2 23.4375 m2


luas dinding = pxl
= 6.25m x 3.75m
luas dinding = 23.4375 m2

4 PEKERJAAN PINTU DAN JENDELA 2,9 m2

Luas Pintu Utama + Kusen


Kusen Pintu :
Panjang = 4,5 m
Lebar = 0,1 m
Volume Kusen Pintu = Pxl
= 4,5m x 0,1m
= 0,45 m2
Kusen Jendela :
Panjang = 4,5 m
lebar = 0,1 m
Volume kusen jendela = Pxl
= 4,5m x 0,1m
= 0,45 m2

Luas kusen pintu (P1) 2 Unit :


panjang = 4,5 m
lebar = 0,1 m
Volume = 2 x (p x l)
= 2 (4,5m x 0,1m)
= 0,9 m2

Kusen Pintu Geser (P2)


Panjang = 4,5 m
lebar = 0,1 m
Volume = pxl
= 4,5m x 0,1m
= 0,45 m2

Kusen pintu + daun pintu (P3) :


panjang = 4,5 m
lebar = 0,1 m
volume = pxl
= 4,5m x 0,1m
= 0,45 m2

Jendela + kusen J1 (2 Unit) :


panjang = 1 m
lebar = 0,1 m
Volume = 2 x (p x l)
= 2 x (1m x 0,1m)
= 0,2 m2
5 PEKERJAAN RANGKA ATAP

5.1 Pemasangan Kuda-Kuda Kayu 0,75 mm 0,4966 m3


Panjang = 27,5922 m
lebar = 0,12 m
tinggi = 0,075 m
jumlah = 2 buah
Volume = n x (p x l x t)
= 2 x (27,5922m x 0,12m x
0,075m)
= 0,4966 m3

5.2 Pemasangan Gording 0,7177 m3


Panjang = 7,25 m
lebar = 0,12 m
tinggi = 0,075 m
jumlah = 11 buah
Volume = n x (p x l x t)
= 11 x (7,25m x 0,12m x
0,075m)
= 0,7177 m3

5.3 Pekerjaan Rangka Atap Genteng 87 m2


Panjang = 7,25 m
lebar = 6 m
jumlah = 2 unit
volume = n x (p x l)
= 2 x (7,25m x 6m)
= 87 m2

5.4 Pekerjaan Pemasangan Lisplank 14,5 m2


panjang = 7,25 m
lebar = 2 m
volume = pxl
= 7,25m x 2m
= 14,5 m2

5.5 Pekerjaan Pemasangan Atap 80 m2


Panjang = 8 m
lebar = 5 m
jumlah = 2 buah
volume = n x (p x l)
= 2 x (8m x 5m)
= 80 m2