Kos Bahan
RM 159.00
Kos Buruh
= 4 jam/ m 3 = RM 8.00
= 2 jam/ m 3 = RM 4.00
RM 56.92
Keluasan tembok :
3369 mm
1275 mm
= 4.26 m
= RM 56.92 x 4.26 m
= RM 242.48
2. Kos Kerja Bata
3369 mm
1275 mm
Panjang Tebal
225 mm 75 mm
= 16875 mm 2
Kos Bahan
Bata
254 biji x RM 0.18 = RM 45.72
Mortar
1 kampit x RM 16.00 = RM 16.00
1
Tukang bata - 1 jam x RM 4.00 = RM 6.00
2
Buruh biasa - 2 jam x RM 2.75 = RM 5.50