Steel Estimate

Wall
Level 1
Perimeter Wall 32 sq. m
Bed Room 1 Partition Wall 8 sq. m
T&B Partition Wall 3.5 sq. m
Total Wall sq.m 43.5 sq. m

Area 130.5 sq. m


Vertical Reinforcement 208.8 m. long
Horizontal Reinforcement 280.575 m. long
Total Reinforcemnts 489.375 m. long

Total order of Steel Bars for Level 1 81.5625


order 82 pcs. @ 10mm Ø bar x 6.00 m. long

Level 2
Perimeter Wall 31 sq. m
Bed Room 2 Partition Wall 6.5 sq. m
T&B Partition Wall 5.7 sq. m
Total Wall sq.m 43.2 sq. m

Area 129.6 sq. m


Vertical Reinforcement 207.36 m. long
Horizontal Reinforcement 278.64 m. long
Total Reinforcements 486 m. long

Total order of Steel Bars for Level 2 81


order 81 pcs. @ 10mm Ø bar x 6.00 m. long

King Post Truss


Perimeter Wall 17.5 sq. m

Area 35 sq. m
Vertical Reinforcement 56 m. long
Horizontal Reinforcement 75.25 m. long
Total Reinforcement 131.25 m. long

Total order of Steel Bars for King Post Truss 21.875


order 22 pcs. @ 10mm Ø bar x 6.00 m. long

Total order of Steel Bars for Wall 184.4375


order 185 pcs. @ 10mm Ø bar x 6.00 m. long
6.00 m. long

6.00 m. long

6.00 m. long

x 6.00 m. long
Formworks
Column Level 1 and 2
Lateral Perimeter 1.4 m
Total Lateral Surface Area 61.6 sq.m
No. of Plywood (pcs.) 21.38889
order 22 pcs. 1/4 in. x 4 x 8 plywood

Wood Frame (2x2) 652.74 bd. ft. 2x2x14 ft.


Wood Frame (2x3) 979 bd. ft. 2x3x14 ft.

Total Order of Wood Frame


2x2 139.773
order 140 pcs. 2 x 2 x 14ft. Wood frame
2x3 139.8571
order 140 pcs. 2 x 3 x 14ft. Wood frame
ITEM NO. DESCRIPTION
ITEMS OF WORK
VII.
7.1 Wall
7.1 .1 Installation of Re-bars for CHB Wall Ground Floor
10 mm Ø bars
7.1.2 Installation of Re-bars for CHB Wall Second Floor
10 mm Ø bars
7.1.3 Installation of Re-bars CHB Wall for King Post
10 mm Ø bars
7.2 Footing
7.2.1 Fabrication Installation for Column Footings
16 mm Ø bars
12 mm Ø bars
7.2.2 Fabrication Installation of Wall Footings
10 mm Ø bars
7.3 Beam
7.3.1 Fabrication of Tie Beams
16 mm Ø bars
10 mm Ø bars
7.3.2 Fabrication of RC Beams
16 mm Ø bars
10 mm Ø bars
7.3.3 Installation of Tie Beams
7.3.4 Installation of RC Beam
7.4 Column
7.4.1 Fabrication of Column for Ground Floor
16 mm Ø bars
Lateral Ties (10 mm x 6m bars)
7.4.2 Fabrication of Column for Second Floor
16 mm Ø bars
12 mm Ø bars
Lateral Ties (10 mm x 6m bars)
7.4.3 Installation of Column for Ground Floor
7.4.4 Installation of Column for Second Floor
7.5 Slab
7.5.1 Installation of Slabs for Ground Floor
10 mm Ø bars
7.5.2 Installation of Slabs for Second Floor
10 mm Ø bars
7.5.3 Installationof Slabs for Balcony
10 mm Ø bars
7.6 Septic Tank
7.6.1 Fabrication of Walls for Septic Tank
10 mm Ø bars
7.6.2 Fabrication of Concrete Slab for Septic Tank
10 mm Ø bars
7.6.3 Installation of Septic Tank
7.7 Catch Basin
7.7.1 Fabrication of Walls for Catch Basin
10 mm Ø bars
7.7.2 Fabrication of Concrete Slab for Catch Basin
10 mm Ø bars
7.7.2 Installation of Catch Basin
7.8 Main Stairs
7.8.1 Fabrication of Main Stairs
16 mm Ø bars
12 mm Ø bars
10 mm Ø bars
X. ELECTRICAL WORKS
10.1 Light Fixtures
10.1.1 Circular Flourscent Lgith (13)
10.1.1.1 Installation of CFL for Ground Floor
10.1.1.2 Installation of CFL for Second Floor
10.1.2 Pin Light (11)
10.1.2.1 Installation of Pin Light for Ground Floor
10.1.2.2 Installation of Pin Light for Second Floor
10.1.3 Lighting Switch (8)
10.1.3.1 Installation of Lighting Switch for Ground Floor
10.1.3.2 Installation of Lighting Switch for Second Floor
10.2 Power Socket
10.2.1 Duplex Convenience Outlet (10)
10.2.1.1 Installation of DCO for Ground floor
10.2.1.2 Installation of DCO for Second floor
10.2.2 Weather Proof Convenience Outlet (2)
10.2.2.1 Installation of Weather PCO for Second Floor
10.2.3 Air Conditioning Unit Outlet (3)
10.2.3.1 Installation of ACU Outlet for Ground Floor
10.2.3.2 Installation of ACU Outlet for Second Floor
10.2.4 Range Outlet (1)
10.2.4.1 Installation of Range Outlet for Ground Floor
10.2.5 Refrigerator Outlet (1)
10.2.5.1 Installation Refrigerator Outlet for Ground Floor
10.2.6 Telephone Outlet (1)
10.2.6.1 Installation of Telephone Outlet
10.3 Panel Board
10.3.1 Installation of Panel Board
MANPOWER
QTY. UNIT PRODUCTION RATE (HR/UNIT)
Skilled

82 pc. 0.3 2

81 pc. 0.3 2

22 pc. 0.3 2

pc. 0.1 1
pc. 0.1 1

pc. 0.1 1

pc. 0.075 1
pc. 0.075 1

pc. 0.075 1
pc. 0.075 1
0.3 1
0.5 1

pc. 0.2 1
s) pc. 0.2 1

pc. 0.2 1
pc. 0.2 1
s) pc. 0.2 1
0.3 1
0.3 1

114 pc. 0.4 2

126 pc. 0.4 2

18 pc. 0.3 2
pc. 0.5 1

pc. 0.5 1
0.2 1

pc. 0.1 1

pc. 0.1 1
0.2 1

pc. 0.5 1
pc. 0.5 1
pc. 0.5 1

1 lot 0.4 1
1 lot 0.4 1

r 1 lot 0.2 1
1 lot 0.2 1

d Floor 1 lot 0.1 1


d Floor 1 lot 0.1 1

1 lot 0.2 1
1 lot 0.2 1

Floor 1 lot 0.2 1

oor 1 lot 0.2 1


oor 1 lot 0.2 1

Floor 1 lot 0.2 1

nd Floor 1 lot 0.2 1

1 lot 0.2 1
1 lot 0.4 1
MANPOWER LABOR RATE (per hour) DURATION (hours)
Labor Cost
Unskilled Skilled Unskilled Computed Rounded

₱13,500.00
₱5,400.00
4 ₱87.50 ₱68.75 4.1000 5 ₱2,250.00

4 ₱87.50 ₱68.75 4.0500 5 ₱2,250.00

4 ₱87.50 ₱68.75 1.1000 2 ₱900.00

₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
₱8,100.00

4 ₱87.50 ₱68.75 7.6000 8 ₱3,600.00

4 ₱87.50 ₱68.75 8.4000 9 ₱4,050.00

4 ₱87.50 ₱68.75 0.9000 1 ₱450.00


₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
₱0.00

2 ₱87.50 ₱68.75 0.0000 0 ₱0.00


2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
2 ₱87.50 ₱68.75 0.0000 0 ₱0.00
₱25,100.00
₱12,800.00

1 0.2000 1 ₱2,400.00
1 0.2000 1 ₱2,800.00

1 0.1000 1 ₱3,600.00
1 0.1000 1 ₱800.00

1 0.0500 1 ₱1,600.00
1 0.0500 1 ₱1,600.00
₱7,200.00

1 0.1000 1 ₱2,000.00
1 0.1000 1 ₱2,000.00

1 0.1000 1 ₱800.00

1 0.1000 1 ₱400.00
1 0.1000 1 ₱800.00

1 0.1000 1 ₱400.00

1 0.1000 1 ₱400.00

1 0.1000 1 ₱400.00
₱5,100.00
1 0.2000 1 ₱5,100.00