CHB INSTALLATION REQUEST

PROJECT: NARA RESIDENCES BY ROCKWELL PH1 DATE PREPARED : WP NO. & SCOPE: PERMIT NO. :
LOCATION: GM Cordova Ave., Buri Road, Bacolod City

REQUESTED BY :

(Contractor) (Name/Designation) (Signature)


WORK ACTIVITY : AREA/LEVEL GRIDLINE/STRUCTURE: INSPECTION DATE/TIME :
Exterior Dryworks (Please enclose key plan) :
Masonry Finishing
Wetworks
PREPARED BY: INSPECTED B DATE START
LINE AND GRADE
CONTRACTOR RLC INSP DATE FINISHED
ACCEPTED
COMPONENTS KPI
YES NO N/A
1.0 Area must be clear and free from debris and loose items Must be upon the surveyors approval
2.0 Layout must be as per plan No deviation must be allowed unless otherwise
approved
3.0 Doors and windows are indicated in the lay out Window and Doors location be comprehendable
4.0 Wall thickness and type must be sufficiently indicated in the layout Wall type be comprehendable
PREPARED BY: INSPECTED BY: DATE START
REBAR
CONTRACTOR RLC INSP DATE FINISHED
ACCEPTED
COMPONENTS KPI
YES NO N/A
1.0 Vertical bar installation must coincide the center of wall partition layout Max deviation of 1 cm side by side
2.0 Reinforcing bars size, specification, splicing & spacing checked No deviation must be allowed unless otherwise
approved
PREPARED BY: INSPECTED BY: DATE START
CHB INSTALLATION
CONTRACTOR RLC INSP DATE FINISHED
ACCEPTED
COMPONENTS KPI
YES NO N/A
1.0 Vertical bar installation must coincide the center of wall partition layout Max deviation of 1 cm side by side
2.0 Reinforcing bars size, specification, splicing & spacing checked Vertical Bar spacing 1200 MM, horizontal bar every 3
3.0 Stirrups on lintel beams and stiffener columns must be as per plan layers
Spacing of stirrups and ties is 150 mm
4.0 Zocalo forms must be as per lay out. Maximum of 1 cm deviationfrom layout per 1m
5.0 Zocalo forms must be plumbed max 5 mm deviation
6.0 Concrete Zocalo must be free of honey combs All honeycombs must be rectified
7.0 CHB unit size and strength complying as per approved specs with no cracks Thermal cracks are permittable but should not be
through and through
CHB breakage manifested by cracks ( 3 to 5 mm)may
be used but should be cut to fit as serojo
8.0 CHB installation must be plumbed and coincides with the zocalo
Max deviation of 2 cm plumbness on the whole height

No deviation is allowed from the zocalo


9.0 Stiffener columns and lintel beams checked if required Stiffener column must be for every 4 m span
Lintel beams must be for every 3 m layers of CHB
There should be Lintel beams and Stiffener columns
per opening
10.0 All MEPF conduits passing through the CHB wall must be installed with Fireprotection
sleeving otherwise signed by RLC Coordinator
Waterline
Sub feeder
Auxillary
Sewer Line
11.0 Installation of styrofoam at the top of the CHB to act as seismic Gap with the Maximum of 100 mm lapse on styro per 1m.
soffit

CIVIL / STRUCTURAL PLUMBING/SANITARY ELECTRICAL / AUX FIREPRO/MECH ARCHITECTURAL SAFETY

RLC Coordinator RLC Coordinator RLC Coordinator RLC Coordinator RLC Coordinator SAFETY OFFICER
PERMITTING: Based on the recommendations of the above personnel, having verified and certified that other works in the area will not conflict with the work specifications, the
Project Engineer in charge of said Activity/Work Item hereby recommends approval of this request and that shop drawings and materials comply with the latest approved plans
and specifications, the Project Engineer in charge of said Activity/Work Item hereby recommends approval of this request.

APPROVED BY : NOTED BY :

Construction Manager RLC Project Manager


DISTRIBUTION : Contractor QC Project Documentation Form 91-S-003 (Jan 2020)